Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Prabhu Poly Pipes Limited vs West Bengal State Electricity ...
2022 Latest Caselaw 7887 Cal

Citation : 2022 Latest Caselaw 7887 Cal
Judgement Date : 29 November, 2022

Calcutta High Court (Appellete Side)
M/S. Prabhu Poly Pipes Limited vs West Bengal State Electricity ... on 29 November, 2022
                           In the High Court at Calcutta
                          Constitutional Writ Jurisdiction
                                   Appellate Side

The Hon'ble Justice Sabyasachi Bhattacharyya

                             W.P.A. No.20630 of 2022

                       M/s. Prabhu Poly Pipes Limited
                                     Vs.
                  West Bengal State Electricity Distribution
                        Company Limited and others

     For the petitioner              :     Mr. Adhip Chandra Kar,
                                           Mr. Manoj Kumar Roy

     For the WBSEDCL                 :     Mr. Srijan Nayak,
                                           Mrs. Rituparna Maitra

     Hearing concluded on            :     24.11.2022

     Judgment on                     :     29.11.2022



     Sabyasachi Bhattacharyya, J:-



1.   The petitioner is a consumer of electricity under the respondent no.1, the

West Bengal State Electricity Distribution Company Limited (WBSEDCL).

2. Initially, the petitioner was enjoying a low tension bulk service connection,

which was converted subsequently to high tension service connection due

to enhancement of load from August 7, 2014.

3. A bill was raised by the WBSEDCL on November 5, 2019 for the first time

for the period September, 2014 to April, 2019 on the ground of arrear,

since a wrong multiplying factor was allegedly applied. The bill was raised

for the billing cycle October, 2019 with the reading date as November 1,

2019. The total amount of dues as per the bill was Rs.1,90,05,225/-, out

of which the due for the current period was Rs.7,09,649.44p and the

alleged arrears for the period from September, 2014 to April, 2019

comprised of the balance. The petitioner has made payment with regard to

the current consumption but has challenged the alleged arrears of

Rs.1,83,07,977/-.

4. The learned Senior Advocate appearing for the petitioner argues that the

claim of the WBSEDCL for the period September, 2014 to April 2019 is

palpably barred by Section 56(2) of the Electricity Act, 2003 (hereinafter

referred to as, "the 2003 Act"), as on November 5, 2019. It is submitted

that, as per the decision of the Supreme Court in Assistant Engineer(D1)

Ajmer Vidyut Vitran Nigam Limited and another Vs. Rahamatullah Khan,

reported at (2020) 4 SCC 650, the "first due" date as contemplated in

Section 56(2) of the 2003 Act is the date when the bill is issued for the first

time to the consumer. In the present case, it is argued, since the bill was

raised only on November 5, 2019, the same was barred under the aforesaid

provision of law.

5. The learned Senior Advocate also submits, on instruction, that a

substantial amount has already been paid in terms of the bills raised in

lieu of arrears. The petitioner is agreeable to clear off the balance amount

of quarterly installments of Rs.15 lakh each, starting from December, 2022

which would take the last installment prior to the completion of the year

2023.

6. Learned counsel appearing for the WBSEDCL places reliance on the

Supreme Court Judgment of M/s. Prem Cottex Vs. Uttar Haryana Bijli

Vitran Nigam Ltd. and others, an unreported judgment dated October 5,

2021 passed in Civil Appeal No.7235 of 2009. In the said judgment, the

Supreme Court reiterated the ratio of Rahamutullah Khan (supra)

inasmuch as the "first due" would mean the date on which the bill is

issued.

7. However, in the said latter judgment, it was also observed by the Supreme

Court that the decision in Rahamatullah Khan (supra) was distinguishable

on facts. The Supreme Court also observed in M/s. Prem Cottex (supra)

that the second part of Section 56(2) of the 2003 Act is an exception to the

law of limitation.

8. In the present case, it is contended by the WBSEDCL, the bill was raised

only on November 5, 2019 andthe said arrears were arrived at on the basis

of less billing. It is submitted that after the LT bulk service connection was

converted to HT bulk service connection due to enhancement of contractual

load on August 7, 2014, the particulars of meter and switch gear were

uploaded in the data-base prior to raising the bill. During such process,

the CT ratio of switch gear was originally set at 50/5A, but erroneously got

registered at 25/5A in the data-base. Hence, the net multiplying factor of

500 was imposed for calculation of billing instead of actual net Multiplying

Factor (MF) of 1000 from the billing cycle September, 2014.

9. When the matter was noticed prior to raising the bill for the cycle May

2019, the same was communicated to the petitioner vide Memo No.

SHE/Bulk/941341400/488 dated May 31, 2019 stating all relevant facts.

It was also indicated in the said Memo dated May 31, 2019 that the

unclaimed part of the bill would be served shortly to the petitioner and

prior to finalizing the arrear bills, one meeting was to be conducted as per

the convenience of the petitioner. Accordingly, the entire process was

allegedly described in a meeting with the petitioner at the office of the

respondents on June 26, 2019.

10. Subsequently, a joint inspection was conducted on July 12, 2019 and an

inspection report was handed over to the petitioner the same day

confirming that the Switch Gear CT ratio was to be set at 50/5A and actual

net multiplication factor would be 1000. Subsequently, the unclaimed part

of the bill was calculated considering the applicable tariff rate and rebate

and ultimately, after several meetings, the bill was raised on November 5,

2019.

11. It is, thus, argued that the erroneous calculation was a bona fide error on

the part of the WBSEDCL, for which the public exchequer ought not to be

penalized by giving an undue advantage to the petitioner.

12. Learned counsel for the distribution licensee argues that since the

petitioner undisputedly consumed electricity at the rate as indicated in the

arrear bill, the said claim was legitimate and the WBSEDCL was entitled to

issue subsequent notices of disconnection for non-payment of the dues by

the petitioner.

13. Upon a consideration of the submissions of counsel, the present

adjudication, it is seen, revolves around the interpretation of Section 56 of

the 2003 Act.

14. Section 56 of the 2003 Act is set out below:

"56. Disconnection of supply in default of payment.

(1) Where any person neglects to pay any charge for electricity or any sum other than a charge for electricity due from him to a licensee or the generating company in respect of supply, transmission or distribution or wheeling of electricity to him, the licensee or the generating company may, after giving not less than fifteen clear

days' notice in writing, to such person and without prejudice to his rights to recover such charge or other sum by suit, cut off the supply of electricity and for that purpose cut or disconnect any electric supply line or other works being the property of such licensee or the generating company through which electricity may have been supplied, transmitted, distributed or wheeled and may discontinue the supply until such charge or other sum, together with any expenses incurred by him in cutting off and reconnecting the supply, are paid, but no longer:

Provided that the supply of electricity shall not be cut off if such person deposits, under protest,--

(a) an amount equal to the sum claimed from him, or

(b) the electricity charges due from him for each month calculated on the basis of average charge for electricity paid by him during the preceding six months, whichever is less, pending disposal of any dispute between him and the licensee.

(2) Notwithstanding anything contained in any other law for the time being in force, no sum due from any consumer under this section shall be recoverable after the period of two years from the date when such sum became first due unless such sum has been shown continuously as recoverable as arrear of charges for electricity supplied and the licensee shall not cut off the supply of the electricity."

15. A two-Judge bench of the Supreme Court, in Rahamatullah Khan (supra),

had, inter alia, arrived at the conclusion that the obligation to pay

electricity charges arises after the bill is issued by the licensee-company,

although the liability arises on consumption. If the consumer fails to pay

the charges within the stipulated period as set out in the bill, they get

carried forward to the next bill as arrears.

16. A distinction was drawn between sub-sections (1) and (2) of Section 56 and

it was held that while the Distribution Licensee is entitled to recover dues

by other modes, it was not permitted to disconnect the electricity supply by

the operation of Section 56(2).

17. Section 56(2) was interpreted not to preclude the licensee-company from

raising a supplementary demand after the expiry of the limitation period of

two years but only restricts the right of the licensee to disconnect electricity

supply due to non-payment of dues after the limitation period of two years

has expired.

18. Other modes of recovery which may be initiated by the licensee-company

for recovery of a supplementary demand, it was held, are not restricted. On

the other hand, it was observed that sub-section (1) of Section 56 confers a

statutory right to the licensee-company to disconnect the supply of

electricity if the consumer neglects to pay the electricity dues, which right

is subject to the limitation of two years provided by sub-section (2) of

Section 56.

19. It was clarified by the Supreme Court that Section 56(2) did not preclude

the licensee-company from raising an additional or supplementary demand

after the expiry of the limitation period under Section 56(2) in the case of a

mistake or bona fide error. However, it did not empower the licensee-

company to take recourse to the coercive measure of disconnection of

electricity supply for recovery of the additional demand.

20. The Supreme Court, in paragraph no.4.4 of Rahamatullah Khan (supra),

observed that the word "due" has been used under Section 56(1) as well as

under Section 56(2) and refers to the amount for which the demand is

raised by way of a bill. The term "first due" would, therefore, imply when

the demand is raised for the first time. It was, thus, held that the bill

raised by the licensee-company would be the starting point for the exercise

of power under sub-section (1) of Section 56.

21. In paragraph no.9.2 of Rahamatullah Khan (supra), the Supreme Court also

discussed the provisions of Section 17(1)(c) of the Limitation Act, 1963

which provides that in case of a suit for relief on the ground of mistake, the

period of limitation does not begin to run until the plaintiff had discovered

the mistake or could, with reasonable diligence, have discovered it.

22. On the other hand, in M/s. Prem Cottex (supra), the Supreme Court, sitting

in a co-ordinate bench of two Judges, discussed the implication of

Rahamatullah Khan (supra). It was observed by the Supreme Court that

the bar contemplated in Section 56 actually operates on two distinct rights

of the licensee, namely, (i) the right to recover; and (ii) the right to

disconnect. The bar with reference to the enforcement of the right to

disconnect was held to be actually an exception to the law of limitation.

Under the law of limitation, it was observed, what is extinguished is the

remedy and not the right. However, Section 56(2) bars not merely the

normal remedy of recovery but also bars the remedy of disconnection.

23. The Division Bench, in M/s. Prem Cottex (supra), went on to observe that

once it is held that the term "first due" would mean the date on which the

bill is issued and once it is held that the period of limitation would

commence from the date of discovery of the mistake, then the question of

allowing the licensee to recover the amount by any other mode but not take

recourse to disconnection of supply would not arise. However, it was held

in the penultimate paragraph of Rahamatullah Khan (supra) that the

licensee may take recourse to any remedy available in law for recovery of

the additional demand but barred from taking recourse to disconnection of

supply under Section 56(2) of the Act.

24. The Supreme Court, in M/s. Prem Cottex (supra), accordingly, observed

that the Supreme Court, in Rahamatullah Khan (supra), was persuaded to

take the view that it did on account of certain peculiar facts. The

consumer in that case was billed under a particular Tariff Code for the

period from July, 2009 to September, 2011. But after audit, it was

discovered that a different Tariff Code should have been applied. A bill was

raised subsequently for the aforesaid period.

25. The Supreme Court went into an analysis of whether the raising of an

additional demand, by itself, would tantamount to any deficiency in service,

clothing the consumer fora with the power to deal with the dispute. The

said question, it was held, was not raised or considered in Rahamatullah

Khan (supra).

26. It is note-worthy that in both the cited judgments, the proceedings arose

from consumer disputes brought before the designated fora.

27. The matter was then discussed from another angle in M/s. Prem Cottex

(supra) and it was held that if the licensee has not raised any bill, there can

be no negligence on the part of the consumer to pay the bill and

consequently the period of limitation prescribed under sub-section (2) of

Section 56 will not start running. So long as limitation has not started

running, the bar for recovery and disconnection will not come into effect.

28. The crux which can be distilled from the above two judgments is that the

Supreme Court, in no uncertain terms, interpreted the "first due" date to be

the date when the bill was raised for the first time.

29. In the present case, the bill for the additional amount was raised for the

first time on November 5, 2019 and, as such, following the principle laid

down in the Supreme Court Judgments, the limitation started running only

from November 5, 2019.

30. As such, it cannot be said that the limitation, either for recovery of such

amount under sub-section (1) of Section 56 or for the purpose of

disconnection of electricity for non-payment as envisaged in sub-section (2)

thereof, commenced.

31. Moreover, taking into account the provision of Section 17(1)(c) of the

Limitation Act, 1963, as reiterated by the Supreme Court in both the

judgments, in a case where there has been a mistake or a bona fide error,

the licensee-company was not precluded from raising an additional or

supplementary demand even after the expiry of the limitation period.

32. However, the question of applying such principle to the present case is

unnecessary, in view of the first due date having been held by the Supreme

Court to be the date of raising of the bill (here, the

additional/supplementary bill) for the first time.

33. In the present case, the additional bill was raised for the first time on

November 5, 2019 for the entire period from September 2014 to April,

2019, which was the unclaimed part of bill from such previous billing cycle,

owing to a bona fide error on the part of the WBSEDCL in applying the

correct parameters and multiplying factor.

34. Hence, it cannot be in doubt that the WBSEDCL was entitled to claim the

amount payable on the said bill at that juncture, since it had been claimed

within two years from the discovery of the mistake in May, 2019.

35. Although the liability of the petitioner to pay, under normal circumstances,

would have arisen from the date when the amounts became due, the

liability and obligation to pay have merged in the present case by

converging on the starting point of November 5, 2019, when the additional

amount became "first due". In view of the amount having been claimed by

way of the additional bill within limitation and thereafter having been

shown by the WBSEDCL in subsequent bills, there cannot be any doubt

that the WBSEDCL was well within its power and not barred by limitation

in any manner to claim the amount at that juncture.

36. Subsequently, the WBSEDCL, on the non-payment of the petitioner of the

said amount, sought to take resort to Section 56(1) of the 2003 Act for

disconnecting the said electricity supply of the petitioner.

37. I find no illegality in such exercise on the part of the WBSEDCL, since the

bar of limitation stipulated in Section 56 (2) is not applicable in the

circumstances of the instant case.

38. Thus, in the facts of the present case, as discussed above, the WBSEDCL is

entitled both to recover the amount of additional claim and to disconnect

the supply of electricity of the petitioner in the event such amount is

refused to be paid by the petitioner within the contemplation of Section 56

of the 2003 Act.

39. However, since the learned Senior Advocate appearing for the petitioner has

submitted that the petitioner is willing to clear off the due amount on

additional bills by quarterly installments of Rs.15 lakh, each starting from

December, 2022, in deference to such submission and since the ultimate

purpose of the WBSEDCL is to recover public money and not merely to

disconnect electricity supply, such opportunity ought to be given to the

petitioner to clear all dues.

40. Hence, W.P.A. No.20630 of 2022 is disposed of by directing the petitioner to

pay the entire amount due in lieu of additional electricity charges for the

billing cycle September, 2014 till April, 2019 by four (04) quarterly

installments of Rs.15 lakh each. The first of such installment shall be paid

by the petitioner by the 31st day of December, 2022. The next three (03)

installments shall be paid respectively within March 31, 2023, June 30,

2023 and September 30, 2023 respectively. The remaining amount of

dues, if any, shall be rounded off with the last installment as indicated

above.

41. Along with such installments, the petitioner shall go on paying the current

electricity charges in accordance with law to the WBSEDCL. In the event

the petitioner deposits such installments and the current electricity

charges in time, the WBSEDCL shall not disconnect the electricity supply

of the petitioner on the ground of non-payment of the outstanding arrears

of the period September, 2014 to April, 2019.

42. However, in default of payment of even one of the said installments, along

with current electricity charges, it will be open to the WBSEDCL to

disconnect the electricity supply of the petitioner upon a notice of Seven

(07) days.

43. There will be no order as to costs.

44. Urgent certified copies, if applied for, be issued by the department on

compliance of all requisite formalities.

( Sabyasachi Bhattacharyya, J. )

Later

When the above judgment is passed today, it is pointed out by the

learned Senior Advocate appearing for the petitioner that the petitioner has

already deposited one of the instalments to the tune of Rs.15 lakh with the

WBSEDCL.

Hence, the amount which has already been deposited shall be

deducted from the instalments payable pursuant to the judgment passed

today.

( Sabyasachi Bhattacharyya, J. )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter