Citation : 2023 Latest Caselaw 3532 Cal
Judgement Date : 18 May, 2023
IN THE HIGH COURT AT CALCUTTA
Constitutional Writ Jurisdiction
Appellate Side
Present:
The Hon'ble Justice Jay Sengupta
WPA 28320 of 2022
Pitambar Flour Mills Private Limited & Anr.
Versus
State of West Bengal & Ors.
For the petitioner : Mr. Ashok Banerjee
Mr. Ramesh Dhara
Ms. Mousumi Choudhury
.....Advocates
For the State : Mr. Nilotpal Chatterjee
Ms. Adreeka Pandey
.....Advocates
Heard lastly on : 23.02.2023
Judgment on : 18.05.2023
Jay Sengupta, J.:
1. This is an application under article 226 of the Constitution
of India, inter alia, praying for directions upon the respondent
to withdraw or cancel or rescind the decision of the
respondent authority rejecting the petitioners'
representation for re-inspection of the Flour Mill.
2. Mr. Banerjee, learned senior counsel appearing on behalf of
the petitioner, submitted as follows. The petitioner no. 2 was a
director of the petitioner no. 1 company. The petitioners were
engaged in the business of conversion of wheat into 45
atta/wholemeal atta in the District of Howrah. Pursuant to
notifications issued by the competent authority from time to time,
the petitioner's firm was selected as Flour Mill of the respondent
in the District of Howrah. The West Bengal Public Distribution
Dystem (Empanelment of Flour Mill and Milling of Fortified
atta/wholemeal atta) Guidelines, 2017 was framed in pursuance
of clauses 36 and 37 of the Rural Control Order of 2013 and
clauses 33 and 34 of the Urban Control Order. For the present
engagement, after a notification was published for empanelment
of Flour Mill, the petitioner company applied for the same and the
concerned authorities issued a certificate about fitness of the
concern. After that an inspection notice was given. The
representatives of the respondent authorities came to inspect the
Flour Mill. However, one machine developed a problem and could
not function. Instead of observing the working for an hour, as
required, the Mill was made to operate for half an hour. When the
petitioner's men took up the issue with the inspectors, it was
understood that the accidental break in the operation of the
machine would not be taken into consideration for fixing the
allocation. The petitioners made a representation before the
respondent authorities for the re-inspection of the flour mill.
However, the same was not done. An order of empanelment was
passed on 23.02.2022. After that a list was published of some of
the empanelled flour mills giving out their provisional allocations.
The petitioner company had the lowest allocation. No basis was
cited for making such a low allocation. Thereafter, a
representation was given. In spite of re-inspection being ordered
to several other flour mills on their request, no re-inspection was
done in respect of the petitioner company. Besides, the reports
filed on behalf of the State respondents were affirmed true to
knowledge. That was obviously not proper as the deponent could
not have vouched for all those facts to be true to knowledge. In
fact, the two reports were quite contradictory. While in the first
report the petitioner's application and an inspection report were
annexed recording satisfaction regarding operation of the
machinery, in the second report a question was posed as to
whether proper machines were installed at the said flour Mill. It
was an admitted position that the petitioner made its application
for re-inspection before the empanelment and execution of the
agreement. This was quite in keeping with paragraph 10 of the
Guidelines. Thus, there could be no bar to have such a re-
inspection ordered. Denying re-inspection and arbitrarily giving
lower allocation of wheat to the petitioner could not be accepted.
3. Ms. Adreeka Pandey, learned counsel appearing on behalf
of the State, submitted as follows. First, the petitioner had no
right to re-inspection. As regards the prayer in the writ petition of
not to touch the allocation, the contract between the parties and
the Guidelines did not warrant fixing of such allocation. The
entities that were inspected upon their request were those which
could not be empanelled for some reason or the other. That is
why re-inspection was necessary. But, the petitioner was
empanelled and an agreement was entered into with it. That is
why there was no need for a re-inspection. The petitioner could
not produce any document to show that a machine had broken
down. Inspection was done properly and the petitioner's
representative signed on the report. Therefore, there could not be
any question on the sequence of events during the inspection.
Clause 5 of the agreement contained certain provisions and the
petitioner was bound by them. Therefore, the petitioner could
neither claim re-inspection or a particular amount of quota. In
fact, reduction of allocation was there, inter alia, because a new
Mill was added. In fact, allocation would also depend on the quota
for the particular State fixed by the Central Government. Strong
reliance was placed on clause 10 of the Guidelines, particularly
sub-clause (2) and the proviso. From all these, it was abundantly
clear that the petitioner neither could claim to have right to a
particular quota of wheat nor any claim of re-inspection as of
right. If such re-inspection were allowed without sufficient
grounds, floodgates would open. It was germane to mention that
the petitioner had not challenged the vires of the Guidelines.
4. I heard the learned counsels for the parties and perused
the petition and the affidavits.
5. The prime contention of the petitioners is that in spite of re-
inspection being ordered to several other flour mills on their
request, no re-inspection was done in respect of the present
petitioner company. To this, the pointed reply of the respondent
authorities was that the entities that were inspected upon their
request were those which could not be empanelled for some
reason or the other. That is why re-inspection was necessary. But
the petitioner was empanelled and an agreement was entered into
with it. Therefore, there is no discrimination or arbitrariness in
this as those others were standing on a different footing.
6. In any event, the petitioner did not have any right to re-
inspection. Pertinently, in the instant case the petitioner's
representative purportedly signed on the report.
7. Secondly, neither the contract between the parties nor the
relevant Guidelines warrant fixing of a particular allocation.
Therefore, the petitioners could not even claim a right to a
particular allocation or quota of wheat. A reference may be made
to the proviso to Clause 10(2) of the Guidelines.
8. There is no place for encouraging monopolies either in
distribution of Government largesse or in the matter of public
engagement or employment. If the State comes up with guidelines
or policies which are in tune with the above, Courts would loathe
interfere with the same.
9. As has been pointed out by the learned counsel for the
State, in the particular case there was a reduction of allocation as
a new mill was added in the array of flour mills. In fact, allocation
would also depend on the quota for a particular State fixed by the
Central Government. All these vindicate the proposition that the
petitioners cannot claim right to a particular quota or allocation
of wheat.
10. Therefore, I do not find any infirmity in the impugned
decision.
11. Accordingly, the writ petition is dismissed.
12. However, there shall be no order as to costs.
13. Urgent photostat certified copies of this judgment may be
delivered to the learned Advocates for the parties, if applied for,
upon compliance of all formalities.
(Jay Sengupta, J.)
S.M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!