Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Essal-Rre Enterprises (Jv) vs The Coal India Limited & Ors
2023 Latest Caselaw 3630 Cal

Citation : 2023 Latest Caselaw 3630 Cal
Judgement Date : 29 May, 2023

Calcutta High Court (Appellete Side)
M/S Essal-Rre Enterprises (Jv) vs The Coal India Limited & Ors on 29 May, 2023
    1                     IN THE HIGH COURT AT CALCUTTA
29.05.2023               CONSTITUTIONAL WRIT JURISDICTION
  n.b/Ali
  VB/ Ct 8                       APPELLATE SIDE

                                   MAT 941 of 2023
                                   IA No.: CAN/1/2023

                             M/s Essal-Rre Enterprises (JV)
                                         Vs.
                             The Coal India Limited & Ors.

                         Mr. Kishore Datta, Sr. Advocate
                         Ms. Sumita Show,
                         Mr. Rahul Kumar Siingh
                                                    ... For the appellant.
                         Mr. Aniruddha Chatterjee,
                         Mr. Syed Nurul Arefin,
                         Mr. S. Mal.
                                       .... For the respondents (ECL)

By a letter of agreement for the work of extraction

of Coal from Coal mine and back filling by way of re-

handling of OB from the New Kenda OC Patch quarry

Nos. 1 and 2 of Kendra area, the appellant obtained the

work order of the above mentioned job to be concluded

by 4745 days. Subsequently, on 2 nd November, 2016 the

formal work order was issued in favour of the appellant.

In the mean time, a writ petition was filed against the

ECL over the said work in the nature of Public Interest

Litigation. Subsequently, by an order passed by the

Division Bench presided over by the Hon'ble The Chief

Justice, the said writ petition was transferred to

National Green Tribunal. The learned National Green

Tribunal, Kolkata initially extended the order of

injunction passed by this court in the aforementioned

writ petition No 2161(W) of 2016 and subsequently the

interim order was vacated. All such incidents happened

during 2016-2017.

The appellant filed WPA 28663 of 2022 assailing

an order of banning and termination dated 2 nd

December, 2022 issued by the ECL for poor performance

and continuous failure to perform despite several letters

issued by ECL by the appellant/petitioner.

On due consideration of rival submissions and

materials on record the writ court dismissed WPA 28663

of 2022.

Hence the instant appeal.

It is submitted by Mr. Kishore Datta, learned

Senior advocate on behalf of the appellant/petitioner

that after execution of the contract the petitioner wrote

series of letter dated 18th June, 2016, 1st March, 2017,

2nd March, 2017, 3rd March, 2017, 1st April, 2017 and 8th

April, 2017 stating inter alia, that the appellant

company could not commence with the quarry work of

Coal due to non supply of the land, obstruction by

villagers, and also several other grounds which were in

the hands of ECL authority to address, but the ECL did

not provide the appellant congenial provision for

execution of such work. Subsequently, on 17 th May,

2022 and 5th/7th April, 2022 the respondent issued two

show cause notices regarding poor performance against

the targeted OB of Coal production, non commissioning

of work and overall poor financial condition of the

company resulting in heavy loss to ECL. No reply was

given to such show cause notices by the petitioner. It is

submitted by Mr. Datta, learned advocate for the

appellant that the appellant did not receive the show

cause notices dated 17th May, 2022 and 5th/7th April,

2022. Again on 21st August, 2022 another show cause

notice was issued to the appellant directing him to show

cause as to why an order of banning of business of the

said company would not be issued. The petitioner made

a detailed reply on 29th August, 2022 stating inter alia,

that with regard to mining operation of quarry the

company is ready to deploy the excavanger for removal

of over burden and coal extraction purpose immediately.

Subsequently, on 2nd February, 2022 the impugned

notice was issued terminating the contract and imposing

banning order which was impugned in the writ petition.

Mr. Datta submits that when a contractor is

banned from taking part in any tender process, such

black listing tarnishes his reputation. The state cannot

ban the impugned contract arbitrarily without

objectively considering the facts and circumstances of

the case of the appellant. On this point, he also refers to

another decision of the Hon'ble Supreme Court in M/s

Erusian Equipment & Chemicals Ltd. Versus State of

West Bengal and Another reported in (1975) 1 SCC 70

and Kulja Industries Limited Versus Chief General

Manager, Western Telecom Project Bharat Sanchar

Nigam Limited and Others reported in (2014) 14 SCC

731.

It is submitted by the learned senior counsel on

behalf of the appellant that the impugned order is devoid

of any reason, the Hon'ble Writ Court failed to

appreciate such aspect and dismissed the writ petition.

Hence, it is prayed on behalf of the appellant that the

instant appeal may be admitted and impugned order

dated 2nd December, 2022 may be stayed. It is also

submitted by Mr. Datta that there is extreme urgency of

the matter because the ECL authority has already

floated tender and the date is fixed today at 3.00 p.m.

for opening of the tender.

Mr. Aniruddha Chatterjee, learned advocate for

the ECL/respondent, on the other hand submits that

the letter dated 19th August, 2022 issued by the ECL in

favour of the petitioner is for all practical purpose the

letter of termination the petitioner did not challenge the

said letter by filing any writ petition. Subsequent letter

dated 2nd December, 2022 is practically banning order

and not the letter of termination. With the letter of

termination not being challenged, the petitioner had no

right to challenge the impugned order dated 2 nd

December, 2022 and the learned Writ court rightly

passed the impugned order. Mr. Chatterjee next has

placed a minute of the meeting between respondents

and the appellant held on 7 th September, 2022, i.e. after

issuance of the so called letter of termination dated 19 th

August, 2022. In the said meeting the appellant clearly

and unequivocally admitted that they failed to carry out

the order and for such purposes no responsibility was

placed upon the ECL.

According to Mr. Chatterjee that the order dated

2nd December, 2022 was passed as the follow up action

of the meeting dated 7th September, 2022.

Mr. Chatterjee next takes us to the General Terms

and Condition (GTC) of ECL. Rules 6.2 States as

follows:-

"6.2. In the event of the contractor's failure to comply with the required progress in terms of the agreed time and progress chart or to complete the work and clear the site on or before the date of completion of contractor or extended date of completion, he shall without prejudice to any other right or remedy available under the law to the company on account of such breach, shall become liable to pay for penalty as under

a) If the average daily progress of work during the calendar months is less than the stipulated rate indicated in the detail tender notice penalty as detailed below will be levied.

i) If the average daily progress of work executed during the calendar month is more than 80% and less

than 100% of stipulated rate of progress, penalty equal to 10% of the contract value of the short fall in work shall be levied.

ii) If the average daily progress of work executed during the calendar month is less than 80% of stipulated rate, penalty equal to 20% of contract value of the short fall in work shall be levied.

iii) The aggregate of the penalties so levied shall not exceed 10% of the total contract value.

Penalty will be calculated every month and withheld. The contractor shall be allowed to makeup the shortfall in the succeeding months within the stipulated time of completion.

The company may waive the payment of compensation, depending upon merit of the case, on request received from the contractor if the entire work is complete within the date as specified in the contract or as validity extended without stipulating any penalty."

He also refers to clause 10 which is quoted below:-

"10. Termination, suspension, Cancellation and Foreclosure of the contract.

The company shall, in addition to other remedial steps to be taken as provided in the conditions of contract, be entitled to cancel the contract in full or in part, if the contractor:-

a) makes default in proceeding with the works with due diligence and continues to do so even after a notice in writing from the Engineer-in- charge, then on the expiry of the period as specified in the notice.

OR

b) Commits default/breach in complying with any of the terms and conditions of the contract and does not remedy it or fails to take effective steps for the remedy to the satisfaction of the Engineer-in-charge, then on the expiry of the period as may be specified by the Engineer-in charge in a notice in writing.

OR

c) Fails to complete the work or items of work with individual dates of completion, on or before the date/dates of completion or as extended by the company, then on the expiry of the period as may be specified by the Engineer-in-charge in a notice in writing."

Mr. Datta, on the other hand refers to

Clause 10.1 (a) of the GTC and submits that as per the

said clause a contract may be terminated only on the

ground of the contractor being insolvent or under

liquidation etc. and for no other purpose the contract

can be terminated. It is also contended by Mr. Datta that

the documents filed on behalf of ECL today cannot be

looked into as it was not supported by an affidavit in

support of his contention. He refers to a decision of

Bharat Singh & Ors. Vs. State of Haryana & Ors.

reported in (1988) 4 SCC 534.

We have duly considered the submissions made

by the learned counsel for the parties. We have also

considered the impugned judgment passed by the Writ

Court. On factual score, it is asserted that after

execution of the contract there was initially some

problem with regard to land excavation work and filling

of OB upto 2017 due to pendency of some cases.

Subsequently, it is asserted from the minutes of the

meeting dated 17th September, 2022 that all such

glitches were duly taken care of by the ECL and there

was no responsibility for the ECL to carry out its part of

performance. On the contrary it was the obligation of the

appellant to commence the work. From the report of the

ECL. It is found that the appellant failed to perform his

part. The Hon'ble Writ court correctly found that even

after issuance of notice dated 19th August, 2022 the

petitioner was given opportunity of hearing and bipartite

meeting was held on 7th September, 2022 where the

appellant admitted his failure. The ECL letter dated 22 nd

July, 2022 clearly states that 21.47 acres of land was

made available to the appellant in quarry No. 1 for

deployment et of machine. None performance or failure

to perform his part is admitted by the petitioner and,

therefore, we are not in a position to Spil ink poses over

the judgment passed by the Writ Court.

In view of the above discussion, the instant appeal

being devoid of any merit is dismissed.

(Bibek Chaudhuri, J.)

I have perused the judgment/order of my learned

brother and have agreed with the decision taken except

the issue of banning the writ petitioner/appellant of

business for a period of three years as per Clause 2 (V)

(b) of guideline for banning of business. It appears from

Clause 6.25 of General Terms and Conditions where

defaulting contractors may be banned from participating

in future tenders for a minimum period of one year, and

there is no mention of outer limit. Although by the said

Clause ECL Authority may ban a contractor from

participating in future tenders but it is to be kept in

mind that as banning is a penalty which deprives a

contractor to participate in tender process and tarnishes

his reputation abundant caution should be taken and

special reasons should be cited if the ban order is to be

imposed for a considerable period. First of all

Administrative authority should be slow in passing ban

orders/black listing orders and secondly sufficient

grounds should be there if the ban order is more than

the minimum period as provided in the rules.

The Hon'ble Supreme Court in the case of M/s

Erusian Equipment & Chemicals Ltd. Versus State of

West Bengal and Another (1975) 1 SCC 70 the

Hon'ble Supreme court observed as follows:-

"17. The Government is a Government of laws and not of men. It is true that neither the petitioner nor the respondent has any right to enter into a contract but they are entitled to equal treatment with others who offer tender or quotations for the purchase of the goods. This privilege arises because it is the Government which is trading with the public and the democratic form of Government demands equality and absence of arbitrariness and discrimination inn such transactions. Hohfeld treats privileges as a form of liberty as opposed to a duty. The activities of the Government have a public element and, therefore, there should be fairness and equality. The State need not enter into any contract with any one but if it does so, it must do so fairly without discrimination and without unfair procedure. Reputation is a part of a person's character and personality. Blacklisting tarnishes one's reputation."

Upon considering the decision of the Hon'ble

Supreme Court and the facts of the case it appears to

me that the order of ban for three years debarring the

writ petitioner/appellant is excessive. No special reason

is cited as to what prompted the ECL Authority to

impose a ban of three years which is thrice the

minimum punishment. Although ECL Authority is to act

in the interest of public with regard to coal but as it is

'State' within meaning of Article 12 of the Constitution of

India it should not be harsh. It should allow

organizations to participate in the tender process and do

business in accordance with the rules and give

reasonable chance to rectify if mistake is made.

In the facts and circumstances, I am of the view

that the period of ban order issued by respondent/ECL

with regard to appellant should be reduced. Although

the usual process is to remit the matter back to

Respondent Authority to reconsider the period of ban

and reduce the same but as considerable period has

passed from the date of such ban order and the

Appellant/Writ Petitioner has already suffered to some

extent with regard to participation in tender such

reference will further delay the matter. Hence in the

interest of justice the period of ban imposed upon the

Appellant/Writ Petitioner with regard to participation in

tender is reduced to one year. I however concur with

other contents of the order of my learned brother.

(Biswaroop Chowdhury, J)

As there is a difference of opinion between us

with regard to a particular issue the matter is

referred to the Hon'ble The Chief Justice for

assigning the case to a learned third Judge.

(Biswaroop Chowdhury, J) (Bibek Chaudhuri, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter