Citation : 2022 Latest Caselaw 7845 Cal
Judgement Date : 28 November, 2022
28th November,
(AK)
W.P.A 19617 of 2018
Smt. Anajna Samaddar Vs.
Calcutta Electric Supply Corporation and others
Mr. Souurav Banerjee ...for the petitioner.
Mr. Om Narayan Rai Mr. Debanjan Mukherjee ...for the CESC Limited.
Learned counsel for the petitioner argues that the
CESC Limited has discriminated against the petitioner
without any reasonable basis inasmuch as the
petitioner's request for a new individual electricity
connection for running the petitioner's shop has been
denied on the ground that other shop owners at the same
housing complex are enjoying electricity from two block
meters.
Learned counsel contends that such enjoyment of
electricity from a sub-meter, connected to a common
block meter, exposes the petitioner to the peril of
disruption of electricity supply due to non-payment by
other consumers.
Moreover, the petitioner seeks to increase the load
for the purpose of extending his business conducted from
the shop room, which is not possible if he enjoys
electricity from a sub-meter along with others from a
common block meter.
Learned counsel argues that Article 14 of the
Constitution of India is patently violated by the CESC
Limited inasmuch as the shop owners in a similarly-
placed adjacent building are enjoying independent and
individual electricity connections, whereas the petitioner
is being refused the same.
More importantly, it is argued by the petitioner, the
appellate tribunal of the West Bengal Housing Board has
been allotted the first floor of the same complex where the
petitioner is running his shop.
However, as opposed to the petitioner and the other
shop owners, the said appellate tribunal has been allotted
an individual and independent electricity connection in
the name of its executive engineer.
Learned counsel submits that the distinction sought
to be made out by the CESC Limited on the tariff being
different for public bodies is not sanctioned by law,
inasmuch as Section 2(15) of the Electricity Act, 2003
does not make any such distinction between private
individuals and public bodies and/or Government
organizations.
Learned counsel appearing for the CESC Limited
cites a coordinate Bench judgment of this court in CESC
Limited and another vs. Ombudsman and another reported
at 2022 SCC Online Cal 354.
It is submitted that, under similar circumstances,
on the writ petition of the CESC Limited, another shop
owner of the same complex as the present petitioner was
refused individual connection on the ground that block
meter was the applicable mode of granting electricity in
the said premises.
Learned counsel places reliance on the facts
narrated by the learned single Judge for strengthening
his argument that the factual scenario of the said case
was similar to the present.
It is further submitted, by placing reliance on the
affidavit-in-opposition, that the adjacent market complex
with which the petitioner claims parity, stands on a
different footing than the market complex where the
petitioner is running his shop.
First, the said adjacent building houses much less
number of shop rooms than the complex where the
petitioner is running his shop.
Secondly, it is submitted that the shop owners'
association of the present complex, where the petitioner's
shop is situated, had entered into an agreement with the
CESC Limited for providing electricity connection by block
meters, whereas, from the inception, the shop owners of
the other adjacent building have been enjoying individual
connections.
As such, it is submitted that the parity sought to be
drawn by the petitioner with the adjacent complex is not
available in law.
Learned counsel for the CESC Limited further places
reliance on the tariff order of the CESC Limited for the
year 2017-2018, a copy of which is handed over in court
today.
In serial no. 7 of the same, it has been mentioned
that public bodies have a different tariff scheme
applicable to them than general consumers.
Since the petitioner falls within the category of a
general consumer as opposed to a public body, whereas
the tribunal situated on the first floor of the complex is a
public body, the distinction made between the two by
giving independent electricity connection to the housing
board and charging different tariff is justified.
The rate slabs of the two categories of consumers, it
is submitted, are entirely different.
Learned counsel for the CESC Limited further
contends that the relevant regulation provides that the
Distribution Licensee has the discretion of giving
electricity supply by way of block meter in case of
bustees, market places, etc where several connections are
taken in close vicinity.
