Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Veekay General Industries vs Eastern Railways
2023 Latest Caselaw 3009 Cal/2

Citation : 2023 Latest Caselaw 3009 Cal/2
Judgement Date : 17 October, 2023

Calcutta High Court
Veekay General Industries vs Eastern Railways on 17 October, 2023
                   IN THE HIGH COURT AT CALCUTTA
                   (Ordinary Original Civil Jurisdiction)
                         COMMERCIAL DIVISION


Present:

The Hon'ble Justice Krishna Rao



                              CS 159 of 2019


                        Veekay General Industries
                                    Versus
             Eastern Railways, Through its General Manager



            Mr. Sourojit Dasgupta
            Mr. Vishwarup Acharyya
                                                  ... for the plaintiff.
            Mr. Avinash Kankani
            Mr. Suman Majumder
                                              ... for the defendant.


Hearing Concluded On : 04.10.2023

Judgment on             : 17.10.2023

Krishna Rao, J.:


1.   The plaintiff has filed the suit for a decree of sum of Rs. 1,74,40,566/-

     along with interest against the defendant.


2.   The defendant had issued a tender Notice dated 4th June, 2013 for

     procurement of jointless grooved copper contact wire made out of

     continuous cast copper wire rods. The plaintiff has participated in the
                                       2


     said tender process. At the time of submission of the tender document,

     the plaintiff had reserved its price variation clause which contained in

     the tender notice and the plaintiff had also enclosed a separate price

     variation clause along with the bid. On 24th October, 2013, the

     defendant had issued letter of acceptance to the plaintiff for the supply

     of 186.184 MT for supply of jointless grooved copper contact wire 107

     sq. mtr.


3.   On receipt of the offer letter, the plaintiff has submitted its

     representation on 29th October, 2013, intimating the defendant that as

     per tender document, the delivery schedule was 50% within 04 months

     and the balance within 04 months thereafter. The plaintiff has

     proposed for changing the Clause as follows : "Delivery to commence

     within 45 days at the rate of 63 MT per month and to be completed

     within three months thereafter." The plaintiff has also informed the

     defendant about the price variation clause and mentioned that: "We

     had in our offer very clearly recorded that the Custom Duty factor shall

     be as 'one' and also Custom Duty factor CD2 shall be 'one'." In reply to

     the request of the plaintiff, the defendant by a letter dated 19th

     November, 2013, accepted the delivery period as proposed by the

     plaintiff but with regard to the Custom Duty factor, the defendant had

     informed that :


                         "Your attention is further invited to Part G.
                  (12) of the Tabulation Statement of Financial BID
                  of the said tender which has been digitally signed
                  by the tenderer where acceptance of PVC clause
                  has been confirmed as per annexed PVC formula
                                           3


                      as per based rate/exchange rate etc. indicated
                      therein has been confirmed by saying 'yes' in the
                      complied column XX in the remarks column. In Pt.
                      E & F technical & commercial statement, no
                      technical and commercial deviation has been
                      offered (copy enclosed)"


             In the said reply, the defendant had further requested the

     plaintiff   to   confirm    unconditional   acceptance    of   the     Advance

     Acceptance letter so that formal order can be issued.


4.   In reply to the letter dated 19th November, 2013, the plaintiff had sent a

     reply to the defendant informing the defendant :


                      "We had assumed that there was a typographical
                      omission in the PVC formula given in the tender
                      documents. That is the reason we attached the
                      standardized PVC formula in our offer as
                      annexure wherein we had predetermined factor
                      CD1 as 1 and did not consider this as a case of
                      commercial deviation.

                      Hence, to summarize the above, please note that
                      the rates offered by us are neither in deviation of
                      PVC formula and nor is there any commercial
                      deviation as the same are based on the
                      standardized PVC formula wherein both CD1 and
                      CD2 are taken as 1. We would now request you
                      kindly to reconsider this case in the light of the
                      above and hope for a favourable response on the
                      same from you."



             Instead of confirming the unconditional acceptance of Advance

      Acceptance letter of the plaintiff, the defendant had issued two work

      orders dated 17.12.2013 for supply of 19.664 MT and 165.416 MT of

      HDGC Contact Wire respectively. On receipt of the work orders, the

      plaintiff vide its letter dated 06.01.2014 informed the defendant that :
                                       4


                  "Kindly      refer      to    our   letter    No.
                  VKGI/COMM/ER/341 dt. 17.12.2013 wherein we
                  had explained our position regarding factor CD1
                  being taken as 'One'. You have not accepted our
                  clarification and placed a Purchase Order
                  No.16.12.6025.1.41371 dated 17.12.2013 &
                  P.O.No.16.11.5028.1.04978 dt. 17.12.2013 for
                  supply of 185.080 MT. ofjointless Grooved Copper
                  Contact wire (107 Sq.mm.) made out of
                  Continuous Cast Copper Wire Rod with factor
                  CD1 as 1.054. As explained in our earlier letters,
                  we shall incur heavy losses on account of wrong
                  interpretation of factor CD1.
                  However, in view of our very long association
                  with Railways, we are going to execute this order
                  under protest. We may take up this issue at
                  suitable time through arbitration."


5.   On 17th February, 2014, the plaintiff sent a letter to the defendant

     informing the defendant that :


                  "We propose to supply 50% quantity of Contact
                  Wire 107 Sq.mm. against the Purchase Order
                  No.16.12.6025.1.41371      dt.  17.12.2013     &
                  P.O.No.16.11.5028.1.04978      dt.   17.12.2013
                  valued at approx. Rs.5,00,00,000.00 (Rupees Five
                  Crores Only) in March/April 2014.

                  We have already advised you that these orders
                  are placed on us not in conformity with our offer
                  and we shall suffer heavy losses in these orders.
                  We would therefore like to execute these orders if
                  our payments are not delayed.

                  In view of the above please confirm that funds
                  shall be available for payments against proposed
                  supply in March/April 2014 so that we can go
                  ahead      with       procurement     of     raw
                  material/manufacture of Contact wire 107
                  Sq.mm."


            On 3rd March, 2014, the plaintiff has again sent a letter to the

      defendant informing the defendant as follows:
                                    5


               "As desired, we shall be offering 50% of the
               ordered quantity of Contact Wire for inspection to
               RITES in the first week of April. The material shall
               be delivered by mid April 2014.

               In this connection kindly refer to our letter
               No.VKGI/COMM/ER/413 dt. 17.02.2014. we
               request you to kindly arrange the required funds
               so that our payment are not delayed."



          On receipt of the letters dated 06.01.2014, 17.02.2014 and

 03.03.2014, the defendant has not sent any reply to the plaintiff and

 accordingly, the plaintiff had again sent a letter on 24.03.2014 stating

 that :


               "1. We have explained to you vide our letter No.
               VKGI/COMM/ER/341 dt. 17.02.2013 and No.
               VKGI/COMM/ER/360 dt. 06.01.2014 that our
               offer in the said tender was with factors CD1 and
               CD2 as 'One'. You have not accepted our offer as
               given but placed order on us with factor CD1 as
               1.054.

               2. We had explained to you that we shall be
               incurring very heavy losses if we agree to supply
               the Contact Wire with factor CD1 as 1.054 instead
               of 'One'. However, in view of our long association
               we had agreed to execute the order subject to
               timely payments. Accordingly, we had agreed to
               executed the order and requested you to confirm
               availability of funds so that we supply the
               material. However, you have failed to confirm
               availability of funds. As such we have not been
               able to execute the order.
               In view of the above, we regret out inability to
               execute the above order. You may consider
               cancelling the same."



    No response were received from the defendant, the plaintiff had

again sent a letter dated 07.04.2014 stating that :
                                       6


            "Ref: Your Letter No. CEE/CON/ER/Store/Contact
            Wire/917 dt. 27.03.2014

            Dear Sir,

               Order placed on us for supply of Contact Wire is not
               as per our offer with deviation. Further, there is no
               confirmation about availability of funds for payment,
               if supplies are made. We have, therefore, requested
               Controller     of   Stores      vide     letter   No.
               VKGI/COMM/ER462 dt.24.03.2014 to cancel this
               order."



6.   The defendant had sent a letter to the plaintiff on 17.04.2014 but the

     said letter was not placed either by the plaintiff or by the defendant

     but on receipt of the said letter, the plaintiff has sent a reply to the

     defendant on 21.04.2014 which reads as follows :

            "Ref: Your Letter No. 16/11/5028 dt. 17.04.2014

            Dear Sir,

            Para-wise comments on your letter under reference dt.
            17.04.2013 is given under :

            1.0.   In this connection kindly refer to our letter No.
                   VKGI/COMM/ER/3055 dt. 29.10.2013 wherein
                   we have clarified that our offer is based on use
                   of indigenous CCC Rod and thus both Factors
                   CD1 & CD2 shall be "One". This is in line with
                   what is being followed by CORE/ALD and our
                   offer.

                   However, you have placed Purchase Order No.
                   16.12.6025.1.41371 dt. 17.12.2013 & P.O. No.
                   16.11.5028.1.04978 dt. 17.12.2013 without
                   incorporating changes as per our offer.

                   In view of our long association with Railways,
                   we had agreed as a very special case to execute
                   this     order    vide    our     letter    No.
                   VKGI/COMM/ER/360        dt.06.01.2014    under
                   protest. We had organized the manufacture of
                   Contact Wire to supply 50% of the ordered
                   quantity by March/April and had accordingly
                                          7


                     requested you to kindly confirm availability of
                     funds for timely payment. Despite our repeated
                     request to you to confirm availability of funds
                     vide our letter No. 06.01.2014, 03.03.2014 and
                     07.04.2014, we did not receive any confirmation
                     to the effect and as such we had no option but to
                     seek cancellation of the order.

             2.0.    The clarification given by you regarding PVC vide
                     your letter No. 16/11/5028 dt. 19.11.2013 has
                     not been accepted by us. We have already
                     clarified     this    vide    our    letter   No.
                     VKGI/COMM/ER/341 dt. 17.12.2013. The
                     Purchase Order has been issued without
                     considering     contents   of   our   offer  and
                     clarifications.

             4.0.   We still can execute this order and arrange
                    supply of the material to enable you to execute
                    target work provide the orders are as per our offer
                    i.e. both Factors CD1 & CD2 are accepted as
                    'One' for purpose of PVC.

             5.0.   Noted."


7.   The defendant by a letter dated 01.05.2014 in reference to the letters

     dated 03.03.2014, 24.03.2014, 17.04.2014 and 21.04.2014 informed

     the plaintiff as follows:

                    "1.0. This office has already clarified/confirmed
                    the contents of your letter dated 29.10.2013 vide
                    letter no. 16/11/5028 dated 19.11.2013 and you
                    have promised vide your letter under ref(1) that,
                    you will be offering 50% of the ordered quantity in
                    the 1st Week of April and material shall be
                    delivered by mid April'2014.

                    2.0. As far as provision of fund is concerned it is
                    well known to you that, unless and until clear
                    fund provision is ensured, Railway do not issue
                    any formal Purchase Order and thus seeking
                    clarification in regard to availability of fund is not
                    understood by this office. This is however, to
                    mention that fund is available for the P.O. placed
                    on you.
                                       8


                  3.0. It is re-iterated that, many project works of
                  this Railway are stuck-up for want of the above
                  item.

                  4.0. You are therefore requested to confirm within
                  seven days from the date of receipt of this letter
                  that, P.O.s will be executed as per its terms and
                  conditions failing which no further reference will
                  be made and this office will be compelled to
                  initiate Risk Purchase action at the risk and cost
                  of your concern.

                  5.0. This is for your information and necessary
                  action please. This letter is issued without
                  prejudice to the Railways right for initiating Risk
                  Purchase      Action   including    other      legal
                  proceedings."



8.   On 13.06.2014, the defendant had sent a letter to the plaintiff which

     reads as follows:

                                  "Office of the
                               Controller of Stores
                   17, Netaji Subhas Road, Kolkata - 700 001

            No: 16.115028                         Date 13.06.2014

            To
            M/S. Veekay General Industries,
            B-46, JhilmilTahirpur Industrial Area,
            G.T. Road,
            Shahdara,                      FAX NO. 01122589469
            New Delhi-110 095.

            Dear Sir,

                  Sub : Risk purchase action against

                    1) P.O.   No.  16/11/5028/1/04978          dated
                       17.12.2013 and

                    2) P.O.   No.   16/12/6025/1/41371       dated
                       17.12.2013 for supply of joint less grooved
                       copper contract wire, 107 sq mm made out of
                       continuous cast copper wire rods as per
                       RDSO SPEC No. ETI/OHE/76(6/97) with A &
                       C slip no. - 1,3,4,5 & 6 against E.Rly's
                            9


           Tender   No.        16/11/5028    Opened     on
           24.06.2013.

       Ref : 1) This office's letters of even no. dated
       17.04.2014 & 01.05.2014.

           2) Your letter no. VKGI/COM/ER/201 dated
              21.04.2014.
      With reference to the above, you are informed that
Eastern Railway had placed above Purchase orders as
mentioned in the subject column for supply of joint less
grooved copper contact wire, 107 sq mm made out of
continuous cast copper wire rods as per RDSO SPEC
NO. ETI/OHE/76 (6/97) with A & C slip no. 1, 3, 4, 5 &
6 on you.
       Despite this office's letter under reference you did
not agree to supply the material as per the terms and
conditions of the contract and rather you have asked for
change in the terms and conditions of the contract vide
letter under reference-2 which is not acceptable at post
contract stage. Hence, having no other way, final
reminder was issued vide this office letter of even no.
dated 01.05.2014 in regard to initiation of Risk
Purchase action against above two P.Os.

      In this connection one Risk Purchase Tender has
been issued/floated against the above P.Os Vide tender
No. 16/11/5028 (since the PO was placed against the
same tender batch) for total quantity of 185.080 MT and
the Risk Purchase Tender is due on 17.07.2014 and
closing at 1:30 PM through IREPS Website (E.Tender).

       You are, therefore, informed that in case you are
interested to quote in the aforesaid Risk Purchase
Tender then as per extant rule, you must submit your
offer along with Security Deposit Money for10% of the
total value of the offer failing which your offer will be
summarily rejected without making any back reference
to you. The copy of instrument of the S.D. Money must
be uploaded along with your offer and original hard
copy of the same should be sent/deposited to
COS/ER/FP/Kolkata office well before the scheduled
tender opening date and time failing which your offer
will be summarily rejected without making any back
reference to you.

     This is without any prejudice to rights of Eastern
Railway as a Purchaser. A copy of Risk Purchase
Tender Schedule is enclosed herewith.
                                       10



                                            (S. Kundu)

                                Dy. Chief Materials Manager/Con-II
                           For & on behalf of the President of India."


9.   The defendant had cancelled both the purchase orders on 12.08.2014

     and 25.08.2014 on the ground that the plaintiff has failed to supply the

     materials as per the purchase orders. After cancellation of the purchase

     orders, the defendant had sent two letters dated 27.11.2014 informing

     the plaintiff that the defendant is entitled to claim of Rs. 18,65,569/-

     and Rs. 1,55,74,996.85/- towards the expenditure incurred in risk and

     purchase in terms of Clauses 2401, 2402 and 2403 of the IRS

     Conditions of Contract.


10. The Controller of Stores, Eastern Railway by his letter dated

     16.02.2015 informed the plaintiff that if the plaintiff fails to comply

     with the terms of the purchase order dated 17.12.2013, the amount of

     Rs. 1,74,40,566/- shall be deducted as risk purchase loss from the

     pending bills of the petitioner. Being aggrieved with the letter dated

     16.2.2015, the plaintiff has filed a Writ application being W.P No.

     10789 (W) of 2015. The Hon'ble Court dismissed the writ petition on

     23.06.2015 by passing the following order :

                         "Despite the existence of an arbitration
                  agreement between the parties, this Court was
                  minded to entertain the writ petition provided the
                  petitioners secured the said amount of Rs.
                  1,74,40,566/- by depositing the same with the
                  Registrar General of this Court for investment
                  thereof in a fixed deposit account of Nationalized
                  Bank. However, the petitioners having declined to
                  secure such amount, there is no good reason as to
                  why they should not be relegated to the forum for
                                      11


                 resolution of dispute by arbitration, which they
                 intended by the letter dated 06.01.2014.

                        This Court is of the clear view that this writ
                 petition ought not to be entertained. The same
                 stands dismissed, without costs.

                       The petitioners are granted liberty to
                 pursue their remedy before the arbitral tribunal in
                 accordance with law.

                        Needless to observe, the observation made
                 above are for the purpose of disposal of this writ
                 petition and shall not influence the relevant Court
                 or the arbitral tribunal, as the case may be, if at
                 all approached by the petitioner.

                        Urgent Photostat certified copy of this order,
                 if applied for, be furnished to the parties as early
                 as possible."


11. The plaintiff being aggrieved with the order      dated 23.06.2015, the

    plaintiff had preferred an appeal being FMA No. 3040 of 2015 and the

    Hon'ble Appellate Court had disposed of the appeal on 05.10.2015 by

    passing the following order :

                  "Having heard the learned senior counsel
                 appearing for the appellants and the learned
                 advocates for the respondents and in view of

nature of the dispute which includes various factual aspects including the issue whether there was concluded contract between the parties we are of the opinion that it was just on the part of the learned Judge not to entertain the issue in a writ proceeding. We asked the parties as to their willingness to submit themselves to arbitration in respect of the dispute and the parties agreed to such suggestion.

Accordingly, we give liberty to the parties to refer the matter for arbitration in accordance with law. We also make it clear that the appellants are at liberty to seek necessary interim relief in contemplation or during the procedure of the arbitration proceeding in

accordance with law with regard to their claim of alleged illegal deduction towards risk purchase loss, if so advised.

With the aforesaid observations the appeal is disposed of.

All issues are kept open."

12. As per the order passed by the Hon'ble Appellate Court, the plaintiff by

a letter dated 14.12.2015 requested the defendant for appointment of

Arbitrator but in the said communication, the plaintiff has made clear

that it is the stand of the plaintiff that there is no concluded contract

between the parties and the plaintiff will take up the issue before the

Learned Arbitrator. On receipt of the said letter, the defendant by a

communication dated 29.12.2015, informed the plaintiff that the

Controller of Stores is not the competent authority to appoint the

Arbitrator and directed the plaintiff to approach the General Manager of

Eastern Railway for appointment of Arbitrator. The plaintiff had

approached the General Manager of the Eastern Railway for

appointment of Arbitrator. The General Manager of the Eastern

Railway had appointed one Shri Sidharth Sharma, Chief Material

Manager as sole Arbitrator. The plaintiff by a letter dated 30.09.2015

informed the defendant that the appointment of the Arbitrator is

contrary to the Arbitration and Conciliation Act,1996 as amended in

2015 as the Arbitrator appointed by the defendant is one of the

employees of the defendant and requested for appointment of another

arbitrator and the plaintiff has also suggested the name of three

arbitrators.

13. As the defendant has not appointed another Arbitrator, the plaintiff has

filed an Arbitration Petition No. 43 of 2017 for appointment of

Arbitrator and during the hearing, the counsel for the defendant

assured the Court, that they will appoint an arbitrator within 30 days

as per the fifth schedule of the Arbitration and Conciliation Act, 1996

failing which the defendant shall forfeit its right to make any

appointment and it would be open for the petitioner to apply afresh for

appointment of arbitrator. In the meantime, the plaintiff has also filed

an application under Section 9 of the Arbitration and Conciliation Act,

1996 being AP No. 54 of 2017 and the Hon'ble Court had disposed of

the said application on 22nd February, 2017. Being aggrieved with the

order dated 22.2.2017, the plaintiff has filed an appeal being APO No.

92 of 2017 and the said appeal was disposed of on 5th April, 2017 by

passing the following order :

"Accordingly, the merits of the order impugned need not be gone into. The tenure of the order dated February 22, 2017 is limited to a period of a fortnight from date, whereupon it will lapse automatically and without reference to any Court. It will be open to the appellants herein to institute a suit before an appropriate forum and apply for interlocutory orders therein in accordance with law. Upon any interlocutory application being filed by the appellants herein in the proposed suit, the forum in seisin of the suit will be entitled to consider the same in accordance with law, not limited or constrained in any manner by the order impugned herein or influenced by the continuation of such order by the present order.

APO No. 92 of 2017 and GA No 1115 of 2017 are disposed of without any order as to costs."

14. The plaintiff being aggrieved with the order dated 05.04.2017 had

preferred an SLP but the same was dismissed on 11.08.2017.

thereafter, the plaintiff has filed the present suit.

15. The defendant has filed written statement and on the basis of the

pleadings and suggested issues, this Court has framed the following

issues :

"1. Whether the suit is maintainable in law?

2. Whether the plaintiff accepted the price variation clause in the tender document?

3. Whether the tender was in the teeth of the govt. policy to allow indigenous copper?

4. Whether the money deducted by Eastern Railway from the plaintiff company was for unjust financial enrichment?

5. Whether the plaintiff is entitled to a decree for Rs.1,74.40.566/- against the defendant?

6. Whether the plaintiff is entitled to interest as claimed on the decretal amount?

7. Whether the claim of the plaintiff is barred by limitation?

8. Whether there was a concluded contract between the parties?

9. Whether the plaintiff acted in breach of the terms of the contract by failing to supply the material?"

The plaintiff has examined one witness on his behalf and during

the examination of the plaintiff's witness altogether 31 documents were

exhibited being "Exhibit A to Exhibit EE".

16. The issue No. 1 is whether the suit is maintainable in law.

As per the case of the defendant, the plaintiff has filed the instant

suit against the defendant who is the Railways Authority but before

filing of the suit, the plaintiff has not issued notice under Section 80 of

the Code of Civil Procedure, 1908 nor the plaintiff has obtained leave to

file the suit dispensing notice under Section 80 of the Code of Civil

Procedure, 1908. The plaintiff relied upon the notice dated 24.12.2014

"Exhibit W". The Plaintiff submits that in the said notice, the defendant

was called upon to retract the letter under reply failing which the

plaintiff will be compelled to avail the appropriate recourse as

permissible under law and equity. The said notice is with reference to

the notice dated 27.11.2014 wherein the defendant has informed the

plaintiff that the defendant is entitled to a claim from the plaintiff for a

sum of Rs. 18,65,559/- and Rs. 1,55,74,996/- towards extra

expenditure incurred in risk purchase in terms of Clauses 2401, 2402

and 2403 of the IRS Conditions of the Contract. After issuance of the

notice dated 24th December, 2014, the Controller of Stores, Eastern

Railway has intimated the plaintiff for deduction an amount of Rs.

1,74,40,566/- on 16th February, 2015. Being aggrieved with the said

notice, the plaintiff had also filed a writ petition against the claim. The

Hon'ble Court had dismissed the said writ application by giving liberty

to the plaintiff to pursue their remedy before the Arbitral Tribunal in

accordance with law. The plaintiff had challenged the said order before

the Hon'ble Division Bench and the Hon'ble Division Bench by an order

dated 5th October, 2015 has given liberty to the parties to refer the

matter for arbitration in accordance with law. The defendant had

appointed the Chief Material Manager of Eastern Railway as Sole

Arbitrator but the plaintiff has raised objection on the ground that the

Arbitrator appointed by the Railway is the employee of the Railway and

is contrary to the Section 12(5) of the Arbitration and the Conciliation

Act, 1996 as amended in the year 2015. The plaintiff had filed an

arbitration petition before the High Court being AP No. 54 of 2017 for

appointment of Arbitrator and by an order dated 15th February, 2017,

the Hon'ble Court had directed the defendant to appoint the Arbitrator

within 30 days failing which the Appointing Authority shall forfeit its

right for appointment of Arbitrator and it would be opened for the

petitioner to apply afresh for appointment of Arbitrator. In the

meantime, the plaintiff had also filed another application being AP No.

54 of 2017 under Section 9 of the Arbitration and Conciliation Act,

1996 and the same was disposed of on 22nd February, 2017. Being

aggrieved with the said order, the plaintiff has preferred an appeal

being APO No. 92 of 2017 and in the appeal, the Hon'ble Division

Bench of the High Court by an order dated 5th April, 2017 given liberty

to the plaintiff to institute a suit before an appropriate forum and apply

for interlocutory orders in accordance with law. The plaintiff has

preferred an SLP but the same was dismissed and thereafter the

plaintiff has filed the instant suit.

Though the plaintiff has issued notice on 24th December, 2014

calling upon the defendant for recalling of the letters dated 27th

November, 2014, wherein the defendant had informed about their claim

against the plaintiff for payment of Rs. 18,65,569/- and Rs.

1,55,74,996.85/- being extra expenditure incurred in risk purchase in

terms of Clauses 2401, 2402 and 2403 of the IRS conditions of

contract.

The plaintiff had relied upon the Judgment reported in (2019)

13 SCC 142 (Y. Savarimuthu -vs- State of Tamil Nadu &Ors.), the

Hon'ble Supreme Court has held that :

"14. On a perusal of the notice dated 14-1-2000, it is clear that this is a legal notice sent by a lawyer of the appellant to the authorities concerned. It is not disputed that it was by registered AD and served upon the authorities. There is also no dispute that the cause of action is sufficiently set out in the said notice, which is the illegality of the partial termination of the contract on 16-12-1999. It was also made clear that though a writ appeal at that point of time was going to be filed against the writ petition dismissal, yet this would be a notice to take "appropriate legal action" against the State. There is no doubt, whatsoever, that more than two months have elapsed from the date of this notice, after which the suit has been filed. In fact, the suit was filed long after, on 12-9-2002. Quite apart from this, on 29-1- 2000 also, the letter of the appellant made it clear to the Divisional Engineer that not only is the partial termination bad in law but that the payments due for work would have to be made.

15. It is clear, therefore, that there is sufficient compliance with the provisions of Section 80 CPC as has been introduced by the Amendment Act introducing Section 80(3) into the statute book. The respondents' argument that Section 80 is not

expressly referred to and that the legal notice and letters were written prior to the disposal of the writ appeal have no legs to stand on. This is for the reason that a notice does not have to state the section under which it is made so long as the ingredients of sub-section (3) of Section 80 are met. It is admitted that there was no need for any legal notice before filing the writ appeal. The notice, therefore, that was sent on 14-1-2000, was only under Section 80 CPC in the event the writ appeal failed and a suit would have to be filed.

16. We are, therefore, of the view that the learned Additional District Judge's judgment was correct. In this view of the matter, we set aside the impugned judgment of the High Court and remit the matter to the High Court to dispose of the two appeals on merits. Further, considering this is a suit of the year 2002, we request the High Court to take up these appeals and dispose of the same at the earliest."

Notices dated 27th November, 2014 issued by the defendant

wherein the defendant has informed about their claim against the

plaintiff for payment of Rs. 18,65,569/- and Rs. 1,55,74,996.85/-

total amounting to Rs. 1,74,40,566/- are marked as Exhibits U and V

and the notice issued by the plaintiff is marked as Exhibit W. After

issuance of the said notice, the defendant had issued an intimation by

a letter dated 16th February, 2015 for recovery of the said amount and

thereafter the plaintiff has filed writ application and several

applications before the Hon'ble Court and subsequently by an order

dated 5th April, 2017, the Hon'ble Division Bench had given liberty to

the plaintiff to institute suit and accordingly the plaintiff has

instituted the suit, thus issue no. 1 is decided in favour of the plaintiff

and against the defendant.

17. Issue No. 7 is whether the claim of the plaintiff is barred by limitation?

As per the case of the defendant, an amount of Rs. 63,77,229/-

was adjusted on 25th August, 2015 and the plaintiff has filed the suit in

the year 2019, thus the suit filed by the plaintiff is barred by limitation.

The defendant has issued two notices to the plaintiff on 27th November,

2014, out of which, in one notice the defendant has claimed an amount

of Rs. 18,65,569/- and in another notice, the defendant had claimed

Rs. 1,55,74,996.89/- being the extra expenditure incurred towards risk

purchase in terms of Clauses 2401,2402 and 2403 of the IRS condition

of contract. Immediately after receipt of the said notices, the plaintiff

had issued a notice dated 24th December, 2014 calling upon the

defendant to recall the said notices failing which, the plaintiff will avail

appropriate recourses as permissible under law. Inspite of receipt of the

notice, the defendant had issued notice on 16th February, 2015, for

deducting an amount of Rs. 1,74,40,566/-. Being aggrieved with the

notice dated 16th February, 2015, the plaintiff has filed writ application

and the said writ application was disposed on 23rd June, 2015 but till

date no amount was deducted/recovered from the plaintiff. Being

aggrieved with the order dated 23rd June, 2015, the plaintiff has

preferred an appeal being FMA No. 3040 of 2015 but during the

pendency of the appeal, the defendant had recovered an amount of Rs.

63,77,229/- from the plaintiff. On 5th October, 2015, the said appeal

was disposed of by giving liberty to the parties to refer the matter to the

arbitration and all issues were kept open. Thereafter also the plaintiff

has initiated several proceedings before the Hon'ble High Court and

finally by an order dated 5th April, 2017, the Hon'ble Division Bench

has granted liberty to the plaintiff to institute suit accordingly the

plaintiff has instituted the present suit. During the pendency of appeal,

the defendant had again recovered an amount of Rs. 1,10,63,335/-

from the plaintiff. Since after the issuance of notices dated 27th

November, 2014, the plaintiff has initiated several legal proceedings

and during the pendency of the proceedings before the Hon'ble Court

against the said recovery, the defendant has recovered the amount on

two occasions. Thus, this Court finds that the suit filed by the plaintiff

is not barred by limitation.

Issue No.7 is decided in favour of the plaintiff and against the

defendant.

18. Issue No. 8 whether there was a concluded contract between the

plaintiff and defendant.

The defendant had issued a tender Notice dated 4th June, 2013 for

procurement of jointless grooved copper contact wire made out of

continuous cast copper wire rods. The plaintiff has participated in the

said tender process. At the time of submission of the tender document,

the plaintiff had reserved its price variation clause which contained in

the tender Notice and the plaintiff had also enclosed a separate price

variation clause along with bid. On 24th October, 2013, the defendant

had issued Letter of Acceptance to the plaintiff for supply of 186.184

MT for supply of jointless grooved copper contract wire 107 sq.mtr. In

the Letter of Acceptance, it is mentioned that "Contract is concluded by

this acceptance. A formal purchase order showing all details is under

issue. Please convey your unqualified acceptance to this offer by return

fax No. (033) 22302553".

On receipt of the offer letter, the plaintiff has submitted its

representation on 29th October, 2013 intimating the defendant that as

per tender document the delivery schedule was 50% within 04 months

and balance within 04 months thereafter. The plaintiff has proposed for

changing the Clause as follows : "Delivery to commence within 45 days

at the rate of 63 MT per month and to be completed within three months

thereafter." The plaintiff has also inform the defendant about the price

variation clause and mentioned that: "We had in our offer very clearly

recorded that the Custom Duty factor shall be 'one' as also Custom Duty

factor CD2 shall be 'one'." In reply to the request of the plaintiff, the

defendant by a letter dated 19th November, 2013, accepted the delivery

period as proposed by the plaintiff but with regard to the Custom Duty

factor, the defendant accepted the request made by the plaintiff which

are marked as Exhibits E & F.

Instead of confirming the unconditional acceptance of Advance

Acceptance letter of the plaintiff, the defendant had issued two work

orders dated 17.12.2013 for supply of 19.664 MT 165.416 MT of HDGC

Contact wire respectively. On receipt of the work orders, the plaintiff

vide its letter dated 06.01.2014 informed the defendant that "However,

in view of our very long association with Railways, we are going to

execute this order under protest. We may take up this issue at suitable

time through arbitration." The said letter is marked as Exhibit 'J'.

On 17th February, 2014, the plaintiff sent a letter to the defendant

informing the defendant that "the plaintiff already advised the

defendant that these orders are placed on plaintiff not in conformity

with the offer and the plaintiff shall suffer heavy losses in these orders.

We would therefore like to execute these orders if our payments are not

delayed".

On 3rd March, 2014, the plaintiff has again sent a letter to the

defendant informing the defendant. Both letters are marked as Exhibits

"K & L".

On receipt of the letters dated 06.01.2014, 17.02.2014 and

03.03.2014, the defendant has not sent any reply to the plaintiff and

accordingly, the plaintiff had again sent a letter on 24.03.2014 stating

that "the plaintiff in its offer in the said tender explained that the factors

CD1 and CD2 as one but the defendant did not accept the offer, placed

order with factor CD1 as 1.054. The plaintiff explained to the defendant

that the plaintiff will suffer heavy losses if the plaintiff agree to supply

with factor CD1 as 1.054 instead of one. The plaintiff further informed

that due to long association with the defendant, the plaintiff agreed to

supply subject to confirmation of funds but the defendant has not

confirmed the availability of fund and thus, the plaintiff is not able to

execute the order and informed the defendant to treat the same as

cancel. The Letters are marked as Exhibits "M & N".

The defendant had sent a letter to the plaintiff on 17.04.2014 but

the said letter was not placed either by the plaintiff or by the defendant

but on receipt of the said letter, the plaintiff has sent a reply to the

defendant on 21.04.2014 which states that "The order can be executed

and supply of material can be arranged to enable the defendant to

execute target work, provided that orders are as per the plaintiff's offer

i.e. both Factors CD1 & CD2 are accepted as 'One' for purpose of PVC."

Thereafter the defendant by a letter dated 01.05.2014 in reference

to the letters dated 03.03.2014, 24.03.2014, 17.04.2014 and

21.04.2014 informed the plaintiff as follows:

"The defendant had mentioned that as far as the provision of fund is concerned it is well known to the plaintiff that unless and until clear fund provision is ensured, Railways do not issue any formal Purchase Order and thus seeking clarification in regard to availability of fund is not understood by the office of the defendant. Therefore the plaintiff was requested to confirm within seven days from the date of the receipt of this letter, failing which no further reference will be made and the defendant will be compelled to initiate Risk Purchase Action at the risk and cost of your concern including other legal proceedings."

On 13.06.2014, the defendant had sent another letter to the

plaintiff which states that "in connection to letters sent by the

defendant to the plaintiff, and various purchase orders made by the

defendant, the defendant had issued/floated against the plaintiff one

Risk Purchase Tender in regards with tender No. 16/11/5028 for total

quantity of 185.080 MT and the Risk Purchase Tender is said to be due

on 17.07.2014. The plaintiff was asked that is case the plaintiff is

interested to quote in the aforesaid Risk Purchase Tender then as per

extant rule, the plaintiff must submit its offer along with Security

Deposit Money for 10% of the total value of the offer failing which your

offer will be summarily rejected without making any back reference to

the plaintiff."

As per the contention of the defendant, the plaintiff has invoked

the provisions of arbitration clause and the plaintiff has also agreed to

supply of materials as per the work orders and thus the act of the

plaintiff proves that there is a concluded contract between the parties.

In the letter dated 6th January, 2014, Exhibit-J, it was the specific

contention that the due to the long association with Railways, the

plaintiff is going to execute the order under protest and the plaintiff

will take up the issue at a suitable time through arbitration. The

plaintiff has also requested the defendant to confirm that fund shall

be available for payment against proposed supply. The defendant has

not given any reply to the said requests and again on 21st April, 2014,

the plaintiff informed the defendant that the plaintiff is still ready to

arrange supply of materials provided the orders are placed by treating

both factors CD1 and CD2 are accepted as 'one' which is marked as

Exhibit O.

Section 10 of the Contract Act, 1872 postulates that all

agreements are contracts if they are made by free consent of parties

competent to contract, for a lawful consideration and with a lawful

object, which are not expressly declared to be void and as such a

transaction to constitute a contract must be preceded by offer of an

proposal by one party and acceptance of the same by the other party.

A valid contract cannot be constituted by the act of one party

and that there must be a valid offer and valid acceptance by the

parties. On analysing the provisions of Sections 7, 8 and 9 of the

Contract Act, 1872, it can be said that if a party to contract makes an

offer and the same is accepted in an absolutely unqualified manner by

the other party then the contract becomes a valid and complete

contract. In a written contract containing signatures of both the

parties is not sine quo non to constitute a valid contract and

executable contract. All those are essential that there should be a

valid offer, unqualified acceptance and agreement of the parties to

abide by the terms and conditions and perform their respective part of

contract.

In this case as per tender notice published by the defendant, the

plaintiff has participated in the said tender. The defendant has issued

letter of acceptance in favour of the plaintiff which is marked as

Exhibit -D. In the said letter of Acceptance, it is mentioned that

"Contract is concluded by this acceptance. A formal purchase order

showing all details is under issue. Please convey your unqualified

acceptance to this offer by return Fax."

The plaintiff has not submitted its unqualified acceptance and

on the other hand, the plaintiff has submitted its request intimating

that the changes made in the letter of Acceptance is not acceptable

and requested the defendant to accept the delivery schedule given in

the tender document and price variation Clause be accepted as given

in their offer. The defendant has accepted the request of the plaintiff

with respect of delivery period but has not accepted the price variation

clause. The plaintiff has not accepted the price variation clause but

the defendant had issued two purchase orders to the plaintiff. By a

letter dated 6th January, 2014, Exhibit-J, the plaintiff has agreed to

execute purchase order "under protest" and also made clear in the

said letter that the plaintiff will take up the issue at a suitable time

through arbitration.

It is found from record, the plaintiff has time to time change its

decisions through various letters being Exhibits -J, K, L, M, N and O

but had never submitted its unqualified acceptance as required by the

defendant in its letter of acceptance.

In the case reported in AIR 2021 SC 341 (Padia Timber

Company (P) Ltd. -vs- The Board of Trustees of Visakhapatnam

Port Trust), the Hon'ble Supreme Court held that :

"56. It is a cardinal principle of the law of contract that the offer and acceptance of an offer must be absolute. It can give no room for doubt. The offer and acceptance must be based or founded on three components, that is, certainty, commitment and communication. However, when the acceptor puts in a new condition while accepting the contract already signed by the proposer, the contract is not complete until the proposer accepts that condition, as held by this Court in Haridwar Singh v. Bagun Sumbrui & Ors. AIR 1972 SC 1242. An acceptance with a variation is no acceptance. It is, in effect and substance, simply a counter-proposal which must be accepted fully by the original proposer, before a contract is made.

57. In Union of India v. Bhim Sen Walaiti Ram (1969) 3 SCC 146, a three-Judge Bench of this Court held that acceptance of an offer may be either absolute or conditional. If the acceptance is conditional, offer can be withdrawn at any moment until absolute acceptance has taken place.

58. In Jawahar Lal Burman v. Union of India (supra), referred to by the High Court, this Court held that under Section 7 of the Contract Act acceptance of the offer must be absolute and unqualified and it cannot be conditional. However, in the facts and circumstances of that case, on a reading of the letter of acceptance as a whole, the appellant's argument that the letter was intended to make a substantial variation in the contract, by making the deposit of security a condition precedent instead of a condition subsequent, was not accepted.

In the present case also the plaintiff has not communicated its

unqualified acceptance and in all communications, the plaintiff has

put one or the other conditions which the defendant has not accepted,

thus there is no concluded contract between the plaintiff and the

defendant.

In view of the above, issue No. 8 is decided in favour of the

plaintiff and against the defendant.

19. Issue No. 2 whether the plaintiff accepted the price variation clause in

the tender document.

The plaintiff had submitted its bid on 22nd June, 2013. At the time

of submission of tender documents, the plaintiff has indicated the

reservations and non-acceptance of the Clause. The plaintiff has also

enclosed a separate price variation clause along with the tender

documents which is marked as Exhibit-C without any objection and the

defendant has admitted the said document. The plaintiff has

categorically mentioned in the said document with regard to delivery

period and price variation clause but the defendant had considered the

delivery period but had not considered the price variation Clause

though the plaintiff time and again requested the defendant and in

none of the request, the plaintiff has accepted the price variation

Clause, thus issue No. 2 is decided in favour of the plaintiff and against

the defendant.

20. Issues Nos. 3, 4, 5 and 6 are taken up together.

Issue No. 3 whether the tender was in the teeth of the Govt. policy

to allow indigenous copper.

Issue No. 4 is whether the money deducted by Eastern Railway

from the plaintiff company was for unjust financial enrichment.

Issue No. 5 is whether then plaintiff is entitled to a decree for Rs.

1,74,40,566/-.

Issue No. 6 is whether plaintiff is entitled to interest on the

decretal amount.

The defendant by way of two letters dated 27th November, 2014

informed the plaintiff that the defendant is entitled to claim from the

plaintiff for a sum of Rs. 18,65,569/- and Rs. 1,55,74,996.85/-

respectively towards extra expenditure incurred in risk purchase in

terms of Clauses 2401, 2402 and 2403 of the IRS Conditions of

Contract governing the said contract. Subsequently, by an notice

dated 16th February, 2015, the Controller of Stores, Eastern Railway

informed the plaintiff for deducting an amount of Rs. 1,74,40,566/- as

risk purchase loss and during the pendency of the proceeding before

the Hon'ble Court, the defendant had deducted/recovered the said

amount from the plaintiff.

The defendant had recovered the said amount in terms of

Clause 2401, 2402 and 2403 of IRS Conditions of Contract. Clauses

2401, 2402 and 2403 reads as follows :

"2401. Whenever am claim or claims for payment of a sum of money arises out of or under the contract against the Contractor, the Purchaser shall be entitled to withhold and also have a lien to retain such sum or sums in whole or in part from the security if any, deposited by the Contractor and for the purpose aforesaid, the Purchaser shall be entitled to withhold the said cash security deposit or the security, if any, furnished as the case may be and also have a

lien over the same pending finalisation or adjudication of any such claim. In the event of the security being insufficient to cover the claimed amount or amounts or if no security has been taken from the Contractor, the Purchaser shall be entitled to withhold and have lien to retain to the extent of the such claimed amount or amounts referred to supra, from any sum or sums found payable or which at any time thereafter may become payable to the Contractor under the same contract or any other contract with the Purchaser or the Government pending finalization or adjudication of any such claim.

It is an agreed term of the contract that the sum of money or moneys so withheld or retained under the lien referred to above, by the Purchaser will be kept withheld or retained as such by the Purchaser till the claim arising out of or under the contract is determined by the Arbitrator (if the contract is governed by the arbitration clause) or by the competent court as prescribed under Clause 2703 hereinafter provided, as the case may be, and that the Contractor will have no claim for interest or damages whatsoever on any account in respect of such withholding or retention under the lien referred to supra and duly notified as such to the otherwise.

2402. For the purpose of Clause 2401, where the Contractor is a partnership firm or a limited company, the purchaser shall be entitled to withhold and also have a lien to retain towards such claimed amount or amounts, in whole or in part from any sum found payable to any partner/limited company, as the case may be, whether in his individual capacity or otherwise.

2403. Lieu in respect of Claims in other Contracts - Any sum of money due and payable, to the Contractor (including the security deposit, returnable to him) under the contract may withhold or retain by way of lien by the purchase or Government against any claim of the Purchaser or Government in respect of payment of a sum of money arising out of or under any other contract made by the Contract with the Purchaser or Government.

It is an agreed term of the contract that the sum of money so withheld are retained under this clause by the Purchaser or Government will be kept withheld or retained as such by the Purchaser or Government till his claim arising out of in the same contract or any other contract is either mutually competent Court under Clause 2703 hereinafter provided, as the case may be, and that the Contractor shall have no claim for interest or damages whatsoever on this account or on any other ground in respect of any sum of money withheld or retained under this clause and duly notified as such to the Contractor."

The issue with regard to whether there was a concluded

contract between the plaintiff and the defendant is decided in favour

of the plaintiff being issue No. 8 and this Court has come to the

conclusion that there was no concluded contract between the plaintiff

and the defendant. As there was no concluded contract between the

plaintiff and the defendant thus the amount recovered by the

defendant in terms of Clauses 2401, 2402 and 2403 of IRS Conditions

of Contract is not applicable in the case of the plaintiff, thus the

amount recovered by the defendant is illegal and is liable to be

returned to the plaintiff.

Accordingly, issue Nos. 3, 4, 5 and 6 are decided in favour of

plaintiff and against the defendant.

In view of the above, the defendant is directed to return the

amount of Rs. 1,74,40,566/-. The amount of Rs. 63,77,229/- shall

carry interest @18% per annum with effect from 25th August, 2015

and Rs. 1,10,63,335/- shall carry interest @ 18% per annum with

effect from 23rd March, 2017 till the realization of the said amount.

21. CS 159 of 2019 is thus disposed of. Decree will be drawn accordingly.

(Krishna Rao, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter