Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Shree Shyam Steel Co vs Commissioner Of Central Tax
2025 Latest Caselaw 3632 Cal/2

Citation : 2025 Latest Caselaw 3632 Cal/2
Judgement Date : 24 December, 2025

[Cites 4, Cited by 0]

Calcutta High Court

Shree Shyam Steel Co vs Commissioner Of Central Tax on 24 December, 2025

Author: Rajarshi Bharadwaj
Bench: Rajarshi Bharadwaj
                                                                        2025:CHC-OS:272-DB
                    IN THE HIGH COURT AT CALCUTTA
                         SPECIAL JURISDICTION
                             ORIGINAL SIDE


                         CEXA 60 OF 2024

                       IA NO: GA 2 of 2024


                  SHREE SHYAM STEEL CO
                           VS
 COMMISSIONER OF CENTRAL TAX, CGST AND CENTRAL EXCISE


BEFORE:
THE HON'BLE JUSTICE RAJARSHI BHARADWAJ
              AND
THE HON'BLE JUSTICE UDAY KUMAR


For the Appellant      : Mr. N.K. Chowdhury, Adv.
                         Mr. Nilotpal Chowdhury, Adv.
                         Mr. Prabir Bera Adv.

For the Respondent     : Mr. Vipul Kundalia, Sr. Adv.,

Mr. Anurag Roy, Adv., Mr. Dhirodatta Chaudhuri Adv.



Hearing concluded on   : 04.12.2025

Judgment on            : 24.12.2025

Uday Kumar, J:-




1. This appeal, preferred by the Assessee under the statutory mandate of

Section 35G of the Central Excise Act, 1944, assails the legality of

Interim Order No. 142/2024 (Defect) dated 14.05.2024, passed by the

Customs, Excise & Service Tax Appellate Tribunal (CESTAT), Eastern

Zonal Bench, Kolkata. By the said order, the learned Tribunal refused CEXA 60 of 2024

2025:CHC-OS:272-DB

to condone a delay of 2262 days in filing the statutory appeal against

the Order-in-Original, resulting in a summary dismissal of the

Assessee's plea upon the characterization of their inaction as "total

negligence."

2. The timeline of the delay is bifurcated into two distinct phases. The

statutory limitation for filing the appeal expired on 10.04.2018;

however, the appeal was eventually preferred only on 28.03.2024.

The Appellant sought to bridge this hiatus by pleading bona fide

reliance upon the Sabka Vishwas (Legacy Dispute Resolution)

Scheme, 2019 (SVLDRS). An application under the said Scheme was

filed on 18.12.2019, but the Appellant asserts that they remained

oblivious to its rejection until late 2023.

3. The learned Tribunal dismissed the application on two primary

grounds:

i. The period between the expiry of limitation (April 2018) and

the filing of the SVLDRS application (December 2019)

remained unaccounted for.

ii. The rejection status was available on a public web portal as

of 20.01.2020; hence, the plea of ignorance was deemed

unsustainablein the eyes of the law

4. Mr. N.K. Chowdhury, learned Counsel for the Appellant, assisted by

Mr. Nolotpal Chowdhury and Mr. Prabir Bera, forcefully submitted

that the Tribunal's decision was founded upon an unduly technical

and rigid interpretation. He emphasized that the delay was actuated CEXA 60 of 2024

2025:CHC-OS:272-DB

by a bona fide, albeit perhaps misguided, attempt to avail a statutory

amnesty. Pressing the jurisprudential standard set in N.

Balakrishnan v. M. Krishnamurthy (1998) 7 SCC 123, he urged

that the expression "sufficient cause" must be liberally construed, as

the acceptability of the explanation is the sole criterion, regardless of

the length of the delay.

5. Conversely, Mr. Vipul Kundalia, the learned Senior

Advocate/Authorized Representative for the respondent / Revenue,

assisted by Mr. Anurag Roy and Mr. Dhirodatta Chaudhuri, sought to

defend the impugned order, by stressing the gross negligence evident

in the initial period of delay. He further argued that the failure to

verify the publicly accessible online status for nearly four years

evinced a profound lack of diligence, justifying the finding of "total

negligence" under the rigors of Section 5 of the Limitation Act, 1963.

6. After hearing the learned counsel for the parties and perusing the

materials on record, the Substantial Question of Law that arises for

our consideration is:

"Whether the learned Tribunal was justified in adopting a hyper-

technical approach by refusing to condone the delay, thereby

extinguishing the Appellant's right to challenge a significant financial

penalty on merits, especially when the delay was attributed to the

pursuit of a State-sponsored Amnesty Scheme?"

7. The factual matrix, while involving a staggering delay, is relatively

straightforward. The statutory limitation for filing the appeal before CEXA 60 of 2024

2025:CHC-OS:272-DB

the CESTAT expired on 10.04.2018. The appeal was eventually filed

on 28.03.2024. The Appellant's primary explanation for this hiatus is

their participation in the Sabka Vishwas (Legacy Dispute

Resolution) Scheme, 2019 (SVLDRS). The Appellant contends that

having applied for the scheme in December 2019, they were under a

bona fide belief that the dispute would be settled. It was only in late

2023 that they allegedly realized their application had been rejected

on the portal.

8. The learned Tribunal took a stern view, characterizing the conduct of

the Appellant as "total negligence." The Tribunal held that the

Appellant failed to explain the "initial lethargy" between April 2018

and the launch of the SVLDRS in 2019. Furthermore, it was observed

that since the rejection status was available on the public portal, the

Appellant could not plead ignorance.

9. We find ourselves unable to subscribe to the view taken by the learned

Tribunal. It is a well-settled principle of law that the expression

"sufficient cause" under Section 5 of the Limitation Act, 1963,

must receive a liberal construction to advance the cause of justice. As

held by the Hon'ble Supreme Court in Collector, Land Acquisition,

Anantnag v. Katiji (1987) 2 SCC 107, when substantial justice and

technical considerations are pitted against each other, the cause of

substantial justice deserves to be preferred.

10. In matters of taxation, the State should not be seen as a litigant

interested in benefiting from the procedural lapses of its citizens. The

SVLDRS, 2019 was a beneficial, State-sponsored mechanism CEXA 60 of 2024

2025:CHC-OS:272-DB

intended to clear the backlog of "legacy" disputes. Even if the

Appellant's application was ultimately found to be ineligible--being a

co-noticee--the act of applying for such a scheme is a clear

manifestation of an intent to resolve the liability. It cannot be termed

as a "dilatory tactic" or mala fide conduct.

11. Regarding the Tribunal's observation on the Appellant's "initial

lethargy," we must emphasize that the law of limitation is not meant

to be an "extinguishing engine" for substantive rights. Once it is

shown that the subsequent delay was rooted in a bona fide pursuit of

a settlement scheme, a slightly broader view must be taken of the

preceding period.

12. Furthermore, we cannot ignore the global disruption caused by the

COVID-19 pandemic. The Hon'ble Supreme Court, in its Suo Motu

Writ Petition (C) No. 3 of 2020, took cognizance of the hardships

faced by litigants and directed the exclusion of the period from

15.03.2020 to 28.02.2022 for the purposes of limitation. The

Tribunal's expectation that the Appellant should have monitored the

digital portal daily during this period is, in our considered view,

divorced from the ground realities of the time.

13. The Order-in-Original in the present case imposes a penalty of Rs.

10,23,864/-. To deny a citizen the right to test the legality of such a

penalty on the grounds of a non-deliberate delay would be

unconscionable. Justice should not be a casualty of procedural

rigidity. As observed in N. Balakrishnan v. M. Krishnamurthy CEXA 60 of 2024

2025:CHC-OS:272-DB

(1998) 7 SCC 123, the length of the delay is irrelevant; what matters

is the acceptability of the explanation.

14. The Order-in-Original imposes a penalty of Rs. 10,23,864/-. To deny

a citizen the right to test the legality of such a penalty on the grounds

of a non-deliberate delay would be unconscionable. Law is not meant

to be an extinguish any substantive rights.

15. While we are inclined to condone the delay, we are also mindful of the

fact that the Revenue has been put to inconvenience due to the

prolonged duration of this litigation. Therefore, the condonation must

be balanced with the imposition of costs.

16. For the reasons stated above, the appeal is allowed and the following

directions are issued:

i. The Interim Order dated 14.05.2024 is set aside.

ii. The delay of 2262 days in filing the appeal before the CESTAT is

condoned, subject to the Appellant paying a cost of Rs.

10,000/- (Rupees Ten Thousand only) to the

Respondent/Revenue within four weeks from the date of receipt

of this order.

iii. Upon production of proof of payment, the learned Tribunal is

directed to restore the appeal to its original number and decide

the matter on its merits, after affording both parties a fair

opportunity of being heard.

17. The Substantial Question of Law is therefore, answered in favour of

the Appellant. There are no further orders as to costs. CEXA 60 of 2024

2025:CHC-OS:272-DB

18. The appeal is disposed of on the aforementioned terms.

19. Urgent photostat certified copy of this judgment, if applied for, be

delivered to the parties upon compliance with all legal formalities.

(RAJARSHI BHARADWAJ, J.)                               (UDAY KUMAR, J.)
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter