Citation : 2023 Latest Caselaw 1194 Cal/2
Judgement Date : 17 May, 2023
In The High Court at Calcutta
Original Civil Jurisdiction
Commercial Division
The Hon'ble Justice Sabyasachi Bhattacharyya
AP NO.72 OF 2023
Tantia Constructions Limited
VS.
Mather and Platt Pumps Limited and another
For the petitioner : Mr. Swatarup Banerjee,
Mr. Sariful Haque,
Mr. Hareram Singh
For the respondents : Mr. Jishnu Chowdhury,
Mr. Aritra Basu, Mr. Ritoban Sarkar, Mr. Debanjan Ghosh
Hearing concluded on : 10.05.2023
Judgment on : 17.05.2023
The Court:
1. The petitioner has filed the present application under Section 11 of
the Arbitration and Conciliation Act, 1996 (hereinafter referred to as
"the 1996 Act") for reference of a dispute which has arisen between
the parties in connection with a Memorandum of Understanding (in
brief, the "MOU") and connected Joint Venture Agreement (for short,
"JVA"), both dated February 3, 2014.
2. As per Clause 16 of the MOU, both parties shall make efforts to settle
the disputes or differences amicably if any. If disputes are not resolved
through amicable settlement, the same shall be referred to the sole
arbitrator mutually selected by both the parties. The decision of the
arbitrator shall be final and binding on both the parties. Arbitration
proceeding shall be conducted in accordance with the 1996 Act (the
year wrongly mentioned in the agreement as "1998") and the venues of
arbitration shall be in Kolkata.
3. There is no contention in principle that disputes, which are otherwise
arbitrable, have arisen between the parties within the purview of the
arbitration clause. However, the respondents contend that the
arbitration clause in the JVA dated February 3, 2014 is no longer
existent in view of Clause 10.1 of a subsequent agreement dated
November 29, 2018 entered into between the parties on the self-same
joint venture. The said clause reads as follows:
" 10.1 The Agreement represents the entire understanding of the parties with respect to the subject matter contained herein and supersedes all prior discussions, understandings and agreements between the Parties with respect thereto any and all agreements, representations, and contracts made or dated prior hereto (whether written or oral) concerning the subject matter hereof."
4. Learned counsel for the respondents places reliance on Section 62 of
the Indian Contract Act, 1872 which provides that if the parties to a
contract agree to substitute a new contract for it, or to rescind or alter
it, the original contract need not be performed.
5. In the present case, it is argued, the subsequent agreement dated
November 29, 2018 specifically supersedes all previous agreements,
discussions, understandings, etc. including the first JVA dated
February 2, 2014. Hence, the arbitration clause in the JVA cannot be
enforced.
6. Learned counsel appearing for the petitioner argues that the alteration
to the JVA does not amount to novation of the same.
7. Moreover, it is contended that the agreement dated November 29,
2018 has to be read as being intrinsically interlinked with the JVA. A
still-subsequent document, captioned as "Amendment To Joint
Venture Agreement (For Joint and Several Liability of Joint Venture
Partner)" is relied on by the petitioner to argue that even in the same,
which was executed between the parties subsequent to the November
29, 2018 agreement, the JVA and the connected Joint Venture
Declaration have been relied on. This indicates that all the three
documents referred to above as Joint Venture agreements or
amendment thereto, are part and parcel of the same joint venture.
Hence, the arbitration clause in the initial MOU covers disputes
arising out of all.
8. Learned counsel for the petitioner cites Choloro Controls India Private
Limited Vs. Severn Trent Water Purification Inc. and Others [ (2013) 1
SCC 641 ] and Ameet Lalchand Shah and Others Vs. Rishabh
Enterprises and Another [ (2018) 15 SCC 678 ] in support of the
proposition that where various agreements constitute a composite
transaction, the court can refer the disputes to arbitration existing
between the signatory or non-signatory parties if all ancillary
agreements between the parties are relatable to a principal agreement
and performance of one agreement is so intrinsically interlinked with
the others that they are incapable of being performed without
performance of the others or severed from the rest.
9. Citing such proposition, it is argued that the parties here are on a still
better footing, since the present parties were signatories to all the
documents.
10. Learned counsel for the petitioner also relies on Sanjiv Prakash Vs.
Seema Kukreja and Others, reported at (2021) 9 SCC 732, where it was
held that a disputed question of novation of the agreement containing
the arbitration clause is non-determinable by the court at the stage of
reference under Section 11 of the 1996 Act.
11. Learned counsel for the respondents submits that, unlike in Chloro
Controls (supra), here the different agreements were entered into on
different dates and the 2018 documents explicitly supersedes the
2014 MOU. Moreover, in the said report, the same transaction was
broken up into separate agreements under different heads, but
pertained to the same main project.
12. Unlike Ameet Lalchand Shah (supra), here the JVA or the MOU were
not the mother/principal agreements. The subsequent agreements
were entered into independently and the clear language of the 2018
agreement superseded all prior discussions, understandings and
agreements, written or oral, on the subject matter, including the 2014
JVA and MOU, the latter of which contained the arbitration clause.
13. Learned counsel for the respondents also seeks to distinguish the
judgment of Sanjiv Prakash (supra) on facts.
14. Upon hearing learned counsel, the first question which begs
consideration is the true purport of the expression "alter" in Section
62 of the Contract Act. Applying the doctrine of noscitur a sociis, the
term "alter" is to be attributed the meaning derived from the previous
expressions used in the Section for similar action. The other two
expressions are "substitute a new contract for it" and "rescind". In the
caption of the section, the terms "novation", "rescission" and
"alteration" have been used in the same breath. Construed in such
perspective, "alter" cannot mean a minor or cosmetic change but must
be a change hitting at the root of the contract, altering the essentials
of the earlier contract to bring forth a novated agreement for all
practical purposes. Even the illustrations to Section 62 exemplify such
view.
15. Scrutinizing the subsequent agreement dated November 29, 2018
closely, certain features of the same stand out in the present context.
16. First, the said agreement refers to the initial JVA and a
supplementary JVA dated December 4, 2014 recording the office
address of the JV and the contract value of "the work". It is stated that
the petitioner TANTIA "was to perform the following works" as
specified therein. However, it was "yet to perform" some of the
activities in compliance with its "obligation". The 2018 agreement
relied on by the respondents further goes on to mention that the
petitioner foregoes its right to receive any payment, if any, which it
was "yet to receive from the JV" pursuant to the invoices raised for the
"work done". It also acknowledged that it shall not initiate any
proceedings for the recovery of the amount which it had waived in
view of the clause. All such factors unerringly indicate that it was
referring to the JVA and the MOU, which were the genesis of the
entire "obligations" and "the work" to be done.
17. Secondly, Clause 10.1 spoke about supersession of the entire
understanding, prior discussions, agreements etc. "concerning the
subject matter hereof". The subject matter thereof was not the
origination of the joint venture project but an alteration of the ratio of
participation in the joint venture itself. Thereby, the petitioner waived
certain rights and conferred them on the respondents, but all flowing
from the original joint venture, of which the parent agreements were the
JVA of 2014 and the connected MOU.
18. A third aspect of the matter is required to be considered as well. In its
supplementary affidavit, the petitioner has annexed another
agreement dated January 31, 2019, which is even subsequent to the
2018 document cited by the respondent. Notably, the said 2019
document provides, in Clause 7 thereof, as follows:
"7. This Agreement form for joint and several liability is an integral part of the Joint Venture Declaration and Contract awarded to the partnership."
19. Thus, it can be seen that an agreement entered into between the
parties even after the 2018 document again refers to the JVA and
connected Declaration/MOU, which presupposes the continuance of
the MOU containing the arbitration clause till after the 2018
document.
20. The JVA mentions in Clause 6 of the same that the Agreement to form
it (the MOU) is entered on the same day. Clause 7 says that the said
Agreement form for joint and several liability is an integral part of the
Joint Venture Declaration and will be finalized in case the Contract is
awarded to the partnership/legal entity prior to the signature thereof.
Hence, the JVA and the MOU are integral parts of each other.
21. All the subsequent agreements and documents, copies of which have
been annexed to the pleadings and relied on by both parties, pertain
to the Joint Venture entered into by the parties by virtue of the MOU
and JVA dated February 3, 2014.
22. Thus, for a proper and complete adjudication of any dispute arising in
connection with the Joint Venture, it is essential that all the
connected documents, which are parts of the same transaction, are to
be looked into. The cause of action as pleaded in the invocation under
Section 21 of the 1996 Act dated January, 4, 2023, reiterating the
invocation dated November 25, 2022, pertains to the entire dispute,
which cannot be segregated into separate agreements.
23. All the agreements-in-question and the components of the dispute are
intrinsically and inextricably interlinked with each other, as
contemplated in Chloro Control (supra). The Supreme Court, in the
said case, went so far as to hold that even the fact that a party to the
arbitration agreement was non-signatory to one or other agreement
may not be of much significance.
24. Although there may be subtle differences between the language and
purport of the different agreements of Chloro Control (supra), Ameet
Lalchand Shah (supra) and the present case, the principles laid down
in the said judgments are equally binding in the facts of the instant
lis.
25. Applying the test laid down in Sanjiv Prakash (supra), following Vidya
Drolia Vs. Durga Trading Corpn. [ (2021) 2 SCC 1 ] and Duro Felguera,
S.A. Vs. Gangavaram Port Ltd. [ (2017) 9 SCC 729, there cannot be any
manner of doubt that detailed arguments on whether the MOU
containing the arbitration clause in the present case has or has not
been novated cannot possibly be decided in exercise of a limited prima
facie review as to whether an arbitration agreement exists between the
parties. Such an inquiry would lead to detailed interpretation of all the
connected documents as well as appreciation of detailed evidence,
which is entirely beyond the limited domain of a court referring the
dispute to arbitration under Section 11 of the 1996 Act, particularly in
view of sub-sections (6) and (6A) thereof.
26. Hence, the objection taken by the respondents is turned down.
27. The disputes, being otherwise arbitrable and falling within the
purview of the arbitration clause, ought to be referred to arbitration
under Section 11 of the 1996 Act, as there does not appear to be any
amicable resolution between the parties.
28. Accordingly, A.P. No. 72 of 2023 is allowed, thereby appointing Justice
Indira Banerjee, a former Judge of the Supreme Court of India (Mobile
No. 9560808777), as the sole arbitrator to resolve the disputes
between the parties, subject to obtaining her consent under Section
12 of the Arbitration and Conciliation Act, 1996.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!