Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Sens Hotels Pvt. Ltd vs State Of West Bengal & Ors
2023 Latest Caselaw 5534 Cal

Citation : 2023 Latest Caselaw 5534 Cal
Judgement Date : 24 August, 2023

Calcutta High Court (Appellete Side)
M/S. Sens Hotels Pvt. Ltd vs State Of West Bengal & Ors on 24 August, 2023
S/L 1
24.8.2023
Court No.26
SD
                                  WPA 24550 of 2016

                                 M/s. Sens Hotels Pvt. Ltd.
                                            Vs.
                                State of West Bengal & Ors.

              Mr. Vipul Kundalia
              Mrs. Sonal Shah
                                                              ... for the Petitioner.
              Mr. Rajarshi Basu
              Mr. Tapas Ballav Mandal
                                                                    ... for the State.
              Mr. Satyajit Talukdar
              Ms. Piu Karmakar
                                                               ... for the K.M.D.A.

                    This is an application under Article 226 of the

              Constitution of India wherein the writ petitioner has

              challenged the show cause notice dated November 24, 2015

              and the subsequent order for payment of penalty dated

              September 19, 2016.

                    The extract of show cause notice is enumerated

              below:-

                    Sir,
                            Whereas it has been verified from records that plot no.
                    5/4 at Block-I, Category- Bulkland under EKADP was allotted
                    to Sens Group vide this office allotment letter no.
                    173/KMDA/Sectt/AD-16/2007 Dated: 23.10.07.
                                                  AND
                            Whereas possession advice was issued on 21.01.2007.
                                                  AND
                            Whereas License deed was executed on 28.04.2008 in
                    respect of Plot no.5/4 Block-I, Category- Bulkland under
                    EKADP.
                                                  AND
                            Whereas according to conditions at clause 2(iii) of the
                    license deed executed on 28.04.2008 the allottee was supposed
                    to complete the construction within 5 (five) years from the date
                    of execution of License deed but it has been seen that the allottee
                    has not submitted completion certificate. So, he is asked to
                    show cause as to why the allotment will not cancelled as per the
                    existing clause of license deed for non construction within
                    schedule time.

                                                             Yours faithfully,

                                                                     Sd/-
                                                             Deputy Secretary,
                                                             Estate Unit, KMDA.
                                           2




         Subsequently, a demand notice was raised by order

dated September 19, 2016 approximately of Rs. 8 crore for

delay in construction.

         Several judgments have been cited on behalf of both

the parties and this Court was on the verge of passing a

judgment on the issue.            However, Mr. Satyajit Talukdar,

counsel appearing on behalf of the respondent authorities

has placed a recent order dated February 10, 2022 passed in

the case of Siddharth Co-operative Housing Society

Ltd. vs. Kolkata Metropolitan Development

Authority & Ors. along with Dinabandhu Andrews

Institute of Technology and Management & Ors. (in

MAT 839 of 2018 with CAN 6085 of 2018) passed by

the Supreme Court.

The Supreme Court has noted that contrary views

were taken in Siddharth Co-operative Housing

Society Ltd. (supra) and Dinabandhu Andrews

Institute of Technology and Management & Ors.

(supra) with regard to issue that is also in question before

this Court. Subsequently, the parties before the Supreme

Court came up with a compromise formula based on a

Pricing Committee meeting held on February 12, 2009 which

reads as under:-


Sl     Category of Plots   Extension          Extension        Extension
No.                        upto 5 years       from      5-10   beyond      10
                                              years            years
1.     Commercial          2% of the rate     5% of the rate   10% of the
                           at which the       at which the     rate at which
                           land      was      land      was    the land was
                           allotted    to     allotted    to   allotted    to
                           them               them             them
2.     Non-Commercial      Not      more      Not      more    Not      more
                           than 2% of the     than 5% of the   than 10% of
                           rate at which      rate at which    the rate at
                           the land was       the land was     which      the
                           allotted    to     allotted    to   land      was
                           them               them             allotted    to
                                                               them





Mr. Talukdar submits that Kolkata Metropolitan

Development Authority has accepted the above table before

the Supreme Court as the basis for charging penal rate.

As it is evident from the show cause notice that the

construction was to be completed by April 2013 while in the

present case, the completion certificate was received in the

year 2016. Therefore, the particular case at hand falls under

the category of "Extension upto 5 years" for which penalty is

to be paid at the rate 2% at which land was allotted to the

petitioner.

In light of the same, the petitioner herein has

submitted that he is willing to make the payment of 2% of

the value of the land, that is, Rs.3,00,40,000/- that was paid

by him in the year 2007.

In light of the submissions made by both the parties,

the petitioner is directed to make payment of 2% of

Rs.3,00,40,000/- within a period of five weeks from date.

In light of the above discussions and observations, the

show cause notice dated November 24, 2015 and order dated

September 19, 2016 are quashed and set aside on the

understanding that the petitioner shall make the payment as

directed above.

In the event, payment is not made, penal charges shall

apply on the said sum at the rate of 15% per annum.

With these observations, WPA 24550 of 2016 is

disposed of.

All parties are to act on the website copy of this order.

(Shekhar B. Saraf, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter