Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Bgm And M-Rpl-Jmct (Jv) vs Eastern Coalfields Limited
2024 Latest Caselaw 157 Cal/2

Citation : 2024 Latest Caselaw 157 Cal/2
Judgement Date : 19 January, 2024

Calcutta High Court

Bgm And M-Rpl-Jmct (Jv) vs Eastern Coalfields Limited on 19 January, 2024

Author: Moushumi Bhattacharya

Bench: Moushumi Bhattacharya

                      IN THE HIGH COURT AT CALCUTTA
                      Ordinary Original Civil Jurisdiction
                               ORIGINAL SIDE
                            (Commercial Division)
 Present :-

 THE HON'BLE JUSTICE MOUSHUMI BHATTACHARYA

                               AP 745 of 2023

                          BGM and M-RPL-JMCT (JV)
                                         Vs.
                           Eastern Coalfields Limited


 For the petitioner                  :         Mr. Debajyoti Basu, Adv.
                                               Mr. Diptomoy Talukdar, Adv.
                                               Mr. Dibyendu Ghosh, Adv.
                                               Ms. C. Chatterjee, Adv.



 For the respondent                  :         Mr. Debnath Ghosh, Adv.
                                               Mr. Sayed Nurul Arefin, Adv.
                                               Mr. Sayed M. Arefin, Adv.
                                               Ms. Rashmi Binayak, Adv.


 Last Heard on                       :         16.01.2024



 Delivered on                        :         19.01.2024


 Moushumi Bhattacharya, J.

1. The petitioner prays for appointment of an arbitrator under section 11 of

The Arbitration and Conciliation Act, 1996. The petitioner relies on clause 13

under the General Terms and Conditions of an e-tender notice dated 8.5.2019

issued by the respondent, Eastern Coalfields Limited (ECL) for removal and

transportation of material for a project at Nakrakonda - Kumardih. Clause 13

of the General Terms and Conditions, appended to the e-tender notice, provides

for settlement of disputes and contains, according to learned counsel appearing

for the petitioner, the arbitration clause.

2. Counsel submits that disputes have arisen between the parties pursuant

to the petitioner being engaged as the contractor for the work described in the

e-tender notice. The dispute allegedly revolves around the parties disagreeing

to changes made to the price component of the contract.

3. Learned counsel appearing for the respondent takes a point of

maintainability of the present application on the ground that there is no

arbitration agreement between the parties.

4. The argument on maintainability is required to be answered first.

5. Clause 13 of the General Terms and Conditions which forms part of the

e-tender notice - and the crux of the dispute - is set out below :

"13. SETTLEMENT OF DISPUTES It is incumbent upon the contractor to avoid litigation and disputes during the course of execution. However, if such disputes take place between the contractor and the department, effort shall be made first to settle the disputes at the company level.

The contractor should make request in writing to the Engineer-in-charge for settlement of such disputes/claims within 30 (thirty) days of arising of the cause of dispute/ claim failing which no disputes/ claims of the contractor shall be entertained by the company.

Effort shall be made to resolve the dispute in two stages.

In first stage dispute shall be referred to Area CGM, GM. If difference still persist the dispute shall be referred to a committee constituted by the owner. The Committee shall have one member of the rank of Director of the company who shall be chairman of the company.

If differences till persist, the settlement of the dispute shall be resolved in the following manner:

In the event of any dispute or difference relating to the interpretation and application of the provisions of commercial contract(s) between Central Public Sector Enterprises (CPSEs)/Port Trusts inter se and also between CPSEs and Government Departments/Organizations (excluding disputes concerning railways, Income Tax, Customs & Excise Departments), such dispute or difference shall be taken up by either party for resolution through AMRCD as mentioned in DPE OM No. 4(1)/2013-DPE (GM)/FTS-1835 dated 22-05-2018.

In case of parties other than Govt. Agencies, the redressal of the dispute may be sought through ARBITRATION AND CONCILIATION ACT, 1996 as amended by AMENDMENT ACT OF 2015"

6. It is evident from the above clause that the parties to the contract were

under an obligation to resolve the dispute in 2 stages if the parties were unable

to settle the disputes at the company level of ECL. The 2 stages are enumerated

in the clause itself and is not being repeated. The second part of the clause

begins with "In case of parties other than Govt. Agencies..." and is relevant for

the present application. The petitioner is a non-government entity.

7. The point which arises for consideration is whether the part of the clause

containing the word "may" can be construed to be an arbitration agreement as

contemplated under section 7 of the 1996 Act.

8. Section 7(1) defines an "arbitration agreement" to mean an agreement by

the parties to submit disputes which have arisen between them in respect of a

defined legal relationship to arbitration. The section includes non-contractual

relationships. Section 7(2) envisages agreements which are embedded in the

contract or in the form of a separate agreement and section 7(3) stipulates that

the arbitration agreement must be in writing. Section 7(4) factors in 3

situations where the arbitration agreement will be accepted to be in writing and

section 7(5) looks at arbitration agreements being incorporated by reference.

9. Section 7 underscores the unequivocal intent of the parties to go to

arbitration by giving shape and form to the arbitration agreement and exit

options to the parties under sub-sections (4) and (5) of section 7.

10. Presence of the word "may" in the arbitration clause in the matter at

hand is required to be tested against mindset of the parties to the agreement.

Parties consenting to arbitration including to the mode and mechanism of the

procedure forms the mainstay of the 1996 Act.

Does "may" negate the existence of an arbitration agreement?

11. In Jagdish Chander vs. Ramesh Chander; (2007) 5 SCC 719, the Supreme

Court set out 4 broad principles on what would constitute an arbitration

agreement. These are :

i) The intent of the parties to enter into an arbitration agreement as

discernible from the terms of the agreement;

ii) Absence of the words "arbitration" / "arbitral tribunal" would not be

fatal to the existence of an arbitration clause if the clause has the

attributes or the elements of an arbitration agreement;

iii) The clause must provide that the disputes shall be referred to

arbitration in the event of disputes arising between the parties;

iv) Mere use of the words "arbitration" / "arbitrator" in a clause will not

make it an arbitration agreement if the clause requires further consent

of the parties for reference to arbitration.

12. Jagdish Chander masterfuly encapsulates the parameters of what

constitutes an arbitration agreement and more important, the parties intention

to arbitrate. The will to arbitrate must clearly be articulated in the arbitration

clause. There is no room for any doubt or second-guessing. Parties must be

clear in their minds that they wish to subject themselves to arbitration as the

chosen mechanism of dispute resolution and ensure that the intention is

expressed in writing in the form of the arbitration agreement.

13. The clarity of intention should hence be expressed through clear-cut

words. Therefore, words such as

"the parties wish .....", or

"the parties will consider .....", or

"the parties will thereafter decide ...." and

"the parties may ....."

will be counter-productive to the unequivocality of the intention to arbitrate.

The above instances are not exhaustive and may include other words which

give a sense of indecision, lack of purpose, prevarification or even saving the

option for arbitration to a later date or as a last resort.

14. An arbitration agreement also does not sit comfortably with conditions

attached for the parties to go to arbitration. The clause should not be subject to

or conditional upon further or future events which may or may not occur.

15. In essence, there cannot be any ifs and buts or an undecided mumble;

the parties must give a resounding "Yes" to arbitration. For a movement

analogy; the arbitration agreement is not about a hesitant 1 step ahead - 2

steps backward / back-tracking but a confident 1-way stride forward to

arbitration.

16. Section 11 of the 1996 Act is one of the earlier interventions by a Court

on the presumption of the existence of an arbitration clause. The Court must

hence ensure the existence of an arbitration agreement before flagging of the

road to the award and beyond. The parties cannot set forth on the procedural

journey if there is no arbitration agreement.

17. In the present case, the arbitration agreement muddies the waters with

regard to the immediate and unequivocal reference of the dispute to

arbitration. The word "may" in the relevant part of the clause gives an option to

the parties to either refer the dispute to arbitration or hold back on the

arbitration. The word "may" makes the clause conditional on a future event/s

or to the other parts of the clause and gives the parties the option to resile from

the clause. In other words, the clause creates a Hamlet-esque hand-on-the-

chin indecision and the Court is also left wondering as to what the parties

actually intended in clause 13 of the agreement.

18. Besides, the absence of an arbitration agreement was urged by the

respondent both before the Commercial Court at Asansol as well as before the

Division Bench of this Court. In any event, absence of an arbitration clause is a

fundamental threshold argument and should be made at the section 11 stage.

19. The Dispute Resolution Clause also makes it clear that the Clause is

divided in 2 parts - The first part and the tiers thereof are relevant for

government agencies and in any event does not refer to arbitration or have the

trappings thereof. The second part applies to the petitioner as a non-

government entity.

20. Although arbitration clauses differ in every case, the Supreme Court has

clarified certain uniform trappings of a valid arbitration agreement. In Food

Corporation of India v. National Collateral Management Services Limited

(NCMSL); (2020) 19 SCC 464, the Supreme Court found a lack of finality in the

arbitration clauses which envisaged reference of the dispute to the CMD of

Food Corporation of India for "settlement". The concerned clauses also

specifically mentioned that the parties understood the clause not to be an

arbitration clause. In Mahanadi Coalfields Ltd. v. IVRCL AMR Joint Venture;

2022 SCC OnLine SC 960, the Supreme Court relied on Jagdish Chander and

construed the relevant clause in the agreement not to be an arbitration

agreement. The concerned clause before the Supreme Court also contained the

word "may". A learned Single Judge of the Bombay High Court in Quick Heal

Technologies Limited v. NCS Computech Private Limited; 2020 SCC OnLine Bom

693 noted the difference between the words "shall" and "may" and concluded

that there was no clear intention of the parties to refer the dispute between

them to arbitration. The Court, in fact, construed the words "shall" and "may"

in the same clause and came to the aforesaid view. Another learned Single

Judge of the Bombay High Court in GTL Infrastructure Limited v. Vodafone Idea

Limited (VIL); 2023 SCC OnLine Bom 39 construed the word "may" to

contemplate a future possibility which would also involve discretion on the part

of the parties whether to refer dispute the arbitration or not.

21. On the other hand, the decisions shown by counsel for the petitioner are

not on the point of negation or dilution of the arbitration agreement by use of

the word "may". Enercon (India) Limited v. Enercon GMBH; (2014) 5 SCC 1 was

on the unworkability of the arbitration clause which is different from the

absence/non-existence of an arbitration clause. Powertech World Wide Limited

v. Delvin International General Trading LLC; (2012) 1 SCC 361 involved

ambiguity in the language of the arbitration clause. The Supreme Court

considered the decision in Jagdish Chander and referred to the correspondence

between the parties and the intention emanating therefrom to refer the dispute

to arbitration. In Babanrao Rajaram Pund v. Samarth Builders and Developers;

(2022) 9 SCC 691, a Single Bench of the Supreme Court also referred to

Jagdish Chander and opined that the arbitration clause before the Court was

substantially different from the arbitration clause in Jagdish Chander. The

Court noted use of the words "shall be referred to arbitration ..." and relied on

the recitals to the agreement to conclude that there was an unambiguous

intention of the parties at the time of the formation of the contract to refer the

disputes to arbitration. Visa International Limited v. Continental Resources

(USA) Limited; (2009) 2 SCC 55, was on the point of existence of a live issue

which was capable of being referred to arbitration under section 11 of the 1996

Act. The Court was also of the view that the attending facts and circumstances

were conducive to the existence of a valid arbitration agreement.

22. None of these decisions assist the petitioner. Unlike the present case, the

arbitration clauses in the cases were not diluted by use of the word "may".

There are also no attending circumstances in the present case by way of

correspondence or otherwise which would show that the parties intended to

refer the dispute to arbitration even if the clause says otherwise.

23. Despite the Court's finding on the absence of an arbitration agreement

between the parties, it is important to record that clause 32 of the Instructions

to Bidders which forms part of the e-tender document gives the option to an

aggrieved party to approach the jurisdictional Court. Hence, the petitioner will

not be rendered remedy-less. It is also important that contractors / parties

engaging with public sector undertakings / Government Companies be made

aware of the words used in the arbitration clause which have the effect of

negating the arbitration agreement altogether. In many cases, the contractor

does not have a say in the drafting of these clauses and it is hence all the more

necessary for the parties to be put on notice and guard themselves against

vague or uncertain dispute resolution clauses.

24. In view of the above finding - that Clause 13 under the General Terms

and Conditions of the e-tender document does not constitute or contain an

arbitration agreement - AP 745 of 2023 is dismissed on the ground of

maintainability. There shall be no orders as to costs.

Urgent photostat certified copies of this judgment, if applied for, be

supplied to the parties upon fulfillment of requisite formalities.

(Moushumi Bhattacharya, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter