Citation : 2023 Latest Caselaw 3128 Cal
Judgement Date : 2 May, 2023
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
W.P.A. No.522 of 2023
Suraj Moulders Private Limited
Vs.
Government of West Bengal, through
the Secretary, Department of Power and others
For the petitioner : Mr. Pranit Bag,
Mr. Rahul Poddar,
Mr. Riddhiman Mukherjee,
Ms. Oindrila Ghosal,
Ms. Shrayasi Dhang
For the respondent no.6 : Mr. Ratnesh Kumar Rai,
Mr. Ankan Rai, Mr. Sayantaan Das
Hearing concluded on : 24.04.2023
Judgment on : 02.05.2023
Sabyasachi Bhattacharyya, J:-
1. The petitioner Suraj Moulders Private Limited is a lessee under
respondent no.5 Machino Transport Private Limited in respect of the
disputed property by virtue of an agreement of lease dated February
24, 2018. In the lease deed it was, inter alia, provided that electricity
up to 50 KW shall be supplied/provided from the transformer installed
at the premises in the name of respondent no.6 and the
lessee/petitioner shall pay all electricity charges for energy consumed
by the lessee and proportionate transformer loss as payable to
respondent no.6 according to the reading in an exclusive sub-meter at
the disputed premises.
2. Subsequently, on September 29, 2022 a copy of a notice purportedly
dated September 20, 2022 was sent on behalf of the respondent no.6
to the petitioner, addressed also to the other tenants at the property,
where it was alleged that the tenants, including the petitioner, were
enjoying supply of electricity from the connection of respondent no.6
and never tried to obtain separate electricity connection from CESC
Limited from their respective consumptions. It was further mentioned
that such supply was a good gesture of the respondent no.6 just to
support the tenants to "grow in their respective businesses". It was
indicated that the respondent no.6 was planning to have future new
projects at the premises which would otherwise increase the electricity
consumption of the said respondent; consequently, there would be
possibilities of explosion in the transformer and other hazardous
activities because the transformer would not be able to bear the
pressure of the heavy consumption of electricity both by respondent
no.6 and the tenants. On such ground, the respondent no.6
expressed its inability, through its advocate's letter, to supply
electricity at the premises of the tenants from its own connection any
further and advised the tenants, including the petitioner, to apply
before the CESC Limited for separate connection at their respective
premises for supply of electricity. Such exercise was directed to be
completed within Ten (10) days within receipt of the notice. In default,
the respondent no.6 threatened disconnection of the supply of
electricity at the premises of the said tenants.
3. The petitioner acted accordingly and, upon due payment, took a new
connection on November 29, 2022. The respondent no.6, on the other
hand, disconnected the supply of electricity to the petitioner's portion
on November 22, 2022.
4. However, again on December 14, 2022 respondent no.6 gave a notice
to the petitioner and the other tenants citing a "judicial order" and
asked the tenants to stop drawing electricity from any other meter
and/or parallel connection, particularly the one lying in the name of
the present writ petitioner, so as to enable respondent no.6 to supply
electricity in alleged compliance of the order dated December 2, 2022
passed in a civil revision between the respondent nos.5 and 6.
5. Learned counsel for the petitioner contends that, in pursuance of
such notice, the CESC Limited issued a notice on January 3, 2023 to
the petitioner, threatening to depute its personnel on January 9, 2023
at 10 am to 12 noon to de-energize the supply of the new meter in the
name of the petitioner. Allegedly, the ground for such threatened
action was the order passed in the Civil Revision bearing CO No.3585
of 2022 between the respondent nos.5 and 6. It was indicated that
reenergizing the same would be subject to further orders of the High
Court.
6. Challenging the said notice, the present petition has been preferred.
Learned counsel for the petitioner argues that the respondent no.6 is
debarred by Estoppel from resiling from its previous position, directing
the petitioner to take a new electricity connection in its own name and
to disconnect the supply from respondent no. 6. It is contended that
the petitioner as well as the respondent no.6 acted on the lease deed,
whereby the respondent no.6 was duty-bound to provide electricity to
the petitioner from its own meter. Again, when the notice dated
September 29, 2022 was issued to the petitioner by the respondent
no.6 itself, directing the petitioner to take its own connection, the
same was also acted upon by the petitioner, who, upon payment of
substantial amounts, took a new connection on November 29, 2022.
Hence, the respondent no.6 cannot, at its own whims, again resile
from such position and seek disconnection of the petitioner's
independent electricity supply.
7. Secondly, it is argued that the sole ground on which the respondent
no. 6 and the CESC Limited sought disconnection was the order
passed in CO No.3585 of 2022 on December 2, 2022. However, the
petitioner was not a party to the said litigation and is not bound by
the said order. Moreover, the direction of the revisional court was
merely an observation that enjoyment of the electricity by the opposite
parties therein may be permitted to be continued in the manner as
before being supplied by the petitioner therein, that is, the present
respondent no.6 till the end of January, 2023.
8. There is nothing in such order, it is argued, which would compel the
CESC Limited or the respondent no.6 to seek disconnection of the
petitioner's independent electricity supply.
9. The dispute as regards the property being joint between the
respondent nos.5 and 6 is sub judice in a civil suit between the said
parties and does not bind the petitioner in any manner whatsoever.
Hence, it is argued that the CESC Limited has no cause of action to
de-energize/disconnect the independent electricity supply of the
petitioner.
10. The respondent no.6 contested the writ petition primarily on the
ground that since the petitioner has been admittedly enjoying
electricity connection in both portions from the meter of the
respondent no.6 throughout its tenancy, it cannot be disputed by the
petitioner that the property is joint.
11. It is further argued that the structure raised on the property, from
which the new electricity connection has been given to the petitioner,
is an unauthorized and illegal construction and, as such, the
electricity supplied therefrom contravenes the law.
12. It is further argued by the respondent no.6 that every co-owner has
right and interest in the whole property. Without permission of the
respondent no.6, a co-owner, the construction could not be raised for
the purpose of giving electricity connection to the tenants by the
respondent no.5.
13. It is further argued that the petitioner was aware from the inception
regarding the issue of over-drawal of electricity in the premises.
However, the petitioner, who is also a tenant of the respondent no.6,
ought to have sought permission before erecting or aiding
unauthorized construction, which it deliberately did not do.
14. Hence, it is argued that the petitioner has not come to court with
clean hands and is not entitled to any relief.
15. In such context, reliance is placed on the judgment of Lourdu Mari
David and others Vs. Louis Chinnaya Arogiaswamy and others,
reported at (1996) 5 SCC 589.
16. The respondent no.6 also cites a judgment reported at (2007) 6 SCC
120 [Arunima Baruah Vs. Union of India and others] to challenge the
maintainability of the writ petitioner. In the said judgment, it was
held that unless all material facts are disclosed, the writ petition
would not be maintainable.
17. The respondent no.6 also places reliance on a Single Judge decision of
the Kerala High Court reported at AIR 2022 Ker 157 [J. Rajendran
Pillai Vs. B. Bhasi and others].
18. It is contended on the strength of such judgment that every co-owner
has a right and interest in the whole property and attempts of one co-
owner to erect any construction in the common property without
obtaining the consent of all co-owners ought to be restrained, along
with any accomplice of his.
19. A perusal of the documents annexed to the pleadings in the present
case clearly bring out certain facts.
20. Although the lease deed dated February 24, 2018 was executed
between the petitioner and the respondent no.5, it was clearly
indicated therein that the lessee would be supplied with electricity up
to 50 KW from the transformer of respondent no.6 and would pay
proportionately for the transformer loss as well as for the energy
consumption. The said deed was admittedly acted upon by regularly
supplying the petitioner with electricity from the transformer of the
respondent no.6, without any dispute being raised in that regard by
the respondent no.6.
21. However, by the subsequent Notice dated September 29, 2022, which
placed reliance on a purported previous notice dated September 20,
2022 the respondent no.6 specifically directed the tenants, including
the petitioner, to take separate connection within ten days. The
reason cited was clearly that the respondent no.6 was planning
certain new future projects which would require a heavier load of
electricity.
22. The petitioner acted upon such direction of the respondent no.6 and
took a new electricity connection on November 29, 2022, which was
provided by the CESC Limited without any demur. The respondent
no.6, moreover, also acted upon its own notice by disconnecting its
supply to the petitioner from the transformer of the respondent no.6,
even before the new connection was given to the petitioner.
23. Hence, the respondent no.6 was bound by Estoppel from resiling from
such position immediately thereafter and giving a notice to the
petitioner on December 14, 2022, asking the petitioner to immediately
stop drawing electricity from its own meter and insisting that the
respondent no.6 only could supply it.
24. Even apart from the bar of Estoppel, the sole ground which was cited
for such directive was the order passed in CO No.3585 of 2022 on
December 2, 2022. However, the petitioner was never a party to the
said proceeding or the suit from which the same arose. Hence, the
petitioner was not bound by the said order by any stretch of
imagination.
25. Moreover, a perusal of the said order clearly indicates that, by virtue
of the same, it was stipulated that enjoyment of electricity by the
opposite parties in the revision, that is, the respondent no.5 and
others, may be permitted to continue in the manner as before, being
supplied electricity by the revisionist petitioner (present respondent
no.6) till the end of January, 2023.
26. The said direction on the respondent no. 6 could not in any manner
justify the disconnection of the petitioner's supply.
27. There is no other reason cited in the notice dated December 14, 2022
than the alleged violation of the order of the revisional court.
28. Rather, the respondent no.6 had specifically directed the petitioner to
take its own electricity supply at the premises under the threat of
disconnection of the existing supply from the transformer of the
respondent no.6, which was fully acted upon by the respondent no.6
itself by disconnecting such supply from its transformer to the
petitioner. The petitioner also acted upon the same and invested huge
amounts of money and resources to take the new electricity
connection. The alleged illegality in the construction from which the
new connection was given never featured in the communications,
either by the respondent no.6 or by the CESC Limited, at any point of
time.
29. It is a new ground sought to be made out before this Court for the first
time in the writ petition. It is well-settled that a new ground for the
impugned action cannot be set up for the first time in the pleadings
made in the affidavit-in-opposition to the writ petition, which has
precisely been done in the present case by the respondent no.6.
30. Insofar as the CESC Limited is concerned, being satisfied of
compliance of all formalities by the petitioner, it had given electricity
supply to the petitioner and there is no allegation on the part of the
CESC Limited that any electricity law or regulation was contravened
by the petitioner at any point of time, to instigate the CESC Limited to
disconnect its supply.
31. Inasmuch as the order of the revisional court is concerned, neither the
CESC Limited nor the petitioner are parties thereto and the said order
does not in any manner necessitate or justify the threat of
disconnection issued by the CESC Limited to the petitioner, which is
entirely unwarranted and de hors the law. In such circumstances, the
impugned notice of the CESC Limited dated January 3, 2023 is
palpably illegal and cannot survive judicial scrutiny.
32. Accordingly, WPA No.522 of 2023 is allowed, thereby setting aside the
impugned notice dated January 3, 2023 insofar as the petitioner is
concerned. The respondent nos.2 and 3, being the CESC Limited and
its District Engineer, are restrained by an order of injunction from
giving any effect whatsoever to the said impugned notice which,
hereby, stands quashed and set aside.
33. There will be no order as to costs.
34. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!