Citation : 2023 Latest Caselaw 3125 Cal
Judgement Date : 2 May, 2023
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
W.P.A. No.6496 of 2023
Rohit Cargo Movers
Vs.
CESC Limited and others
For the petitioner : Mr. Subhasish Pachhal,
Mr. Sandip Chakraborty,
Mr. Rahul Kinkar Pandey
For the CESC Limited : Mr. Debjit Mukherjee
For the respondent No.5 : Mr. Sakya Sen,
Mr. Priyankar Saha, Mr. Lalratan Mondal
Hearing concluded on : 27.04.2023
Judgment on : 02.05.2023
Sabyasachi Bhattacharyya, J:-
1. Vide order dated April 26, 2023, a prayer of the private respondent for
holding an inspection through a Special Officer was refused.
2. The context of the prayer can be found in the crux of the dispute
between the parties. The petitioner, claiming to be in settled
possession of the disputed property, sought an electricity connection
in its name. The licensee/CESC Limited does not have any objection
to give the same, subject to compliance of all formalities by the
petitioner. However, the private respondent no.5 objects on the
ground that the said respondent is in exclusive possession of the
property and, by way of taking an electricity connection, the petitioner
is seeking to encroach upon the property.
3. It is contended by learned counsel for the private respondent no.5 that
the petitioner has failed to show settled possession, which is the sine
qua non for getting an electricity connection even within the
contemplation of Section 43 of the Electricity Act, 2003 (for the sake of
brevity, "the 2003 Act").
4. Learned counsel places reliance on a three-Judge Bench decision of
this Court in Abhimanyu Mazumdar Vs. The Superintending Engineer
and another, reported at AIR 2011 Cal 64. The Full Bench, inter alia,
held that in order to get an electricity connection, a trespasser must
be in actual physical possession of the property over a sufficiently long
period, which must be to the knowledge (either express or implied) of
the owner or without any attempt at concealment by the trespasser
and which contains an element of animus possidendi. The nature of
possession of the trespasser would, however, be a matter to be
decided on the facts and circumstances of each case. The process of
dispossession of the true owner by the trespasser must be complete
and final and must be acquiesced to by the true owner.
5. Learned counsel then contends that Section 43 of the 2003 Act does
not create a right per se but imposes duty on the licensee to supply
electricity on request. An essential component of supply, it is argued,
is the laying of the lines for giving such connection. In such context,
it is argued that the Works of Licensees Rules, 2006 (for short, "the
2006 Rules") acquire relevance. The expression "lawful occupation"
used in the said Rules was interpreted in the context of Section 43 of
the 2003 Act by the Full Bench of this Court in Abhimanyu Mazumdar
(supra). It is submitted that the documents produced by the petitioner
do not establish the petitioner‟s settled possession in respect of the
property. The trade licence submitted by the petitioner and annexed
to the writ petition, it is argued, does not indicate any fees having
been paid by the petitioner for running its transport business, which
is allegedly the business of the petitioner.
6. On the contrary, it is the private respondent no.5 who is running a
transport business at the property.
7. It is next argued that the Telephone Bill annexed to the writ petition is
not sacrosanct to prove the settled possession of the petitioner, since
the very existence of a telephone at the property is disputed which, it
is argued, can only be established by visual inspection.
8. It is reiterated that the court is not powerless to issue a visual
inspection to ascertain the actual physical possession of the property.
9. Learned counsel for the private respondent no.5 next places reliance
on the affidavit-in-opposition of the said respondent and its
annexures. A Commissioner‟s report filed in connection with a suit
filed by the private respondent no.5 against the Kolkata Port Trust
(KoPT) indicates that there are R.T. Shed Rooms on the property,
which belong to the petitioner. Moreover, the private respondent no.5
is enjoying a status quo order with regard to the property against the
KoPT on the strength of the said respondent‟s possession. Even in a
proceeding under Section 144 of the Criminal Procedure Code, a
report filed by the police indicates that the private respondent no.5 is
in occupation of the property.
10. Hence, it is argued, in the absence of any proof as to the settled
possession of the petitioner, the connection cannot be given by the
licensee.
11. Learned counsel appearing for the petitioner controverts such
contention and argues that there are several documents annexed to
the affidavit-in-reply, including documents to show transactions from
the disputed property by the petitioner, which clearly prove that the
petitioner is in occupation of the same.
12. It is argued that, to establish the right of the petitioner to get an
electricity connection at the property, it is only required that the
petitioner has to show prima facie possession with regard to the
property, which has been sufficiently established by the documents-
on-record. It is argued that the petitioner has produced several
documents to establish possession over a period of time, which cannot
be negated at the stage of giving electricity connection to the
petitioner.
13. Upon hearing learned counsel for the parties, it is seen that the
petitioner has annexed a Certificate of Enlistment at page 12 to the
writ petition, which pertains to the year 2022-2023, which is valid up
to March 31, 2023. Under Serial No. 2 thereof, it is indicated that the
petitioner has paid fees for "Specific Services" to the tune of
Rs.2,500/- and under Serial No.1, fees for Certificate for Enlistment of
Rs.500/- has also been deposited. The petitioner argues that no
payment has been shown under any of the other heads contained
therein, which goes on to indicate that a consolidated fee of Rs.3050/-
was taken for the issuance of the Certificate of Enlistment.
14. Hence, it is arguable as to whether the said trade licence can be
disproved merely on the ground of that no separate payment under
the head of storing in warehouse, transport, etc., was deposited.
Moreover, the Certificate of Enlistment is sufficient prima facie proof of
possession of the petitioner for carrying on trade in the nature of
transport business at Jagat Banerjee Ghat Road, where the disputed
property is situated.
15. Insofar as the telephone bill dated November 5, 2022 is concerned, the
same also indicates that the petitioner is in possession of the
premises. It is doubtful as to whether, while hearing the present writ
petition arising out of an electricity matter, the court can enter into
the detailed exercise of collecting evidence by directing visual
inspection to see whether a telephone is physically located in the said
premises or not. A visual inspection to ascertain physical possession
would amount to a roving enquiry, particularly within the limited fact-
finding scope of a writ petition. Even the distribution licensee, while
giving a new connection, is not required to hold an inspection to
ascertain whether there is actually a telephone installed at the
premises. The telephone bill sufficiently indicates that at least there is
a telephone connection at the premises, which is sufficient for the
present purpose.
16. In the affidavit-in-reply, the petitioner has annexed a further receipt of
payment of telephone bill dated March 14, 2023, which is of
comparatively recent origin.
17. Several road challans, invoices, etc., have also been annexed to
indicate prima facie that the petitioner is in possession of the property.
In fact, elaborate bank statements and GST return receipts have also
been annexed, which indicate that the petitioner is operating from the
disputed premises. Such elaborate materials cannot be brushed aside
without a full-fledged and detailed enquiry by taking evidence, which
is not the standard of proof expected to be applied by the licensee in
order to give a new electricity connection to an applicant.
18. In the present matter, the CESC Limited could not even hold any
inspection to ascertain feasibility of giving a connection to the
petitioner. As such, the licensee is obliged by Section 43 of the 2003
Act to supply electricity to the petitioner at the premises, in view of
sufficient prima facie material having been produced to show the
possession of the petitioner.
19. A consideration of the Full Bench Judgment of this Court in
Abhimanyu Mazumdar (supra) shows that the said judgment involved
a question as to whether a person who is an encroacher upon the land
belonging to another without any right of permission conferred by
such owner can be treated to an occupier. In such context, the
definition of "occupier" in the 2006 Rules was also read in conjunction
with Section 43 of the 2003 Act. The Full Bench, in its wisdom, had
placed reliance on several judgments of the Supreme Court. One of
the tests in case of a trespasser was that he must be in actual
physical possession of the property over a sufficiently long period,
which has to be to the knowledge (either expressed or implied) of the
owner or without any attempt at concealment by the trespasser and
which contains an element of animus possidendi. In case of a
trespasser, it was further observed that the process of dispossession
of the true owner by the trespasser must be complete and final and
must be acquiesced to by the true owner.
20. The said yardsticks were borrowed by the Full Bench while
considering the concept of settled possession in the context of the
right to dispossess a trespasser. It was observed that the trespasser‟s
possession must be settled, extending over sufficiently long period of
time, and cannot be a casual act of possession.
21. In the present case, in view of the plethora of documents produced by
the petitioner, there is no doubt that „settled possession‟ has been
established by the petitioner. There is nothing on record to indicate
that the respondent no.5 has ever litigated for eviction of the
petitioners from the property-in-dispute. The entire litigation at the
behest of the respondent no.5 was against the KoPT. The petitioner is
not a party either in the civil suit or proceeding under Section 144 of
the Criminal Procedure Code. In any event, a police report filed in
such criminal proceeding cannot be sufficient proof of the petitioner‟s
dispossession, once the petitioner has shown prima facie settled
possession.
22. It is fully probable that the petitioner is in settled possession of at
least a portion of the property, despite the private respondent no.5
having obtained orders against the KoPT, a third party to the present
writ petition, with regard to the property. In the absence of
impleadment of the petitioner as a party to the suit, none of the orders
and/or reports or other documents filed therein can be binding on the
petitioner, the entire exercise having been undertaken behind the
back of the petitioner.
23. In the supplementary affidavit, the private respondent no.5 has
annexed documents with regard to the same address, showing a
plastic bottle manufacturing business being run from the premises.
The challans annexed to the supplementary affidavit corroborate such
stand.
24. However, the Certificate of Enlistment issued to the petitioner is
clearly in respect of a transport business, which is also reflected from
the name of the petitioner-Company. The dispute as to possession is
undoubtedly arguable, but is a civil dispute in nature and cannot be
conclusively adjudicated either by the writ court or by the licensee, for
the limited purpose of giving electricity connection. Section 43 of the
2003 Act casts a duty on the licensee to give electricity supply to the
applicant upon an application being made. However, a duty cast on
the licensee is nothing but the other side of the coin which creates a
right in favour of the applicant to get such connection.
25. There is another perspective which is required to be explored in the
context of the Full Bench judgment of this Court. In the said
judgment, the provisions of Rule 3 of the 2003 Rules were considered.
In the said Rule, the expression "occupier" has been used for the
purpose of fixing liability of the licensee to take prior consent. In the
event a dispute is raised by the occupier, permission in writing is
required to be obtained from the District Magistrate or the
Commissioner of Police.
26. The definition of "occupier", unless the context otherwise requires, is
the occupier of any building or land, being a person in „lawful
occupation‟ of that building or land.
27. Seen in proper context, the 2006 Rules, insofar as the expression
„occupation‟ is concerned, deal with the stage when the lines are
required to be laid or drawn by the licensee for the purpose of
supplying electricity to the petitioner.
28. Although such comparison found place in the Full Bench judgment in
the context of whether the applicant is to be in settled possession of
the property, the use of the expression "occupier" in the 2006 Rules is
specifically in the context when electricity line is drawn or laid over or
through the property of such „occupier‟. On the other hand, the
„occupier‟ envisaged in Section 43 of the 2003 Act does not speak
about the person who holds the premises over which such connection
is being given to someone else but the person who applies for the
electricity connection himself to his property. Section 43(1) stipulates
that on an application by the owner or occupier of any premises, the
licensee shall giver supply of electricity to such premises within one
month after receipt of the application. The proviso thereto
contemplates that if the supply requires extension of distribution
mains, etc., the distribution licensee shall supply electricity
immediately after such extension or commissioning of sub-station.
Sub-section (2) speaks about the licensee providing electric plant or
electric line for giving such supply, in default of which sub-section (3)
is attracted, under which the failure of the licensee to supply
electricity within the period of one month is visited by liability to pay
penalty extending up to Rs. 1,000/- for each day of default.
29. Such obligation on the part of the licensee to lay the line, extending
the line, commissioning a sub-station, provide an electric plant or
electric line, is undoubtedly governed by the 2006 Rules.
30. However, the right to get electricity supply on the part of the applicant
is rather divorced from such process, inasmuch as the property to
which the line is being given is the concern of the applicant, in respect
of which the term „occupier‟ has not been qualified by the adjective
„lawful‟.
31. On the other hand, when the licensee draws the line or extends the
mains or installs a sub-station, the same has to be done over the
property of a third party, in respect of which the definition of
"occupier" as a „lawful occupant‟ comes into play.
32. The dispute arisen in the present writ petition is squarely in respect of
the applicant‟s possession on the property where the connection is
sought to be given and not the property over which the line is sought
to be drawn by the licensee. Hence, a consideration of Section 43
cannot have any element of „lawfulness‟ to qualify the occupation of
the applicant.
33. As discussed hereinabove, sufficient prima facie material has been
produced by the petitioner to establish that the petitioner is in settled
possession of the property over a period of time.
34. The documents and counter documents produced by the parties in
relation to the dispute as to possession can only be the subject-matter
of a regular civil suit before the competent court and cannot be
decided either within the limited conspectus of the writ petition or by
the licensee.
35. In such view of the matter, the petitioner has established settled
possession within the contemplation of the Full Bench judgment of
Abhimanyu Mazumdar (supra), read in conjunction with Section 43 of
the 2003 Act and Article 21 of the Constitution of India. Hence, it
cannot be said that the component of lawful occupation over the
property through which the supply will be given can be equated with
the premises to which such connection is being given, the latter being
the sole subject-matter of the present proceeding.
36. Accordingly, WPA No.9496 of 2023 is allowed on contest, thereby
directing the CESC Limited to hold an inspection to ascertain the
feasibility and appropriate location for giving new electricity
connection to the petitioner. Such inspection shall be held within a
week from date and, thereafter, a quotation shall be duly raised by the
CESC Limited within a week thereafter. Upon compliance of all
formalities by the petitioner, the new electricity connection will be
given at the premises to the petitioner within a further week from the
date of compliance of such formalities. If, either at the time of holding
inspection or at the time of giving such connection from the existing
meter-board position, if any, the CESC Limited personnel face any
obstruction from the respondent no.5 and/or his men and agents, it
will be open to the CESC Personnel to approach respondent no.4, the
Inspector-in-Charge of the Shibpur Police Station for adequate police
assistance, which will be given by respondent no.4 by acting on a
server copy of this order at the cost of the petitioner on both such
occasions of inspection and giving connection.
37. It is, however, made clear that such connection, as and when given to
the petitioner, shall not create any special right or equity in favour of
the petitioner which the petitioner otherwise does not have and also
shall not prejudice the rights and contentions of the parties with
regard to the civil disputes which have arisen between them.
38. There will be no order as to costs.
39. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!