Citation : 2023 Latest Caselaw 1616 Cal
Judgement Date : 13 March, 2023
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
W.P.A. No.17828 of 2019
Sureka Modern Rice Mill Private Limited
Vs.
The West Bengal State
Electricity Distribution Company Limted
and others
For the petitioner : Mr. Amritam Mondal,
Ms. Ananya Chakraborty,
Ms. Shipra Naskar
For the WBSEDCL : Mr. Srijan Nayak,
Mr. Sujit Sankar Koley
Hearing concluded on : 02.03.2023
Judgment on : 13.03.2023
Sabyasachi Bhattacharyya, J:-
1.
The petitioner, a rice mill, is a consumer under the West Bengal State
Electricity Distribution Company (WBSEDCL). Although the petitioner
has paid all electricity bills on a regular basis, on March 5, 2018, the
WBSEDCL intimated the petitioner that the bills for the month of
November, 2017, December, 2017 and January, 2018 were wrongly
generated due to alleged defective Potential Transformer (PT) circuit
developed on and from November 3, 2017, resulting in partial demand
as per consumption in the meter during the said period.
The WBSEDCL demanded that the dues outstanding for the said
period of three months amounted to ₹ 17, 03, 072/-.
2. The petitioner rebutted such claim by a reply dated March 9, 2018.
However, subsequent disconnection notices were sent to the petitioner
on the ground of non-payment of such alleged outstanding dues. This
prompted the petitioner to prefer the instant challenge against the
alleged rectified outstanding bill.
3. The petitioner disputes the allegation that the meter in question was
defective at any point of time. It is argued that in the event the
circuit/meter was defective, there was no justification for the
WBSEDCL to chargeoutstanding amounts for the period from
November 2017 to January 2017 but omitting the months of February
2018 and March 2018 while raising the revised bill, although the
defective meter was alleged to be replaced only in April, 2010.
4. It is further submitted that the WBSEDCL never inspected the meter
for the purpose of ascertaining whether it was actually defective and
that the alleged replacement of the same by the WBSEDCL was not
done with any notice to the petitioner.
5. Learned counsel appearing for the petitioner submits that intimation
is required to be given to the consumer in case a defective
meter/circuit is changed in terms of clauses 3.8.3 and 3.6.1 of
Regulation 55 of the West Bengal Electricity Regulatory Commission
(for short, "the WBERC"). Such provisions were not complied with in
the present case.
6. From August 2017 onwards, there was a flood in the area, due to
which the paddy used for the purpose of the rice mill rotted. As such,
during the period in question, rice production took a toll, resulting in
less consumption of electricity than the corresponding months of the
previous year and/or the previous months. However, such fact was
not considered by the WBSEDCL in arbitrarily coming to the
conclusion that the meter reading for such periodwas faulty.
7. Learned counsel for the petitioner next cites Clause 11.1 of Regulation
57 of the WBERC, which specifically provides for the procedure in
case of meters being detected to be defective.In such case, the
distribution licensee has to install a testing meter for a particular
period for the purpose of ascertaining the condition of the meter,
which has not been done in the present case.
8. Learned counsel also relies on the Draft (Rights of Consumers) Rules,
2020 framed by the Ministry of Power, Government of Indiaand
published on September 9, 2020. Rule 7 thereof provides for testing of
meters, if found to be defective.
9. Learned counsel for the petitioner next cites certain judgements in
support of his contention that the due procedure in such cases was
not conformed to by the WBSEDCL.
10. First, learned counsel cites AIR 1985 MP 70 (Smt. Basantibai v. MP
Electricity Board, Indore and Ors.) where a Division Bench of the
Madhya Pradesh High Court held that when a difference or dispute
arises regarding whether an electricity meter was defective, the same
has to be referred to the Electrical Inspector.
11. Learned counsel next relies on a Single Judge-Bench decision of the
Delhi High Court, reported at 2008 (103) DRJ 107(Vinod Kumar Jain v.
Bses Rajdhani Power Ltd.) where in case of the dispute the High Court
directed the meter to be tested.
12. Learned counsel for the petitioner then places reliance on Nirmala
Metal Industries v. KSEB [2006 (3) KLT 465]. A Division Bench of the
Kerala High Court held therein that if a consumer entertained any
doubt that the meter is defective, not the Board the consumer can get
the meter tested by the Electrical Inspector.
13. Again, in Bombay Electricity Supply & Transport Undertaking v.
LAFFANS (INDIA) (P) Ltd. and Anr., reported at (2005) 4 SCC 327, the
Supreme Court held that although the meters were said to be
incorrect and had been removed and replaced by the licensee, the
most material evidence being the meter itself had been lost by the
licensee in removing the incorrect meter. The licensee cannot be
permitted to take advantage of its own acts and omission - the acts of
removing the meter and the omission to make a reference to the
Electrical Inspector.
14. Lastly, learned counsel for the petitioner places reliance on Mrityunjay
Pani and Anr. v. Narmada Bala Sasmal and Anr. (AIR 1961 SC 1353)
for his proposition that convenience cannot accrue to a party from his
own wrong.
15. In reply, learned counsel for the WBSEDCL submits that the
established method, as provided by the WBERC Regulations, is that
the average daily of the corresponding months of the previous year or
for three months before or after the detection of the defect in the meter
is the basis of calculation in case of defective meters.
16. It is further argued that the defect was cured by way of replacing the
meter and, as such, the petitioner cannot take the plea that the
WBSEDCL did not take corrective measures.
17. Learned counsel places reliance on Clauses 3.5 and 3.6 of Regulation
46 to submit that the Regional Grievance Redressal Officer (RGRO) is
the competent authority to decide on meter disputes. It is argued that
the RGRO is a technical person, competent to deal with such disputes.
18. Learned counsel for the WBSEDCL argues that no counter was filed
by the petitioner to the Draft Settlement Order passed by the RGRO.
As such, as per the prevailing regulations, the same became final. In
support of such contention, learned counsel refers to Clause 7 of
Regulation 56 of the WBERC.
19. Inasmuch as non-service of prior notice to the petitioner is concerned,
learned counsel submits that Clause 8 of Regulation 55 gives access
to the licensee to the meter and no notice is required to be given to the
consumer in order to replace a meter.
20. Insofar as the petitioner's argument regarding reference of the meter
to an Electrical Inspector goes, it is argued that the said provision
existed in the Electricity Act, 1910, on which the cited judgements
were rendered. However, upon the coming into force of the Electricity
Act, 2003, there is no existence of an Electrical Inspector. The RGRO
himself, it is submitted, is a technical authority and is fully competent
to decide issues regarding defective meters.
21. As such, it is argued that the WBSEDCL acted well within its
jurisdiction and authority to assess and claim the outstanding dues
on the basis of calculation as per law, regarding the period for which
the meter was defective.
22. A scrutiny of the cited judgments would be of benefit in the present
context. The judgments inSmt. Basantibai (supra) and Bombay
Electricity Supply (supra) were rendered by the Madhya Pradesh High
Court (Indore Bench) and the Supreme Court respectively, both on the
basis of Section 26(6) of the Electricity Act, 1910. The provisions
regarding reference to an Electrical Inspector have been done away
with in the present Act of 2003, under which the instant case is
governed. Hence, the said two judgments cannot be binding
precedents for deciding the instant lis.
23. The Division Bench of the Kerala High Court, in Nirmala Metal
Industries (supra), also placed reliance on pre-2003 Act provisions and
is not applicable to the present case.
24. The proposition laid down in Mrityunjay Pani (supra) is trite law. No
one can take advantage of his own wrong. In the said context, we are
to test whether the WBSEDCL did so.
25. In Vinod Kumar Jain (supra) also, the learned Single Judge resorted to
the Delhi Regulations and the Electricity Rules, 1956, which are not
applicable to the present case, which is governed by the Electricity
Act, 2003 and the West Bengal Regulations. However, the relevant
clauses of the West Bengal Regulations are in the same tune as the
said Rules.
26. Notification 57 of the WBERC brings in amendments to Regulation 46
of 2010 and substitutes Clause 11.1 of the principal Regulations
which provides for replacement of faulty meters/metering system
where supply is not affected, precisely as in the case at hand. For
rural areas, as per the said regulation, the meter shall be inspected
within 7 working days from the date of receipt of the complaint. In
case the meter/metering system is found otherwise faulty than being
burnt out, it shall be tested and the same shall be replaced/rectified
within 30 days from the date of inspection.
27. Clause 3.8.1 of Regulation 55 provides for provisional charging at the
prevailing tariff in case of unusual variation in meter reading for a
billing cycle, on the basis of average consumption for the prior six
months or consumption of similar period of the last year.
28. However, inClause 3.8.3 of Regulation 55 of the WBERC, it is
stipulated that in case the meter reading shows unusual consumption
in the next billing cycle also, the consumer shall be informed in
writing and shall be advised to clarify the reason for sudden change in
consumption by the licensee. If the explanation given by the consumer
is found to be satisfactory by the licensee, the consumer shall be
charged for actual consumption of both the billing cycles. If, however,
the explanation given by the consumer is not found to be satisfactory
by the licensee or no explanation is given by the consumer or if the
meter is suspected to be defective either by the consumer or by the
licensee, the licensee shall keep a test meter connected in series with
the existing meter for a reasonable period to check the correctness of
the meter to the satisfaction of both the licensee and the consumer.
Only if, on the basis of test results, the existing meter is found to be
defective, the same shall be replaced by a tested correct meter by the
licensee.
29. Such provisions have been given a go-bye on the part of the
WBSEDCL in the present case. Although it is alleged that the
WBSEDCL replaced the defective meter, there was no prior notice to
the consumer/petitioner alleging the defect in the metering system. In
the absence of such notice, any test meter being connected, or any
satisfaction of the licensee as to the correctness of the meter, the
provisions of Clause 3.8.3 of Regulation 55 are contravened, thereby
rendering the entire exercise futile and unlawful.
30. That apart, the provisions of the amended Clause 11.1 of Regulation
46 in respect of testing the meter/metering system has also been
flagrantly contravened in the present case, despite the dispute arising
in a rural area as envisaged in the said clause.
31. Although it is argued by the WBSEDCL that the RGROs are
technically equipped to decide meter disputes, in the present case
there is no reflection at all in the order of the RGRO of having tested
the meter or complied with the provisions as discussed above with
regard to the testing of the allegedly defectivemeter. No test meter as
contemplated in clause 3.8.3 of Regulation 55 was connected, in
series or otherwise, in the present case, nor was any test held or the
petitioner's satisfaction as to correctness or otherwise of the meter
recorded.
32. Neither the RGRO nor the Ombudsman returned any finding as to the
condition of the meter being tested prior to the same being allegedly
replaced.
33. The reliance by learned counsel for the WBSEDCL on Clause 3.6.1 of
Regulation 55 is entirely misplaced. The same provides that if, on
inspection by the distribution licensee on its own or on the basis of a
complaint of the consumer, the meter of the consumer is found
defective or defunct for a reason other than theft of electricity and no
theft of energy can be reasonably suspected, the consumer shall be
provisionally charged for such consumption of electricity for the period
during which the meter has been suspected to have been defective or
defunct, on the basis of average consumption and other parameters
for the preceding and/or succeeding three months or during any
previous and/or subsequent period that may be reasonably
comparable before the meter has been found to be defective or
defunct.
34. In the present case, the petitioner has made out a specific case that
there was a flood in the area in the month of August, 2017. In fact, a
specific report of the concerned Block Development Officer (BDO) has
been annexed to the writ petition which clearly indicates that there
was a flood in the area at the relevant juncture, which caused the
paddy used as raw material in the Rice mill to rot. As such, it is
reasonably argued by the petitioner that the consumption of electricity
would be considerably low in the succeeding few months, since the
rotted and soaked paddy had to be thrown out, bringing down the
production activity in the rice mill and, along with it, the electricity
consumption.
35. Such contention was brushed aside in a cryptic manner by the
authorities on the assumption that flood affected the region only for a
month, overlooking the obvious consequences thereof to a rice mill
such as the petitioner's.
36. The RGRO's order was utterly cryptic, without a single line of
reasoning. Even if he/she was a technical person, the RGRO did not
bother to decide on merits the cardinal question as to whether the
meter was at all defective in the relevant period.
37. Further, the RGRO failed to take into consideration that the written
instruction of the Block Development Officer to the petitioner as well
as two other rice mills was itself dated August 29, 2017 (annexed at
page 169 of the writ petition). In the said communication, the BDO
specifically found that the foodgrains stuffed in the mills were mostly
rotten and were breaking out foul odour, which might cause pollution
any time in the surrounding locality. Hence, the petitioner and the
other mills were instructed to dispose of the rotten foodgrains from the
mills immediately. It is pretty obvious that it could reasonably have
taken the rice mills a few months' time to recover from such loss by
procuring fresh foodgrains/paddy after getting rid of the rotten
foodgrains. Such minimum gestation period ought to have been taken
into consideration for the purpose of assessing the period during
which the petitioner was under-producing, in order to ascertain the
veracity of less consumption of electricity during the relevant period of
three months succeeding the flood.
38. Surprisingly, in spite of having substantially recorded the arguments
of the petitioner, the RGRO did not take the trouble of discussing or
deciding the most germane questions involved, as to the dispute
regarding the PT circuit being defective at all. Instead, the
'Observation' part of the RGRO comprised of a single sentence to the
effect that the petitioner did not pay the outstanding bill amount as
per the regenerated bills.
39. Thus, there was no adjudication at all in the first place in the Draft
Settlement Order for the petitioner to have "consented" to or
"admitted" by non traverse. As such, the non-filing of any further
objection to such a non-existent adjudication could not tantamount to
the petitioner's admission of the contents of the same.
40. In view of the petitioner having disputed the bills as well as the very
allegation of the PT circuit being defective, the onus had shifted on the
WBSEDCL to prove its case, which the latter miserably failed to
discharge.
41. There was no basis at all for the regeneration of the bills for November
2017 to January 2018, that too, on the specific allegation that the PT
circuit was defective from a particular date, that is, November 3, 2017.
42. Hence, the only possible outcome of the consideration by both the
forums could be a setting aside of the regenerated bills simpliciter,
without directing further regeneration, as the payment of current
electricity charges for the three months in issue has already been
completed by the petitioner previously.
43. The RGRO's order, being devoid of reason, cannot but be set aside in
any event. Hence, the Ombudsman, who is not a technical person
trained to decide such a dispute, became the first forum of
adjudication for all practical purposes, thereby depriving the petitioner
of a forum.
44. Now let us consider some of the relevant findings of the Ombudsman.
45. The Ombudsman's order clearly records that, despite clear
instructions of the forum in terms of the Order dated May 16, 2019 to
produce the report of the inspection as alleged to have been conducted
by the WBSEDCL on March 17, 2018, in which the malfunctioning of
the meter was detected, the WBSEDCL, without producing the said
inspection report, has submitted copy of the inspection report
regarding re-commissioning of the PT circuit in the service connection
of the complainant on April 6, 2018. No explanation was forthcoming
from the WBSEDCL for withholding such best evidence, if existent.
46. It was also observed by the Ombudsman that the accuracy of the
meter should have been tested by the local office of the WBSEDCL
before reaching the conclusion that the PT circuit of the installed
meter of their service connection became defective on November 3,
2017, as per the Regulatory provisions, prior to replacement of the
allegedly defective PT circuit, which has not been done.
47. In his conclusive observations, the Ombudsman unambiguously held
that the WBSEDCL has failed to established with supporting
documents that they actually conducted the inspection on March 17,
2018 to ascertain the status of functioning of the meter of the service
connection of the complainant which necessitated the regeneration of
the original bills for the three months from November 2017 to January
2018.
48. It was further held that even if such malfunctioning was detected,
then also the accuracy of the meter should have been tested by
placing a check meter in series with the existing meter for a
reasonable period keeping the complainant informed in conformity
with the Regulatory provisions and the meter, if found defective,
should have been replaced subsequently keeping the complainant
duly informed, which has not been done. Hence, it was further
observed, the actions taken by the WBSEDCL for replacement of PT
circuit of the meter without conducting testing of the accuracy of the
meter as per Regulatory provisions are to be considered as unjustified
and in violation of the Regulatory provisions. Since the alleged
defective PT circuit has also been replaced, there is no scope of
ascertaining the accuracy of the meter at the relevant point of time
which necessitated the regeneration of bills for the said three months,
which has been disputed by the complainant/petitioner. Accordingly,
the only logical conclusion which can be drawn, in the opinion of the
Ombudsman, is that the WBSEDCL has failed to establish the
justification and correctness of the regenerated bills for the period
from November 2017 to January 2018 as per Regulatory provisions on
the basis of supporting documents. Those bills, are, therefore to be
cancelled. However, the Ombudsman misdirected himself in directing
further regeneration of the erroneously regenerated bills for the three
months from November 2017.
49. As such, the conclusion arrived at by the Ombudsman was contrary
to his previous observations and findings. Hence, the order of the
Ombudsman directing further regeneration of bills for the relevant
period cannot be sustained.
50. Accordingly, WPA 17828 of 2019 is allowed on contest, thereby setting
aside the order of the Ombudsman to the extent that the same
directed the WBSEDCL to further regenerate bills for the period from
November 2017 to January 2018 and setting aside the order of the
RGRO as a whole. The regenerated bills impugned herein are hereby
cancelled and quashed. Since the petitioner has already paid the
current electricity charges for the said period as per regular bills
raised by the WBSEDCL, no further amount need be paid by the
petitioner for the period-in-question.
51. There will be no order as to costs.
52. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!