Citation : 2023 Latest Caselaw 4851 Cal
Judgement Date : 8 August, 2023
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
WPA No. 18204 of 2023
M/s. Greentech Environ Management Private Limited
and another
Vs.
The State of West Bengal and others
For the petitioners : Ms. Reshmi Ghosh,
Mr. Soumya Sarkar Chini
For the State : Mr. Jayanta Samanta,
Ms. Arpita Mandal
For the KMDA : Mr. Sirsanya Bandopadhyay,
Mr. Avishek Guha,
Ms. Akansha Chopra
Hearing concluded on : 02.08.2023
Judgment on : 08.08.2023
Sabyasachi Bhattacharyya, J:-
1. The petitioner no. 1-company deals with bio-remediation and bio-
mining of municipal and legacy waste. The petitioner no. 2 is its
director.
2. The petitioner no. 1 participated in a tender floated by the Kolkata
Metropolitan Development Authority (KMDA) and turned out
successful. Consequently, the petitioner no. 1 was awarded work
contracts in respect of several districts, all dated February 17, 2021.
The work contracts pertain to bio-mining of legacy waste and land
2
reclamation of dumpsites utilizing scientific method. The petitioner no.
1 is still working under the said contracts.
3. After performing the work for some time, on September 6, 2021, a
certificate was issued by the Chief Engineer, Sewerage, Drainage and
Solid Waste Management Sector, KMDA. The said document certified,
inter alia, that the petitioner no. 1 had successfully completed bio-
remediation of legacy waste quantity of 6.10 Lakh Metric Tons "up to
31.07.2021" at the sites across West Bengal, as mentioned therein. It
was further stated that the certificate-issuing authority was satisfied
with the performance of the petitioner no. 1 "so far".
4. However, on June 23, 2023, the respondents issued a show-cause
notice to the petitioner as to why the said certificate would not be
cancelled.
5. The petitioners gave a written reply to the show-cause on June 26,
2023.
6. However, the respondents, vide communication dated July 27, 2023,
revoked the certificate and requested the petitioners to return the
original certificate within seven days.
7. Being thus aggrieved, the petitioners have preferred the present
challenge.
8. Learned counsel for the petitioners argues that valuable rights flowing
from the certificate have accrued in favour of the petitioners and the
respondents cannot, unilaterally, withdraw such rights. The
respondents, it is argued, are also barred by the principle of Estoppel.
9. It is contended that the grounds cited in the show cause notice are not
valid in law. Moreover, the impugned cancellation of the certificate is
devoid of reasons. In such context, learned counsel appearing for the
petitioners cites Assistant Commissioner, Commercial Tax Department,
Works Contract and Leasing, Kota Vs. Shukla and Brothers, reported at
(2010) 4 SCC 785.
10. Learned counsel next argues that the respondents themselves issued
the credential certificate upon completion of a substantial portion of
the work by the petitioners in respect of several districts. Even now,
the respondents do not dispute the veracity of the facts stated in the
certificate. Hence, the impugned cancellation is bad in law and ought
to be set aside.
11. It is alleged that the impugned order is violative of Article 19 of the
Constitution of India.
12. Learned counsel for the respondent-authorities contends that the
petitioners do not have any statutory or Constitutional right to have a
certificate issued in their favour. Although the respondents initially
issued the certificate-in-dispute, the same was being misused by the
petitioners. Learned counsel denies that the certificate was a
„completion‟ certificate or a „credential‟ certificate. However, the
petitioners have been rampantly using the said certificate as
credential/completion certificate for participating in other tenders
before several authorities in different states.
13. It is contended that the petitioners, on the basis of the certificate,
have been claiming around that the same was a credential certificate
and should be treated as proof of completion of work by the
petitioners under the tender floated by the present respondents.
14. Queries were raised by such other tendering authorities in several
states as to the credibility of the said certificate issued by the
respondents, for which the latter‟s goodwill is suffering.
15. For example, it is submitted, tendering authorities from Cuttack
sought to clarify doubts regarding the certificate, which was produced
by the petitioners in a tender floated by the said authorities to claim
completion of similar work, as contemplated in the said tender, for the
respondents.
16. It is argued by the respondents that the doctrine of Estoppel is not
attracted, since the petitioners did not perform any act on the basis of
the certificate, but would have participated in other tenders in any
event, even if the certificate was not issued.
17. Since the petitioners have no statutory right to claim a certificate, the
respondents, it is argued, can at any time revoke the same at their
discretion.
18. Upon hearing learned counsel for the parties, it is to be first
considered whether any statutory or Constitutional right of the
petitioners has been violated by the impugned cancellation. The
respondents are right in arguing that the petitioners do not have any
such right in the first place to enforce issuance of a certificate.
19. However, the mere fact of the petitioners not having a right to have
such a certificate is an insufficient defence in the present case, since
the factual developments here have crossed the stage of directing the
issuance of a certificate. Here, the petitioners are not seeking any
direction on the respondents to issue a certificate. The respondents, in
the present case, issued the certificate of their own volition. The
petitioners have acted on the basis of such issuance by participating
in several tenders floated by different authorities in several states,
claiming credentials on the basis of such certificate which would
satisfy the conditions of the said tenders. As such, the defence against
Estoppel, on the ground that the petitioners did not act on the basis of
the certificate, is lame.
20. The petitioners fully acted on the basis of the certificate by
participating in subsequent tenders on the strength of the said
certificate, and might not have participated in those tenders at all if
the certificate was not issued.
21. The purpose of a certificate, addressed "To Whom It May Concern", is
obviously not a personal communication but intended to be used
before other authorities.
22. Hence, the respondents cannot escape the rigour of Estoppel ex facie.
The bar would apply, however, in the facts of the case, and with the
rider that if the respondents, for subsequent reasons and following
due process of law and natural justice, find any irregularity committed
on the basis of the certificate or abuse thereof, may take valid steps in
law in that regard.
23. In the instant case, the matter does not rest there. Here, the
respondents cannot be said to have cancelled the certificate
„unilaterally‟ or „at their sweet will‟, since a proper show-cause notice
and right of reply was given to the petitioners, which was availed of by
the petitioners by giving a written reply.
24. The show-cause notice has three important features:
25. First, it denies that the certificate can be treated as a credential
certificate.
26. Secondly, it alleges that the petitioners‟ submission of the certificate
as credential certificate to various organizations during participation
in tender is enough to create a doubt in the mind of the officials of the
organizations and affects the image of the KMDA in the public domain.
27. Thirdly, the petitioners have used the certificate instead of bringing it
to the notice of the competent authority of KMDA for appropriate
course of action.
28. The first stand taken by the KMDA is arguable. A certificate issued by
the authorities "To whom it may concern" is obviously a general
certificate addressed to the world at large and speaks for itself.
Whether the contents of the same satisfy the conditions of a particular
tender document is entirely for the tenderer to consider in each case.
There is a distinction between „credential‟ and „completion‟.
„Credential‟ refers to antecedents. The petitioners can very well claim
that they have completed the work up to the stage as indicated in the
certificate.
29. The petitioners, however, cannot claim that the certificate indicates
that the entire work awarded to them has been done. Thus, it cannot
be a „completion‟ certificate, since it indicates that only a part of the
work was done till the date of its issuance.
30. A perusal of the certificate shows that the petitioners have
successfully completed "bio-remediation" (which, admittedly, is only a
component of "bio-mining", for which the work was assigned), that
too, only up to July 31, 2021.
31. The KMDA, as per the last line of the certificate, express their
satisfaction with the petitioners‟ performance "so far".
32. Hence, the certificate is self-explanatory. It does not claim to be either
a credential certificate or a completion certificate, but stands for what
it is.
33. Coming to the petitioners‟ argument that the impugned cancellation is
devoid of reasons, in the cited judgment of Assistant Commissioner
(supra), the Supreme Court was primarily dealing with judicial orders.
In such context, it was observed that recording of reasons is an
essential feature of dispensation of justice and that reasons are the
soul of orders.
34. The above principle was laid down in the context of orders of a judicial
or quasi-judicial nature having some impact on the concerned party.
In the present case, however, the respondents were merely cancelling
a certificate voluntarily issued by themselves. The petitioners did not
have a statutory right to get such certificate in the first place. Thus,
detailed reasons, as required in a judicial order or an administrative
order taking penal action against someone, are not expected in the
impugned cancellation.
35. The show-cause notice sufficiently disclosed the allegations and the
impugned order recorded dissatisfaction on the reply given by the
petitioners.
36. Thus, the argument of dearth of reasons, per se, cannot be a factor
vitiating the impugned cancellation.
37. The remaining issue is, whether the KMDA is suffering in any manner
from the alleged misuse of the certificate issued by it, by the
petitioners, before other tenderers.
38. There is some justification in the argument of the KMDA that there is
scope of misreading the certificate-in-question as a completion
certificate, although it does not ex facie claim to be so. Such
misunderstanding can arise, particularly, on the following counts:
39. First, the certificate speaks about the petitioners having "successfully
set up" and "operating" the concerned facilities for "bio-remediation
and bio-mining" of legacy waste, although the petitioners have not
done any substantial work of bio-mining till the date of issuance of the
certificate. The work consists of two periodic components - 3 months
for machine installation and the rest for bio-mining. Hence, as on the
date of issuance of the certificate, that is, September 6, 2021, only
about 7 months had elapsed from the issuance of the work orders on
February 17, 2021. The first 3 out of the said 7 months were
stipulated for machine installation. Thus, the actual contractual work
could only have been done for merely 4 months.
40. Secondly, between the two charts given in the certificate,
inconspicuously sat a sentence which indicated that only bio-
remediation was completed, that too, up to July 31, 2021, which is 2
months earlier than the issuance of the certificate. This takes the
actual period of work done to only 2 months.
41. The expression "so far" at the bottom of the certificate merely qualifies
the contents above it, so does not have any particular significance.
42. The conspicuous placement of two charts in the certificate, the first of
which covers the total volume of the work (not even a small fraction of
which was done by the petitioners in reality at that point of time),
evidently gives an impression, at first glance, if produced as a
„credential‟ or „completion‟ certificate before any tendering authority,
that the petitioners completed the entire job.
43. In any event, completion of only two effective months of bio-
remediation work, which is a miniscule part of the total work
contemplated under the tender floated by the KMDA, cannot serve any
effective purpose for the petitioners, unless the same is intended to be
abused as a completion certificate. So, it cannot be said that any vital
right of the petitioners is being taken away by cancellation of the
certificate.
44. Thus, the bar of Estoppel, taken in proper perspective, is substantially
diluted, since no valuable right could have accrued in favour of the
petitioners on the basis of the certificate, nor could the petitioner
claim to use the certificate as a „completion‟ certificate since,
admittedly, only a small part of the work was done at the stage of
issuance of the same.
45. Thus, to avoid unnecessary misunderstanding and abuse of the
certificate, the KMDA was justified in cancelling the same.
46. The show-cause was, in fact, sufficient, since it disclosed categorically
the grounds of proposed cancellation. The reply given thereto was not
sufficient to dispel the apprehension of misuse of the certificate,
particularly since the same has already been used by the petitioner
before several tendering authorities as credential/completion
certificate.
47. However, the already-accrued rights in favour of the petitioners, in
respect of tenders where the petitioners have already produced the
certificate, cannot be retrospectively curtailed.
48. Accordingly, WPA No. 18204 of 2023 is disposed of without interfering
with the impugned order cancelling the certificate-in-dispute.
However, it is made clear that the certificate shall be treated to be
valid, for whatever it is worth, in respect of tenders where the
petitioners have already participated by production of the said
certificate.
49. There will be no order as to costs.
50. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!