Hence, the CESC Limited, it is submitted, was
justified in insisting upon giving a block meter for
technical reasons as well.
A consideration of the submission of the parties
indicates that the premise on which the block meter is
being insisted upon by the CESC Limited is Clause 18 of
Regulation no. 53 of 2013 of the WBERC.
The said clause provides that in bustees, market
places etc., where it may not be possible to segregate one
consumer from an adjacent consumer because of
existence of a very large number of consumers in a
relatively small premises, and where because of
multiplicity of the wirings of such a large number of
consumers, there may arise fire and safety hazards, the
licensee may effect supply of electricity to all the
consumers/intending consumers through a suitably
located common meter of adequate capacity, to be known
as a Block Meter.
In the present case since, in the perception of the
CESC Limited, it is not technically feasible, keeping in
mind the fire and safety hazards, to give individual
electricity connections to each of the shop owners, it
cannot be said that there is gross discrimination on the
part of the CESC Limited between the petitioner and
other equally placed persons.
That apart, as rightly pointed out by learned counsel
for the CESC Limited, the parties to the agreement, being
the shop owners of the complex where the petitioner is
running his shop, are bound by the initial arrangement
made between them and the CESC Limited.
Even if the petitioner wants to deviate, it is not
feasible to do so, in view of all the other shop owners in
the same complex enjoying electricity from sub-meters,
connected to two common block meters.
Inasmuch as the first floor Housing Appellate
Tribunal is concerned, the CESC Limited is justified in
drawing a distinction between the same and the petitioner
on the ground that the former is a public body whereas
the petitioner is not.
The same justifies different tariff rates and
electricity supply being given by separate arrangements,
in the case of the petitioner by a block meter.
Moreover, although under Section 43 of the
Electricity Act 2003, the petitioner is entitled as a
consumer/intending consumer to get supply of electricity,
it is well within the authority of the Distribution Licensee
to reasonably distinguish between the petitioner and
other consumers on intelligible and reasonable grounds
insofar as the mode of giving such connection is
concerned.
In the present case, the line of distinction drawn
between the petitioner and the adjacent building shop
owners as well as the tribunal situated above are
sufficiently intelligible and cogent.
Although Section 2 (15) of the 2003 Act does not
make any distinction between public bodies and private
individuals inasmuch as the expression "consumer" is
concerned, the same does not have a bearing in the facts
of the present case.
Moreover, this court is bound by the coordinate
Bench judgment rendered in CESC Limited and another
Vs. Ombudsman and another (supra). The facts and
circumstances in the said case were similar to the present
one.
The respondent no.2 therein was an individual shop
owner in the Calcutta Greens Commercial Complex at
1050/2, Survey Park, Kolkata-700075, which is the same
complex where the petitioner is running his shop.
The application of the respondent no.2 for individual
connection, which had been allowed by the Ombudsman,
was set aside by the learned Single Judge.
In the said case, the same argument was made, on
which the Court held that the extant regulation, that is,
Regulation 18 as mentioned above, does not make a
distinction between old and new commercial complexes
and applies to both types equally.
In such view of the matter, since the distinction
sought to be drawn by the CESC Limited between the
petitioner and the others referred to by the petitioner is
justified, there is no scope of observing that there has
been a violation of Article 14 of the Constitution of India
on the party of the CESC Limited.
In any event, since all other shop owners at the
premises-in-question are enjoying electricity as per the
previous arrangement from sub-meters attached to two
block meters, there is no particular reason why the
petitioner, who is situated on a similar footing as the
other shop owners vis-à-vis the CESC Limited, should be
specially favoured with an individual connection, which
will also disrupt the safety and security of the premises
inasmuch as fire and electricity hazards are concerned.
As such, there is no scope of interference in the
present writ petition.
Accordingly, WPA 19617 of 2018 is dismissed on
contest without, however, any order as to costs.
Urgent photostat copies of this order, if applied for,
be given to the parties upon compliance of all requisite
formalities.
(Sabyasachi Bhattacharyya, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!