Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Diwakar Ray @ Rai vs Cesc Limited And Others
2022 Latest Caselaw 7676 Cal

Citation : 2022 Latest Caselaw 7676 Cal
Judgement Date : 21 November, 2022

Calcutta High Court (Appellete Side)
Diwakar Ray @ Rai vs Cesc Limited And Others on 21 November, 2022
21st November,
 2022
 (AK)
 04




                                      W.P.A 3185 of 2022

                                     Diwakar Ray @ Rai
                                             Vs.
                                   CESC Limited and others


                              Mr. Indranil Halder
                                                         ...for the petitioner.

                              Mr. Rajiv Lall
                                                       ...for the CESC Limited.

                              Mr. Mainak Ganguly
                              Mr. Dhiraj Kr. Gupta
                              Mr. Abhishek Singh
                                               ...for the respondent no.4.

Learned counsel for the petitioner contends, by

placing reliance on the annexure to the affidavit-in-

opposition filed by the respondent no.4, along with the

annexure to the affidavit-in-reply filed by the petitioner,

that although previously the respondent no.4 had

obtained an ex parte injunction order allegedly protecting

his possession in respect of the disputed property, a

subsequent order of injunction was passed by another

civil court, where, upon hearing both sides, the court

came to the conclusion that the present petitioner is in

possession of a portion for the property, which entitles

the plaintiff/petitioner to the use of electricity.

Learned counsel appearing for the private

respondent controverts the allegation as regards the

petitioner being in possession and submits that the prior

order of injunction was subsisting in favour of the

respondent no.4, observing that the said respondent was

in possession of the property, when the second injunction

order was passed in favour of the petitioner. In such

circumstances, allegedly suppressing the same, the

present petitioner obtained the order of injunction from

the other civil court.

It is further apprehended by the private respondent

that if any electricity connection is given in favour of the

petitioner, the same may create a special equity in favour

of the petitioner, particularly insofar as the pending civil

suits are concerned.

Learned counsel appearing for the CESC Limited

submits that, otherwise, the CESC has no objection to

give electricity connection to the petitioner. However, due

to obstruction put up by the private respondent and his

men and agents, such connection is not being able to be

given.

A perusal of the respective injunction orders passed

by the two courts in favour of each of the contesting

parties indicates that the order of status-quo passed in

favour of the present private respondent was obtained on

December 16, 2016.

The said order, however, was passed ex parte,

although even such an order is equally binding as one

passed on contest.

However, the complication has arisen subsequently

when the present writ petitioner preferred another suit

before a different civil court, that is, the Civil Judge,

Senior Division, Seventh Court at Alipore bearing Title

Suit No. 470 of 2019, where the said civil court, upon a

contested hearing of both sides, including the private

respondent, passed an order restraining the private

respondent and the other defendants from causing any

disturbance in the supply of electricity to the plaintiff

therein, that is, the present writ petitioner.

It was also prima facie found by the said civil court

in the subsequent contested order that the writ petitioner

is in possession of a portion of the suit property,

irrespective of whether the writ petitioner is a trespasser

or not, which entitels the petitioner to use electricity on

the premises.

In view of such conflicting findings, it is beyond the

scope of the writ court to enter into the factual merits and

demerits of the respective cases of the parties,

particularly as regards their right, title and possession in

respect of the disputed property.

However, since the order passed in favour of the writ

petitioner was subsequent and was passed on contest, for

the purpose of ascertaining electricity connection, we

have to presume on a prima facie footing that the

petitioner is all probability in possession of the said

property.

Of course, such issue will be thrashed out by the

parties and decided by the civil courts ultimately in

connection with the suits.

Even then, the argument of the private respondent

that the definition of "occupier" in Rule 2 of the Works of

Licensees Rules, 2006 includes a person in lawful

occupation cannot cut ice in the present case.

The various provisions of the 2006 Rules indicate

primarily that prior consent of the owner or occupier of

any building or land has to be taken before carrying out

works as envisaged therein. Hence, the said definition

operates in a separate field that Section 43 of the

Electricity Act, 2003.

However, Section 43 of the Electricity Act, 2003,

which is the parent statute, clearly elucidates that merely

being an occupier, a person is entitled to electricity

connection.

Moreover, there are several judgments of this court

and it is no longer res integra that an occupier of

premises, irrespective of the legality of his possession, is

entitled to get electricity connection at the property.

Inasmuch as Clause 3.2.1 of Regulation 46 of the

WBERC, 2010 is concerned, the 'Way Leave'

contemplated therein from the lawful owner cannot be

insisted upon in the present case, since it is well-settled

that the provisions of Section 43 of the 2003 Act, coupled

with Article 21 of the Constitution of India, confer the

right on an occupier to get electricity supply. Such right

cannot be objected to under normal circumstances.

Although it cannot be determined beyond doubt at

this stage as to who is in actual physical possession of

the disputed property, for the reasons as delineated

above, the petitioner is held to be entitled to electricity

connection in the petitioner's name upon being prima

facie in occupation of the property.

Accordingly, WPA 3185 of 2022 is disposed of by

directing the CESC Limited to give electricity connection

to the petitioner at the premises in dispute, subject to

compliance of all formalities by the petitioner, as

expeditiously as possible, preferably within a fortnight

from date or from compliance of all formalities, whichever

is later.

In the event the CESC personnel face any

obstruction in doing so, it will be open to the said

personnel to approach the respondent no.3, the Officer-

in-Charge of the Mahestala Police Station for adequate

police assistance.

If so approached, the respondent no.3 shall grant

such assistance to the CESC personnel for the limited

purpose as indicated above and, if necessary, to open any

padlock or other hindrance in doing so, at the cost,

however, of the petitioner.

It is, however, clarified that the electricity

connection, as and when given to the petitioner, shall not

create any special right, equity or interest in favour of the

petitioner and/or per se be an indicator of the petitioner's

occupation of the property for the purpose of the pending

civil suits.

It will be open to the civil courts to decide such

issue, along with other issues pending before those,

independently in due course of law without being

influenced in any manner by any of the observations

made herein.

Affidavit-in-opposition and affidavit-in-reply filed in

court today be kept on record.

Learned counsel for the private respondent also

urges that in view of the petitioner having got an order of

electricity connection from a competent civil court, the

present writ petition is not maintainable to enforce the

same.

However, such argument is not acceptable on the

face of it, since, in the same breath, the private

respondent cannot dispute the right of the petitioner to

get electricity connection and resist the maintainability of

the present writ petition on the ground that the petitioner

is so entitled in terms of a civil court's order.

As such, the said ground is turned down.

Parties as well as all concerned shall act on the

written communication of the learned Advocates for the

parties, coupled with server copy of this order, without

insisting upon prior production of a certified copy thereof.

There will be no order as to costs.

Urgent photostat copies of this order, if applied for,

be given to the parties upon compliance of all requisite

formalities.

(Sabyasachi Bhattacharyya, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter