Citation : 2022 Latest Caselaw 7926 Cal
Judgement Date : 30 November, 2022
IN THE HIGH COURT AT CALCUTTA
Constitutional Writ Jurisdiction
Appellate Side
Present :- Hon'ble Justice Amrita Sinha
WPA No. 15950 of 2022
Sabita Nandy
Vs.
Bidhannagar Municipal Corporation & Ors.
For the writ petitioner :- Mr. Arindam Banerjee, Adv.
Mr. Rupayan Deb, Adv.
For the BMC :- Mr. Arka Kumar Nag, Adv.
Mr. Tirthankar Dey, Adv.
For the respondent no. 5 :- Mr. Rahul Karmakar, Adv.
Ms. Gargi Goswami, Adv.
Mr. Sounak Mukherjee, Adv.
Mr. S. S. Bhutoria, Adv.
Ms. Piyasi Chakraborty, Adv.
Hearing concluded on :- 08-08-2022
Judgment on :- 30-11-2022
Amrita Sinha, J.:-
The matter is being taken up for consideration as per the direction
passed by the Hon'ble Supreme Court of India on 3rd August, 2022 in petition for
Special Leave to Appeal (C) No. 13235 of 2022.
The said Leave to Appeal was filed challenging the order dated 15th July,
2022 passed by the Hon'ble Division Bench of this Court in MAT 1077 of 2022
(Sabita Nandy -vs- The State of West Bengal & Ors.) affirming the order passed by
the learned Single Judge on 11th July, 2022 in WPA 6780 of 2022 (Ganesh
Chandra Patra -vs- The State of West Bengal & Ors.).
The aforesaid WPA 6780 of 2022 was filed by Ganesh Chandra Patra
praying for implementation of the order of demolition of the unauthorised
construction dated 9th February, 2018 passed by the Commissioner, Bidhannagar
Municipal Corporation ('BMC' for short).
The Court, by order dated 11th July, 2022, directed the Corporation to
proceed with the demolition scheduled on 12th July, 2022, in accordance with
2
law. Challenging the order passed by the learned Single Judge the petitioner
herein i.e. Sabita Nandy preferred appeal before the Hon'ble Division Bench. By
order dated 15th July, 2022 the Hon'ble Appeal Court was pleased not to interfere
with the order of the learned Single Judge and dismissed the appeal. The Hon'ble
Division Bench directed that the Officer-in-Charge of the jurisdictional police
station, if approached by the officers of the BMC, shall extend cooperation for
implementing the order of demolition.
Sabita Nandy challenged the said order before the Hon'ble Supreme
Court. Being made aware of the fact that the order of demolition was under
challenge in the present writ petition being WPA 15950 of 2022, the Hon'ble
Supreme Court was pleased to direct the learned Single Judge to take up the said
petition for consideration on merits.
The present writ petition being WPA 15950 of 2022 was filed by Sabita
Nandy on 18th July, 2022 i.e. after the appeal preferred by Sabita Nandy stood
dismissed by the Hon'ble Division Bench on 15th July, 2022.
In the present writ petition the petitioner has prayed for a direction
upon the BMC to rescind and revoke the order of demolition dated 9th February,
2018 and to rescind and revoke the report prepared by the Executive Engineer of
the BMC after physical spot inspection was held on 20th February, 2017.
Facts
leading to passing the order of demolition by the BMC are as
follows:-
A complaint was filed by the respondent no. 5 Ganesh Chandra Patra
alleging unauthorised construction made by Sabita Nandy, the petitioner herein,
in the premises situated at Mouza - Krishnapur, R.S. Dag No. 3845, Ward No. 26,
Kolkata - 700102 under the jurisdiction of BMC. As the objection raised by
Ganesh Chandra Patra was not taken up for consideration by BMC, the said
Ganesh Chandra Patra filed a writ petition before this Court being WP 2128 (W) of
2014.
The said writ petition was heard and disposed of by this Court on 6th
March, 2014 directing the Board of Councillors, Rajarhat Gopalpur Municipality,
under which the property then fell, to initiate proceedings under Section 218 of
the West Bengal Municipal Act, 1993, after giving opportunity of hearing to the
petitioner as well as the private respondent Sabita Nandy.
Sabita Nandy filed a writ petition before this Court in the year 2017
being WP no. 11956 (W) of 2017 by impleading Ganesh Chandra Patra as
respondent and sought for a direction upon the municipal authority to initiate
demolition proceeding against the unauthorised construction made by Ganesh
Chandra Patra. The said writ petition was heard and disposed of by this Court on
8th November, 2017 directing the respondent authority i.e. BMC to dispose of the
representation by passing a reasoned order in accordance with law, after giving
reasonable opportunity of hearing to the parties.
In compliance of the direction passed by the Court, spot physical
inspection of the property of Sabita Nandy was conducted and the Commissioner,
BMC passed order recording, in details, the nature of deviation of the
construction. The order to demolish the unauthorised construction was passed
on 9th February, 2018 directing Sabita Nandy to demolish the same within thirty
days failing which the respondent authority would demolish the same at the cost
of the offending party.
Ganesh Chandra Patra filed a writ petition being WP no. 17998 (W) of
2018 before this Court seeking implementation of the order of demolition dated
9th February, 2018 passed by the Commissioner, BMC. The aforesaid writ petition
was taken up for consideration by the Court on 27th September, 2018. Being
apprised of the fact that an appeal had been filed by Sabita Nandy challenging
the order of demolition, the Court disposed of the writ petition by directing the
appellate authority to consider and dispose of the said appeal.
On 12th January, 2022 Ganesh Chandra Patra lodged a further
complaint before the Officer-in-Charge, Baguihati Police station highlighting the
unauthorised constructions made by Sabita Nandy and requested the police to
take steps to stop the construction work.
A hearing was held by the Commissioner, BMC on 12th March, 2022 in
compliance of the direction passed by this Court on 8th November, 2017 in WP
no. 11956 of (W) of 2017. Sabita Nandy through her learned advocate made a
representation before the BMC highlighting her grievances with regard to the
unauthorised construction made by Ganesh Chandra Patra. A physical
inspection was conducted by the engineers of BMC and an order was passed on
29th March, 2022 under Section 287 of the West Bengal Municipal Corporation
Act, 2006 directing Ganesh Chandra Patra to demolish the entire 2nd floor and
the terrace within four weeks.
Ganesh Chandra Patra filed a further writ petition before this Court
being WPA no. 1592 of 2022 which was disposed of on 28th February, 2022 by
granting liberty to the petitioner to bring to the notice of the Corporation, the
subsequent construction which have been made by Sabita Nandy after the order
of demolition dated 9th February, 2018.
Ganesh Chandra Patra again filed a writ petition being WPA 6780 of
2022 for implementation of the order of demolition. The Court directed BMC to
proceed with the demolition of the unauthorised construction made by Sabita
Nandy on the scheduled date i.e. 12th July, 2022.
Petitioner is aggrieved by the order of demolition dated 9th February,
2018.
The primary contention of the petitioner is that the order of demolition
passed in the year 2018 was never tested before the Court of law. On each and
every occasion the private respondent approached this Court praying for
implementation of the order of demolition. While passing order for implementing
the order of demolition, the Court never had the occasion to adjudicate the
legality and validity of the order of demolition. The order of demolition was never
decided on merits by the Court.
Sabita preferred appeal against the order of demolition before the Mayor
of the BMC. This Court in WP 17998 (W) of 2018, in the matter of Ganesh
Chandra Patra, directed the appellate authority to dispose of the said appeal in
accordance with law.
It has been submitted that the inspection report relying on which the
order of demolition was passed, was never forwarded to the petitioner, and
accordingly, there has been violation of the principle of natural justice.
It has been submitted that initially the premises in question fell within
the jurisdiction of the Rajarhat Gopalpur Municipality and the relevant law
according to which action could have been taken against the unauthorised
construction is under the provision of the West Bengal Municipal Act, 1993. After
the jurisdiction of the Rajarhat Gopalpur Municipality got transferred and merged
with the jurisdiction of BMC, the provision of the West Bengal Municipal
Corporation Act, 2006 will apply.
When the cause of action arose, the West Bengal Municipal Act, 1993
was in vogue, and as such, no steps could have been taken against the alleged
unauthorised construction made by the petitioner under the provision of the West
Bengal Municipal Corporation Act, 2006.
It has been submitted that by order dated 6th March, 2014 passed in
WP 2128 (W) of 2014 the Court directed the Board of Councillors, Rajarhat
Gopalpur Municipality to initiate proceeding under Section 218 of the West
Bengal Municipal Act, 1993, accordingly, any steps taken by the Commissioner,
BMC in terms of the order passed by the Court, would be without jurisdiction.
It has been contended that the order passed under Section 218 of the
Act of 1993 is appealable before the Court having jurisdiction. The petitioner
preferred an appeal before the Mayor of the Bidhannagar Municipal Corporation
but no step was taken by the Mayor to dispose of the appeal preferred by the
petitioner.
Reliance has been placed on the repeal and savings clause of the 1993
Act. The petitioner stresses on the fact that BMC would not have jurisdiction in
the matter as the initial order was passed by the Rajarhat Gopalpur Municipality
and, accordingly, any order passed by BMC is null and void in the eye of law.
Learned advocate representing Ganesh Chandra Patra i.e. the complainant,
at whose instance the demolition proceeding was initiated by the authority relies
upon Section 383 of the West Bengal Municipal Corporation Act, 2006 relating to
the savings clause. It has been submitted that any proceeding instituted or any
action taken under the West Bengal Municipal Act, 1993 may be continued by
the Corporation after jurisdiction of the Rajarhat Gopalpur Municipality was
transferred to the jurisdiction of BMC. It has been contended that, presently,
jurisdiction of the property lies within BMC and the WB Municipal Corporation
Act, 2006 will be applicable.
It has been submitted that prior opportunity of hearing was given to
Sabita and she had enough scope to defend herself. Though Sabita challenged the
order of demolition before this Court by filing WP No. 7672 (w) of 2018, but
thereafter, for reasons best known to her, withdrew the same. Sabita acted as a
fence sitter and chose to sit tight over the order of demolition. The Court ought
not to permit the petitioner to challenge the 2018 demolition order in the year
2022 after the earlier writ petition challenging the same demolition order, with
the same relief, was withdrawn without obtaining leave to file afresh.
It has been argued that the private respondent is fighting for his rights
for a very long time and the right of the private respondent cannot be scuttled in
the year 2022, by which time, the order of demolition attained finality.
Reference has been made to the series of illegalities committed by
Sabita at the time of making construction. Prayer has been made for giving effect
to the order of demolition.
Learned advocate representing BMC relies upon the averments made by
the petitioner in paragraphs 9 to 13 of the writ petition wherein the petitioner
admitted that she was all along well aware of the proceeding conducted by the
BMC in the matter. BMC acted in compliance with the direction passed by this
Court on 6th March, 2014 in WP no. 2128 (W) of 2014 directing the then Rajarhat
Gopalpur Municipality to proceed in the matter.
Sabita thereafter filed a writ petition being WP 7672 (W) of 2018
challenging the order of demolition passed by BMC. In the said writ petition
Sabita admitted in paragraph 11 that the alleged deviation/ departure from the
authorized sanction plan may be tolerated and regularised and are not required
to be demolished.
Learned Advocate for BMC points out that, in WP 7672 (W) of 2018
Sabita contended that the order of demolition was not in accordance with the
provisions of Sections 266 & 287 of the West Bengal Municipal Corporation Act,
2006 and it is only the Commissioner who can pass an order of demolition. In the
said writ petition Sabita prayed for setting aside the impugned order of
demolition. The aforesaid writ petition was thereafter withdrawn by Sabita and no
leave was sought for from the Court to challenge the said order of demolition
afresh. Without the leave of the Court Sabita cannot be permitted to challenge the
said order of demolition all over again in the present writ petition.
The learned advocate relies upon the provision of Order 23 Rules 1, 3 &
4 of the Code of Civil Procedure. Sabita did not take any steps from 2018 till
2022. The writ petition at such delayed stage ought not to be maintainable.
It has been contended that the Bidhannagar Municipality came under
the West Bengal Municipal Corporation Act, 2006 in June, 2015. The impugned
order of demolition was passed by the Commissioner in the year 2018. The order
of demolition is appealable before the Municipal Tribunal. As the Tribunal is not
functional as yet, the petitioner approached this Court for remedy by filing the
writ petition being WP 7672 (W) of 2018.
The Court by an order dated 20th January, 2017 passed in WP 2128 (W)
of 2014 recorded the fact that the Rajarhat Gopalpur Municipality has become
the Bidhannagar Municipal Corporation. Section 218 of the Municipal Act, 1993
will not apply. The affairs of the new Municipal authority i.e, BMC are controlled
by the West Bengal Municipal Corporation Act, 2006. All the rights and
obligations of Rajarhat Gopalpur Municipality including compliance of the Court's
order have been taken over by BMC. The Commissioner of the Corporation was
directed to file report before the Court as to how he proposes to comply with the
order dated 6th March, 2014.
By order dated 1st July, 2022, the Court, in the contempt proceeding
arising out of WPA 2128 of 2014, directed that if there is no order of stay of the
demolition order, then the contemnor shall be personally present in Court. It has
been submitted that the Corporation being the contemnor in the said application
is duty bound to comply the order of demolition which is yet to be stayed/ set
aside or modified by any competent forum.
Submission has been made for dismissing the writ petition and
permitting the Corporation to proceed with the order of demolition.
In reply to the submission made on behalf of the respondents the
petitioner contends that as the earlier writ petition being WP no. 7672 (W) of 2018
was not decided by the Court on merits but was withdrawn simpliciter,
accordingly, the provision of Order 23 Rules 1, 3 & 4 will not apply.
It has been submitted that the subject matter in the earlier writ petition
and the present writ petition are different. Reliance has been placed on Section 9
of the West Bengal Municipal Corporation Act, 2006 which mentions that for the
purpose of carrying out the provision of the Act, the Corporation, the Mayor in
Council and the Mayor are the competent authorities. The Commissioner does
not have any jurisdiction to pass the order of demolition. It has been submitted
that according to Section 30 (1) (a) of the Act of 2006 the Commissioner is merely
an officer of the Corporation.
The petitioner prays for setting aside the order of demolition whereas
the respondents pray for dismissal of the writ petition.
I have heard and considered the rival submissions made on behalf of
both the parties.
It would have been suffice to just mention that the petitioner challenges
an order of demolition. The matter being hotly contested by the parties, the Court
thought it appropriate to note down the facts in details to arrive at a logical
conclusion to adjudicate the issue.
It appears from the facts as narrated herein above that the petitioner,
Sabita and the private respondent, Ganesh are adjacent owners of the land and
structures standing on their respective premises. Dispute cropped up between
the parties when Sabita made construction allegedly in deviation of the
sanctioned plan. A complaint was lodged by Ganesh before the Rajarhat
Gopalpur Municipality which had jurisdiction over the property at the relevant
point of time.
As the objection of Ganesh remained unattended, he filed a writ petition
being WP 21391 (W) of 2013. The Court by order dated 18th September, 2013
disposed of the same by granting leave to Ganesh to file complaint before the
municipal authority. Pursuant to the said leave, Ganesh lodged complaint before
the Municipality but as the said complaint was not considered by the municipal
authority, Ganesh was compelled to file a further writ petition being WP 2128 (W)
of 2014 which stood disposed of on 6th March, 2014 directing the Board of
Councillors of the Municipality to initiate proceeding under Section 218 of the
Municipal Act, 1993. The Court directed the Municipality to afford opportunity of
hearing to all the parties and granted liberty to Sabita to file written objection
against the complaint. If any unauthorized construction was found to have been
raised, the same was directed to be demolished in accordance with law.
As the order passed by the Court on 6th March, 2014 was not complied
with by the respondent authority, a contempt application being CPAN no. 2296 of
2014 was filed. At the time of consideration of the said application for contempt,
it was submitted before the Court by the learned advocate representing the
authority that, the Rajarhat Gopalpur Municipality stood amalgamated with the
Bidhannagar Municipal Corporation and, accordingly, steps are to be taken by
the Corporation at present in terms of the West Bengal Municipal Corporation
Act, 2006. The Court permitted the Commissioner of the Corporation to take
appropriate steps in the matter.
In compliance of the direction passed by the Court in the contempt
proceeding, the Commissioner BMC intimated the parties that a physical
inspection shall be conducted on 20th February, 2017 by the engineers of the
Corporation. The parties were present at the time of physical inspection and it
was revealed that there were deviations and accordingly, the Commissioner of
BMC passed order under Section 287 of the WB Municipal Corporation Act, 2006
and directed the persons responsible to demolish the unauthorized construction.
The order of the Commissioner records in details the deviations from the building
plan that were detected. The deviations are as follows:
1. Front open space in ground floor of the alleged building is found 900 mm whereas in sanctioned building plan it is shown 1200 mm and a cantilever is projected at 1st floor which is not shown in sanctioned building plan.
2. On the North side of the alleged building a 450 mm cantilever is projected through the length at 1st floor and two nos. of cupboards of size 4.94m X 0.50m and 3.15m X 0.50m are present in ground floor which is not shown in the sanctioned plan.
3. On the South side, the open space in ground floor is 960 mm whereas in sanctioned building plan it is shown 1200 mm but 730 mm is projected throughout the length at 1st floor and half landing of size 2.45m X 0.73m is projected which is not shown in the sanctioned building plan.
4. Backside open space of the building is 570 mm and no cantilever is shown at 1st floor whereas back side open space in sanctioned building plan is 2.0 m.
5. Position of septic tank is shifted from back side to North side of the building.
6. One garage is shown on sanctioned building plan which is converted to bed room.
7. One shop is shown in sanctioned building plan which is converted to two nos. of shop.
The order of demolition was duly communicated to Sabita, who being
aggrieved by the order of demolition, preferred a writ petition before this Court
being WP 7672 (W) of 2018. Prayer was made for cancelling/ quashing the
impugned order of demolition. In the writ petition Sabita alleged that the order of
demolition was passed without any legal basis and without affording any
opportunity of hearing to her.
For reasons best known to Sabita, the said writ petition was withdrawn
without obtaining any leave from the Court to file fresh writ petition on the self
same cause of action. After withdrawal of the writ petition Sabita preferred an
appeal against the order of demolition before the Mayor of BMC in July, 2018
along with an application praying for condoning the delay in preferring the appeal
wherein Sabita averred that she got the knowledge of the impugned order of
demolition from the communicating letter of BMC.
In connection with the said appeal an application for stay was also filed
by Sabita as late as in 7th July, 2022. In the application for stay Sabita averred
that the order of demolition was passed in connection with a writ petition filed by
Ganesh. The Court in WP no. 17998 (W) of 2018, in order dated 27th September,
2018, took note of the fact that the appeal against the order of demolition
preferred by the writ petitioner Sabita was pending and accordingly directed the
appellate authority to consider and dispose of the said appeal.
As the order of demolition was not implemented, Ganesh again filed an
application for contempt being CPAN no. 1003 of 2019. The Court on 1st July,
2022 was left wondering as to why the order of demolition was not acted upon
even though no formal order setting aside or staying the order of demolition was
passed by any competent Court or Tribunal.
As the order of demolition remained unimplemented, Ganesh filed yet
another writ petition for implementation of the same. The Court, at the time of
consideration of the writ petition on 11th July, 2022, considered the submission
of BMC that an appeal along with an application for stay of the order of
demolition was pending consideration before the Mayor and was of the opinion
that according to the provisions of Section 266(3) of the West Bengal Municipal
Corporation Act, 2006 the order of the Commissioner was appealable before the
Municipal Building Tribunal and there was no provision in the Act for preferring
appeal before the Mayor of the Corporation.
The Court opined that an appeal preferred before an authority which
does not have the jurisdiction to decide the issue is non est in the eye of law.
Taking note of the fact that an application for contempt was pending, the Court
directed the Corporation to proceed with the demolition on the scheduled date.
Sabita carried the order dated 11th July, 2022 in appeal being MAT
1077 of 2022 with IA CAN 1 of 2022. The Hon'ble Division Bench took note of all
submissions made on behalf of Sabita and by order dated 15th July, 2022 was
pleased to dismiss the appeal and the connected application by affirming the
opinion of the Ld. Single Judge that the appeal before the Mayor was not
maintainable.
The order of demolition not being implemented for a considerable period
of time the Hon'ble Division Bench was pleased to direct the Officer-in-Charge of
the jurisdictional police station to render assistance if approached by the officers
of the Corporation for implementing the same.
Challenging the order passed by the Hon'ble Appeal Court, Sabita
preferred the special leave to appeal before the Hon'ble Supreme Court when
submission was made that the order of demolition was under challenge in the
present writ petition being WPA 15950 of 2022. The Hon'ble Supreme Court
directed the appropriate Bench to decide the writ petition on merits. The present
writ petition challenging the order of demolition, for the second time, was
affirmed on 18th July, 2022 i.e, after the Hon'ble Division Bench of this Court
directed the Corporation to proceed with the implementation of the order of
demolition.
The earlier writ petition filed by Sabita challenging the self-same order
of demolition being WP no. 7672 (W) of 2018 stood withdrawn without obtaining
any liberty to file afresh. The respondents have relied upon the provisions of the
Code of Civil Procedure mandating that fresh proceeding cannot be instituted
where the petitioner/ plaintiff withdraws the claim without permission to file
afresh on the self same cause of action.
On a perusal of the earlier writ petition and the present writ petition
filed by Sabita it appears that both the writ petitions have been filed challenging
the same order of demolition. The averments and the prayers made in the writ
petitions are more or less similar. Though it is correct that the issues in the
earlier writ petition were not decided and the principle of res judicata will not
apply, but provision of Order 23 Rule 1(3) precludes the plaintiff from filing fresh
suit on the same subject matter.
The aforesaid Rule is based on the policy to prevent institution of Suits
over and over again on the self same cause of action. It is so because to put an
end to a proceeding and not to keep the issue open to be re-agitated in future. On
disposal of a proceeding the parties get to know as to where they stand and the
avenues open to them to exercise their rights seeking justice. Permitting the party
to reopen the issue which stood abandoned in the earlier proceeding will lead to
uncertainty and the subsequent action taken by a party may be set at naught.
The bar under the Code of Civil Procedure is very much applicable to writ
petitions under Article 226 of the Constitution of India and as such, it will be
highly improper to reopen an issue which has already been settled and attained
finality by the passage of time and also by the subsequent acts of the parties.
It is surprising to note that even though Sabita preferred appeal before
an inappropriate forum (Mayor) in July, 2018, but thereafter she did not proceed
to pursue with the said appeal. She merely filed the same and deliberately kept it
pending with the oblique intention to take advantage of filing of the appeal at an
opportune moment and shift the burden upon the Corporation in not taking steps
to dispose of the same.
During the interregnum between 2018 and 2022 several other
proceedings came to be initiated by Ganesh praying for implementation of the
order of demolition. Had Sabita been genuinely aggrieved by the order of
demolition, then she ought to have proceeded with the appeal in its right earnest
and not merely file the same and leave it unattended. Sabita, however, was
successful in getting the unauthorized construction of Ganesh demolished.
The appeal was preferred beyond the prescribed period of limitation
along with an application praying for condoning the delay in preferring the same.
Sabita never cared to press the application for condoning the delay, and as such,
it can be safely concluded that, the appeal has not been formally registered in the
eye of law, and as on date, no appeal has been preferred against the order of
demolition.
Despite being aware of the fact that according to the provision of law,
the Mayor of the Corporation is not the competent forum before which an appeal
may be preferred against the order of the Commissioner, Sabita, as late as on 7th
July, 2022, filed an application for stay of the demolition order before the Mayor.
The learned Single Judge recorded in the order dated 11th July, 2022 passed in
WPA 6780 of 2022 that an appeal before any authority which does not have
jurisdiction to decide the issue is non est and the order of the Ld. Single Judge
has been affirmed by the Hon'ble Division Bench. After the Division Bench
dismissed the appeal preferred by Sabita, the present writ petition has been filed.
The impugned order of demolition was passed after the Corporation
inspected the property in presence of both the parties. Sabita, in her earlier writ
petition challenging the order of demolition, admitted that there has been
deviation, but in the same breath submitted that, instead of imposing a harsh
punishment of demolition, the Corporation may regularise the said unauthorized
construction. Despite filing the said writ petition, Sabita chose to withdraw the
same, that too, without obtaining any leave to file fresh writ petition on the self
same cause of action.
The conduct of Sabita suggests that she was absolutely sure that after
withdrawal of the writ petition she would be in a position to manage the
respondent authority not to proceed with the order of demolition. It appears that
even though the order of demolition was passed in February, 2018, Sabita was
successful in withholding implementation of the said order of demolition even in
the year 2022. Ganesh, on the other hand, is diligently pursuing the matter since
2007 and even after fifteen years of lodging the complaint, his grievance is yet to
be redressed. An illegal act does not get legalised by the passage of time.
The Corporation also does not appear to have proceeded with the
complaint of Ganesh in the proper direction. Time and again Ganesh was
compelled to approach this Court for relief. Orders were passed directing the
Corporation to act in accordance with law which the Corporation failed to do.
Repeated contempt applications had to be filed for implementation of the order
passed by the Court. Though the Corporation opposes the prayer of Sabita, but
the action of the Corporation does not suggest that it really intends to implement
the order of demolition. Had the Corporation acted with bona fide intention, then
the order of demolition would have been implemented long back. Ganesh would
not have been compelled to approach this Court on repeated occasions for
implementing the order of demolition.
The Government of West Bengal by a notification dated 18.06.2015
published in the Kolkata Gazette Extraordinary constituted the municipal area
of Rajarhat Gopalpur, a Municipal Corporation area with headquarter at
Bidhannagar under Section 3 of the West Bengal Municipal Corporation Act,
2006. The construction made by Sabita presently falls within the jurisdiction of
the Bidhannagar Municipal Corporation and the Commissioner of the
Corporation is the competent authority to pass the order of demolition.
Proceeding was initiated against Sabita for demolition of the
unauthorised construction in the year 2014 prior to the Rajarhat Gopalpur
Municipality being made part and parcel of the Bidhannagar Municipal
Corporation. After the area in question was brought within the jurisdiction of
the Corporation, a fresh inspection was conducted by the men and agents of
the Corporation in the presence of all the parties and demolition order was
passed on 9th February, 2018.
It appears from the documents annexed to the writ petition that
Ganesh was subjected to regular threats at the instance of Sabita for standing
up against the illegal construction made by her. Ganesh lodged several
complaints before the police as well as the other authorities complaining about
the threats.
It does not appear that the Corporation acted either in excess of its
jurisdiction or there was any error in the decision making process in passing
the order of demolition. Principle of natural justice was duly complied with
prior to passing the said order. It is evident that Sabita made construction by
not maintaining the statutory side open spaces and deviating from the
sanctioned plan. The Corporation concluded that there has been deviation at
the time of making construction and, as such, passed the order of demolition.
The petitioner is trying to find out technical procedural loop holes in
the act of the Commissioner, BMC in passing the order of demolition. She is
trying to take advantage of the transition of the Municipality to the
Corporation. Her submission that as the cause of action arose when the 1993
Act was in force, accordingly, action cannot be taken under the 2006 Act is
absolutely misconceived. Inspection was conducted and demolition order was
passed in accordance with the 2006 Act and as such all subsequent steps are
required to be taken under the Act that is currently holding the field.
Sabita is trying tooth and nail and leaving no stone unturned to hold
on to the unauthorised construction. She is unsuccessfully trying to hunt out
technical flaws to save the unauthorized structure from being demolished. At
this stage, it would be highly improper not to implement the order of demolition
specially after noticing the nature and extent of deviation made by Sabita at the
time of making construction.
Nowadays, there is a growing tendency to make construction either in
deviation of the plan sanctioned or without a sanctioned plan. In most of the
cases the illegality remains undetected and the laws relating to construction
are blown in the winds. In a good number of cases, the illegality allegedly gets
mutually settled between the complainant and the wrong doer in lieu of
material gain. In only a handful of cases, like the case at hand, does the
complainant persistently hold on to the complaint and cries for justice. The
Court will be miserably failing in its duties if, despite noticing the deviations
made at the time of construction, does not direct the authority to implement
the demolition order. If that be so, henceforth builders will not care to follow
the building rules and make construction accordingly to their sweet will and
desire.
As per law, construction is to be made in accordance with the plan
sanctioned and not in deviation thereof. Any portion of the structure that has
been constructed in deviation of the sanctioned plan is liable to be demolished
in accordance with the provisions of the Act failing which the persons
responsible for making unauthorized construction would get an impetus and
will look for ways and means to flout the provision of law.
Any leniency to deal with unauthorized construction will send out a
very wrong message to the society at large and builders will take advantage of the
same by not adhering to the statutory provisions and tend to make construction
in deviation of the plan sanctioned. None will be able to muster the courage to
stand up against such illegalities. The Court cannot turn a blind eye to such
activities and permit the unauthorized construction to remain. Justice must be
seen to be done.
The Court is of the considered opinion that the order of demolition does
not call for any interference and is liable to be implemented.
Writ petition stands dismissed.
No costs.
Urgent certified photocopy of this judgment, if applied for, be supplied
to the parties or their advocates on record expeditiously on compliance of usual
legal formalities.
(Amrita Sinha, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!