Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Harji Engineering Works Pvt. Ltd vs Union Of India And Another
2023 Latest Caselaw 4142 Cal

Citation : 2023 Latest Caselaw 4142 Cal
Judgement Date : 6 July, 2023

Calcutta High Court (Appellete Side)
Harji Engineering Works Pvt. Ltd vs Union Of India And Another on 6 July, 2023
6th July,
 2023
 (AK)
  30


                               W.P.A 12900 of 2023
                               IA No: CAN 1 of 2023


                          Harji Engineering Works Pvt. Ltd.
                                         Vs.
                            Union of India and another


                          Mr. Kishore Dutta
                          Mr. Rupak Ghosh
                          Mrs. Sweta Gandhi
                                                      ...for the petitioner.

                          Mr. Asit Kumar De
                                               ...for the Union of India.

                          Mr. Rohit Das
                          Ms. Kishwar Rahman
                          Mr. Preetam Majumdar
                                           ...for the respondent no.2.

Learned senior counsel for the petitioner contends

that the respondent authorities have acted in

contravention of law and natural justice in floating a new

tender for the completion of the balance work, which was

yet to be completed by the petitioner in terms of a

contract awarded to the petitioner, without permitting the

petitioner to conclude its work.

It is submitted that despite the private respondents

having given the petitioner an option to complete the

balance work, prior to such extension itself, the new

tender was floated.

It is submitted that during pendency of the writ

petition, a termination notice was issued against the

petitioner by the respondent authorities, which is also

required to be challenged.

Learned counsel appearing for the respondent

authorities controverts the submissions of learned senior

counsel for the petitioner and argues that sufficient

opportunities were given to the petitioner to complete the

work awarded to the petitioner.

However, in spite of such option being given and a

further extension being given even after the floating of the

impugned new tender, the petitioner failed to complete

such work in time, due to which the contract of the

petitioner was terminated on June 11, 2023.

It is further argued that, in the meantime, the new

tender has been given effect to by awarding the balance

work to a third party, which has already undertaken such

balance work.

Learned counsel appearing for the respondent

authorities also places reliance on the relevant clauses of

the fresh tender, floated in the meantime by the

respondents, and indicates that the same included a

procedure for subsequent reverse auction after the

technical bid opening date.

That apart, it is submitted that a six-month window

was left for awarding the contract in terms of the new

tender, which gave ample time to the respondent

authorities to assess whether the petitioner is able to

complete the work awarded to the petitioner, in terms of

the extension, in the meantime.

However, in view of the petitioner having failed to

utilize such opportunity, the new tender was given effect

to subsequently.

Learned counsel for the respondents cites two

judgments of the Supreme Court in support of the

contention that the window of interference under judicial

review in a tender process is extremely limited,

particularly in respect of public projects.

The first judgment cited is N.G. Projects Limited vs.

Vinod Kumar Jain and others reported at (2022) 6 SCC

127 and the second Food Corporation of India and others

vs. Jagannath Dutta and others reported at 1993 Supp (3)

SCC 635.

Upon a consideration of the submissions of parties,

the chronology of events in the present matter can be

summed up as follows:

After the petitioner having sought to foreclose the

contract on certain allegations on January 5, 2023, a

communication was issued by the respondent - Bharat

Heavy Electricals Limited (BHEL) on January 6, 2023

whereby the BHEL warned the petitioner that the

petitioner had not submitted any request letter for time

extension nor had taken any action from their side to

continue the work.

It was also mentioned in the said letter that, despite

lot of persuasions by BHEL vide previous letters, the

petitioner had allegedly failed to submit request letter for

time extension in line with Clause 2.11.1 of the General

Conditions of Contract (GCC), along with balance work

completion plan, within the stipulated time period, that

is, by January 3, 2023.

However, in the second paragraph of the letter dated

January 6, 2023, the BHEL gave a further opportunity to

the petitioner to arrange for immediate submission of a

request for time extension, along with taking corrective

measures regarding augmentation of manpower etc.

towards fulfillment of contractual obligations, failing

which the BHEL might be left with no option other than

exercise its right to complete the work through suitable

alternatives at the 'Risk and Cost' of the petitioner in line

with the provision of the contract (2.7.2 of the GCC).

Thereafter, the BHEL, upon the petitioner having

not applied for extension till then, floated the impugned

new tender on February 2, 2023.

Subsequently, on February 10, 2023, an application

for extension was made by the petitioner, upon which an

extension was granted on April 1, 2023, till April 4, 2023.

However, thereafter, the petitioner's contract was

apparently terminated on June 11, 2023, upon giving a

notice of termination on June 10, 2023 by the BHEL, on

the allegation that despite the time having been extended,

the petitioner failed to complete its work in terms of the

contract awarded to it.

Upon a perusal of the communication dated

January 6, 2023, it is evident that the same was not

merely a reminder to the petitioner to apply immediately

for submission of request for time extension, but also a

warning to the petitioner that they had failed to avail

previous opportunities of applying for extension of time

and/or completion of the work.

After having waited for a reasonable period, for

almost one month, awaiting such extension application

from the petitioner, the BHEL floated the new tender on

February 2, 2023.

Notably, in Clause 17.0 of the said tender

document, it was stated that the validity of the offer shall

be for six months from the latest due date of offer

submission (including extension, if any), unless specified

otherwise.

Clause 18.0 of the same also stipulated that the

BHEL shall resort to Reverse Auction for the tender.

Reverse Auction was to be conducted among the techno-

commercially qualified bidders.

The date of opening of the tender, on the techno-

commercial aspect, was February 13, 2023. Hence, the

BHEL kept sufficient leeway reserved for awaiting the

completion of the work by the petitioner within the time

which was extended at the behest of the BHEL.

Such floating of the tender at the relevant juncture,

that is, on February 2, 2023, thus, cannot be faulted per

se, since the BHEL could not have waited till the eleventh

hour, till after failure of the petitioner, to initiate

proceedings for floating a tender completion of the

balance work by a third party sufficiently in advance,

keeping in view the urgent and public nature of the work

contemplated.

Subsequently, on February 10, 2023 upon the

petitioner having applied for extension of time to complete

its work, an extension was duly granted by the BHEL on

April 1, 2023 till April 4, 2023.

It is relevant to mention that in the meantime, no

effect had been given to the new tender floated by the

BHEL by awarding work to any third party.

However, after waiting sufficiently for two months

thereafter, a termination notice was issued on June 10,

2023 and the termination of the petitioner's contract was

effected on June 11, 2023, on the allegation that the

petitioner, despite getting such extended time and two

months thereafter, failed to complete its work.

Even without going into the veracity of such

allegations and/or the merits of the said allegations, it is

clear that as on the date of filing of the writ petition, there

was no irregularity or illegality on the part of the BHEL

merely by floating the new tender which has been

assailed in the writ petition.

In view of the above developments, it can be seen

from the records that the BHEL had acted sufficiently in

consonance with the principles of natural justice and in

terms of the contract, rather, going out of its way to give

several extensions to the petitioner for completion of the

work.

Hence, the writ petition, as it stands, does not

justify any interference with the tender process.

However, a subsequent cause of action arose for the

petitioner during pendency of the writ petition, by

termination of the contract.

The termination of the contract of the petitioner on

June 11, 2023, during pendency of the writ petition, is

not the subject matter of the present writ petition and is

only a subsequent cause of action which has been

brought to the notice of the court by way of an

interlocutory application filed in connection with the writ.

Hence, the right of the petitioners has to be reserved

with regard to intended challenge, if any, against such

subsequent termination.

However, insofar as the present writ petition is

concerned, the same cannot succeed in view of the

observations made above.

Accordingly, WPA 12900 of 2023 is dismissed on

contest, without any order as to costs. CAN 1 of 2023 is,

accordingly, dismissed as well.

Nothing in this order shall preclude the petitioner

from challenging the subsequent termination of the

petitioner on June 11, 2023 and/or the notice of

termination which resulted in such termination by way of

a fresh writ petition.

If a fresh writ petition is so filed against such

termination by the petitioner, the writ court shall decide

the same afresh, in accordance with law and without

being swayed in any manner by any of the observations

made herein.

It is further made clear that since an objection as to

maintainability of the present writ petition and the

prospective writ petition on the ground of availability of

an arbitration clause in the contract between the parties

has been taken by the respondents, the question of

maintainability of the subsequent writ petition, if so filed,

is left open to be decided in the fresh writ petition.

Since no affidavits have been called for, it is deemed

that none of the allegations made by the parties are

admitted by the other parties.

Urgent photostat copies of this order, if applied for,

be given to the parties upon compliance of all requisite

formalities.

(Sabyasachi Bhattacharyya, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter