Citation : 2023 Latest Caselaw 3436 Cal
Judgement Date : 16 May, 2023
16.05.2023
Item No.02
Court No.6.
S. De
M.A.T. 875 of 2023
with
I.A. No. CAN/1/2023
Sri Sambhu Das.
Vs
Goutam Dey.
Mr. Debojyoti Basu,
Mr. Tanmoy Sett,
Mr. Pran Gopal Das,
...for the appellant.
Mr. Alok Kumar Ghosh,
Mr. Swapan Kr. Debnath,
...for the K.M.C.
Mr. Anirban Majumder,
Mr. Somnath De,
...for the respondent/writ petitioner.
By consent of the parties the appeal and the
connected application are taken up together for
hearing.
An order dated May 3, 2023, interim in nature
in the sense that the writ petition on which such order
was passed by the learned Single Judge, is still
pending, is under challenge in this appeal.
The appellant as developer had constructed a
building without obtaining sanctioned plan from the
Corporation. Proceedings having been initiated,
demolition order was passed by the Corporation.
The present writ petition was filed for demolition
of the unauthorized building in implementation of the
order of demolition.
Several earlier orders were passed on the writ
petition which may not be relevant today.
By the order impugned the learned Judge
recorded, on the basis of a report filed by the
Executive Engineer (Civil)/Building Department,
Borough-III, Kolkata Municipal Corporation signed on
May 2, 2023, that substantial portions of the building
in question have been demolished. The floors have
become unfit for human habitation. It was submitted
before the learned Judge on behalf of the appellant
herein that he was the developer of the property. After
the development was complete, the development
agreement stood terminated and possession was
handed over to the occupants.
The learned Judge directed the present
appellant, as the person responsible, to take the
responsibility for removing the unauthorized pillars
which are still standing. The learned Judge observed
as follows in the order impugned.
"As the respondent no.11 was the person responsible for making such unauthorized construction, accordingly, he ought to take the responsibility for removing the unauthorized pillars.
The respondent no.11 is directed to take steps for demolishing the pillars at once. The demolition work shall be done by maintaining proper safe
and security of the adjacent properties.
The matter is directed to appear in the list once again on 16th May, 2023.
A report shall be filed by the Corporation upon inspection of the property as to whether the pillars have been removed or not. In the event the pillars are not removed, the respondent no.11 shall appear personally before this Court on the adjourned date."
Being aggrieved, the respondent no.11 in the
writ petition has come up by way of this appeal.
The appellant says that proceedings having been
initiated under Section 400(8) of the Kolkata Municipal
Corporation Act, it is the responsibility of the
Corporation to demolish the unauthorized
construction. The appellant should not be directed to
do so. Further, the appellant has been acquitted of
charges in a criminal proceeding under Section 401A
of the Kolkata Municipal Corporation Act. In any
event, the appellant should not be foisted with the
costs of demolition of whatever remains of the
unauthorized construction.
We do not find any apparent infirmity in the
order impugned before us. The appellant admits to be
the developer. He was acquitted in the criminal
proceeding because the learned Magistrate was not
satisfied that the unauthorized construction was likely
to endanger human life or any property of the
Corporation. Even in the judgment of the learned
Magistrate, it is mentioned that the construction is
unauthorized. The learned Single Judge rightly
directed the appellant as the person responsible to
remove the remainder of the unauthorized
construction.
However, we see that the appellant is reluctant
to demolish the structure. We are also of the view that
it may be better if the Corporation carries out the
demolition activity as the same will be more systematic
and safe for the adjacent premises. The structural
stabilities of the adjacent premises are less likely to be
adversely affected if the experts from the Corporation
carry out the demolition activity. However, this will be
obviously at the cost of the appellant.
Accordingly, in partial modification of the order
of the learned Single Judge which is under challenge
in this appeal, we direct the Kolkata Municipal
Corporation to carry out the demolition activity at the
earliest. We request the learned Single Judge to pass
necessary orders to ensure that the Corporation
carries out the demolition activity within the time
period to be stipulated by the learned Judge. The
Corporation will be at liberty to raise bills for the cost
incurred by it for the demolition, on the respondent
no.11 in the writ petition along with the progress of
the work. Such bills will be paid by the respondent
no.11 promptly.
Since we have not called for affidavits, the
allegations contained in the stay application are
deemed not to be admitted by the respondent.
Accordingly, MAT 875 of 2023 is disposed of
along with the application being I.A. No. CAN 1 of
2023.
Urgent certified photostat copy of this order, if
applied for, shall be given to the parties as
expeditiously as possible on compliance with all the
necessary formalities.
(Arijit Banerjee, J.)
(Apurba Sinha Ray, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!