Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

B.K. Consortium Engineers ... vs Indian Institute Of Management
2023 Latest Caselaw 191 Cal/2

Citation : 2023 Latest Caselaw 191 Cal/2
Judgement Date : 19 January, 2023

Calcutta High Court
B.K. Consortium Engineers ... vs Indian Institute Of Management on 19 January, 2023
                      IN THE HIGH COURT AT CALCUTTA
                      Ordinary Original Civil Jurisdiction
                               ORIGINAL SIDE
                            (Commercial Division)



Present:

The Hon'ble Justice Shekhar B. Saraf

                                 AP/237/2021

            B.K. CONSORTIUM ENGINEERS PRIVATE LIMITED
                                      VS
            INDIAN INSTITUTE OF MANAGEMENT, CALCUTTA


For the Petitioner:                   Mr. Jayanta Kumar Mitra, Sr. Adv.
                                      Mr. Dhruba Ghosh, Sr. Adv.
                                      Mr. Sakya Sen, Adv.
                                      Ms. Dola Adhikari, Adv.
                                      Mr. Rohit Banerjee, Adv.
                                      Mr. Sunil Gupta, Adv.
                                      Mr. Altamash Alim, Adv.
                                      Ms. Ajeyaa Choudhury, Adv


For the Respondent:                   Mr. Sabyasachi Chowdhury, Adv.
                                      Mr. Bhaskar Mukherjee, Adv.
                                      Ms. Nafisa Yasmin, Adv.




Last heard on: December 16, 2022
Judgment on: January 19, 2023




                                                                    Page 1 of 54
 Shekhar B. Saraf, J.:



    1.   The petitioner B. K. Consortium Engineers Private Limited

         (hereinafter referred to as the 'BKC') has filed this application

         under Section 11 of the Arbitration & Conciliation Act, 1996

         (hereinafter referred to as 'the Act') praying for appointment of a

         sole arbitrator to adjudicate the disputes which have arisen

         between the parties.



    2.   The petitioner has challenged the appointment procedure of the

         arbitrator, provided in its contract with the respondent Indian

         Institute of Management, Calcutta (hereinafter referred to as the

         'IIMC'), which empowers the IIMC director to appoint a sole

         arbitrator for dispute resolution between the parties.



Facts

    3.   The factual matrix of the case is delineated below -



         a.   A notice inviting tender dated July 9, 2008 was issued by the

              respondent for civil work and basic utility works for the

              proposed residential (hostel) complex at IIMC, Joka. A bid was

              submitted by the petitioner and in response to the same, a

              work order was issued on August 29, 2008, in terms of which

              the project was required to be completed within August 31,

              2009, at a total cost of INR 39,03,20,185 (Rupees Thirty-Nine

                                                                  Page 2 of 54
             Crores Three Lakhs Twenty Thousand One Hundred Eighty-

            Five Only). Subsequently, a formal contract being CDP/6 of

            2008-09 was entered into by and between the petitioner and

            respondent in respect of the said work as stipulated in the

            said work order.



b.          During the course of execution of the work, the respondent,

            from time to time, introduced additions to the scope of work,

            and as a result, the value of the contract stood revised to INR

            80,23,73,260/- (Rupees Eighty Crores Twenty-Three Lakhs

            Seventy-Three Thousand Two Hundred Sixty Only). The

            petitioner sought extension from the respondent on the

            following grounds -



       i.       Delay in handing over clear work site; the piling work

                being done by another contractor was not completed

                before September 2009, and hence the clear site area

                could not be handed over to the petitioner till September

                2009;

      ii.       Additions      and   alterations   incorporated   during   the

                contract period;

     iii.       Various changes in the specifications were introduced;

     iv.        The execution of the project was suspended for a

                considerable period. The work resumed only on March

                14, 2011.

                                                                    Page 3 of 54
      In view of the aforesaid, the time for completion of work was

     extended by the respondent from time to time. The last of

     such extensions was granted till August 31, 2014. The work

     was completed in all aspects by August 31, 2014.



c.   The respondent issued the final bill on March 11, 2016 and

     the petitioner accepted the same by way of a letter dated

     March 15, 2016, under the signature of two directors of the

     petitioner, namely C. Mozumder and U.S. Mozumder. The

     acceptance stated that "we accept the final bill and final

     settlement of all demands against the contract and we will not

     prefer any claim in future in this regard". By way of another

     letter dated March 17, 2016, bearing the signature of B.K.

     Mozumder,    Chairman     and   Managing    Director     of   the

     respondent, the acceptance of the final bill was reiterated but

     in addition to this, a request for price escalation was made.

     Pursuant to the acceptance of the final bill, the final

     completion certificate was issued by the respondent on May 5,

     2016. It is to be noted here that this was not the first time

     price escalation requests were submitted to the respondent.



d.   On May 16, 2016, the petitioner sent another letter claiming

     price escalation. It was acknowledged in the said letter that

     the final bill against work done has been settled, and the

     retention money against the contract has been refunded by

                                                            Page 4 of 54
      the respondent. However, the petitioner also stated, in the

     said letter, that its escalation claim under Clause 10(CC) of

     the contract has not been settled yet. Surprisingly, it also

     sought permission from the petitioner to invoke arbitration in

     terms of clause 25 of the said contract.



e.   After a brief lull, letter dated August 25, 2017 was sent by the

     petitioner with respect to the earlier price escalation requests.

     In response, the respondent replied vide letter September 12,

     2017 denying the validity of any such claim in light of the full

     & final settlement of the claim and bill pertaining to the job

     contract. It was reiterated by the respondent that "any claim

     related to the escalation thus cannot be accepted under the

     said contract agreement; hence can't be entertained at this

     stage". A reply to this was sent by the petitioner vide letter

     dated September 15, 2017 wherein they claimed to have

     accepted the final settlement of the bill under coercion.



f.   The last in the series of price escalation letters by the

     petitioner was sent on February 22, 2019 wherein the earlier

     claims were reiterated. The respondent responded vide its

     advocate's letter dated March 13, 2020, denying the existence

     of any claims whatsoever in the first place. It was again

     clarified by the respondent that basis the terms of the

     contract   and    subsequent     acceptance    of   the     entire

                                                            Page 5 of 54
      consideration money in lieu of full and final settlement

     against the enhanced work order, the respondent was not

     liable to pay for any further claims.



g.   Furthermore, letters dated February 26, 2021, and February

     3, 2021, were delivered by the petitioners reiterating their

     escalation claims.



h.   Finally, the petitioner dispatched a Section 21 notice dated

     March 8, 2021 invoking arbitration. Through the said notice,

     disputes arising as a result of non-payment of escalation

     claims were sought to be referred to an arbitrator. In the same

     notice, the appointment procedure of the sole arbitrator was

     challenged as invalid under the provisions of Arbitration &

     Conciliation Act, 1996 and as such, Justice (Retd.) Ashim

     Kumar Banerjee was nominated by the petitioner as their

     nominee arbitrator.



i.   In response to the aforesaid notice invoking arbitration, the

     respondent denied the existence of any further dispute and

     reiterated that all claims have been settled and that the

     petitioner is not entitled to any further amount from the

     respondent. However, despite denying the existence of any

     dispute, the respondent appointed Shri Basab Majumdar,

     retired DG, CPWD as their nominee arbitrator. The respondent

                                                          Page 6 of 54
               also stated that such appointment was without prejudice to

              their contentions regarding non-existence of any dispute.



Submissions



   4.   Mr. Jayanta Kumar Mitra, Senior Advocate, appearing on behalf of

        the petitioner has put forth the following arguments:



        a.    The counsel argued that the resumption of work on March 14,

              2011 was accepted by the petitioner subject to its right to

              receive price escalation under clause 10(CC) of the contract.

              Further, the counsel stated, there was no contemporaneous

              denial of such a proposal by the respondent. On this basis

              and being assured that escalation would be considered, work

              was resumed and completed to the utmost satisfaction of

              IIMC on August 31, 2014. The counsel added that the final

              completion    certificate   dated   May   5,   2016   not    only

              acknowledged the satisfactory completion of work but also the

              fact that prolongation of the contract period was not

              attributable to any fault on part of the petitioner. This, as per

              the petitioner, has been clearly and unambiguously admitted

              by the respondent.



        b.    The counsel submitted that keeping in mind the afore stated

              admission, the petitioner suffered considerable loss by reason

                                                                     Page 7 of 54
      of being paid on the basis of the rates quoted way back in the

     year 2008. Therefore, the counsel contended that the

     petitioner became entitled to invoke the clause 10(CC) of the

     contract which provided for the escalation as per the formula

     provided therein. The counsel stated that both time and cost

     overrun of the project had caused huge financial losses to the

     petitioner and this issue was brought to the notice of

     respondent through protracted contemporaneous undisputed

     correspondence. He argued that the petitioner's bills were

     never disputed by the respondent and in fact, the petitioner

     was assured that the same would be taken care after

     completion of the work.



c.   The counsel submitted that pursuant to the request of the

     petitioner, a sub-committee of IIMC was constituted which

     held a meeting with the petitioner on November 12, 2012.

     Here, the claim was discussed in detail and the petitioner was

     requested to complete the work in all respects with an

     assurance to settle escalation claim thereafter. Headed that

     BKC relied upon the said assurance and duly proceeded

     thereafter to complete the work. It is only after about 14

     months from the date of submission of the final bill, the

     executive engineer of the respondent vide its letter dated

     March 11, 2016 instructed the petitioner to accept the final

     bill as prepared by the respondent in their specified format.

                                                         Page 8 of 54
      Hence, the counsel argued, the petitioner had no option other

     than to accept the final bill, as prepared by the respondent,

     under compulsion and duress even though the same did not

     accommodate their price escalation claims.



d.   Continuing his submissions on the point of acceptance of the

     final bill, the counsel stated that the long-standing dues of

     the petitioner could not be realized even after repeated

     persuasions and being under tremendous financial stress, it

     was impossible for the petitioner to wait for realization of the

     outstanding     sum,       and   under   such     circumstances,          the

     petitioner accepted the final bill by way of a letter dated

     March 15, 2016 undersigned by two directors of the petitioner

     company. Immediately afterwards, in the letter dated March

     17, 2016, the managing director of the petitioner company not

     only   reiterated    its    acceptance    but    also   reminded          the

     respondent of its price escalation claim.



e.   The counsel submitted that the final payment was accepted

     under duress and hence to overcome the damaging 'No

     Objection Certificate' issued on March 15, 2016, and after

     receipt   of   payment      on   May     05,    2016,   the        petitioner

     superseded     the   earlier     acceptance     by   way      of     another

     communication dated May 16, 2016. The counsel argued that

     the certificate issued by petitioner through letters dated

                                                                        Page 9 of 54
      March 15, 2016 and March 17, 2016 stood withdrawn in view

     of the petitioner's fresh communication dated May 16, 2016.

     Therefore,   the   counsel   contended    that   the   acceptance

     certificate of the final bill was earlier issued under compelling

     circumstances and the same cannot tantamount to negation

     or waiver of the petitioner's right to claim price escalation in

     terms of clause 10(CC) of the contract.



f.   Moving on, the counsel submitted the escalation claim was

     disputed by the respondent for the very first time on

     September 12, 2017 and on the grounds that the petitioner

     had issued a full and final acceptance certificate of the final

     bill was by way of a letter dated March 15, 2016. The counsel

     contested that the escalation bill was not separately dealt

     with nor was specifically rejected by the respondent. The

     counsel also put forth the argument that since September 12,

     2017 was the first time wherein the price escalation claim was

     disputed by the respondent, the same should be considered

     as the starting point for the purposes of calculation of

     limitation period for issuance of Section 21 notice. In support

     of this contention, reliance was placed upon Geo Miller &

     Company Private Ltd. -v- Rajasthan Vidyut Utpadan

     Nigam Limited reported in 2019 SCC OnLine SC 1137, the

     relevant paragraph of which has been reproduced below -



                                                            Page 10 of 54
          "Having perused through the relevant precedents, we

         agree that on a certain set of facts and circumstances, the

         period during which the parties were bona fide negotiating

         towards an amicable settlement may be excluded for the

         purpose of computing the period of limitation for reference

         to arbitration under the 1996 Act. However, in such cases

         the entire negotiation history between the parties must be

         specifically pleaded and placed on the record. The Court

         upon careful consideration of such history must find out

         what was the 'breaking point' at which any reasonable

         party would have abandoned efforts at arriving at a

         settlement and contemplated referral of the dispute for

         arbitration. This 'breaking point' would then be treated as

         the date on which the cause of action arises, for the

         purpose of limitation. The threshold for determining when

         such a point arises will be lower in the case of commercial

         disputes, where the party's primary interest is in securing

         the payment due to them, than in family disputes where it

         may be said that the parties have a greater stake in

         settling the dispute amicably, and therefore delaying

         formal adjudication of the claim."




g.   Continuing his arguments, the counsel added that the

     limitation for issuing the said Section 21 notice would expire

                                                         Page 11 of 54
      on September 12, 2020 but in the light of the Supreme Court

     order in In Re: Cognizance for Extension of Limitation

     with M.A. No. 29 Of 2022 in M.A. No. 665 Of 2021 in Suo

     Moto Writ Petition (C) No. 3 Of 2020, the period from March

     15, 2020 till February 28, 2022 stood excluded in computing

     the limitation period. Therefore, the Section 21 notice issued

     by the petitioner on March 08, 2021 is well within the

     limitation period.



h.   The counsel submitted that pursuant to the aforementioned

     letter dated September 12, 2017, the petitioner responded on

     September 15, 2017 wherein it restated that the final bill was

     accepted under constraint. The counsel argued that the

     respondent thereafter never refuted the petitioner's stance

     and the same being in accordance with the settled position of

     law as enunciated in various judgments of the Supreme Court

     which clearly lays down that mere issuance of full and final

     certificate cannot prevent a contractor to ventilate its

     legitimate claims arising under a contract.



i.   Moving forward, the counsel asserted that the petitioner

     continued to pursue its claim and the last letter in this

     connection was the one dated February 22, 2019. This was

     replied to by the respondent on March 13, 2020 wherein it

     denied and disputed the liability to pay any amount and in

                                                        Page 12 of 54
      doing so, as per the counsel, erroneously relied upon

     acceptance issued on March 15, 2016. Here, the counsel

     argued that the communications dated March 15, 2016, and

     March   17,     2016,   stood    withdrawn     pursuant      to    their

     correspondence dated May 16, 2016.



j.   The   counsel    submitted      that   the   stand   taken    by    the

     respondent as indicated in the advocate's notice dated March

     13, 2020 was given a go-by and the matter was looked into

     and considered by a Special Committee comprising of high-

     level IIMC officials. He drew the attention of the Court towards

     the fact that the petitioner was invited for a virtual meeting

     scheduled for January 13, 2021 where it duly presented its

     escalation claim and pursuant to request of the said

     committee, written submissions were also submitted on

     January 20, 2021, and February 3, 2021 together with

     relevant documents.



k.   In response to the respondent's contentions that the claims

     are time barred and deadwood, the counsel opposed the same

     and stated that by the virtue of negotiations in such meetings

     and exchange of documents, the claim stands alive and falls

     out of the purview of being a deadwood.




                                                               Page 13 of 54
 l.   The counsel contended that by reason of such a legitimate

     claim being withheld and/or denied, a dispute has arisen

     between the parties which are referable to arbitration as per

     the terms of the contract. The counsel further submitted that

     no intimation was received about the final bill being ready for

     payment and as such, the period for invoking the arbitration

     clause has not lapsed. Elaborating further on the point of

     arbitration,   the   counsel   questioned     the   appointment

     procedure as invalid as it empowered the respondent to

     appoint a sole arbitrator and the same is hit by the

     disqualification contained in Schedule V to the Arbitration

     and Conciliation Act, 1996.



m.   The counsel in support of his contentions cited the judgment

     of the Supreme Court in Vidya Drolia and Ors -v- Durga

     Trading Corporation reported in [2020] 11 S.C.R. 1001

     and advocated that the Court's approach in a Section 11

     arbitration petition should be "when in doubt, do refer".



n.   Next, the counsel relied upon the judgment of the Supreme

     Court in Bharat Sanchar Nigam Ltd. & Anr. -v- M/S Nortel

     Networks India Pvt. Ltd. reported in [2021] 2 S.C.R. 644,

     and submitted that this Court can deny reference to

     arbitration in a Section 11 arbitration application 'only if there

     is not even a vestige of doubt that the disputes are ex-facie

                                                            Page 14 of 54
      time-barred and deadwood'. The counsel opined that the

     present case is not one of complete deadwood as it is clear

     that the issue herein does not fall within the category of those

     which are ex-facie time barred and which would have

     otherwise been liable to be dismissed per the afore-cited

     judgments.



o.   Elaborating upon his contentions, the counsel put forth the

     judgment of the Supreme Court in the case Uttarakhand

     PurvSainik Kalyan Nigam Ltd. -v- Northern Coal Field

     Ltd. reported in [2019] 14 S.C.R. 999. The following

     paragraphs were cited by the counsel:



         9.8 In view of the legislative mandate contained in Section

         11(6A), the Court is now required only to examine the

         existence   of    the   arbitration     agreement.    All   other

         preliminary or threshold issues are left to be decided by

         the arbitrator under Section 16, which enshrines the

         Kompetenz-Kompetenz principle.



         9.9. The doctrine of "Kompetenz-Kompetenz", also referred

         to as "Compétence-Compétence", or "Compétence de la

         recognized",     implies   that   the    arbitral    tribunal   is

         empowered and has the competence to rule on its own

         jurisdiction, including determining all jurisdictional issues,

                                                               Page 15 of 54
     and the existence or validity of the arbitration agreement.

    This doctrine is intended to minimize judicial intervention,

    so that the arbitral process is not thwarted at the

    threshold, when a preliminary objection is raised by one of

    the parties.



    *

Limitation is a mixed question of fact and law. In ITW

Signode India Ltd. v. Collector of Central Excise, a three

judge bench of this Court held that the question of

limitation involves a question of jurisdiction. The findings

on the issue of limitation would be a jurisdictional issue.

Such a jurisdictional issue is to be determined having

regard to the facts and the law."

Seeking support from this judgment, the counsel reminded

the Court that the respondent did not raise any dispute

regarding the existence of the arbitration clause invoked by

the petitioner, and that in the absence of such an objection,

this Court has to refer the matter to arbitration and any

questions with respect to the jurisdiction or otherwise has to

be adjudicated upon and decided by the arbitrator. Further,

the respondent had itself acknowledged that the matter in

hand can be referred to arbitration process and had also

independently suggested an arbitrator vide its letter dated

April 10, 2021.

5. Mr. Sabyasachi Chowdhry, Advocate appearing on behalf of the

respondent, has propounded the following arguments:

a. The counsel submitted that the said petition is misconceived,

not maintainable and is liable to be dismissed. He contended

that the alleged claim, on the face of the record, is barred by

limitation and even considered otherwise, the said claim is

beyond the scope of the contract and therefore, is not

maintainable.

b. The counsel asserted that it is a matter of record that all

claims under the contract were settled, resulting in final

payment on March 15, 2016 which in turn was accepted by

the petitioner as 'final settlement' of all demands against the

contract. Not only that, the petitioner undertook to 'not prefer

any claim in future in this regard'. The counsel continued to

argue that the respondent vide its letter dated March 17,

2016 iterated their acceptance once again and merely made a

'request' to consider 'some relief in the form of escalation

against the contract'.

c. The counsel further contended that the dispute subsequently

was raised as an afterthought to wriggle out of such

settlement on the allegation of 'duress'. The counsel

vehemently denied that the petitioner was 'instructed' by the

respondent to accept the final bill in any specified format or

under any 'compelling circumstances'.

d. Be that as it may, the counsel contended that mere bald plea

of fraud, coercion, duress or undue influence is not enough

and a party who sets up such plea must prima facie establish

the said allegation by placing relevant material before the

Chief Justice or his designate. He relied upon the decision of

the Supreme Court in New India Assurance Company

Limited -v- Genus Power Infrastructure Limited reported

in 2015 2 SCC 424 in support of his contentions to argue

that in the present case, the ratio of the aforementioned case

squarely applies, particularly in the context of the letters

dated March 15, 2016, and March 17, 2016, whereby the

petitioner had accepted the final bill as full and final

settlement and had merely made a 'request' which cannot be

subsequently elevated to claim or demand.

e. In any case, he argued that a period of more than three years

has lapsed from the date on which the right to sue, if any,

had first accrued, i.e., from March 15, 2016 onwards.

Therefore, the counsel added, that on March 8, 2020 when

the arbitration was invoked by the petitioner, there could not

have been any subsisting dispute between the parties.

Moreover, the counsel reasoned that the unilateral letters by

the petitioner in geminating the same points will not save

limitation and any reply to such letters is not an

acknowledgement within the meaning of Article 18 of the

Limitation Act, 1963, and consequently, there exists no jural

relationship between the petitioner and respondent.

f. The counsel contested that the petitioner is not entitled to

invoke clause 10(CC) of the contract and does not have any

right to receive any escalation claim under the said clause or

otherwise at all. Further, as per clause 17 of the special terms

and conditions, no escalation was payable in relation to the

said contract for any reasons whatsoever. He contended that

the allegations regarding escalation are immaterial and

irrelevant, particularly after the contract was revised on

September 27, 2013 wherein the total value thereof was

enhanced to INR 80.23 crores from the original value of

around INR 39 crores.

g. The counsel submitted that in view of petitioner's acceptance

of the final bill and the final settlement of all its demands on

March 16, 2016, there was no occasion to make any response

thereafter. He observed that the contents of the letter dated

September 12, 2017, are self-explanatory and merely

reiterated their earlier stated position.

h. The counsel denied that any high level committee was

constituted to reconsider the grievance of the petitioner as

alleged. In any event, the counsel submitted, the formation of

any internal committee will not entitle the applicant to

reagitate its stale and dead claim afresh. The counsel states

that by repeatedly raising the issue of barred claim in diverse

places was to desperately seek a response in an attempt to

create evidence.

i. The counsel stated that in light of the principles laid down by

the Supreme Court in Vidya Drolia and Ors. -v- Durga

Trading Corporation reported in [2020] 11 S.C.R. 1001, it

is now very well settled that "the Court at the referral stage can

interfere only when it is manifest that the claims are ex-facie

time-barred and dead, or there is no subsisting dispute." The

present petition, he contended, fell within the category of a

deadwood and therefore is liable to be dismissed as there does

not exist anything in the present dispute which would make it

eligible to be referred to arbitration.

j. The counsel submitted that even if the letter dated May 16,

2016 is treated as a notice under Section 21 of the Arbitration

and Conciliation Act, 1996, then this arbitration petition is

also barred by limitation as per Article 137 of the Limitation

Act, 1963.

k. Elaborating on the scope of judicial interference in a Section

11 application, the counsel cited the judgment of the

Supreme Court in the case of Bharat Sanchar Nigam Ltd.

& Anr. -v- M/S Nortel Networks India Pvt. Ltd. reported in

[2021] 2 S.C.R. 644 to argue that "while exercising

jurisdiction under Section 11 as judicial forum, the Court may

exercise the prima facie test to screen and knockdown, ex-facie

meritless, frivolous and dishonest litigation."

l. Lastly, the counsel, in the hearings, placed reliance upon the

judgment of Supreme Court in Geo Miller & Company

Private Limited -v- Rajasthan Vidyut Utpadan Nigam

Limited reported in 2019 SCC OnLine SC 1137 to contend

that the petitioner cannot justify the unreasonable delay in

invocation of arbitration merely on the grounds of purported

settlement discussions. He argued that the breaking point, if

any, for invocation of arbitration would be March 11, 2016,

i.e, the date when the final bill was issued by the respondent.

He further submitted (for argument's sake) that in any event,

the starting day for the limitation point to begin would be May

16, 2016, that is, the date when the petitioner sought to

invoke arbitration for the first time. The relevant paragraph

has been extracted below-

29. Moreover, in a commercial dispute, while mere failure

to pay may not give rise to a cause of action, once the

applicant has asserted their claim and the respondent

fails to respond to such claim, such failure will be treated

as a denial of the applicant's claim giving rise to a dispute,

and therefore the cause of action for reference to

arbitration. It does not lie to the applicant to plead that it

waited for an unreasonably long period to refer the

dispute to arbitration merely on account of the

respondent's failure to settle their claim and because they

were writing representations and reminders to the

respondent in the meanwhile."

(Emphasis supplied)

m. Concluding his arguments, Mr. Chowdhury placed reliance

upon the judgment of Supreme Court in Secunderabad

Cantonment Board -v- B. Ramachandraiah and Sons

reported in (2021) 5 SCC 705, which further endorses the

principles as laid down in Vidya Drolia (supra) and BSNL -v-

Nortel (supra), to argue that mere exchange of letters or

settlement discussions will not be sufficient to stretch the

limitation period.

Observations & Analysis

6. I have heard the counsel appearing on behalf of the parties and

perused the materials on record.

7. Before delving into other major issues plaguing the present

application, I will proceed first with the petitioner's challenge to

the appointment procedure of the sole arbitrator as laid down by

clause 25 of the contract between the parties. In my view, this

challenge is at the centre point of the present petition, which later

expands like a banyan tree spreading outwards.

8. In the light of the apex court's pronouncements in Perkins

Eastman Architects DPC & Another -v- HSCC (India) Ltd.

reported in [2019] 17 S.C.R. 275 and TRF Ltd. -v- Energo

Engineering Projects Ltd. reported in [2017] 7 S.C.R. 409, it is

crystal clear that unilateral appointment of an arbitrator by a

party who has some sort of interest in the final outcome or

decision is not permissible. The cardinal importance of the

independence and neutrality of the arbitral tribunal has been

reiterated by the Supreme Court on multiple occasions. For

arbitration to be seen as a viable dispute resolution mechanism

and as an alternate recourse to litigation, the independence of

arbitration process outside the purview of undue influence and

favor needs to be ensured in both letter and spirit. And in case of

non-adherence to such principles, the courts must step in. If one

takes a careful look, the very basic essence of the principle laid

down in the above-mentioned case laws is the natural justice

principle of nemo judex in causa sua that is 'no one should be

made a judge in his own case'. For arbitration decisions to be

respected and accepted as decrees of the court, a similar level of

integrity in the appointment of arbitrators must be ensured.

9. Keeping the aforesaid principles in mind, this Court is in absolute

agreement with arguments advanced by Mr. Mitra that the

appointment procedure as per clause 25 of the contract cannot be

sustained as it is in direct contravention to the aforecited judicial

pronouncements and legal principles.

10. Nonetheless, as the saying goes it is not the end of the world or in

our case, the end of the matter. Therefore, before proceeding ahead

with the appointment of an arbitrator the arguments advanced by

Mr. Chowdhury cannot be overlooked and needs to be adjudicated

upon by this Court. He argued on the point of limitation and

stated that the claims are hopelessly time-barred and the same

would entail this Court to decline referring the matter to

arbitration at the first instance.

11. Mr. Mitra, Senior Advocate, appearing on behalf of the petitioner

argued that judicial intervention in a Section 11 arbitration

application is limited to mere examination of the validity and

existence of the arbitration agreement. I find myself in

disagreement with this argument as in a Section 11 application,

the Court is not supposed to undertake a meager cosmetic exercise

to examine the existence and/or validity of the arbitration

agreement, and then simply refer the matter to arbitration just

because the arbitration clause is valid. Had this been the intent of

the law makers and the judicial pronouncements on this subject,

the determination could have been delegated to an AI-empowered

computer system, thereby eliminating the need for applicability of

a judicial mind and relieving the courts of the sedulous task of

adjudicating such matters.

12. In my view, if it is manifestly evident on the face of it that the

issues purported to be referred to arbitration are hopelessly time-

barred and/or are non-arbitrable, the courts can intervene and

decline reference to arbitration in such cases. The entire objective

of judicial intervention, in certain circumstances, has been to

ensure the efficacy and utility of the arbitration process. Just like

water is crucial to a fish's survival, the presence of an arbitrability

element in a Section 11 application is a must for it to be accepted

and referred to an arbitrator for further adjudication. For instance,

if a person appears to be dead and when on examination of the

pulse, it is palpably evident that there is no life left, one is not

supposed to send the body to the operation theatre but rather to a

morgue.

13. At this juncture, this Court finds it imperative to broach the

Supreme Court's decision in Vidya Drolia (supra) wherein the

scope of intervention in a Section 11 application was defined and

made permissible in certain circumstances only. The same has

been enumerated herein below -

92. (iv) Most jurisdictions accept and require prima facie

review by the court on non-arbitrability aspects at the

referral stage.

*

(vi) Exercise of power of prima facie judicial review of

existence as including validity is justified as a court is the

first forum that examines and decides the request for the

referral. Absolute "hands off" approach would be

counterproductive and harm arbitration, as an alternative

dispute resolution mechanism. Limited, yet effective

intervention is acceptable as it does not obstruct but

effectuates arbitration.

(vii) Exercise of the limited prima facie review does not in

any way interfere with the principle of competence-

competence and separation as to obstruct arbitration

proceedings but ensures that vexatious and frivolous

matters get over at the initial stage.

(viii) Exercise of prima facie power of judicial review as to

the validity of the arbitration agreement would save costs

and check harassment of objecting parties when there is

clearly no justification and a good reason not to accept

plea of non-arbitrability......

*

(xi) The interpretation appropriately balances the

allocation of the decision-making authority between the

court at the referral stage and the arbitrators' primary

jurisdiction to decide disputes on merits. The court as the

judicial forum of the first instance can exercise prima facie

test jurisdiction to screen and knockdown ex facie

meritless, frivolous and dishonest litigation. Limited

jurisdiction of the courts ensures expeditious, alacritous

and efficient disposal when required at the referral stage."

The Court further went on to hold that-

93. Section 43(1) of the Arbitration Act states that the

Limitation Act, 1963 shall apply to arbitrations as it

applies to court proceedings. Sub-section (2) states that for

the purposes of the Arbitration Act and Limitation Act,

arbitration shall be deemed to have commenced on the

date referred to in Section 21. Limitation law is procedural

and normally disputes, being factual, would be for the

arbitrator to decide guided by the facts found and the law

applicable. The court at the referral stage can interfere

only when it is manifest that the claims are ex facie time

barred and dead, or there is no subsisting dispute. All

other cases should be referred to the arbitral tribunal for

decision on merits. Similar would be the position in case of

disputed 'no claim certificate' or defence on the plea of

novation and 'accord and satisfaction'. As observed in

Premium Nafta Products Ltd., it is not to be expected that

commercial men while entering transactions inter se

would knowingly create a system which would require

that the court should first decide whether the contract

should be rectified or avoided or rescinded, as the case

may be, and then if the contract is held to be valid, it

would require the arbitrator to resolve the issues that have

arisen.

14. A bare reading of the aforementioned paragraphs will nullify the

arguments raised by Mr. Mitra that there is no scope for judicial

intervention in Section 11 applications except to determine the

existence and validity of the arbitration agreement. Within a

certain category of cases which satisfy the principles as laid down

in Vidya Drolia (supra) and expanded in subsequent decisions

(cited later in this judgment), the courts as opposed to a

completely hands-off approach can put their hands back on and

decline the appointment of the arbitrator provided the facts fall

within the ambit of those certain category of cases.

15. It is not a universal principle that every case calls for the

appointment of an arbitrator and that any and all disputes should

be decided by the arbitrator. The courts act as a doorkeeper where

entry is permitted for all the disputes but the doorkeeper can

restrict the entry if certain specific criteria as laid down in the

aforementioned judgments are not met. Reliance can be placed

upon the decision of the Supreme Court in DLF Home Developers

Limited -v- Rajapura Homes Pvt. Ltd. & Anr. in Arbitration

Petition (Civil) No. 16 of 2020 wherein it was clarified that -

"18. The jurisdiction of this Court under Section 11 is primarily

to find out whether there exists a written agreement between

the parties for resolution of disputes through arbitration and

whether the aggrieved party has made out a prima facie

arbitrable case. The limited jurisdiction, however, does not

denude this Court of its judicial function to look beyond the

bare existence of an arbitration clause to cut the deadwood. A

three-judge bench in Vidya Drolia (Supra), has eloquently

clarified that this Court, with a view to prevent wastage of

public and private resources, may conduct 'prima facie review'

at the stage of reference to weed out any frivolous or vexatious

claims.......

*

19. To say it differently, this Court or a High Court, as the case

may be, are not expected to act mechanically merely to deliver

a purported dispute raised by an applicant at the doors of the

chosen arbitrator. On the contrary, the Court(s) are obliged to

apply their mind to the core preliminary issues, albeit, within

the framework of Section 11(6-A) of the Act. Such a review, as

already clarified by this Court, is not intended to usurp the

jurisdiction of the Arbitral Tribunal but is aimed at streamlining

the process of arbitration. Therefore, even when an arbitration

agreement exists, it would not prevent the Court to decline a

prayer for reference if the dispute in question does not correlate

to the said agreement."

16. Reference can also be made to the apex court's decision in Bharat

Sanchar Nigam Ltd. & Anr. -v- M/s Nortel Networks India Pvt.

Ltd. reported in [2021] 2 S.C.R. 644 wherein the court held that

adjudication of the limitation issue at the referral stage does not

tantamount to stepping into the arbitrator's jurisdictional territory.

The relevant paragraphs have been delineated below-

30. Issue of Limitation is normally a mixed question of fact

and law, and would lie within the domain of the arbitral

tribunal. There is, however, a distinction between

jurisdictional and admissibility issues. An issue of

'jurisdiction' pertains to the power and authority of the

arbitrators to hear and decide a case. Jurisdictional

issues include objections to the competence of the

arbitrator or tribunal to hear a dispute, such as lack of

consent, or a dispute falling outside the scope of the

arbitration agreement. Issues with respect to the

existence, scope and validity of the arbitration agreement

are invariably regarded as jurisdictional issues, since

these issues pertain to the jurisdiction of the tribunal.

*

32. The issue of limitation, in essence, goes to the

maintainability or admissibility of the claim, which is to be

decided by the arbitral tribunal. For instance, a challenge

that a claim is time-barred, or prohibited until some pre-

condition is fulfilled, is a challenge to the admissibility of

that claim, and not a challenge to the jurisdiction of the

arbitrator to decide the claim itself.

*

36. In a recent judgment delivered by a three-judge bench

in Vidya Drolia v. Durga Trading Corporation, on the scope

of power under Sections 8 and 11, it has been held that

the Court must undertake a primary first review to weed

out "manifestly ex facie non-existent and invalid

arbitration agreements, or non-arbitrable disputes." The

prima facie review at the reference stage is to cut the

deadwood, where dismissal is bare faced and pellucid,

and when on the facts and law, the litigation must stop at

the first stage. Only when the Court is certain that no

valid arbitration agreement exists, or that the subject

matter is not arbitrable, that reference may be refused.

*

37. The upshot of the judgment in Vidya Drolia is

affirmation of the position of law expounded in Duro

Felguera and Mayavati Trading, which continue to hold

the field. It must be understood clearly that Vidya Drolia

has not re-surrected the pre-amendment position on the

scope of power as held in SBP & Co. v. Patel Engineering

(supra). It is only in the very limited category of cases,

where there is not even a vestige of doubt that the claim is

ex facie time-barred, or that the dispute is non-arbitrable,

that the court may decline to make the reference.

However, if there is even the slightest doubt, the rule is to

refer the disputes to arbitration, otherwise it would

encroach upon what is essentially a matter to be

determined by the tribunal.

17. I disagree with Mr. Mitra's argument that the principle in case of a

Section 11 application is that of non - interference. In my view, the

principle is rather of very limited and selective interference in

certain category of cases. While party autonomy and independence

of the arbitral tribunal are the cornerstones of creating an

arbitration friendly atmosphere, but at the same time, the courts

are not supposed to act as mere spectators in every Section 11

application.

18. Mr. Mitra relied upon Uttarakhand Purv Sainik (supra) to argue

that the Court is 'only required to examine the existence of

arbitration agreement' and 'all other preliminary or threshold issues

are left to be decided by the arbitrator under Section 16, which

enshrines the kompetenz-kompetenz principle'.

19. However, to my mind, this is an incomplete reading of the position

of law on the aspect of judicial interference in a Section 11

application as the kompetenz-kompetenz principle upheld in

Uttarakhand Purv Sainik (supra) emanated from the reasoning

where the question of limitation is within the arbitrator's domain

under Section 16 of the Act. Having said that, the apex court in

BSNL -v- Nortel (supra) held that the question of limitation is not

a challenge to the arbitrator's jurisdiction under Section 16 of the

Act but rather it is a challenge to the admissibility of the claims

itself. In the light of the same, the judgment adduced by Mr. Mitra

is not concrete enough to seize the judicial hands of this Court in

determining the question of limitation at the referral stage.

20. In addition to the above, in Vidya Drolia (supra), the Supreme

Court has upheld in that -

"92.(vii) Exercise of the limited prima facie review does not

in any way interfere with the principle of competence-

competence and separation as to obstruct arbitration

proceedings but ensures that vexatious and frivolous

matters get over at the initial stage."

21. Now, the question before me is whether the claims here are ex-

facie time barred and therefore, falls under the restrictive category

of deadwood. To determine the starting point of cause of action

and ascertain the expiry of the limitation period, this Court finds it

pertinent to refer back to the judgment of the Supreme Court in

BSNL -v- Nortel (supra) wherein it made explicitly clear that a

notice invoking arbitration must be sent by the claimant party

within three years from the date on which the escalation claim is

rejected. The relevant paragraphs have been extracted -

"17. Given the vacuum in the law to provide a period of

limitation under Section 11 of the Arbitration and

Conciliation 1996, the Courts have taken recourse to the

position that the limitation period would be governed by

Article 137, which provides a period of 3 years from the

date when the right to apply accrues. However, this is an

unduly long period for filing an application u/s. 11, since

it would defeat the very object of the Act, which provides

for expeditious resolution of commercial disputes within a

time bound period. The 1996 Act has been amended twice

over in 2015 and 2019, to provide for further time limits to

ensure that the arbitration proceedings are conducted and

concluded expeditiously. Section 29A mandates that the

arbitral tribunal will conclude the proceedings within a

period of 18 months. In view of the legislative intent, the

period of 3 years for filing an application under Section 11

would run contrary to the scheme of the Act. It would be

necessary for Parliament to effect an amendment to

Section 11, prescribing a specific period of limitation

within which a party may move the court for making an

application for appointment of the arbitration under

Section 11 of the 1996 Act.

*

39. The present case is a case of deadwood / no

subsisting dispute since the cause of action arose on

04.08.2014, when the claims made by Nortel were

rejected by BSNL. The Respondent has not stated any

event which would extend the period of limitation, which

commenced as per Article 55 of the Schedule of the

Limitation Act (which provides the limitation for cases

pertaining to breach of contract) immediately after the

rejection of the Final Bill by making deductions. In the

notice invoking arbitration dated 29.04.2020, it has been

averred that: "Various communications have been

exchanged between the Petitioner and the Respondents

ever since and a dispute has arisen between the Petitioner

and the Respondents, regarding non payment of the

amounts due under the Tender Document." The period of

limitation for issuing notice of arbitration would not get

extended by mere exchange of letters, or mere settlement

discussions, where a final bill is rejected by making

deductions or otherwise. Sections 5 to 20 of the Limitation

Act do not exclude the time taken on account of settlement

discussions. Section 9 of the Limitation Act makes it clear

that : "where once the time has begun to run, no

subsequent disability or inability to institute a suit or

make an application stops it." There must be a clear notice

invoking arbitration setting out the "particular dispute"

(including claims / amounts) which must be received by

the other party within a period of 3 years from the

rejection of a final bill, failing which, the time bar would

prevail."

22. Now, the task before this Court is to apply the above-mentioned

cases in the present issue at hand and to determine when the

cause of action first arose. After perusing the facts of the present

case and looking at the materials placed on record, this becomes

quite evident that the final bill was prepared by the respondent

IIMC on March 11, 2016, and was accepted by the petitioner on

March 15, 2016 and the acceptance iterated on March 17, 2016.

Pursuant to receipt of such an acceptance, the respondent issued

a final completion certificate to the respondent on May 5, 2016.

23. Therefore, the way I see it, the right to sue / cause of action first

arose when the final bill was first issued on March 11, 2016. The

limitation clock in the present case started ticking from March 11,

2016, and despite multiple opportunities to reject the final bill and

invoke arbitration, the petitioner BKC opted not to do that and

instead proceeded with acceptance of the final bill. In this context,

the argument of Mr. Mitra that rejection of the price escalation for

first time by the respondent on September 12, 2017 is when the

cause of action first arose becomes meritless.

24. On top of that, the aforesaid argument of Mr. Mitra stands on a

foundationless ground as well. A careful examination of the

materials placed on record makes it evident that even before the

preparation of the final bill, the escalation claims were raised

multiple times by the petitioner. In my view, the very fact that the

final bill was prepared by the respondent on March 11, 2016

without taking into account the said escalation claim would

undoubtedly tantamount to being the first instance of rejection of

the petitioner's price escalation claim which in turn would give rise

to the cause of action for invoking arbitration. The acceptance of

the final bill by the petitioner would also mean the acceptance of

such rejection by the respondent.

25. At this point, it would be apt to refer to the decision of the apex

court in Secunderabad Cantonment Board -v- B.

Ramachandraiah & Sons (supra) as cited by Mr. Chowdhury.

On perusal of the paragraphs reproduced below, it becomes crystal

clear that the factual situation in that case is akin to the one in

the present matter. The relevant portion has been extracted below

-

"19. Applying the aforesaid judgments to the facts of this

case, so far as the applicability of Article 137 of the

Limitation Act to the applications under Section 11 of the

Arbitration Act is concerned, it is clear that the demand for

arbitration in the present case was made by the letter

dated 7-11-2006. This demand was reiterated by a letter

dated 13-1-2007, which letter itself informed the appellant

that appointment of an arbitrator would have to be made

within 30 days. At the very latest, therefore, on the facts

of this case, time began to run on and from 12-2-2007.

The appellant's laconic letter dated 23-1-2007, which

stated that the matter was under consideration, was

within the 30-day period. On and from 12-2-2007, when

no arbitrator was appointed, the cause of action for

appointment of an arbitrator accrued to the respondent

and time began running from that day. Obviously, once

time has started running, any final rejection by the

appellant by its letter dated 10-11-2010 would not give

any fresh start to a limitation period which has already

begun running, following the mandate of Section 9 of the

Limitation Act. This being the case, the High Court was

clearly in error in stating that since the applications under

Section 11 of the Arbitration Act were filed on 6-11-2013,

they were within the limitation period of three years

starting from 10-11-2020. On this count, the applications

under Section 11 of the Arbitration Act, themselves being

hopelessly time-barred, no arbitrator could have been

appointed by the High Court."

Likewise in the present matter, the limitation is set to have

commenced on March 11, 2016 itself when the final bill was

prepared by the respondent after due consideration of the

petitioner's price escalation claims. This being the case, once the

time has started running, any further rejection of the earlier

claims will not give fresh start to the limitation period.

26. In addition to that, Mr. Mitra's contention that the acceptance of

the final bill was revoked by the petitioner vide its letter dated May

16, 2016 is also ought to be rejected as a bare reading of the said

acceptance letter reveals that it was mere repetition of its earlier

acceptance letters dated March 15, 2016, and March 17, 2016 and

in fact, there was no mention of any sort of revocation of these

earlier acceptance letters.

27. Moreover, I found it strange for the petitioner to seek respondent's

permission to invoke arbitration in terms of clause 25 of the

contract as the said clause contains no such requirement

necessitating one party to seek another's permission to invoke

arbitration.

28. There is a limited period within which an arbitration notice has to

be sent, failing which a party's right to do so would extinguish. The

Supreme Court in BSNL -v- Nortel (supra) held that by merely

sending letter a party cannot claim an extension of the limitation

period. Therefore, if Mr. Mitra's stance is accepted then it would be

highly damaging wherein the period of limitation would expand by

merely sending letters, thereby, putting the other party at a huge

disadvantage. Logically, repetition of its earlier stance by the

respondent would not amount to initiating a fresh cause of action

or extend the limitation period.

29. Mr. Chowdhury, counsel appearing on behalf of the respondent

cited the decision of the Supreme Court in Geo Miller &

Company Private Ltd. -v- Rajasthan Vidyut Utpadan Nigam

Ltd., reported in 2019 SCC OnLine SC 1137 to argue that the

limitation period in the present case had already expired and that

the petitioner cannot justify the unreasonable delay in invocation

of arbitration by taking refuge in the purported settlement

discussions. While this Court accepts the principle propounded in

the aforesaid case as was also done by the apex court in BSNL -v-

Nortel (supra) but the present case factually differs from the

situation in Geo Miller (supra). In Geo Miller (supra), the final

bill was still pending settlement whereas in the present case the

final bill was not only settled but the retention money was also

refunded to the petitioner. The petitioner clearly accepted the

settlement by two letters, indicating no duress or coercion

whatsoever, accepted the payments as per the final bill and the

refund of the retention money.

30. Next, Mr. Mitra sought to challenge the acceptance of such final

bill on the grounds that the same was done under duress from the

respondent. This reminded me of the old saying of hitting arrows

in the dark in the hope that one of them will hit the intended

target. I firmly believe that one should not keep arguing for

argument's sake. If a certain claim is made before the Court, the

same needs to be backed up by some evidence. He failed to satisfy

this Court regarding the existence of duress or any such

extraneous factor which led the petitioner to accept the final bill.

In my view, compelling financial circumstances and the

petitioner's eagerness to receive the payment cannot tantamount

to duress from the respondent's side.

31. It is now well settled that the claims in the present petition are ex-

facie time barred. However, as a last ditch effort Mr. Mitra

contended that since the respondent in its letter dated April 10,

2021 had themselves appointed the arbitrator, the question

regarding the existence of any dispute does not arise anymore. In

my view, limitation is not something to be decided by the consent

between the parties, but it is something which is statutorily

mandated and judicially enforced. If there is a boundary drawn by

the legislature and enforced by the judiciary, parties cannot act

outside of it on the grounds that their consent should be the

primary consideration in such cases. While this Court accepts that

appointment of arbitrator by the respondent is impermissible but

that would not permit the parties to venture beyond the

boundaries of limitation.

32. The letter dated April 10, 2021 of the respondent is quite explicit

with regards to non-admissibility of the claim and on the point of

limitation. Even though the respondent appointed an arbitrator it

clearly stated as follows:-

"In view of the above, our client states that there is no existing

dispute referable to arbitration as alleged in your letter under

reference. In any event the alleged claim sought to raised, is

clearly barred by limitation.

Without prejudice to the above contentions, since your client

has sought to invoke the arbitration clause, our client hereby

nominates Shri. Basab Majumdar, Retd. DG, CPWD as its

nominee arbitrator."

Ergo, the appointment per se cannot be treated as an acceptance of

the claim resulting in extension of the limitation as the letter

specifically denies the claim and states that the same is barred by

limitation.

33. At this juncture, reference can be made to the Delhi High Court's

decision in Extramarks Education India Pvt. Ltd -v- Shri Ram

School and Anr. reported in 2022 SCC OnLine Del 3123

wherein Bhambani J. held that limitation cannot be extended by

consent. The relevant portions have been extracted below -

14. To be abundantly clear as to the concept of 'limitation'

barring a legal remedy, the following observations of the

Hon'ble Supreme Court in N.9Balakrishnan v. M.

Krishnamurthy may be noticed:

"11. Rules of limitation are not meant to destroy the

rights of parties. They are meant to see that parties

do not resort to dilatory tactics, but seek their remedy

promptly. The object of providing a legal remedy is to

repair the damage caused by reason of legal

injury. The law of limitation fixes a lifespan for such

legal remedy for the redress of the legal injury so

suffered. Time is precious and wasted time would

never revisit. During the efflux of time, newer causes

would sprout up necessitating newer persons to seek

legal remedy by approaching the courts. So a lifespan

must be fixed for each remedy. Unending period for

launching the remedy may lead to unending

uncertainty and consequential anarchy. The law of

limitation is thus founded on public policy. It is

enshrined in the maxim interest reipublicae up sit

finislitium (it is for the general welfare that a period

be put to litigation). Rules of limitation are not meant

to destroy the rights of the parties. They are meant to

see that parties do not resort to dilatory tactics but

seek their remedy promptly. The idea is that every

legal remedy must be kept alive for a legislatively

fixed period of time."

(emphasis supplied)

*

34. For completeness, the two other objections raised on

behalf of the petitioner may also be answered. The

petitioner's objection that the schedule of payments, as

set-out in Annexure 3 to Agreement dated 31.03.2015, ran

up-to May 2018 is of no relevance of consequence, for the

reason that admittedly the petitioner terminated the

contract with the respondent by Notice dated 04.01.2017;

and could not therefore have demanded payment up-to

May 2018 in the same breath. The petitioner's other

objection, that since in its reply dated 31.08.2021 the

respondent themselves were willing to accept and had

given their consent for appointment of an arbitrator "near

to the locality" where the respondents were located, is

neither here nor there, since if the court finds that the

payments made are ex-facie time-barred, limitation for

invoking a legal remedy cannot be extended even by

consent. Conceptually, limitation bars a legal remedy and

not a legal right, the legal policy being to ensure that legal

remedies are not available endlessly but only up-to a

certain point in time. Needless to add however, that if the

respondents are conceding the petitioner's claim itself, and

are ready and willing to pay-up, such payment would not

be illegal and there could not be any legal impediment in

doing so. A party may concede a claim at any time; but

cannot concede availability of a legal remedy beyond the

prescribed period of limitation."

35. This Court is in agreement with the principles laid down by the

Delhi High Court in the aforesaid judgment. While time should

never be a hindrance in dispensing justice, the same would not

mean that the time for claiming recourse to a remedy never ends

as this would defeat the very purpose for which such remedies

exist. The goal is never just to ensure that justice is done but also

to make sure it is done in a timely manner, and within certain

boundaries of limitation as laid down by the law. In my view,

limitation does not act as a barrier in the pathway of justice, but

instead it acts as a means to ensure efficiency in the process of

justice.

36. For ease of reference of the parties, I have attempted to

encapsulate below the relevant juridical principles which emerge

from the various judgments discussed above -

a. The Supreme Court vide its decisions in Perkins Eastman

Architects DPC & Another -v- HSCC (India) Ltd. (supra)

and TRF Ltd. -v- Energo Engineering Projects Ltd. (supra)

has univocally made it clear that unilateral appointment of an

arbitrator by an interested party is not permissible.

b. The three judges' bench in Vidya Drolia -v- Durga Trading

Corporation (supra) empowered the Courts adjudicating a

Section 11 application to intervene in certain circumstances

and held that such interventional exercise does not interfere

with the principle of competence-competence and separation

as to obstruct arbitration proceedings but ensures that

vexatious and frivolous matters gets weeded out at the initial

stage. It is to be noted that the Supreme Court in this case

observed that an absolute hands off approach would be

counterproductive and harm arbitration, whereas limited yet

effective intervention is acceptable as it does not obstruct but

effectuates arbitration. Thus, the Courts at the Section 11

referral stage, with a view to prevent wastage of public and

private resources, can interfere when it is manifest that the

claims are ex-facie time barred and dead, or there is no

subsisting dispute.

c. Similarly, in DLF Home Developers Limited -v- Rajapura

Homes Pvt. Ltd., (supra) the apex court affirmed that the

limited jurisdiction under Section 11 does not denude this

Court of its judicial function to look beyond the bare existence

of an arbitration clause to cut the deadwood. The Court went

ahead to say it differently that this Court or a High Court, as

the case may be, are not expected to act mechanically merely

to deliver a purported dispute raised by an applicant at the

doors of the chosen arbitrator. A limited review by the Court

is not intended to usurp the jurisdiction of the Arbitral

Tribunal but is aimed at streamlining the process of

arbitration.

d. The Supreme Court further clarified in Bharat Sanchar

Nigam Limited -v- Nortel Networks India Pvt. Ltd. (supra)

that adjudication of the limitation issue at the Section 11

referral stage does not tantamount to stepping into the

arbitrator's jurisdictional territory. In essence, it opined, that

the issue of limitation is a challenge to the maintainability or

admissibility of the claim itself and not a challenge to the

jurisdiction of the arbitrator to decide the claim. Basis this

reasoning, Uttrakhand Purv Sainik (supra) cited by Mr.

Mitra stood distinguished.

e. Again in Bharat Sanchar Nigam Limited -v- Nortel

Networks India Pvt. Ltd. (supra), the Supreme Court held

that there must be a clear notice invoking arbitration setting

out the particular dispute (including claims / amounts) which

must be received by the other party within a period of 3 years

from the rejection of a final bill, failing which, the time bar

would prevail. It also concluded that the period of limitation

for issuing notice of arbitration would not get extended by

mere exchange of letters, or mere settlement discussions,

where a final bill is rejected by making deductions or

otherwise.

Likewise in Geo Miller & Company Private Ltd. -v-

Rajasthan Vidyut Utpadan Nigam Ltd. (supra), the apex

court held that 'breaking point' is the date where any

reasonable party would have abandoned efforts at arriving at

a settlement and contemplated referral of the dispute for

arbitration. This date would then be treated as the date on

which the cause of action arises, for the purpose of limitation.

The threshold for determining when such a point arises will

be lower in the case of commercial disputes, where the party's

primary interest is in securing the payment due to them, than

in family disputes where it may be said that the parties have

a greater stake in settling the dispute amicably, and therefore

delaying formal adjudication of the claim.

f. In Secunderabad Cantonment Board -v- B.

Ramachandraiah & Sons (supra), the apex court ruled that

once the limitation period has started running, any final

rejection by the respondent would not give any fresh start to

the limitation period which has already begun running,

following the mandate of Section 9 of the Limitation Act,

1963.

g. Lastly, in Extramarks Education India Pvt. Ltd -v- Shri

Ram School (supra), the Delhi High Court remarked that

limitation for invoking a legal remedy cannot be extended

even by consent and that unending period for launching the

remedy may lead to unending uncertainty and consequential

anarchy.

37. For the convenience of the parties, I have summarized below the

factual findings of this Court -

a. The final bill of March 11, 2016 was a result of reworking and

enhancement of the initial costs from a figure of INR

39,03,20,185 to INR 80,23,73,260/-.

b. Therefore, the cause of action arose on March 11, 2016 itself,

i.e., on the day when the final bill was issued by the

respondent, and therefore, the limitation period started to run

from that day itself;

c. Two letters were issued by the respondent accepting the final

bill, and subsequently, they received payments for the same

and also refund of the retention money. In fact, the

petitioner's letter of acceptance only makes a 'request' for

further enhancement and nothing more.

d. Subsequent demand letters by the petitioners do not utter a

single word on coercion or duress, and in any case, no

evidence was ever produced to show that their acceptance of

the final bill dated March 11, 2016, was made under duress

or coercion;

e. The letter by the respondent in 2017 rejecting the demands of

the petitioner is only a reiteration of its earlier stand and

cannot be accepted as the breaking point of negotiations to

allow a fresh period of limitation. This argument of Mr. Mitra

and his reliance on Geo Miller (supra) is misplaced as in that

case, the final bill was never settled, and therefore, in that

case, the rejection was taken as the starting point of

limitation. The present case is clearly distinguishable on

facts.

f. In light of the above, the limitation period started on March

11, 2016 itself and the notice of arbitration under Section 21

issued on March 8, 2021, is patently barred by limitation as

per Article 137 of the Limitation Act, 1963.

g. In arguendo, if May 16, 2016, is assumed to be the 'breaking

point,' i.e., the day when the petitioner raised their escalation

claims for the first-time post receipt of payment, retention

money, and the final completion certificate, and also sought

to invoke arbitration, even then the present application is

barred by limitation.

h. Even though the respondent appointed an arbitrator in their

letter dated April 10, 2021, the same would not be treated as

an acknowledgement of the petitioner's claim as the letter not

only denied such a claim but also stated that the same is

barred by limitation.

38. I would like to put on record my appreciation of the lawyers

appearing for both parties for their assiduous efforts in trying to

convince the court on behalf of their clients. Arguments made

during the course of the hearing were both invasive and thought-

provoking and have resulted in substantial enhancement in the

ken of knowledge of this Court on the subject.

39. In view of the above-mentioned findings by this Court, and humbly

disagreeing with Mr. Mitra, I hold that it is patently clear that the

claim giving rise to the present dispute is ex-facie time barred and

falls within the limited category of deadwood. Resultingly, the

reference to arbitration is hereby declined.

40. Accordingly, AP 237/2021 is dismissed. There shall be no order as

to costs.

41. An urgent photostat-certified copy of this order, if applied for,

should be made available to the parties upon compliance with

requisite formalities.

(Shekhar B. Saraf, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter