Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

State Of West Bengal & Ors vs Bimal Sardar & Ors
2022 Latest Caselaw 6835 Cal

Citation : 2022 Latest Caselaw 6835 Cal
Judgement Date : 22 September, 2022

Calcutta High Court (Appellete Side)
State Of West Bengal & Ors vs Bimal Sardar & Ors on 22 September, 2022
                    IN THE HIGH COURT AT CALCUTTA
                         Civil Appellate Jurisdiction
                                Appellate Side


Present:

The Hon'ble Justice Shekhar B. Saraf

                           R.V.W 271 of 2017
            IA No. CAN. 1 of 2017 (Old No. CAN 11258 of 2017)
            IA No. CAN. 2 of 2017 (Old No. CAN 11259 of 2017)
                                     In

                        W.P.A. 25094 of 2016
                                 With
                        W.P.C.R.C. 172 of 2017



                   STATE OF WEST BENGAL & ORS.

                                 VERSUS

                        BIMAL SARDAR & ORS.



For the Applicants/Respondents            : Mr. Chandi Charan De, Adv.,

Mr. Rabindra Narayan Dutta, Adv., Mr. Hare Krishna, Adv.

For the Respondents/Writ Petitioners : Mr. Debasis Sur, Adv.

Mr. Himadri Sekhar Paul, Adv.

Last Heard on : September 08, 2022

Judgment on : September 22, 2022

Shekhar B. Saraf, J.:

1. This review application has been filed by the State against an order

dated April 10, 2017 passed by Justice R.K. Bag in W.P. No. 25094(W)

of 2016.

2. The facts of the present matter are as follows :

a. The Applicant/Respondent is the State of West Bengal, service

through the Secretary, Department of Land & Land Reforms,

Government of West Bengal and others.

b. The Respondent no. 1/ Writ Petitioner is Bimal Sardar. He is the

recorded owner of Plot No. 492 (area - 1.13 acres) Plot No. 493

(area 0.04 acres) and Plot No. 494 (area 66 decimals) of Mouza -

Baunia Abad, J.L. No. 20, Khaitan No. 3041 and 4741 under P.S.

Sandeshkhali, District - North 24 Parganas.

c. The plot was agricultural land and the Respondent/ Writ

Petitioner had khas possession of the plot. He was cultivating this

using his own men, bullocks and family members. In 2009, due to

Cyclone Aila, Sunderbans were affected and the embankment was

demolished, where the Writ Petitioner resided. Due to the damage

and the Respondent was no longer able to cultivate the land.

d. After the Cyclone Aila, in order to protect the local area and

residential houses in the area, the Applicants/Respondents

decided to prepare a ring bandh to prevent further flooding. In lieu

of this, the Applicants acquired land, including the land of the

Respondent/Writ Petitioner, under the provisions of the Land

Acquisition Act, 1894.

e. The Respondent/Writ Petitioner states that the

Applicant/Respondent had acquired and took over possession of

the demarcated land. The acquisition of the Respondent's/Writ

Petitioner's land was registered as L.A. Case No. LA-4/116 of

2012-2013 and an award was made in connection with this case.

f. Subsequently, a dispute between the parties arose regarding the

payment of compensation owed to the Respondent/Writ Petitioner,

for the land that was acquired from them under the provisions of

the Land Acquisition Act, 1894, and in connection with L.A. Case

No. LA-4/116 of 2012-13. The Respondent/Writ Petitioner

contends that the award associated with the case has not been

paid. The impugned order dated April 10, 2017 of Justice R.K. Bag

also observed that there was nothing on record to indicate that the

payment had been made to the Respondent/Writ Petitioner.

g. From December 7, 2010 to September 1, 2016, the

Respondent/Writ Petitioner approached various authorities to

disburse the compensation amount owed to him. He approached

the Sub-Divisional Officer, Haroa, Irrigation Sub-Division,

Basirhat, North 24 Parganas, Executive Engineer, Basirhat

Irrigation Division duly recommended by Pradhan, Nazat-I Gram

Panchayat, Sandeshkhali - I, ADM (LO) Land Executive, North 24-

Pargananas, Barasat, Project Directorate - I, the Deputy Secretary

of the Govt of West Bengal as well as the Superintending Engineer,

Eastern Circle, Irrigation and Waterways Directorate. Despite this,

no action was taken by any of the concerned authorities to release

the said compensation.

h. On February 21, 2013 the Executive Engineer submitted a

proposal in the aforesaid LA Case No. LA-4/116 of 2012-2013 to

Additional District Magistrate and District Land and Land Reforms

Office and conveying the fact that relevant estimate of land in

question was sanctioned by the appropriate authority in

connection with the said L.A. case for placement of fund as per

provision of the Land Acquisition Act, 1894.

i. On February 27, 2013, The Executive Engineer also solicited

before the Additional District Magistrate and District Land and

Land Reforms Officer, Barasat for compensation to be released

under Act-I of 1894 through the Basirhat Irrigation Division, with

regard to the acquisition of more or less 0.552 acres.

j. The Respondent/Writ Petitioner did not receive compensation

despite filing numerous applications before the concerned

authorities and proceeded to send a demand letter dated

September 1, 2016, to the concerned authorities, for the

compensation and the interest thereto for the purpose of Aila,

through his learned advocate on record.

k. Being aggrieved by the inaction of the concerned authorities,

despite approaching them on multiple occasions, serving a

demand of justice, repeated prayers and remainders, the

Respondent/Writ Petitioner preferred a writ petition under Article

226 of the Constitution, registered as W.P. 25094 of 2016. The

Respondent/Writ Petitioner prayed for direction upon the

Applicants/Respondents to make payment of compensation for

acquisition of land in connection with L.A. Case No. LA-4/116 of

2012-2013.

l. The Counsel for the Respondent/Writ Petitioner stated before the

learned Judge that the Respondent/Writ Petitioner will be satisfied

with the award assessed under the provisions of the Land

Acquisition Act, 1894.

m. After hearing the Writ Petition, Justice R.K. Bag passed an order

dated April 10, 2017 directing the Additional District Magistrate

and District Land and Land Reforms Officer, Barasat to pay the

amount of award in connection with L.A. Case No. LA-4/116 of

2012-13 to the petitioner within a period of 8 weeks from the date

of the order.

n. Justice R.K. Bag also observed that the Applicants/Respondents

prayed for accommodation, however, since the

Applicants/Respondents has notice of the case since October,

2016, he refused the prayer for accommodation. In light of this,

the learned Judge directed the Additional District Magistrate and

District Land and Land Reforms Officer, Barasat to disburse the

amount of award to the petitioner in connection with the L.A.

Case.

o. Aggrieved by this order, the Applicants/Respondents filed an

application on June 16, 2017, for recalling or modifying the said

order. However, this application was rejected in a hearing on

November 3, 2017, by Justice R.K. Bag. The

Applicants/Respondents were granted the liberty to file an appeal

or a review application against the order.

p. On June 16, 2017, the Applicants/Respondents preferred the

present review application against an order dated April 10, 2017,

passed by Justice R.K. Bag.

q. The Applicants/Respondents also filed a C.A.N Application No.

11258/2017 on November 30, 2017 praying for condonation of

delay in filing the review petition. The petition was filed on the

grounds that they did not have knowledge about the order dated

April 10, 2017 and the pendency of recalling application led to an

unintentional and unavoidable seven and half month delay in

filing the review matter.

r. The Applicants/Respondents also filed CAN Application

No.11259/2017 on November 30, 2017 praying for a stay on the

order dated April 10, 2017 or that appropriate order be passed

keeping the contempt proceedings being W.P.C.R.C. 172 of 2017 in

abeyance till the disposal of the instant review matter.

