Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Damodar Valley Corporation And ... vs Bla Projects Private Limited And ...
2023 Latest Caselaw 4006 Cal

Citation : 2023 Latest Caselaw 4006 Cal
Judgement Date : 3 July, 2023

Calcutta High Court (Appellete Side)
Damodar Valley Corporation And ... vs Bla Projects Private Limited And ... on 3 July, 2023
                                                  MAT NOS (894 OF 2023 & 895 OF 2023)
                                                             REPORTABLE

         IN THE HIGH COURT OF JUDICATURE AT CALCUTTA
                  CIVIL APPELLATE JURISDICTION
                             APPELLATE SIDE



                         RESERVED ON: 08.06.2023
                         DELIVERED ON:03.07.2023



                                 CORAM:

        THE HON'BLE MR. CHIEF JUSTICE T.S. SIVAGNANAM

                                    AND

      THE HON'BLE MR. JUSTICE HIRANMAY BHATTACHARYYA

                          MAT NO. 894 OF 2023
                         (I.A. NO. CAN 01 OF 2023)
                                   WITH

                          MAT NO. 895 OF 2023
                         (I.A. NO. CAN 01 OF 2023)


           DAMODAR VALLEY CORPORATION AND OTHERS
                                 VERSUS
          BLA PROJECTS PRIVATE LIMITED AND ANOTHER


Appearance:-
Mr. Anirban Ray, Learned Government Pleader.
Mr. Swarajit Dey, Advocate.
Ms. Riddhi Jain, Advocate.
                                                           ...For the Appellants


Mr. Kishore Datta, Advocate.
Mr. Amitesh P. Ray, Advocate.
                                       ...For the Respondent/BLA Projects

Ms. P. Saha Saha (Das)
                                                ...For the Respondent No. 2 in
                                                          MAT No. 895 of 2023

                                 Page 1 of 24
                                                       MAT NOS (894 OF 2023 & 895 OF 2023)
                                                                 REPORTABLE

                                      JUDGMENT

(Judgment of the Court was delivered by T.S. SIVAGNANAM, CJ.)

1. These intra court appeals are directed against the common order

passed in WPA No. 26117 of 2022 and WPA No. 27405 of 2022. Since the

facts in both the cases are identical and common submissions were made by

the learned advocates for the parties, with their consent the appeals are

disposed of by this common judgement and order.

2. The first respondent in this appeal is the writ petitioner, BLA Projects

Private Limited, Kolkata. The writ petitions were filed challenging the

correctness of the decision taken by the appellant, DVC, as communicated

to the respondent vide email dated 15.11.2022. By the said communication,

the respondent writ petitioner was informed that their tender submitted for

the subject work has been rejected during the technical evaluation by the

duly constituted Committee for the reasons "administrative grounds". The

writ petition was filed challenging the rejection of the petitioners technical

bid primarily on the ground that the order of rejection did not contain any

reasons. On 24.11.2022 the appellant informed the respondent the reasons

for rejection in reply to the writ petitioner's letter dated 16.11.2022 wherein

they sought for reasons for rejection. In the communication dated

24.11.2022 the following were the reasons for rejection:-

Reference to your letter dated 16.11.2022, the reasons on which the Technical Evaluation Committee has rejected your bid is furnished as below:

1) Fraudulent practice was noticed against you related to pilferaging of DVC's transported good quality coal and replacement of the same with some extraneous materials like boulders, mud,

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

stones etc. While executing a coal transportation contract of RTPS, DVC. Same was proved on 01.06.2018 by RTPS officials in presence of contract's representatives. Letter was issued to you on 02.06.2018 intimating this incident of ill practice by them FIR was registered on 09.06.2018 by DVC official. The Charge Sheet/Final Report was issued by Raghunathpur PS, Dist, Purulia, W.B. on 24.10.2019.

2) You have repeatedly suppressed the above charge of pilferage and fraudulent practices.

3) Thus, you have committed a transgression through a violation of Section 3 of Integrity Pact.

4) Decision was taken on administrative grounds as per legal opinion as the above investigation towards the incident of pilferage and fraudulent practices is sub-judice at Hon'ble Calcutta High Court.

3. The writ petitioner contended that in the tender document/conditions

of tender there is no clause requiring the petitioner to disclose any FIR or

charge sheet. In any event the disclosure has to be made if it is within three

years and in the instant case three years had lapsed from the date on which

the FIR was lodged i.e. on 09.06.2018. The petitioner relied upon the stand

taken by the appellant before the Hon'ble Supreme Court in Special Leave

Petition arising out of an order passed by the Division Bench of this Court in

WPA No. 23775 of 2022 wherein the appellant had stated that a

transgression had been committed by the writ petitioner in June 2018 when

the incident occurred. Therefore it is submitted that in terms of Section 5 of

the tender conditions the three year period has been stipulated and the

subject tender having been invited much after the period of three years,

there is no requirement for any voluntary disclosure of the alleged

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

transgression. Further by referring upon clause 2.3(iii) of the Policy for

Withholding and Banning of Business Dealings, the voluntary disclosure is

encouraged not with a view to reject the bid but to keep an alert watch on

the bidder's action in the tender and subsequent contract. Further it was

contended that the action of the appellant in rejecting tender was arbitrary

and meant for certain extraneous reasons and not as per terms of tender

and therefore the action is not only arbitrary but mala fide as well. Further

it was contended that in terms of the tender the Integrity Pact is required to

be signed by the intending bidder which does not provide for any scope for

disclosure of any information along with the Integrity Pact and all that the

bidder is required to do is to sign the Integrity Pact and submit the same to

the tender inviting authority. It was further submitted that even assuming

that there was a transgression, in terms of the clause 2.3(iii) of the Policy for

Withholding and Banning of Business Dealings it would not mean automatic

disqualification of the bid as conditions stipulates that the declared conflict

of interest may be evaluated and mitigating steps if possible should be taken

by the procuring entity. Further voluntary reporting of previous

transgression of code of integrity elsewhere should be evaluated and barring

cases of various grades of debarment, alert watch may be kept on the

bidder's action in the tender and subsequent contract. Further it is

submitted that the Director of the company was a person against whom the

charge has been laid in the criminal case and the company is not the

accused. Subsequently the criminal case has also been stayed in the

proceedings initiated by the writ petitioner before this Court. Further the

three year time limit prescribed in Section 5 of the conditions of tender

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

should not be computed from the date on which the charge sheet was laid

but as admitted by the appellant from the date on which the FIR was

registered and if done so the subject tender having been invited much after

the period of three years, the technical bid of the writ petitioner ought not to

have been rejected. Further it was contended that the appellant had placed

reliance on the decision of the Division Bench of this Court in MAT No. 1932

of 2022 which was an appeal arising out of the order passed in WPA No.

23775 of 2022 filed by the respondent writ petitioner and the said decision

cannot be pressed into service as the respondent writ petitioner had

preferred appeal to the Hon'ble Supreme Court in Special Leave to Appeal

No. 3031 of 2023 and the Hon'ble Supreme Court after hearing the parties

by order dated 03.03.2023 ordered that the matter requires consideration.

Therefore the appellant cannot place reliance on the said decision.

4. The appellant resisted the prayer sought for in the writ petition inter

alia contending that the reasons for rejection was clearly set out and

communicated to the writ petitioner and the reasons cannot be said to be

bad in law. It was further contended that in terms of clause 2.3 of the policy

conditions the writ petitioner is obliged to disclose any previous

transgression of code of integrity whether asked or not and admittedly the

writ petitioner had suppressed the fact that their Managing Director had

been charge sheeted under various provisions of the Indian Penal Code on

24.10.2019. Furthermore the writ petitioner's bid has been rejected on the

ground that the writ petitioner has repeatedly suppressed the fact of the FIR

being registered and subsequently the laying of the charge sheet and

participated in 14 previous tender in the year 2021 and 2022 and

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

admittedly in none of those tenders writ petitioner had disclosed about the

pendency of the criminal proceedings. Further by referring to the definition

of the "fraudulent practise" as defined in the policy it was submitted that

any omission or mis representation or making false declaration or providing

false information would be "fraudulent practice". It was contended that it is

the appellant who is entitled to interpret the terms of the tender and it is not

for the writ petitioner to make an independent interpretation to the said

terms. Further it was contended that Section 5 of the tender conditions

would have no application to the facts of the case as the order rejecting the

technical bid was by referring to Section 3 of the tender conditions wherein

there is no mention of any time limit of three years and time limit prescribed

in Section 5 cannot be read into Section 3 of the tender conditions. It was

further submitted that Section 3 of the tender conditions contains two

limbs. the first of which deals with transgression committed before or during

the execution of the work through the violation of Section 2 of the conditions

and the second limb is in any other form stage to put the bidder's reliability

or credibility in question and in either of the contingencies the appellant is

entitled to disqualify such bidder from the tender process or to terminate the

contract if already signed and take action as per procedure of "Banning of

Business Dealings". Thus, it was contended that suppression of material

fact regarding criminal proceeding itself is a transgression and in terms of

Section 3 of the Integrity Pact the appellant was entitled to reject the bid of

the writ petitioner. It was reiterated that even assuming that three years

period is applicable the same has not expired since three years had not

lapsed after the charge sheet was laid. Furthermore the suppression by the

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

respondent writ petitioner has led to doubt the reliability and credibility of

the writ petitioner and the appellant was entitled to reject the bid in terms of

Section 3 of the Integrity Pact.

5. The Learned Single Bench proceeded to decide the question as to

whether the impugned rejection of the writ petitioner's technical bid falls in

Section 3 of the Integrity Pact or any of the relevant clauses which was

referred to by the parties. After noting Section 3 and Section 5, the learned

writ court took note of clause 2.3 of the Policy for Withholding and Banning

of Business and held that the from a conjoint reading of all the conditions, it

is clear that the obligations on the part of the writ petitioner was to disclose

past transgression which occurred in the three year period prior to the date

of the tender and hence does not cover the alleged fraudulent practice which

occurred before June, 2018 which is specifically the case as stated by the

appellant in their letter dated 24.11.2022. Further the learned writ court

held that the scheme of the terms and conditions makes it clear that the

culpability with regard to the violation of any of the sections relating to

transgression must relate to a fraudulent practice which is limited to three

years preceding the tender. Further the court held that the sharpness of the

penalty has somewhat been blunted by clause 2.3(iii) of the Policy.

Thereafter the learned writ court proceeded to note the decisions of the

Hon'ble Supreme Court with regard to the scope of interference of a writ

court in matters of tender and held that the decision of the Hon'ble Supreme

Court reinforce the view that the tender document is the best judge to

understand the requirements of the Tender and the Court should not

disturb the interpretation given by the Tendering Authority. The learned writ

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

court then proceeded to point out that all the decisions of the Hon'ble

Supreme Court however preserve the window for arbitrariness and a mala

fide award or rejection of a Tender, including for extraneous considerations.

Ultimately the learned writ court came to the conclusion that the decision to

exclude the writ petitioner from participating in the Tender as arbitrary

unreasonable and would call for interference by the learned writ court. With

regard to the decision of the Division Bench of this court in MAT No. 1932 of

2022, the court held that the said judgment was challenged before the

Hon'ble Supreme Court and orders have been passed by the Hon'ble

Supreme Court on various dates which make it clear that the matter is

under consideration of the Hon'ble Supreme Court. Further the writ court

came to the conclusion that the order of rejection of the technical bid of the

writ petitioner amounts to virtually blacklisting the writ petitioner without

giving any opportunity of hearing. Accordingly the communications which

were impugned in the writ petitions were quashed and direction was issued

to the appellant to evaluate the technical bid of the writ petitioner and allow

the writ petitioner to participate in the Tenders. Challenging the correctness

of the orders passed by the learned writ court the present appeals have been

preferred.

6. We have elaborately heard Mr. Anirban Ray, learned Government

Pleader assisted by Mr. Swarajit Dey and Ms. Ridhhi Jain, learned

Advocates for the appellants and Mr. Kishore Datta, learned Senior Advocate

assisted by Mr. Amitesh P. Ray, learned Advocate for the respondent/BLA

Projects and Ms. P. Saha Saha (Das), learned Advocate for the Respondent

No. 2 in MAT/895/2023.

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

7. The learned Advocates appearing on either side elaborately reiterated

the submissions made before the learned writ court and also placed reliance

on the decisions which were relied upon by them when the writ petition was

heard. The issue which falls for consideration in these appeals is whether

the action of the appellant in rejecting the technical bid of the respondent

writ petitioner in respect of subject tenders could be called in question in a

writ proceeding and if so under what circumstances and is there any

limitation or embargo placed upon the learned writ court to interfere in any

such matters.

8. Before we proceed to take a decision on the facts and circumstances of

the case on hand, it would be necessary and beneficial to take note of the

legal position which have been clearly enumerated/ adumbrated in various

decisions of the Hon'ble Supreme Court. To be noted that the learned writ

court in paragraph 19 of the impugned order has referred to various

decisions and has held that the author of the tender document is the best

judge to understand requirements of the Tender and the Court should not

disturb the interpretation given by the tender inviting authority.

Nevertheless the learned writ court quashed the decision of the appellant on

the ground that the same is arbitrary and unreasonable as it which was a

permissible a ground for the learned writ court to step in.

9. In Tata Cellular Versus Union of India 1 the Hon'ble Supreme Court

held that the principles of judicial review would apply to exercise all the

contractual powers by government bodies in order to prevent arbitrariness

or favouritism, however there are inherent limitations in exercise of that

(1994) 6 SCC 651

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

power of judicial review. The government is the guardian of the finances of

the State and it is expected to protect the financial interest of the State. The

right to reflect the lowest offer in a tender is always available to the

government but the principles laid down in Article 14 of the Constitution

have to be kept in view while upsetting or refusing tender. There can be no

question of infringement of Article 14 if the government tries to get the best

persons or the best quotation. The right to choose cannot be considered to

be an arbitrary power and however if the said power is extraneous or for any

collateral purpose, exercise of that power will be struck down. Further it was

pointed out that the doubt of the court is to confine itself to the question of

illegality, that it's concern should be (i) whether the decision making

authority exceeded its powers? (ii) committed an error of law (iii) committed

the breach of rules of natural justice (iv) reached a decision which no

reasonable tribunal would have reached or (v) abused its powers. It was held

that it is not for the court to determine whether a particular policy or

particular decision taken in the fulfilment of the policy is fair and it is only

concerned with the manner in which those decisions have been taken. Thus,

the ground on which the administrative action could be subject matter of

judicial review were categorise in three categories namely illegality,

irrationality and procedural impropriety.

10. In an earlier decision in the case of Ramana Dayaram Shetty

Versus The International Airport Authority of India 2 it was held that

the terms of notice inviting tender cannot be ignored as been redundant or

(1979) 3 SCC 489

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

being superfluous and they must be giving a meaning and necessary

significance.

11. In Silppi Constructions Contractors Versus Union of India and

Another 3 as it was held that the court must realise the limitations and the

havoc which needless interference in commercial matters would cause. In

contracts involving technical issues, the court should be even more

reluctant because most of the Judges do not have the necessary expertise to

adjudicate upon technical issues which is beyond the domain of the Court.

Further the Court should not use a magnifying glass while scanning the

tender and make small mistakes to appear as big blunders. The Court must

give fair play in the joints to the government and public sector undertakings

in the matter of contracts. Further that the Court should exercise restrain

while exercising the power of judicial review in commercial matters. The

Court will normally loathe to interfere in any contractual matters unless

clear cut case of arbitrariness or mala fide or bias or irrationality has been

met out.

12. In National High Speed Rail Corpn. Ltd. Versus Montecarlo

Limited 4 the Hon'ble Supreme Court sounded a word of caution while

entertaining the writ petition and/or granting stay which ultimately may

delay the execution of mega projects. In Jagdish Mandal Versus State Of

Orissa & Ors.5 it was held that evaluating tender and awarding contracts

are commercial functions; principles of equality and natural justice stay at a

distance; if the decision relating to award of contract is bonafide and is in

(2020) 16 SCC 489

(2022) 6 SCC 401

(2007) 14 SCC 517

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

public interest, courts will not, in exercise of power of judicial review,

interfere even if a procedural aberration or error in assessment or prejudice

to a tenderer is made out; the power of judicial review will not be permitted

to be invoked to protect private interest at the cost of public interest or to

decide contractual disputes. The above decisions were noted by the Hon'ble

Supreme Court in M/S N.G. Projects Limited Versus M/S Vinod Kumar

Jain & Ors. 6 In the said decision it was held that the question as to

whether a term of the contract is essential or not is to be viewed from the

perspective of the employer and by the employer. It was held that

satisfaction whether a bidder satisfies the tender condition, is primarily

upon the authority inviting the bids, as such authority is aware of the

expectations from a tenderer while evaluating the consequences of non-

performance. It was further held that the Writ Court should refrain itself

from imposing its decision from the decision of the employer as to whether

or not to accept the bid of a tenderer. As the Court does not have the

expertise to examine the terms and conditions of the present day economic

activities of the State and this limitation should be kept in view and Court

should be even more reluctant in interfering with contracts involving

technical issues as there is a requirement of the necessary expertise to

adjudicate upon such issues. Further it was held that the approach of the

Court should not be to find fault with magnifying glass in its hands, rather

the Court should examine as to whether the decision making process is after

complying with the procedure contemplated by the Tender Conditions.

Further, it was held that if the Court finds that there is total arbitrariness or

(2022) 6 SCC 127

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

that the tender has been granted in a malafide manner, still the Court

should refrain from interfering with the grant of tender, but instead relegate

the parties to seek for damages for wrongful exclusion rather than to injunct

the execution of the contract.

13. In Tata Motors Ltd. Versus Brihan Mumbai Electric Supply and

Transport & Ors.7, the Hon'ble Supreme Court after taking note of the

decision in Silppi Constructions Contractors (Supra) held that ordinarily

a Writ Court should refrain from imposing its decision from the decision of

the employer as to whether or not to accept the bid of a tenderer unless

something very gross or palpable is pointed out. The Court ordinarily should

not interfere in matters relating to tender or contract. To set at naught the

entire tender process at the stage when the contract is well under way,

would not be in public interest and initiate a fresh tender process may

consume lot of time and also loss to the public exchequer to the tune of

crores of rupees. Further, after referring to the decision of the Hon'ble

Supreme Court in Air India Ltd. Versus Cochin International Airport

Limited 8 it was held that award of a contract, whether by a private party or

by a State is essentially a commercial transaction. A State can choose its

own method to arrive at a decision and it is free to grant any relaxation for

bona fide reasons, if the tender conditions permit such relaxation, further

even when some defect is found in the decision making process, the Court

must exercise its discretionary powers under Article 226 with great caution

and should exercise it only in furtherance on public interest and not merely

2023 SCC Online SC 671

(2000) 2 SCC 617

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

on making of a legal point that the Court should always keep the large

public interest in mind in order to decide whether its intervention is called

for or not and only when it comes to a conclusion that overwhelming public

interest requires interference, the Court should interfere.

14. Bearing the above legal principles in mind, we now examine the facts

of the case on hand. At the first instance, the writ petitioner was informed

by an auto-generated mail that their tender has been rejected during

technical evaluation by the duly constituted committee for the reason

"administrative ground". It is no doubt true that the said communication did

not set out as to what was the "administrative ground" on which the tender

was rejected during technical evaluation. The explanation offered by the

learned Advocate for the appellant is that it is an auto-generated mail and,

therefore, it has mentioned the reason for rejection as "administrative

ground" nevertheless when the appellant sought for the reasons, the same

has been furnished. In the earlier portion of this judgment and order we

have set out the reasons for rejection. The first among the three reasons is

that fraudulent practices as noticed against the writ petitioner relating to

pilferage of DVC's transported good quality coal and replacement of the

same with some extraneous materials like boulders, mud, stone and etc.

while executing the coal transportation contract of RTPC, DVC. The said

fraudulent practice is stated to have been established/ proved on

01.06.2018 by the officials of DVC in the presence of the contractor's (writ

petitioner's) representative and a letter was issued to the writ petitioner on

02.06.2018 intimating the illegality and FIR was registered on 09.06.2018

and charge sheet has been laid on 24.10.2019. The second reason for

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

rejection is that the writ petitioners have repeatedly suppressed the said

charge of pilferage and fraudulent practices. The third reason is that the

appellants have committed a transgression through a violation of Section 3

of the Integrity Pact.

15. The Integrity Pact is a form which is mandatorily required to be

executed by the bidder. Section 2 of the said Pact deals with commitment of

the bidders/ contractors. Clause 1 of Section 2 states that the bidders/

contractors commit themselves to take all measures necessary to prevent

corruption. The bidders/ contractors commit themselves to observe the

principles which have been set out in Clauses (a) to (e) in Sub-section (1) of

Section 2 of the Pact during participation in the tender process and during

the contract execution. Section 3 deals with disqualification from tender

process and exclusion from future contracts which reads as follows:

SECTION-3: DISQUALIFICATION FROM TENDER PROCESS AND EXCLUSION FROM FUTURE CONTRACTS

If the Bidder(s)/Contractor(s), before award or during execution has committed a transgression through a violation of section-II above, or in any other form such as to put his reliability or credibility in question, the Principal is entitled to disqualify such Bidder(s)/Contractor(s) from the tender process or to terminate the contract, if already signed and to take action as per the procedure or "Banning of business dealings" of the Principal.

16. Section 5 deals with previous transgression which is quoted

hereunder :

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

SECCTION-5: PREVIOUS TRANSGRESSION (1) The Bidder declares that no previous transgressions occurred in the last three years with any other Company in any country conforming to the anti-corruption approach or with any Public Sector Enterprise in India that court justify his exclusion from the tender process.

(2) If the Bidder makes incorrect statement on this subject, he can be disqualified from the tender process or action can be taken as per the procedure of "Banning of business dealings" of the Principal.

17. Apart from the Tender Conditions which are enumerated under

different heads described as "Sections", there are other conditions which are

in the nature of policy which also forms part of the Tender Conditions and

the policies are to be read along with the substantive part of the Tender

Conditions. In the case on hand, the Policy for Withholding and Banning of

Business Dealings would be relevant. The said Policy states that the

registration of contractors and their liability to participate in

DVC's procurement is subject to the compliance of Code of Integrity for

public procurement and good performance in contracts. The policy sets out

the contingencies for debarment from bidding, the guidelines on debarment

of firms from bidding, debarment of firms only in DVC. The bidders are

required to sign the declaration for abiding by the Code of Integrity for

public procurement in registrations applications and in bid documents with

a warning that in case of any transgression of the code, their name is not

only liable to be removed from the list of registered contractors but would be

liable for other punitive action such as cancellation of contracts, banning

and blacklisting or action in Competition Commission of India and so on.

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

18. In terms of Clause 2 of the policy the procuring authorities as well as

the bidders should observe the highest standards of ethics and should not

indulge in various prohibited practices either directly or indirectly at any

stage during the procurement process or during execution of the resultant

contracts. The prohibited practices have been enumerated in Clause 2.2 of

the policy. Clause 2.3 deals with obligations for pro-active disclosures and

the same is quoted hereunder :

2.3 Obligations for Proactive disclosures:

i) Procuring authorities as well as bidders, suppliers, contractors and consultants/ service providers, are obliged under Code of Integrity for Public Procurement to suo-moto proactively declare any conflicts of interest (coming under the definition mentioned above- pr-existing or as and as soon as these arise at any stage) in any procurement process or execution of contract. Failure to do so would amount to violation of this Code of Integrity; and

ii) Any bidder must declare, whether asked or not in a bid document, any previous transgressions of such a Code of Integrity with any entity in any country during the last three years or of being debarred by any other Procuring Entity. Failure to do so would amount to violation of this Code of Integrity:

iii) To encourage voluntary disclosures, such declarations would not mean automatic disqualification for the bidder making such declarations. The declared conflict of interest may be evaluated and mitigation steps, if possible, may be taken y the procuring Entity. Similarly, voluntary reporting of previous transgressions of Code of Integrity elsewhere may be evaluated and barring cases of various grades of debarment, an alert watch may be kept on the bidders' actions in the tender and subsequent contract.

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

19. On a combined reading of the three sub-clauses in clause 2.3, it is

seen that the disclosure required to be made is voluntarily. Precisely, for

this reason condition has been imposed that the bidders are obliged under

the Code of Integrity for Public Procurement to suo-moto pro-actively declare

any conflict of interest and failure to do so, would amount to violation of the

Code of Integrity. Furthermore, it is stipulated that the bidder must declare,

whether asked or not in the bid document, any previous transgression of

such a Code of Integrity with any entity in any country during the last 3

years or of being debarred by any other procuring entity and failure to do so

would amount to violation of the Code of Integrity. The Clause 2.2(iii) states

that to encourage voluntary disclosure, such declarations would not mean

automatic disqualification for the bidder making such declaration.

20. It is an admitted fact that for certain transgression action was

initiated against the respondent writ petitioner and a criminal case was

registered against its Managing Director. The FIR was investigated and

offence having been made out, charge sheet has been laid. The matter has

not attained finality primarily for the reason that the writ petitioner has

obtained stay of the proceedings by approaching this Court. The question

would be as to whether non-declaration of the adverse information against

the writ petitioner would be a justifiable reason for rejecting the technical

bid of the writ petitioner by the technical evaluation committee. As pointed

out earlier, the learned Writ Court was of the view that alleged transgression

had occurred 3 years prior to the notice inviting the subject tender and

therefore, there was no such embargo on the part of the writ petitioner

requiring to disclose such information. Thus, the question would be whether

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

the time limit which is mentioned in Section 5 of the Tender Conditions

could be interpolated in Section 3 of the Tender Conditions. Section 3 of the

Tender Conditions deals with disqualification from tender process and

exclusion from future contracts. Section 3 contains two limbs, the first of

which being, if the bidder before the award or during the execution has

committed a transgression through violation of Section 2, it would result in

disqualification. The second limb is that if the bidder has acted in any other

form such as to put his reliability and credibility in question, that would

also result in disqualification. Section 5 deals with previous transgression.

In terms of Clause (1) of Section 5, it is mandatory for the bidder to declare

that no previous transgression occurred in the last 3 years with any other

company in any country confirming to the anti-corruption approach or with

any public sector enterprises in India that could justify the exclusion from

the tender process. Therefore, Section 5 is a stand alone provision dealing

with previous transgression mandating the bidder to make a self-declaration

of any such previous transgression occurred in the last 3 years with any

other company in the country or with any other public sector enterprises in

India. Therefore, the time limit of 3 years stipulated, is qua the previous

transgression with any other company in the country or any other private

sector enterprises in India in the last 3 years whereas the second limb of

Section 3 empowers the DVC to disqualify a bidder if the action of the bidder

is in a form so as to put his reliability or credibility in question. Admittedly,

criminal case has been registered and charge sheet has been laid. We see no

reason to fault the decision of the appellant in doubting the reliability or

credibility of the respondent writ petitioner at this stage of the matter. This

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

is so because the criminal proceedings have not attained finality and the

matter has been stayed in a proceeding initiated by the writ petitioner.

Therefore, unless and until the writ petitioner gets himself absolved of all

the charge, it cannot be stated that DVC were wrong in doubting the

reliability and credibility of the writ petitioner in participating as a bidder in

the subject tenders. Therefore, the time limit prescribed in Section 5 of the

Tender Conditions cannot be interpolated in Section 3 of the Tender

Conditions. With regard to the Policy for Withholding and Banning of

Business Dealings is concerned, though the matter has not travelled upto

the said stage, in terms of Clause 2.3(iii) the time limit of 3 years is with

regard to any other entity in the country or any debarment by any other

procuring entity and this should be mandatorily disclosed by the bidder by

way of a self-declaration. The learned Writ Court was of the view that the

Clause 2.3(iii) has diluted the rigour of the debarment. We are unable to

persuade ourselves to agree with the said conclusion as sub-clause (iii) of

Clause 2.3 gives discretion to the tender inviting authority namely, the

appellant. It has been clarified that such disqualification would not be

meant automatic disqualification, the declared conflict of interest may be

evaluated and mitigating steps, if possible, may be taken by the procuring

entity. Similarly voluntary reporting of previous transgression of Code of

Integrity elsewhere may be evaluated and barring cases of various grades of

debarment, an alert watch may be kept on the bidder's action in the tender

and subsequent contract. We find there is no dilution of the rigour of the

provisions of debarment and all that Sub-clause (iii) of Clause 2.3 gives is a

discretion to the procuring entity to evaluate the mitigating steps or to

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

evaluate the voluntary report reporting of previous transgression. Admittedly

the writ petitioner has not voluntarily reported the previous transgression.

Therefore, the stand taken in the writ petition is a clear afterthought and the

writ petitioner seeks to interpret the terms and conditions of tender to suit

its convenience which they are not entitled to do. Above all, the Court

exercising jurisdiction under Article 226 of the Constitution is not the

authority to decide as to who would be best suited to perform the contract.

The Court cannot take a decision sitting in the arm chair of the tender

inviting authority as it is the exclusive domain of the tender inviting

authority to decide upon the tenderer who would be best suitable. The

learned Writ Court was of the view that the decision of the appellant was

arbitrary and unreasonable and if it is so, it was permissible for the Writ

Court to interfere. In the light of the conclusion which we have arrived at

namely, that the time limit prescribed in Section 5 cannot be interpolated in

Section 3, we find no arbitrariness in the decision making process.

Secondly, there can be no unreasonableness in the decision itself. It is not

for the Writ Court to question the decision of the appellant and it is only the

decision making process that that needs to be examined. The transgression

which had been committed is admitted and the writ petitioner seeks to

escape out of the rigour of the terms and conditions of tender by referring to

the time limit prescribed in Section 5 which we have held has no application

to the facts and circumstances of this case. Similarly, the time limit in Sub-

clause (ii) of Clause 2.3 of the Banning Policy would apply to cases where

the bidder makes voluntary declaration of the previous transgression with

any other entity in the country or by any other procuring entity during the

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

last 3 years. In the instant case, the transgression is with the procuring

entity itself. One other reason which has been set out in the reasons for

rejection is that repeatedly the writ petitioner has suppressed the

transgression. It is an admitted fact that the writ petitioner had participated

in 14 tenders floated by the appellant organization; however appears to have

been unsuccessful but the fact remains that in the 14 tenders this

transgression has not been disclosed. Therefore, this is one more reason for

the appellant to doubt the reliability and credibility of the writ petitioner.

The learned Writ Court has referred to the stand taken by the appellant to

state that the starting point of the alleged transgression was when the FIR

was registered and not when the charge-sheet was laid. Though, we have

held the said time limit prescribed in Section 5 of the Tender Conditions,

has no application to the case on hand. That apart, the transgression is

continuing and the matter has not attained finality largely attributable to

the writ petitioners themselves as they have obtained stay of those

proceedings. Therefore, the writ petitioner cannot be permitted to probate

and reprobate and take advantage of their own action and to fault the

decision of the appellant in rejecting their technical bid. It was submitted by

the learned Senior Advocate for the respondent writ petitioner that it is the

Director of the company who has been charge-sheeted and the company is

not the accused. To verify the correctness of the said submission we have

perused the charge-sheet which was laid on 24.10.2019 wherein it has been

mentioned that the writ petitioner had violated various provisions of the

Contract and that it has been noticed that the writ petitioner had created a

heap of inferior coal mixed with extraneous material with intent to commit

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

fraudulent and corrupt practice. The Managing Director of the company has

been named as the "owner" in the charge-sheet who is said to have

voluntarily surrendered before the Trial Court on 13.02.2019. Therefore, it is

incorrect to state that the company has not been mentioned in the charge-

sheet which has been laid.

21. In the light of the above conclusion, that it may not be necessary for

us to examine as to whether the decision in the respondent's own case in

MAT No. 1932 of 2022 would be a good ground to dismiss the writ petition.

To be noted that during the pendency of the writ petition, there was an

interim order in force from December, 2022, consequently the entire tender

process has been halted. In so far as the tender which is the subject matter

of MAT No. 894 of 2023 is concerned, a reverse re-auction has already been

conducted and the successful bidder has been selected. On account of the

order for stay, the appellants have submitted that great prejudice has been

caused to the thermal power plant which is to function for 24 hours on all 7

days in a week and the fly ash which is generated and taken to the ash pond

in celery form is a continuous process and the ash pond has to be cleared or

otherwise the power plant will have to be shut down. Thus, on account of

the interim order, public interest has definitely suffered and any disruption

to the running of the power plant would undoubtedly be against public

interest. It is not in dispute that there is no mala fides alleged by the writ

petitioner against the appellant and therefore, the challenge to the rejection

of the technical bid cannot be brought under the said head.

MAT NOS (894 OF 2023 & 895 OF 2023) REPORTABLE

22. Thus, for the above reasons we are of the clear view that the decision

of the appellant in rejecting the technical bid of the respondent writ

petitioner was just and proper and calls for no interference.

23. In the result the appeals are allowed. Consequently, the writ petitions

are dismissed and the appellant is directed to proceed with both the tenders

in accordance with the procedure.

(T.S. SIVAGNANAM, CJ.)

I Agree.

(HIRANMAY BHATTACHARYYA, J.)

(P.A- PRAMITA/SACHIN)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter