Citation : 2023 Latest Caselaw 3988 Cal
Judgement Date : 21 June, 2023
21.06.2023
SL No.2
Court No.37
(gc/sg)
In The High Court at Calcutta
Civil Appellate Jurisdiction
Commercial Division
FA 187 of 2022
CAN 1 of 2022
CAN 2 of 2022
Eastern Coalfields Ltd.
Vs.
VSAIPPL-PE-SI(JV) & Ors.
Mr. Debnath Ghosh,
Mr. Syed Nurul Arefin,
Mr. Rahul Singh,
Ms. Rashmi Binayak,
...for the Appellant.
Mr. Partha Pratim Roy,
Mr. Srijib Chakraborty,
Mr. Satyaki Mukherjee,
Mr. Aditya Mondal,
...for the Respondents.
By consent of the parties, the appeal and the stay
application along with the application for evidence are
taken up together and disposed of by this common order.
The plaintiffs have filed an application for judgment
upon admission. The claim for judgment upon admission
is based on two letters being letter dated 27th June, 2018
addressed to the respondent by the agent of the mine
concerned and the letter dated 23rd July, 2018 from the
Eastern Coalfields Ltd. to the plaintiffs.
Mr. Debnath Ghosh, learned Counsel appearing on
behalf of the appellant submits that the tenor of the said
letter would not show that there has been an admission of
the claim of the plaintiffs as the recommendation of the
agent is dependent upon an approval being obtained from
the competent authority regarding the quantity mentioned
by the agent with regard to the excavation of coal and
removal of Over Burden (in short "O.B"). Mr. Ghosh
further submits that the plaintiffs have abandoned the
site and did not complete the work for which there is a
requirement of retender and the plaintiffs are liable for the
costs and expenses to be incurred for completing the
balance work.
Mr. Partha Pratim Roy, learned Counsel
representing the plaintiffs submits that the said two
letters unequivocally show the work done by the plaintiffs
and the amount is required to be paid on the basis of the
works carried out by the plaintiffs under the work
contract awarded to the plaintiffs. Mr. Roy also submits
that pursuant to the recommendation of the agent, the
plaintiffs, in fact, have accepted the quantification made
by the agent towards O.B. and coal quantity at the colliery
concerned and having regard to the fact that the offer of
the agent has been accepted by the plaintiffs, it is a
concluded contract and the appellant is bound to release
the payments on the basis of the acceptance
communicated to the agent on 26th July, 2018.
We have considered the submissions made on
behalf of the parties. We could not find any satisfactory
reply from Mr. Ghosh for not releasing the amount after
there is an acceptance of the offer duly communicated to
the E.C.L on 26th July, 2018. In the written statement
filed before the Commercial Court, there is no whisper of
any decision being taken by the competent authority of
the E.C.L. suggesting a contrary recommendation than
what was suggested by the agent. In fact, as rightly
pointed out by the learned Counsel for the plaintiffs under
the works contract "all measurements of O.B. removed
will have to be certified by Colliery Surveyor, Management
and Project Officer/Agent". In the instant case, the agent
has duly certified for the O.B. and the other works and
has forwarded his recommendation to the competent
authority for consideration. One would have expected
from the appellant to disclose in the written statement the
reason for non-acceptance of the recommendation of the
agent. Surprisingly, till date no counter-claim has been
made in the pending proceeding and by this time it may
have been time barred. The plaintiffs cannot suffer due to
lackadaisical approach of the competent authority in not
considering the recommendation of the agent. We have
not been shown a single document emanating from the
competent authority with regard to the recommendation
of the agent.
However, in view of the fact that there is no
unequivocal admission per se, in terms of money and that
in the written statement, it has been alleged that by
reason of abandonment of the work retendering was
necessary and the entire amount may not be payable, we
modify the order passed by the learned Trial Judge to the
extent that the appellant shall furnish an unconditional
bank guarantee of Rs.2.60 crores within two weeks from
date to the satisfaction of the learned Trial Court, in
default, the decree shall revive and would be immediately
executable.
The learned Trial Court is requested to follow the
case management strictly and conclude the trial as
expeditiously as possible without granting any
adjournment to either of the parties unless unavoidable.
The judgment of the learned Trial Court is modified
to the aforesaid extent.
In the event the suit is decreed, it is needless to
mention that the plaintiffs shall be entitled to interest
from the date of presentation of the plaint till the decree
is passed. The impugned order is modified to the
aforesaid extent.
With the aforesaid observation, the appeal and the
connected applications stand disposed of.
Urgent Photostat certified copy of this order, if
applied for, be given to the parties on usual undertaking.
(Uday Kumar, J.) (Soumen Sen, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!