3. Mr. Rabindra Narayan Dutta, counsel appearing on behalf of the

Applicants/Respondents has made the following arguments :

a. The counsel contends that it is a settled position of law that

parties to a matter should be allowed to submit their applications

and have all those applications heard by the Court. He submits

that the order was passed without calling for the records of the

alleged Land Acquisition case or any affidavits, thereby vitiating

this order as there is an error apparent on the face of the record.

b. The counsel also questions the very existence of the land

acquisition case. He submits that the land acquisition lapsed and

no notice of acquisition proceedings was published in the

newspaper or in the Government Gazette. The counsel argued that

the Applicants/Respondents under the statute has no power or

authority to pay compensation and to proceed with the said

acquisition case and more specifically there is no existence of the

alleged acquisition case.

c. Continuing his arguments, the counsel states that the Land

Acquisition No. 4/116 of 2012 - 2013 is wholly wrong. He further

submits that the Respondent/Writ Petitioner had suppressed

material facts that would have otherwise provided a clear picture

of how much land the Respondent/Writ Petitioner actually owned

and how much of it was being acquired by the State. The counsel

claims that there was no acquisition in respect of the Plot Nos.

492, 493 and 494 as mentioned by the Respondent/Writ

Petitioner, rather only 0.15 acre or 1.5 decimals of the plot was

under notice of acquisition and the acquiring authority after

completion of the proceedings under Section 9 of the Land

Acquisition Act, 1894. He further submits that the

Respondent/Writ Petitioner did not own plot no. 492 and 493

Mouza - Baunia Abad under J.L. No. 3041 and 4741, Police

Station - Sandeshkhali, District - North 24 - Parganas and that

these facts were not brought to the notice of the learned Judge

when he was passing the said impugned order. Concluding his

arguments, the counsel submits that the Respondent/Writ

Petitioner and other co-sharers are still in possession and

occupation of the said land in question and hence the judge erred

in passing this order with an error apparent on the face of record.

4. Mr. Debasis Sur, counsel appearing on behalf of the Respondent/Writ

Petitioner has made the following arguments:

a. The counsel argues that it is a settled principle of law that when

land is acquired by the State, then the owner is entitled to

compensation under the provisions of the Land Acquisition Act,

1894. He states that the Applicant/Respondent had acquired and

took over possession of the demarcated land and this included the

Respondent's/Writ Petitioner's plots. The acquisition of the

Respondent's/Writ Petitioner's land was registered as L.A. Case

No. LA-4/116 of 2012-2013 and that an award was made in

connection with this case. However, such compensation has not

been paid for a prolonged period of time. He contends that the

Respondent/Writ Petitioner is entitled to get compensation with

reasonable interest for delayed disbursement of their

compensation.

b. The counsel contends that there was no embargo on the

authorities to release the compensation as Respondent No.5 in the

writ petition, i.e., the Executive Engineer, Irrigation and Water

Ways Directorate, Basirhat, Irrigation Division, had already

accepted the proposal for compensation notwithstanding the fact

that for last six years no amount of compensation has been paid.

Furthermore, he submits that the local land owners jointly

adopted resolution dated November 8, 2012 whereby in presence

of the local Pradhan the affected land owners gave a No Objection

Certificate so far as the lands of Mouja - Baunia Abad J.L. No.20

in favour of the State so that ring bandh be made; a copy of this

NOC has been annexed with the Writ Petition. The counsel

elaborates upon this contention and states that the authorities

had accepted this No Objection Certificate and thereby completed

the project a long time ago. And that in light of this, there was no

bar to take a decision relating to the grant of compensation.

c. The counsel submits that the State has acted illegally by acting in

ignorance of the procedure laid down for payment of

compensation. The Executive Engineer had also submitted a letter

to the Additional District Magistrate and District Land and Land

Reforms Office, conveying the fact that the relevant estimate of the

land in question was sanctioned by the appropriate authority in

connection with the said L.A. Case for placement of fund as per

provisions of the Land Acquisition Act, 1894.

d. Lastly, the counsel for the Respondent/Writ Petitioner states in its

Affidavit in Opposition to CAN Application No. 11258/2017, that

the Executive engineer had informed the Superintending Engineer,

Eastern Circle, Irrigation and Waterways Directorate vide letter

dated March 19, 2015 wherein it re-submitted the land acquisition

and payment of LA compensation relating to the compensation.

The Respondent/Writ Petitioner also received a letter from the

Sub-Divisional Officer, Haroa, Irrigation Sub-Division, Basirhat, on

December 12, 2015 informing the Respondent/Writ Petitioner

about the completion certificate stating the acquisition of three

plots; a copy of this letter has been annexed in the said Affidavit of

Opposition to CAN Application No. 11258/2017.

Observation and analysis:

5. I have heard the counsel appearing for the respective parties and

perused the materials on record.

6. At the very outset, it would to apt to discuss the jurisdiction of this

Court to review its own judgment. I had the occasion to examine the

principles of review while sitting on the Division Bench with the Hon'ble

Justice Harish Tandon in the case of The State of West Bengal &

Anr. Vs. Confederation of State Government Employees & Ors.

reported in (2019) 3 WBLR (Cal) 39. After examining a catena of

Supreme Court Judgments [See Sasi (D through LRs -v-

Aravindakshan Nair reported in (2017) 4 SCC, paras 6-9; Haridas

Das -v- Smt. Usha Rani Banik reported in (2006) 4 SCC 78, paras

15-18; Parsion Devi -v- Sumitri Devi reported in 1997 (8) SCC 715,

paras 7-10; Aribam Tuleshwar Sharma -v- Aribam Pishak Sharma

reported in (1979) 4 SCC 389, para 3] I had culled out the principles

that emerge from a perusal of the land-mark Supreme Court

Judgments on the issue of review. The same are delineated below :-

a. The power to review is inherent in the High Court and the High

Court can review its own order/judgment passed in a writ petition.

b. This power of review is a limited power and would be governed by

the principles of Section 151 read with Order XLVII Rule 1 of the

Code of Civil Procedure.

c. Firstly, a Court can review its own judgment when there is

discovery of new and important matter or evidence that was in

spite of exercise of due diligence not within the knowledge or could

not be produced due to cogent reasons by the party seeking a

review. Secondly, the court may review its order or judgment on

account of some mistake or error apparent on the face of the

record. Thirdly, a residuary clause in Rule 1 of Order XLVII

provides for a review 'for any other sufficient reason.' It is to be

noted that the Apex Court on several occasions has held that the

third condition "for any other sufficient reason" has to be read

within the four corners of the first two conditions.

d. An error which is not self-evident and has to be detected by a process of reasoning is not an error apparent on the face of the record.

e. A review petition has a limited purpose and cannot be allowed to be "an appeal in disguise". There is a sharp distinction between an

erroneous decision that can be only appealed against and an error apparent on the face of the record that is subject to review.

7. Given the limited scope of review as elucidated in the principles above, I

am of the opinion that the contentions raised by the

Applicants/Respondents in this review application do not satisfy any of

the aforementioned principles regarding review by the Court of its own

judgment.

8. It is the contention of the Applicants/Respondents in this review

petition that there has been suppression of material facts by the

Respondent/Writ Petitioner in order to secure the impugned order

dated April 10, 2017 from this Court. The Applicants/Respondents

claimed that the Writ Petitioner/Respondent did not disclose to the

Court that the said land has not been acquired by the acquiring

authority and that the writ petitioner is not the owner of the entirety of

the said plots.

9. It is axiomatic that any petitioner in a writ petition has to approach the

Court with "clean hands" based on good faith and has to produce

before the Court all material facts that are relevant for adjudication of

the said matter. In Asiatic Engineering Co. -v- Achhru Ram and

others reported in AIR 1951 Allahabad 746 (Full Bench), the Court

observed that no relief can be granted in a writ petition under Article

226 which is based on misstatement or suppression of material facts.

As authored by Ruma Pal, J. in S.J.S. Business Enterprises (P) Ltd.

-v- State of Bihar and others reported in (2004) 7 SCC 166,

suppression of a material fact by a litigant disqualifies such litigant

from obtaining any relief. The relevant portion has been extracted

below:

"13. As a general rule, suppression of a material fact by a litigant disqualifies such litigant from obtaining any relief. This rule has been evolved out of the need of the courts to deter a litigant from abusing the process of court by deceiving it. But the suppressed fact must be a material one in the sense that had it not been suppressed it would have had an effect on the merits of the case. It must be a matter which was material from the consideration of the court, whatever view the court may have taken........"

10. In my view, this submission by the State is incorrect as there has been

no suppression of material facts whatsoever. Upon perusal of the

impugned order dated April 10, 2017, it is clear that this Court directed

the State to make payment of compensation for acquisition of land in

connection with the State's own assessment for land acquisition being

L.A. Case No. LA-4/116 of 2012-13. It is to be noted that in the

impugned order Justice R.K. Bag had observed that the

Respondent/Writ Petitioner did submit several applications before the

appropriate authorities for release of compensation and the same had

been placed on record. The No Objection Certificate given by the

affected land owners was also placed on record.

11. Furthermore, the Executive Engineer, Basirhat Irrigation Division

himself submitted a letter dated February 21, 2013 to the Additional

District Magistrate and District Land and Land Reforms Office,

requesting for the relevant estimate of the land in question as

sanctioned by the appropriate authority in connection with the said

L.A. Case for placement of fund as per provisions of the Land

Acquisition Act, 1894. The Respondent/Writ Petitioner has also stated

in their Affidavit in Opposition to CAN Application No. 11258/2017,

that the Executive Engineer, Basirhat Irrigation Division informed

Superintending Engineer, Eastern Circle, Irrigation and Waterways

Directorate vide a letter dated March 19, 2015 and re-submitted the

land acquisition and payment of LA compensation relating to the

compensation. In addition to this, the Respondent/Writ Petitioner

received a letter from the Sub-Divisional Officer, Haroa, Irrigation Sub-

Division, Basirhat, on December 12, 2015 which informed the

Respondent/Writ Petitioner about the completion certificate stating the

acquisition of three plots. Therefore, there exist no reasons to accept

the contention that there was suppression of material facts by the

Respondent/Writ Petitioner in the writ petition.

12. As far as the contentions by the Applicants/Respondents that the

impugned order was passed without calling for the records of the

alleged Land Acquisition case or any affidavits, it can be clearly seen

from the impugned order passed by Justice R.K. Bag wherein he

observed that the Applicants/Respondents had received the notice of

this case in the month of October, 2016 itself. He was not inclined to

give any more opportunity to the Applicants/Respondents for seeking

instructions to make effective submission in connection with this case.

This Court is also of the same opinion as there exists no grounds to

interfere with his findings.

13. The law on review is very clear wherein a party that files a review is

required to show that there is discovery of new and important matter or

evidence that was inspite of exercise of due diligence not within the

knowledge or could not be produced due to cogent reasons by the party

seeking a review. In this particular case, it is evident that there was

failure on the part of Applicants herein to produce relevant documents

at the time of hearing of the matter. Secondly, this review petition does

not concern an error which is self-evident and the review sought clearly

entails re-examination of new facts and further process of reasoning

which is not within the scope of a review petition. Lastly, one may recall

the exquisite words of Justice Krishna Iyer in P.N. Eswara Iyer -v- The

Registrar, Supreme Court of India reported in 1980 (2) SCR 889

wherein he laments and states :

".......... unchecked review has never been the rule. It must be supported by proper grounds. Otherwise, every disappointed litigant may avenge his defeat by a routine review adventure and thus obstruct the disposal of the 'virgin' dockets waiting in the long queue for preliminary screening or careful final hearing........."

Justice Iyer went on to further state as follows:

"Even otherwise, frivolous motions for review would ignite the 'gambling' element in litigation with the finality of judgments even by the highest court, being left in suspense. If, every vanquished party has a fling at 'review' lucky dip and if, perchance, notice were issued in some cases to the opponent the latter-and, of course, the

former, -would be put to great expense and anxiety. The very solemnity of finality, so crucial to judicial justice, would be frustrated if such a game were to become popular."

Ergo, it can be said that review cannot be an appeal in disguise and

that review jurisdiction has to be exercised by the Court in rare cases

so that finality of judgements can be maintained.

14. Accordingly, for the reasons discussed above, this review petition is

dismissed. There shall be no order as to costs.

15. Urgent Photostat certified copy of this order, if applied for, should be

made available to the parties upon compliance with the requisite

formalities.

(Shekhar B. Saraf, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter