Citation : 2023 Latest Caselaw 1324 Cal
Judgement Date : 22 February, 2023
IN THE HIGH COURT AT CALCUTTA
Constitutional Writ Jurisdiction
Appellate Side
Present :-
The Hon'ble Justice Moushumi Bhattacharya.
W.P.A 21965 of 2022
With
CAN 1 of 2022
The Ramco Cements Limited & Anr.
vs.
The Board of Trustees of Syama Prasad Mookerjee Port,
Kolkata & Ors.
For the petitioners : Mr. S. N. Mookherjee, Sr. Adv.
Mr. Deepan Kr. Sarkar, Adv.
Mr. Saptarshi Banerjee, Adv.
Mr. Soumitra Datta, Adv.
Ms. Ananya Sinha, Adv.
For the Port/respondents : Mr. Kishore Datta, Sr. Adv.
Mr. Ashok Kumar Jena, Adv.
Last Heard on : 6.02.2023.
Delivered on : 22.02.2023.
2
Moushumi Bhattacharya, J.
1. An Interim order was passed on 21.9.2022 restraining the Shyama
Prasad Mukherjee Port from taking any steps pursuant to the impugned
Demand Notice dated 9.9.2022. This order was extended on 30.11.2022 in
the presence of learned counsel representing the Port Authorities.
2. The impugned Demand Notice was issued by the respondents for a
sum of Rs. 20.28 crores on account of the Minimum Guarantee Tonnage
(MGT) short fall in quantity which the petitioners were allegedly due to pay.
The Port threatened to encash the bank guarantee furnished by the
petitioners in case of failure of the petitioners to make payment within 7
days from receipt of the impugned notice.
3. After hearing the parties on 30.11.2022, the interim order was
directed to continue till 13.1.2023. The interim order was further extended
thereafter and the parties have filed their respective notes of arguments. The
matter was reserved for judgment on 6.2.2023.
4. The petitioner no. 1 claims to be a Company which manufactures
cement at a plant in Kolaghat, West Bengal. A Contract of Affreightment was
entered into between the petitioner no. 1 and Sea Port Logistics Private
Limited whereby cement clinker was to be carried in vessels capable of
carrying the cargo to Haldia Dock operated by the respondent authorities for
a period of 5 years from 1.7.2017 - 30.6.2022. The petitioner no. 1 was
granted priority in berthing of vessels carrying cement clinkers at Haldia
Dock by the respondents by a letter dated 4.4.2018. This berthing facility
was for a period of 1 year against the commitment of minimum handling of
1 million metric tons (MMT) per annum of coastal cargo backed by a Bank
Guarantee equivalent to applicable on-board, wharfage and cleaning charges
for 1 MMT of cargo. The port charges against the shortfall was to be
recovered from the petitioner in the event the petitioner was unable to fulfil
the MGT commitments of 1 MMT. There was a shortfall in the MGT volume
after expiry of the period of one year which the petitioners say was beyond
the control of the petitioner no. 1. The petitioners requested the respondents
to grant priority berthing facilities to the petitioner no. 1 for three years on
the condition that the shortfall quantity from the first tenure would be
performed by the petitioner no. 1 during the three year period and a total
quantity of 34,13,792 MT of cement clinker would be handled by the
petitioners at the Haldia Dock for the said period.
5. The second tenure of priority berthing facilities was granted by the
respondents by a letter dated 20.6.2019 for a period of three years. The
relevant terms for the grant included the petitioner no. 1 mobilising
34,13,792 MT Cargo over a period of three years and that the performance
of the petitioner no. 1 would be assessed at the end of the three year period.
The petitioner no. 1 was also required to furnish a bank guarantee
equivalent to the wharfage, on-board and cleaning charges which was to be
valid till 31.12.2022. The petitioner furnished a bank guarantee dated
2.7.2019 for a sum of Rs. 27,79,00,000/- which was issued by the
respondent no. 7, ICICI Bank on behalf of the petitioner no. 1. The said
bank guarantee contained terms and conditions which included that the
bank guarantee would remain in force till 31.12.2022 and could not be
invoked simpliciter but only upon satisfaction of certain conditions
precedent. The bank guarantee was amended pursuant to the request of the
respondents following which the bank guarantee dated 30.7.2019
containing the additional terms was issued by the respondent no. 7 to the
respondent no. 1 Port.
6. The Covid 19 pandemic disrupted all businesses on a global scale
from 2020 onwards. The petitioner no. 1 hence requested the respondents
by a letter dated 1.9.2020 to extend the performance period up to 30.6.2024
for mobilising the MGT. A Memorandum of Understanding dated 17.2.2021
was executed between the parties followed by a letter dated 24.2.2021
issued by the respondents whereby the 2nd tenure was extended from
19.6.2022 to 30.6.2024 for fulfilling the MGT obligations of the petitioner
no. 1.
7. The petitioners faced several difficulties after the onset of the
pandemic which included scrapping of the vessel provided by Sea Port
Logistics. The petitioner no. 1 was forced to charter another vessel for
carrying cement clinker. There was also a decline in cement demand and a
rise in freight rates pursuant to lockdowns caused by the Pandemic. The
petitioner no. 1 made several representations to the respondents indicating
the unforeseen conditions and requested the respondents for time till
September, 2022 to resume coastal movements. The petitioner no. 1 availed
of the priority berthing for the last time in February, 2021. The respondent
no. 4 thereafter issued a letter to the petitioner no. 1 on 8.12.2021 stating
that the respondents had extended the period for fulfilment of MGT up to
30.6.2024 and a further request for extending the timeline could not be
acceded to.
8. Due to the continuing economic downturn and the unsustainable
freight rates, the petitioner no. 1 was constrained to withdraw from the MGT
and by a letter dated 31.12.2021 requested the respondents to calculate the
amount to be paid to the respondents. The respondent no. 4 being the
General Manager (Traffic), Port however did not accept the withdrawal and
asked the petitioner no. 1 to resume the cargo movements within
September, 2022 on a continuous basis failing which the bank guarantee
would be encashed proportionately up to 31.12.2021. The petitioner no. 1
was thereafter constrained to again request the respondents to extend the
time frame for cargo movements due to the war in Ukraine. The respondent
no. 5 being the Senior Deputy Manager, Port called upon the petitioner to
pay an amount of Rs. 20,28,89,796/- by a letter dated 22.7.2022. The
petitioner no. 1 made certain representations thereafter.
9. The exchange of letters continued till issue of the impugned Demand
Notice dated 9.9.2022 by which the petitioner was requested to pay Rs.
20,28,89,796/- within 7 days from receipt of the letter failing which the
respondents would encash the said amount from the bank guarantee dated
2.7.2019.
10. From the submissions made by learned counsel for the parties and
the documents shown to the Court, it is evident that the threat of invocation
of the bank guarantee is not in accordance with the terms of the bank
guarantee. The respondents had not accepted the petitioner's withdrawal
from the priority berthing scheme and had instead issued a letter on
21.1.2022 granting the petitioner no. 1 time till September, 2022 to resume
cargo movements on a continuous basis. Hence, the shortfall calculation
should have been made only after expiry of 5 years that is till 30.6.2024 as
expressed in the letter of 20.6.2019 and the MOU. According to the terms of
the bank guarantee, the petitioner no. 1 would be liable for Port charges
against the shortfall quantity in the event the petitioner failed to pay the
same and the bank guarantee would be encashed on a proportionate basis.
The MGT obligation which was initially for a period of 3 years from
20.6.2019 to 30.6.2022 had been extended by the respondents for an
additional 2 years from 19.6.2022 to 30.6.2024. Despite granting such
extension the respondents however called upon the petitioner to pay an
amount of Rs. 20,28,89,796/- which was calculated on a pro rata basis
taking a time frame of 3 years instead of 5 years.
11. Therefore, the time to meet the shortfall stood extended by the
documents exchanged between the parties including the MOU dated
17.2.2021.
12. The special equities in the case arise out of at least two factors. First,
the respondents have not suffered any loss on account of the petitioner no.
1 not availing of berthing services provided by the respondents to the
petitioner no. 1. The priority granted to the petitioner no. 1 with regard
berthing of vessel carrying cement clinkers at Haldia Dock did not mean
that the respondent authorities would be under an obligation to give a dock
for the vessels of the petitioner no. 1. It only meant that if there was more
than 1 vessel arriving at the Dock at the same point of time, the petitioner
no. 1's vessel would get priority in calling and berthing. In the event more
that 1 MGT provider was present at the Dock, the senior most vessel
according to the MGT provider would get priority. Hence, by making a
demand of Rs. 20,28,89,796/- without suffering any loss would amount to
the respondent authorities making a windfall gain and unjust enrichment.
The privilege of priority berthing was in any event availed of by the petitioner
no. 1 for the last time in February, 2021.
13. Second, the bank guarantee furnished by the petitioner was valid up
to 31.12.2022 which meant that the performance of the petitioner no. 1 was
to be assessed at the end of the period 30.6.2022 as per the agreement
covered by the letter dated 20.6.2019. The terms of the bank guarantee were
never amended after the second tenure was extended for 2 years from
19.6.2022 to 30.6.2022.
14. Third, the petitioner no. 1 was also not required to make any payment
to the respondent authorities before 30.6.2024 after the MOU of 17.2.2021
and the letter dated 24.2.2021 issued by the respondent authorities by
which the second tenure was extended from 19.6.2022 to 30.6.2022 for
fulfilment of the MGT obligation. The petitioners however, to show their bona
fides, voluntarily requested to the respondent to calculate a fair penalty
being Rs. 4,25,21,912/- calculated till February, 2021 till which date the
petitioner no. 1 had availed of the priority berthing facilities.
15. The respondents seeking to encash the bank guarantee is hence
arbitrary as the respondents gave a go-by to the 5-year contract period and
instead calculated penalty on a pro rata basis by relying on the 3-year
contract which was superseded on and from 24.2.2021. The respondent
authorities also sought to make a windfall gain despite not suffering any
loss.
16. This Court hence finds that the petitioners have made out a case
against invocation of bank guarantee. It may also be mentioned that the
respondents could not give a satisfactory answer as to why the MGT
requirement was calculated on 3-year basis when the petitioner no. 1 was
given a 5-year extension. There is also no satisfactory answer as to the
reason for the respondents invoking the bank guarantee when the
petitioners had unequivocally expressed their desire to withdraw from the
arrangement on and from 31.12.2021.
17. In Cargill International SA v. Bangladesh Sugar & Food Industries
Corporation; (1996) 4 WLR 563, the Court of Appeal held that the defendant
would make a substantial windfall where it had not suffered any loss which
would run counter to the general proposition that compensation for breach
of contract depends on proof of loss. The Supreme Court in Kailash Nath
Associates v. Delhi Development Authority; (2015) 4 SCC 136 stressed on the
expression "whether or not actual damage or loss is proved to have been
caused thereby" in section 74 of The Indian Contract Act, 1872 and held
that the expression meant that where it is possible to prove actual damage
or loss such proof is not dispensed with, only where the damage or loss is
difficult or impossible to prove that the liquidated amount named in the
contract can be awarded if it is a genuine pre-estimate of damage or loss. In
Omega Shelters Pvt. Ltd. v. United Construction Co. Pvt. Ltd.; (2009) 4 CHN 22
a Division Bench of this Court, after considering the relevant facts, held that
the invocation was not in terms with the bank guarantee and thus the bank
was not obliged to honour the same or make payments on the basis of the
demands which were not in conformity with the terms of the invocation. The
Division Bench also noted that the appellant had not asserted that the
amount claimed is due by way of loss or damage caused to the appellant or
that the concerned party would suffer by reason of any breach by the
contractor.
18. The conduct of the respondents would also be apparent from the
documents in CAN 1 of 2022 which has been filed by the petitioners for
setting aside two letters issued by the respondents on 11.11.2022 and
16.11.2022. These letters were issued to the petitioners with the express
threat that the respondents would lodge a claim and encash the bank
guarantee if the respondents did not receive the extension of the validity of
the bank guarantee. Both these letters were issued after the Court passed
the interim order on 21.9.2022 which was communicated to the
respondents soon thereafter.
19. Submissions made on behalf of the respondent authorities and the
notes/documents placed before the Court does not disclose any reason to
depart from the view taken on 21.9.2022 and 30.11.2022 when the first
interim order was granted and extended respectively.
20. For the above reasons, this Court is inclined to confirm the interim
orders and quash the impugned Notice of Demand dated 22.7.2022 and
9.9.2022 together with the subsequent letters issued by the respondents on
11.11.2022 and 16.11.2022. This judgment shall not preclude the
respondent authorities from demanding a justifiable amount of penalty from
the petitioner no. 1. It is made clear that the petitioner no. 1 shall be liable
for penalty on account of the shortfall which is to be calculated from and on
the basis of the letters and MOU between the parties including the last
understanding arrived at between the parties. The petitioners shall pay the
calculated amount to the respondent authorities within the framework of the
correspondence or within any agreed timeframes and on such terms thereof.
21 WPA 21965 of 2022 along with CAN 1 of 2022 are disposed of in terms
of the above.
Urgent photostat certified copies of this judgment, if applied for, be
supplied to the parties upon fulfillment of requisite formalities.
(Moushumi Bhattacharya, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!