Citation : 2023 Latest Caselaw 4316 Cal
Judgement Date : 19 July, 2023
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
W.P.A. No. 4640 of 2023
Jai Hind Logistics and another
Vs.
Indian Oil Corporation Ltd. and others
For the petitioners : Mr. Debabrata Saha Roy
Mr. Pingal Bhattacharyya
Mr. Subhankar Das
Mr. Neil Basu
Mr. Sankha Biswas
For the respondent
Nos.1 to 7 : Mr. Amit Kr. Nag
Mr. Partha Banerjee
For the respondent
No.9 : Mr. P.K. Dutta
Mr. Anant Shaw
Mr. Santanu Deb Roy
Mr. Mainak Ganguli
For the respondent
No.10 : Mr. Kallol Bose
Mr. Joy Chakraborty
Ms. Ipsita Ghosh
Hearing concluded on : 14.07.2023
Judgment on : 19.07.2023
Sabyasachi Bhattacharyya, J:-
1. The petitioner and the respondent nos.9 and 10 participated in a
tender floated by the IOCL (Indian Oil Corporation Limited) under a
Two-Bid System from Tank Truck (TT) owners for an award of contract
for road transportation of bulk petroleum products. The petitioner
participated therein but was disqualified at the technical evaluation
stage.
2. The present writ petition has been preferred challenging the
acceptance of the bids of respondent nos.9 and 10 as successful
bidders.
3. It is argued that, after the technical stage being crossed, a reverse
auction was to be held within the contemplation of the tender.
Thereafter, the bidder with the newest vehicles would be chosen as
successful and work orders would be issued to them.
4. In the present case, it is argued, the respondent nos.9 and 10
furnished forged documents, on the basis which they were declared to
be successful bidders. It is argued by the petitioner that fraud vitiates
all and, as such, even the writ court can enter into the question as to
whether the forgery committed by the respondent nos.9 and 10,
allegedly in collusion with the IOCL, vitiates the tender process.
5. Learned counsel for the petitioner, in such context, cites Munjal
Showa Ltd. Vs. Commissioner of Customs and Central Excise (Delhi-IV),
reported at 2022 SCC OnLine 1296, where it was held that fraud
vitiates everything. Learned counsel also relies on (2008) 12 SCC 306
[Behari Kunj Sahkari Avas Samiti Vs. State of Uttar Pradesh and
others], where it was observed by the Supreme Court that a person
committing fraud is not entitled to any equitable remedy.
6. Learned counsel for the petitioner submits that there were gross
discrepancies in the RC Books/Smart Cards offered in respect of TTs
of the respondent nos.9 and 10, insofar as the copies thereof annexed
to the opposition of the IOCL and the said respondents are concerned.
7. Uploading of RC Book/Smart Card is mandatory in tenders for
engagement of TTs, it is contended. In support of such submission,
the petitioner cites an unreported judgment of this Court dated April
19, 2022 passed in WPA No.4391 of 2022. In the said context, an
unreported Division Bench judgment of this Court passed on July 18,
2022 in MAT 687 of 2022, whereby the Single Judge secision cited
above was overturned, has also been cited. Lastly, an unreported
Supreme Court judgment dated September 30, 2022, passed by the
Supreme Court in Civil Appeal No.7038 of 2022, which distinguished
the Division Bench judgment and upheld the judgment of the learned
Single Judge, is also cited by the petitioner.
8. It is submitted next that merely because there is some disputed
question of fact, the writ court need not necessarily refuse to entertain
a writ petition. In support of such contention, learned counsel places
reliance on 2021 SCC OnLine SC 99 [Unitech Limited and Others Vs.
Telangana State Industrial Infrastructure Corporation (TSIIC) and
Others], where portions of the judgment reported at (2004) 3 SCC 553
[ABL International Limited and another Vs. Export Credit Guarantee
Corporation of India Ltd. and others] were also considered.
9. Learned counsel submits further that, in an appropriate case, where
there is a violation of a fundamental right, in the present case under
Article 14 of the Constitution of India, and/or natural justice,
alternative remedy is not a bar. In such context, the petitioner cites
Madhya Pradesh High Court Advocates Bar Association and Another
Vs. Union of India and Another, reported at 2022 SCC OnLine SC 639.
10. Learned counsel for the respondent no.9 argues that the authenticity
of the Registration Certificates issued by the concerned RTO (Regional
Transport Officer), with the seal and signature of the registering
authority, has not been rebutted. It is evident from the said
Certificates that the vehicles were registered on November 25, 2022
and the Registration Certificates were issued on November 28, 2022.
The authenticity of those was also confirmed by the RTO by a letter
dated April 17, 2023. All the said documents are part of a report filed
in the form of an affidavit by the IOCL and affirmed on June 6, 2023,
which is a part of the records of the instant writ petition.
11. It is further argued that even if there is any discrepancy in the m-
Parivahan Portal, that is, the "Vahan" portal, the respondent no.9
cannot be saddled with any responsibility in that regard. The writ
petitioners‟ Registration Certificates were also issued by the same
authority on the same date, that is, November 28, 2022.
12. Learned counsel appearing for the respondent no.10 contends that the
writ petition is liable to be dismissed in limine, since the petitioner
participated in the tender process. The tender process was completed
and Letter of Acceptance was issued on February 8, 2023. Work order
was subsequently issued on March 4, 2023. Hence, there is no scope
of interference in the present writ petition at this stage.
13. It is argued that the petitioner sought to confuse a previous co-
ordinate Bench after receiving a copy of the affidavit-in-opposition of
the respondent no.10, where photocopies of Registration Certificates of
vehicles as well as Work order and Letter of Acceptance were annexed.
The petitioner sought to argue thereafter that the RC Book was not
uploaded, by seeking to confuse the court.
14. It is submitted that the petitioners‟ document was also uploaded in
the e-tender portal, as the petitioner was technically qualified. It is
also seen from the documents-in-question that the process of
registration of the respondent no.10 was duly completed and
approved. Only in the column of RC Print/Smart Card, it was shown
as „not available‟. The mere mention of such fact, it is argued, could
not have altered the status of the petitioners‟ vehicles as duly
registered.
15. It is argued that there is no basis of the allegations of forgery
regarding the RC Books of the respondent nos.9 and 10.
16. A document is sought to be produced by the petitioner during
arguments, in support of the submission that there were
discrepancies in the RC Books/Smart Card of the vehicle. However,
the said document neither contains any seal nor any signature of the
transport authority. Not only has the IOCL denied the allegation of
forgery but also the transport authority of Nagaland, which issued the
relevant certificates. As such, it is argued that the writ petition ought
to be dismissed.
17. It is further argued that the judicial review sought to be invoked by
the petitioner is not maintainable, since there is no public interest
element involved.
18. Heard learned counsel. The tender document indicates that the bid
submission was to start from November 21, 2022 and end on
November 30, 2022. One of the pre-qualification criteria stipulated in
the bid document was that RC Book copy was to be submitted for
Tank Truck. It was also provided that failure to meet the pre-
qualification criteria would render the bid to be summarily rejected.
19. Thus, there is no doubt on the requirements as per the tender
document.
20. The petitioner has relied on certain documents opted from the Vahan
portal of the Government, where the documents pertaining to the
present tender were uploaded. The said documents, insofar as those
pertained to respondent nos.9 and 10, indicate that the RC
Print/Smart Card status was shown to be „not available‟. It is
submitted that the said situation prevailed till after the conclusion of
the bid submission date.
21. However, from the same document, it is also seen that, with regard to
the application numbers of the respondent nos.9 and 10, the current
status of the new registration of the vehicles of the said respondents
were shown to be completed/approved on November 24, 2022. Again,
the Certificates of Registration produced by respondent nos.9 and 10
indicate that the date of issuance of those was November 28, 2022,
which is also prior to the conclusion of the bid submission period.
The registration date, as indicated therein, is November 24, 2022 and
the date when the copy thereof was issued was November 28, 2022.
22. The petitioners also seek to rely on a document which is purportedly a
"Tender Summary Report". In the said document, as against the
name of the respondent nos.9 and 10, the submission dates of the
documents are shown to be November 29 and November 30, 2022
respectively. The authenticity of the said documents, at least prima
facie, is also corroborated by a communication dated May 10, 2023 by
the Regional Transport Officer, Kohima, Nagaland. In the said
document, at the behest of the writ petitioner, the registration
authorities had furnished certain documents with regard to
respondent nos.9 and 10, where the date of alteration in RC as per
Parivahan portal was shown to be November 29, 2022, and the date of
print of altered RC as per Parivahan portal was shown to be „not
available‟ for one of the said respondents, and December 8, 2022 for
the other.
23. However, it has to be noted that the said dates relate to "alteration in
RC" and not to the original Registration Certificates. Hence, the
possibility cannot be ruled out of the said entries having been made in
respect of subsequent alterations of the Registration Certificates on
certain technical aspects, due to which such entries do not
conclusively throw any light on the veracity or otherwise of the
Registration Certificate on the date of issuance of the original.
24. Mere non-availability of RC Print/Smart Card cannot be an indicator
that the documents were actually not issued or were forged.
25. That apart, the entries in the Vahan portal are maintained by the
Government authorities. Neither the IOCL nor the respondent nos.9
and/or 10 is responsible for the same. As such, even if any
discrepancy was seen in the documents obtained by the petitioner
regarding the respondent nos.9 and 10 from the said portal, the same
could not, per se, vitiate the acceptance of the bids of the said
respondents as valid.
26. What is to be seen is whether the respondent nos.9 and 10 uploaded
genuine documents on the website of the IOCL, for the purpose of
tender process and whether the IOCL independently verified the same
to be correct.
27. The relevant communications annexed at pages 35 and 37 of the
affidavit-in-opposition of the IOCL speak for themselves. Vide the first
communication dated April 4, 2023, the Transport Commissioner,
Motor Vehicles Department, Government of Nagaland, sought a
verification of the Registration Certificate at the behest of the IOCL,
for re-verification of the authenticity of the allegation made by the
petitioner. In reply, the RTO, Kohima, Nagaland, by his
communication dated April 17, 2023 clearly responded that the copy
of the 15 Registration Certificates received for verification were indeed
registered in the Officer of the RTO, Kohima and found to be genuine.
28. Hence, two crucial steps were passed by the respondent nos.9 and 10
with flying colours. First, the documents (Registration Certificates)
submitted online by the respondent nos.9 and 10 were prima facie
genuine. Secondly, on an independent enquiry, the IOCL
subsequently was informed by the registering authority itself that
those documents were genuine. Hence, there cannot be any further
question regarding the genuineness of the documents offered by the
respondent nos.9 and 10, who are successful bidders.
29. Insofar as the challenge of the petitioner is concerned, the same is
also tainted by insufficient particulars of fraud/forgery having been
furnished in the pleadings, following the principle of Order VI Rule 4
of the Code of Civil Procedure.
30. No specific particulars as to how and when the forgery was committed,
has been established by the petitioner.
31. That apart, such an enquiry is beyond the scope of the writ
jurisdiction, which has a short window of interference in judicial
review.
32. In the present case, nothing on record shows beyond doubt or even
substantially that the respondent nos.9 and 10 committed any forgery
or fraud in uploading invalid and/or manufactured documents and/or
the IOCL acted without authority in accepting those.
33. The IOCL, thus, did not commit any error in acting in terms of the
tender document to accept the bids of the respondent nos.9 and 10.
34. Hence, it cannot be said that the petitioners‟ allegation of
fraud/forgery has been substantiated in any manner.
35. Even taking into consideration the judgments cited by the parties, the
scope of interference in judicial review is limited. Unless specifically
pleaded and proved on every particular, there is no scope of fraud
having been substantiated, for it to vitiate any action of the
respondents.
36. Hence, the judgments cited on fraud by the petitioner are not germane
in the present context at all.
37. Rather, it is well-settled that participants in a tender process, after
becoming unsuccessful, ought not to be permitted to turn back and
challenge the tender process.
38. The petitioner, in the present case, participated fully in the tender
process and after becoming unsuccessful, has challenged the
documents furnished by the respondents as forged.
39. Such act on the part of the petitioner appears to be inspired not by
bona fides but as an afterthought, to gain an unfair advantage by
creating a cloud on the success of the respondent nos.9 and 10 in the
very tender process where the petitioners participated, but turned out
to be unsuccessful. Such endeavour on the part of the writ petitioners
ought to be deprecated.
40. Accordingly, there is no scope of interference in the present writ
petition. Hence, WPA No.4640 of 2023 is dismissed on contest,
without any order as to costs.
41. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!