Citation : 2022 Latest Caselaw 6480 Cal
Judgement Date : 12 September, 2022
IN THE HIGH COURT AT CALCUTTA
Civil Appellate Jurisdiction
(Appellate Side)
M.A.T. 309 of 2022
With
I.A. CAN 1 of 2022
Damodar Prasad Agarwal
Vs.
State of West Bengal & Ors.
Before: The Hon'ble Justice Arijit Banerjee
&
The Hon'ble Justice Rai Chattopadhyay
For the Appellant : Mr. Partha Chakraborty.
Ms. Sharmistha China.
For the State : Mr. Samrat Sen, ld. AAAG.
Mr. Nilotpal Chatterjee.
For the K.M.D.A : Mr. Satyajit Talukdar,
Mr. Abhishek Sarkar.
Hearing Concluded on : 27.06.2022
Judgment On : 12.09.2022
Page 2 of 24
Rai Chattopadhyay, J.:
(1) The sole appellant, since deceased, has been substituted by
his legal heirs, vide this court's order dated 08.06.2022.
(2) The appellant/substituted appellants are aggrieved by the
action of the respondent authority in cancelling the
allotment of a plot granted in favour of the appellant, since
deceased, on December 12, 1996, on the ground of non
fulfilment of the stipulated conditions of agreement and
challenged the cancellation order in the Court of Ld. Single
Judge. However, Ld. Single Bench has not allowed the
prayer of the appellant/writ petitioner and dismissed the
writ petition, vide judgment and order dated February 10,
2022. The appellants are aggrieved by that order of Ld.
Single Bench and have challenged the same in this appeal.
(3) The questions that fall for consideration by this appeal court
are whether the Ld. Single Judge was justified in coming to
the findings in the order impugned; whether or not by the
purported action, the respondent authorities have infringed
any legal or constitutional right of the appellants which was
required to be remedied by an order of the court; whether in
the decision making process, Ld. Single Judge has failed to
consider infringement if any, as mentioned above and has
come to an erroneous conclusion; whether the impugned
judgment and order dated February 10, 2022, is liable to be
set aside or not.
(4) Before discussing the arguments advanced by the respective
parties, the factual background of the case may be narrated
in a nut shell for better understanding of the perspective
thereof, which follows hereunder :
The writ petitioner/appellant, since deceased, was
inducted as a licensee for 99 years in respect of Plot No.268 in
MIG II category in Block B, at East Kolkata Area Development
Project, Phase 1 in Dist:-South 24 Paraganas, measuring
about approximately 173 sq. meter. The license commenced
with effect from the date of execution of the agreement, i.e,
from December 11,1996. The appellant/writ petitioner, since
deceased, duly submitted the consideration money as well as
the subsequent premium amount including the interest. He
was given possession over the land with effect from May
23,1997. The appellant/writ petitioner, since deceased, was
unable to raise/complete construction of his residential house
on the said land in terms of Clause 2 (III) of the deed dated
December 11,1996, within the stipulated period of 5 years. In
spite of that he deposited the entire license fee before the
authority within the year 2010, which was duly accepted by it.
On February 16, 2018, a show cause notice was issued by
the respondent authority to the appellant since deceased,
requiring him to show cause as to why the deed of license
would not be cancelled on the ground of violation of Clause 2
(III), as mentioned above. In reply, the then writ petitioner
(now deceased), prayed for extension of time to raise
construction vide his letter dated February 28, 2018. On
August 9,2018, the authority again sent a letter to the
erstwhile writ petitioner, since deceased, demanding penal
charges to the tune of Rs.99,48,452/- for extension of time to
complete construction i.e, within December 10,2019. As the
writ petitioner exclaimed his inability to pay the penal
amount as calculated by the respondent authorities, the deed
of license in his favour, granted earlier on December 11, 1996,
was cancelled by the authority and the possession of the land
was withdrawn, by its Memo No.1029/K.M.D.A/37 dated
December 31, 2018, issued by the Secretary, K.M.D.A.
(5) Thus being aggrieved by the alleged violation of his legal
and rightful claim, the writ petitioner/appellant, since
deceased, had filed the writ petition being W.P No.3443 (w)
2019 to challenge the impugned memo of the respondent
no.2 dated December 31,2018. After hearing the parties, Ld.
Single Bench has delivered its judgment dated February
10,2022, there by rejecting the writ petitioner's prayer.
(6) In the impugned judgment Ld. Single Judge has inter alia
held that the appellants/writ petitioner has failed to comply
with the terms of the license agreement/deed as the
construction over the demised land could not be raised
within 5 years from the date of issuance of the said deed. It
has been observed that the writ petitioner did not act
proactively to seek additional time from the authority for
due compliance of the terms of the license but only
responded to the show cause notice issued to him on
February 16, 2018. Ld. Single Bench has found that while
cancelling the deed in terms of Clause 2 (III) of the license
deed, the authority has acted within its rights and
jurisdiction, irrespective of the fact whether any penal
charges were claimed or not. It decided that even payment
of license fee by the writ petitioner/appellant since deceased
would not come in the way in case the respondent authority
has taken action upon violation of the terms of agreement
by the appellant/writ petitioner. These reasons prompted
the Court to reach to the decision that the writ petition
would not be maintainable.
(7) The main answering respondents, i.e, respondents no.2, 3
and 4 being Kolkata Municipal Development Authority and
its various other officials, have contested the appeal by filing
affidavit-in-opposition to the stay petition. Respondent has
stated inter alia that it has been continuously following the
rate chart prepared by the Land and Flat Allotment
Committee (L.F.A.C), in its meeting dated October 1, 2012,
which duly propagates regarding penal charges for delayed
construction in respect of residential plots. It has
categorically enumerated the calculations and the break up
by dint of which the penal charge of Rs. 99,48,452/- was
arrived at. The said answering respondents categorically
state that there has been no illegality and irregularity in
their action as alleged and that the appellant is not entitled
to any relief as sought for.
(8) The appellants have argued that they obtained allotment of
the land in question, in accordance with due process of law.
They say that possession of the land was duly handed over
to them and all these happened only after execution of a
proper licence deed dated December 11, 1996. Appellants
state that after expiry of the period of 5(five) years, within
which period they were stipulated to complete the
construction but failed to comply with the said condition,
the respondent authority has never come up requiring him
to comply with the conditions of the license deed or
cancellation thereof. Instead, the respondents accepted
licence fee upto the year of 2010. Thus, according to the
appellants, the respondent authority is now estopped to
claim withdrawal of licence or cancel the licence deed, as it
has done. Hence, the impugned action, by dint of Memo
No.1029/K.M.D.A/37 dated December 31, 2018, is wholly
illegal. Appellants have further stated that claim of penal
charges by the respondent is wholly arbitrary and malafide
in so far as the same was not stipulated in the license deed.
They say that the respondent's action after acceptance of the
licence fee beyond the period of 5(five) years without taking
any action against the appellants would justify appellant's
possession and right over the landed property and
imposition of penal charges by the respondents beyond the
scope of the agreement between the parties, is an after
thought and arbitrary action which jeopardises the
appellant's rightful claim and possession over the property
in question. The appellants further state that Ld. Single
Judge, in the judgment impugned, failed to appreciate the
facts in their proper perspective, has wrongly directed
himself not to understand the prejudice to the appellants
and has come to a wrong finding and decision. Appellants
pray for setting aside of the order impugned dated February
10, 2022.
(9) Per contra the respondent authority justifies its action by
pointing out firstly that the appellants have failed to comply
with the stipulated condition of the licence deed executed
between themselves to have a construction made within
5(five) years of execution of the said deed dated December
11, 1996. Respondents have further relied on the decision of
Land and Flat Allotment Committee (L.F.A.C) dated
October 1, 2012, to state that the penal charges have been
levied in case of the appellants, in accordance with the
policy decision and there is no element of arbitrariness in
the same as alleged or at all. Respondents support the
impugned judgment of Ld. Single Judge to the effect that
the terms of licence deed are violated and as per stipulations
in the deed, the same is liable to be cancelled in view of such
violation. Respondents have urged that there may not be
any interference with the judgment impugned.
(10) The facts (i) that a licence deed was executed between the
parties on December 11, 1996, (ii) that the possession of the
land in question was handed over to the appellant (since
deceased) on May 23, 1997, (iii) that the appellant paid the
consideration money and the subsequent premium amount
with interest applicable, (iv) that the appellant failed to
make any construction on the land within a period of 5(five)
years from the date of execution of the deed, (v) that the
respondent claimed penal charges which the appellant has
refused to pay, and (vi) that the respondent cancelled the
licence deed and withdrew possession of land vide its letter
dated December 31, 2018 - are facts admitted by the parties
in this appeal.
(11) Relevant portions of the licence deed dated December 11,
1996 may be set out as hereunder :
2(iii)At the own cost of the LICENSEE within five years from the date hereof or within such further time as the authority may at its option allow in writing on sufficient and reasonable grounds, to erect, construct and complete a house or building on the said land for being used for residential purposes with boundary walls, sewers and drains in accordance with plans, sections and specifications as may be approved by the appropriate body according to the rules and regulations framed for the purpose.
(12) The other clauses of the agreement may be of some
relevance, as narrated below :
2(i)(b)The LICENSEE shall be liable to pay to the Authority the charges as may be imposed by the Authority from time to time in respect of the said land and in such cases where the said payments are not made within due dates then the Authority shall be at liberty to determine the LICENCE hereby granted after due notice.
4(i)If the premium hereby agreed or any part thereof shall remain unpaid for six months after becoming payable (whether formally demanded or not) or if there by any breach of any covenant on the LICENSEE's part herein contained and to be performed or observed or any of the terms and conditions hereof then in the said cases it shall be lawful for the Authority at any time thereafter to re-enter upon the said land or any part thereof in respect of- any breach of the LICENSEE's covenants herein contained.
4(iii) Any relaxation or indulgence granted by the Authority to the LICENSEE or by the said LICENCEE to the Authority shall not in any way prejudice the rights of the parties under this Deed of LICENCE.
(13) Appellant admits not to have complied with clause 2(iii) of
the deed, as mentioned above. However, he claims that the
respondents are estopped to espouse their rights under the
said deed to cancel the allotment in case of noncompliance
by the appellant of its stipulations, as the respondent
authority has not been prompt in taking action, accepted
fees and allowed the appellant to retain the land beyond
such period of time.
(14) The deed of licence does not stipulate the time within which
the respondent authority should act, in case of
noncompliance of the settled clauses in the deed. However,
certain actions including cancellation of the deed have been
stipulated therein upon noncompliance of the terms. The
deed does not even specify any action like acceptance of fees
by the authority, during the period from the date of expiry of
five years span from the date of execution of the deed, till
the date of taking action by the authority, to determine the
fate of the contract in any other way, than to be terminated
on the ground of noncompliance. Therefore, the appellant,
being bound by the terms of the said deed, is found to have
argued the point, not to the satisfaction of this court.
(15) Here this court should also meet the point, whether
concerning a contract between the parties, the appellant is
right or not in espousing his cause before this court of
equity.
Rights and responsibilities of the respective parties in this
case arise out of the agreement/ contract entered into
between them on December 11, 1996. Appellant is aggrieved
by respondent's alleged inaction/ non compliance of the
terms of the said agreement. Admittedly their relationship is
governed by the said terms of the deed dated December 11,
1996. The observation of the Apex Court on this aspect as
held in the case of M/S Radhakrishna Agarwal& Others vs.
State of Bihar & Others reported in AIR 1977 SC 1496, may
be relied on, which is as follows:
"After the State or its agent have entered into the field of ordinary contract, the relations are no longer governed by the constitutional provisions but by the legally
valid contract which determines rights and obligations of the parties inter se. No question arises of violation of Article 14 or any of other constitutional provision when the State or its agents, purporting to act within this field, perform any act. In this sphere, they can only claim rights conferred upon them by contract and are bound by the terms of the contract only unless some statute steps in and confer some special statutory power or obligation on the State in the contractual field which is apart from contract".
Another Apex Court verdict may also be relied upon,
i.e, Barelly Development Authority and Another vs Ajay
Pal Singh and Others reported in (1989) 2 SCC 1496 wherein
it has been held that once the parties after voluntarily
accepting the conditions of the contract enter into such
contract they can only claim the right conferred upon them
by the said contract and are bound by the terms of the
contract.
Findings of the Apex Court as mentioned above,
squarely apply in case of the appellant/appellants. Hence,
decision may be arrived at that the appellants could not
have maintained their case successfully in a court of equity.
(16) Finally, we may discuss the point raised by the appellants
that the respondent authorities could neither claim penal
charges as the same was not envisaged in the deed as
entered into between the parties nor could they terminate
the agreement due to non payment of such penal charges by
the appellants.
As discussed earlier, after handing over possession of land
to the appellant on May 23, 1997, the respondent authorities
issued a letter to him, dated February 16, 2018, to show
cause, reason being non fulfilment by him of the terms of
the deed, i.e, his inaction in completing the construction
within five years of allotment of the land. Appellant replied
with the request to extend such time for him.
Respondent authority says that during the period from
allotment of land to the appellant, till the time he requested
for extension of time for him, the authority has undertaken
a policy to allow extension of time for any allotee, in lieu of
'penal charges'. Such policy was formulated on October 1,
2012, pursuant to the decision of the Land and Flat
Allotment Committee (L.F.A.C). Obviously no such term
was mentioned in the license deed dated December 11, 1996,
entered into between the parties and the appellant had no
knowledge of such a policy of the respondent authority. In
such circumstance, the appellant raises the question if such
policy of the respondent could be applicable to him.
A recent decision of the Supreme Court may be mentioned,
i.e, Punjab State Power Corpn. Ltd. v. Emta Coal Ltd.,
(2022) 2 SCC 1, wherein the Hon'ble Court has been pleased
to determine that the decision-makers' freedom to change
the policy in public interest cannot be fettered, that so long
as the Government does not act in an arbitrary or in an
unreasonable manner, the change in policy does not call for
interference by judicial review; that if the decision of the
authority is not vitiated by illegality, irrationality or
procedural impropriety, the same should not be interfered
with by the Court.
In this case the change in policy decision by the authority
shall withstand the tests as enunciated by the Apex Court in
the judgment mentioned above in absence of any challenge
to the same. Therefore, the appellant's plea of prejudice,
having been bedevilled with 'penal charges' without any
prior knowledge about the same shall also not be
substantiated and succeed.
Pertinent to mention here that clause 2(i)(b)of the license
deed dated December 11, 1996, as mentioned above,
categorically provides for imposition of charges by the
authority, liability of the allotee to pay the same and right of
the authority to terminate allotment in case of failure by the
allotee to pay the same. This provision of the deed will also
operate against the appellant/appellants.
Under these facts and circumstances, change in
policy made by the concerned authority in the midst of the
period of subsistence of the agreement between the parties
and its implementation cannot be held to be improper or
illegal. There is no doubt about the correctness of the
findings of Ld. Single Judge that respondent's action of
termination of lease deed falls within the purview of the
terms and conditions of the contract entered into between
the parties, upon non-fulfilment of the terms of covenant
and irrespective of payment or non-payment of the 'penal
charges' by the appellants. Even the appellants could not
have embraced success, had their allotment been terminated
due to non-payment of said 'penal charges'. Needless to
mention here that the terms of the licence deed dated
December 11, 1996, have independent application, in case of
violations as stipulated and would not necessarily require to
be qualified with any further conditions.
(17) Discussions as made above would indicate the findings of
this court regarding the legality and propriety of the
judgment of Ld. Single Judge, dated February 10, 2022 and
the same is hereby affirmed.
(18) The present appeal being MAT 309 of 2022 is dismissed.
Arijit Banerjee, J.:
(1) I have had the advantage of reading the judgment of my
Sister Justice Rai Chattopadhyay. While agreeing with the
conclusion reached by my learned Sister, I take this
opportunity to add a few words.
(2) The Deed of Licence executed by KMDA in favour of the
appellant essentially constituted a contract between the
appellant and KMDA. The contractual relationship between
the two parties were to be governed by the terms of the
contract. One of the conditions of the Licence Deed was that
the licensee/allottee of the plot of land in question would
construct a building on the land within five years from the
date of the Licence Deed. Admittedly the appellant failed to
make any construction within the stipulated time period or
even long thereafter.
(3) The Licence Deed was dated December 11, 1996. Hence, the
appellant was contractually obliged to put up a building on
the land in question by December 10, 2001. He failed to
make any construction within that time or thereafter. On
February 16, 2018, a show-cause notice was issued to him by
KMDA calling for an explanation as to why the licence
should not be cancelled. The appellant requested for
extension of time for complying with the stipulation in the
Licence Deed as regards constructing a building within 5
years from the date of the Licence Deed. By a letter dated
August 9, 2018, KMDA demanded penal charges in the sum
of Rs. 99,48,452/- for granting extension of time for putting
up the building within December 10, 2019. Upon the
appellant expressing his inability to make such payment, by
its memo dated December 31, 2018, KMDA cancelled the
Deed of Licence and possession of the land in question was
withdrawn. This was under challenge before the learned
Single Judge.
(4) The relationship between the appellant and K.M.D.A. was
purely contractual. The appellant was admittedly in breach
of a contractual term. The contract/Licence Deed authorised
KMDA to cancel the Licence Deed upon breach by the
appellant of any of the covenants in the Licence Deed.
KMDA exercised such right and cancelled the Licence Deed.
Prior thereto, in terms of a policy formulated by KMDA, it
agreed to accede to the appellant's request for extension of
time for making construction upon payment of penal
charges. The appellant pleaded inability to pay such charges.
Thereupon KMDA cancel the licence.
(5) In my opinion, KMDA need not have shown any indulgence
to the appellant and the indulgence shown did not in any
way affect its contractual right to terminate the licence.
While operating in the realm of a private contract having no
statutory flavour, like in the present case, the State or a
Statutory Authority should be allowed to act as any other
private party and there action should not be interfered with
lightly as being unreasonable or arbitrary.
(6) The Competent Authority in K.M.D.A. has framed a
schedule of charges to be levied on defaulting allottees of
land as a pre-condition for extension of time to make
construction. It is a financial policy of a statutory authority
with which the writ court should not easily interfere. The
schedule of charges in terms whereof KMDA demanded
money from the appellant for granting extension of time to
make construction, is not under challenge in the present
proceedings.
(7) There is also a clause in the licence deed to the effect that
any relaxation granted or indulgence shown by KMDA to the
licensee shall not in any way prejudice the rights of the
parties under the Licence Deed. KMDA offered to extend
time for construction against payment of charges. Such offer
was not accepted. This indulgence shown by KMDA in no
manner affected its right to repossess the land in question
upon termination of the licence in view of the appellant's
failure to make construction on the land within the
contractually stipulated period or even much beyond such
time.
(8) Accordingly, in my considered view, there is no infirmity in
the order under appeal. The appeal deserves to be and is
dismissed.
(9) Interim order, if any, stands vacated. Application, connected
with this appeal, if any, stands disposed of.
(10) Urgent certified website copies of this judgment, if applied
for, be supplied to the parties subject to compliance with all
the requisite formalities.
(Rai Chattopadhyay, J.) (Arijit Banerjee,J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!