Citation : 2023 Latest Caselaw 3123 Cal
Judgement Date : 2 May, 2023
Ml- 02.05.2023
235 Ct.15
W.P.A. 9702 of 2015
rkd (IA NO: CAN 1/2016 (Old No: CAN 4726/2016)
Gopal Krishna Banerjee
-vs-
Kolkata Municipal Corporation & Ors.
Mr. Sakya Sen,
Mr. Sidhartha Sharma,
Mr. Rishav Dutt,
Mr. Rohit Bhattacharjee
....for the petitioner.
Mr. Aniruddha Mitra,
Mr. Anirban Ghosh
....for the respondent no.6.
Mr. Alak Kumar Ghosha, Mr. Achintya Kumar Banerjee, Ms. Era Ghose ....for the KMC.
The writ petition is presented, inter alia,
challenging a notice dated 21st April, 2015 issued by
the Deputy Chief Engineer (Building), Borough -VII
whereby it was intimated to the petitioner that
pursuant to the order of the Learned Building
Tribunal, Kolkata Municipal Corporation dated 4th
December, 2008 steps were taken for demolishing
portion of the structure erected by the petitioner but
the work of demolition was not complete therefore
petitioner was also informed that according to the
Corporation certain portions of the structure of the
petitioner are left to be demolished vide order
passed by the Building Tribunal.
Mr. Sen, learned counsel representing the
petitioner submits that order of the Learned
Municipal Building Tribunal dated 4th December,
2008 was questioned before the coordinate Bench
by instituting a writ petition being W.P.O. 271 of
2009 and the coordinate Bench by delivering a
judgment dated 2nd September, 2010 upheld the
decision of the Building Tribunal and thereby order
of the Building Tribunal dated 4th December, 2008
was confirmed. Against that petitioner preferred an
intra Court appeal before the Hon'ble Division
Bench and the appeal was disposed of vide order
dated 14th March, 2011 confirming the order passed
by the learned Single Judge.
However, it has been submitted on the
petitioner that pursuant to the order passed by the
Building Tribunal being confirmed by the Hon'ble
Division Bench vide order dated 14th March, 2011 a
notice dated 4th July, 2011 was served upon the
petitioner for demolition of the unauthorized
construction and according to the petitioner
demolition work was completed by the Kolkata
Municipal Corporation pursuant to the said
demolition notice dated 4th July, 2011 and the
nothing is left to be demolished.
The impugned notice dated 21st April, 2015
which is at page 191 of the writ petition is not
tenable according to the petitioner since the same
was issued four years after the notice of demolition
was issued on 4th July, 2011 therefore according to
the petitioner such impugned notice dated 21stApril,
2015 is afterthought. It has also been contended on
behalf of the petitioner that the notice dated 21st
April, 2015 is devoid of particulars and the same is
vague.
The learned advocate representing the
Kolkata Municipal Corporation has drawn attention
to the affidavit-in-opposition affirmed on behalf of
the Corporation on 18th August, 2015 wherein it
has been averred that albeit demolition programme
was fixed on 12th July, 2011 but on that date all the
illegal constructions could not be demolished due to
the reasons beyond control therefore demolition
order should be executed in its true letter and
spirit.
The learned advocate representing the
added respondent no.6 also supports the contention
of the Kolkata Municipal Corporation which
emanates from the affidavit-in-opposition affirmed
on behalf of the Corporation and it has further been
submitted that respondent no.6 is the owner of the
property in question wherein the petitioner runs the
club.
It is also contended that de novo inspection
is required to be made on behalf of the Kolkata
Municipal Corporation to find out whether the
demolition order was truly carried out in order to
complete the demolition process but according to
estimation of the respondent no.6 the demolition
work which was carried out pursuant to the
demolition notice dated 4th July, 2011 was not
complete.
Having considered the submissions made
by the respective parties, it appears that after the
order of the Municipal Building Tribunal dated 4th
December, 2008 was confirmed by the order of the
Hon'ble Division Bench dated 14th March, 2011 a
demolition work was carried out vide demolition
notice dated 4th July, 2011 by the Kolkata
Municipal Corporation. It is true that subsequent
notice for completing the demolition work was
issued on 21st April, 2015 which is four years after
the initial demolition notice was issued by the
Corporation after disposal of the appeal by the
Hon'ble Division Bench vide notice dated 4th July,
2011.
However, taking into consideration the
submissions made on behalf of the parties and the
stand which has been expressed by the Kolkata
Municipal Corporation by affirming affidavit-in-
opposition it appears that an exercise is required to
be carried out in order to find out whether the
demolition work could be made complete strictly in
terms of demolition sketch plan dated 8th May, 2003
after issuance of demolition notice dated 4th July,
2011 or not.
In order to complete such exercise, this
Court finds it apt to direct the Executive Engineer
(Civil) (Building Department), Kolkata Municipal
Corporation, Borough-VII being the respondent no.4
to inspect the area where according to the
Corporation the building in question situates and
also take into consideration the demolition sketch
plan dated 8th May, 2003 which was prepared by
the concerned authority of Corporation in order to
find out the extent of unauthorized construction
carried out by the petitioner at the material point of
time and prepare a report indicating whether the
illegal construction was demolished pursuant to the
demolition notice dated 4th July, 2011 in its
entirety. Such inspection is to be carried out by the
respondent no.4 within four weeks from the date of
communication of this order by either of the parties
upon issuing seven days' notice to the petitioner
and the respondent no.6.
After the aforesaid exercise is made
complete by the respondent no.4, the respondent
no.4 shall pass an order within four weeks
thereafter indicating whether the demolition work
was complete in the year 2011 pursuant to the
demolition notice dated 4th July, 2011 or some
portions are left to be demolished.
However, it is made clear that Special
Officer (Building) in his order dated 8th May, 2003
had categorically indicated in the concluding
portion that the construction which were specified
under Part-A can be retained by the petitioner (club)
on completion of formalities therefore no further
exercise shall be required to be made by the
respondent no.4 in order to find out the nature of
such construction falling under Part-A.
After taking such decision by the said
respondent no.4, the same shall be communicated
to the petitioner and the respondent no.6 within a
period of two weeks thereafter.
Interim protection granted by the
coordinate Bench on this writ petition by passing
order dated 14th May, 2015 which was extended till
disposal of this writ petition vide order dated 26th
November, 2015 however shall continue for a period
of four weeks after the receipt of order to be
passed by the respondent no.4 pursuant to the
aforesaid direction.
With the aforesaid direction, the writ
petition stands disposed of.
Application, if any pending, also stands
disposed of.
However, there shall be no order as to
costs.
Urgent photostat certified copy of this
order, if applied for, be given to the learned
Advocates for the parties on the usual
undertakings.
(Saugata Bhattacharyya, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!