Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sitaram Barasia vs The State Of West Bengal & Ors
2024 Latest Caselaw 4903 Cal

Citation : 2024 Latest Caselaw 4903 Cal
Judgement Date : 23 September, 2024

Calcutta High Court (Appellete Side)

Sitaram Barasia vs The State Of West Bengal & Ors on 23 September, 2024

Author: Joymalya Bagchi

Bench: Joymalya Bagchi

Sl. No. 77




                  -IN THE HIGH COURT AT CALCUTTA
                      CIVIL APPELLATE JURISDICTION
                            APPELLATE SIDE
Present:
The Hon'ble Justice Joymalya Bagchi
               And
The Hon'ble Justice Gaurang Kanth


                            F. M. A. 999 of 2024
                               (CAN 1 of 2024)

                             Sitaram Barasia
                                   -Vs-
                      The State of West Bengal & Ors.


For the Appellant       :     Mr. Tapash Kumar Bhattacharya, Adv.
                              Mr. Aviroop Bhattacharya, Adv.


For Respondent no.5     :     Mr. Pratik Majumder, Adv.
[Pradhan]                     Mr. Abdul Mullick, Adv.


For Respondent No.9     :     Mr. Parashar Baidya, Adv.
                              Mr. Santanu Talukdar, Adv.
                              Mr. Priyankar Ganguly, Adv.
                              Ms. Shalini Bairagi, Adv.

Heard on                :     23.09.2024



Judgment on             :     23.09.2024


Joymalya Bagchi, J. :-

1. Appellant had approached this court alleging unauthorised

construction by private respondent no.9.

2. In view of such complaint, Hon'ble Single Judge in WPA 12404 of

2022 disposed of the matter directing the Pradhan, Karimpur-I Gram

Panchayat to consider the grievance of the appellant in the following

manner :-

a) An inspection shall be conducted. Such inspection shall be held in the presence of the petitioner and the respondent no.12 within three weeks.

Advance notice of the inspection shall be served upon the petitioner and the respondent no.12.

b) In case, it is found on preliminary inspection that there may be reasons to believe that the construction was without permission and was continuing, the authorities may take such interim measures by stopping such construction.

c) The report of such inspection shall be prepared along with the sketch map, indicating the extent and nature of unauthorised construction, if any.

d) Such report shall be handed over to the parties.

e) A hearing shall be given to the petitioner and the respondent no.12. The parties must also be allowed to furnish their written objection/version to the said report and adduce oral and documentary evidence in support of their contentions before the competent authority. All points raised by either party shall be decided.

f) A reasoned order shall be passed and communicated to the parties. On the basis of what transpires at the hearing and during inspection, the proceedings shall be reached to its logical conclusion in terms of the statute.

3. Pursuant thereto, the Pradhan, Karimpur-I Gram Panchayat

passed order dated 13.02.2023 wherein he noted as follows :-

i) As per deed the area of the premises is 807 sq. ft. but B.L.&L.R.O. has found the area of the building to be 870 sq. ft.

ii) Panchayat had sanctioned a structure of 574 sq. ft.

iii) The building was constructed without maintaining mandatory side open spaces.

iv) No permission from Panchayat or Zilla Parishad was obtained to make the G+2 storied construction.

4. In light of the aforesaid findings, Pradhan directed the private

respondent no.9 to demolish the unauthorised portions of the building.

5. Appellant again approached this court in the instant writ petition

seeking implementation of the order of the Pradhan. During hearing,

Hon'ble Single Judge noted the order was passed without complying with

the directions of this court in WPA 12404 of 2022 and remitted the matter

to the Pradhan to undertake enquiry in terms of the aforesaid order in

WPA 12404 of 2022 and pass a reasoned order with regard to complaint

regarding unauthorised construction. Hon'ble Single Judge further

directed if any unauthorised construction was noted, the same shall be

referred to the Sub-Divisional Officer in terms of Section 23(5) of the West

Bengal Panchayat Act, 1973.

6. Mr. Tapas Kumar Bhattacharya for the appellant contends the

order passed by the Pradhan is self-evident with regard to deviations from

the sanctioned plan. He also contends the said order had not been

assailed.

7. Learned Advocate for the Pradhan, Karimpur-I Gram Panchayat,

however, is unable to place on record report of inspection including

sketch map showing the extent and nature of unauthorised construction.

8. Learned Advocate for private respondent no.9 submits no copy of

the inspection report had been served upon him during hearing.

9. We have considered the materials on record. By order dated

05.09.2022 in WPA 12404 of 2022 Hon'ble Single Judge directed the

Pradhan, Karimpur-I Gram Panchayat to hold inspection and thereupon

prepare an inspection report enclosing sketch map indicating the nature

and extent of unauthorised construction. Report was directed to be

handed over to the parties and after hearing them vis-a-vis objections to

the report, necessary order was required to be passed.

10. Order passed by the Pradhan does not reflect inspection report

with sketch map was prepared and circulated amongst the parties

including private respondent no.9. Consequently private respondent no.9

was in the dark with regard to the contents of the inspection report and

could not effectively make representation when the order directing

demolition of unauthorised construction came to be passed.

11. Under such circumstances, we are of the view order of the

Pradhan, Karimpur-I Gram Panchayat was not only in breach of the

directions of this court in WPA 12404 of 2022 but also in breach of

principles of natural justice and fair procedure.

12. Accordingly, we are of the view Hon'ble Single Judge was justified

to direct fresh inquiry in terms of the order passed by this court in WPA

12404 of 2022 within a time frame. Hon'ble Judge had further directed in

the event unauthorised construction was noted, matter shall be referred

to the Sub-Divisional Officer under Section 23(5) of the West Bengal

Panchayat Act, 1973 which addresses the concern of the appellant. The

impugned order does not call for interference.

13. We direct the Pradhan, Karimpur-I Gram Panchayat to conclude

enquiry in terms of the impugned order within six weeks from the date of

communication of this order. In the event, unauthorised construction is

noted, the said order shall be forwarded to the Sub-Divisional Officer

under Section 23(5) of the West Bengal Panchayat Act, 1973 within one

week thereof for necessary action in accordance with law.

14. With the aforesaid directions, appeal is disposed of.

15. In view of disposal of the appeal, connected application being CAN

1 of 2024 is also disposed of.

16. There shall be no order as to costs.

17. Photostat certified copy of this judgment, if applied for, be given to

the parties on compliance of all formalities.

I agree.

(Gaurang Kanth, J.)                               (Joymalya Bagchi, J.)




akd

 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter