Citation : 2022 Latest Caselaw 7451 Cal
Judgement Date : 10 November, 2022
IN THE HIGH COURT AT CALCUTTA
Civil Appellate Jurisdiction
APPELLATE SIDE
Present:
The Hon'ble Justice Tapabrata Chakraborty
&
The Hon'ble Justice Raja Basu Chowdhury
F.A. 39 of 2019
Land Acquisition Collector
versus
Sri Akshay Kumar Khamrai.
For the Appellant : Mr. Supratim Dhar,
Mr. Dhananjay Nayak.
For the Respondent : Mr. Sudhakar Biswas,
Mr. Sukanta Das.
Hearing is concluded on : 24th August, 2022. Judgment On : 10th November, 2022. Raja Basu Chowdhury, J. :
1. The present appeal has been filed challenging the judgment and
decree dated 15th September 2016 passed by the Court of the learned
Additional District Judge, 5th Court, Paschim Midnapore in L.A. Case No.
20 of 2010.
2. Origin of the instant lis dates back to 26th November 1979, when two
notices under section 3(1) of the West Bengal Land (Requisition and
Acquisition) Act, 1948 (hereinafter referred to as Act II 1948) were issued
and forwarded to the respondent. The said notices were in Form 1 and
the respondent was required to deliver possession of the land as
described in such notices on 4th December, 1979 (hereinafter referred to
as the said notices). As would appear from the above, the plots of land
were requisitioned by the State and possession thereof was taken over on
4th/5th December, 1979. Although it would be apparent from the
requisition notices, that the plots of land were requisitioned for the
purpose of establishing Milk Chilling Plant, yet the land was not
acquired until the time hereinafter mentioned. No steps were taken by
the Land Acquisition Collector to initiate any acquisition proceeding
under the provisions of Act II 1948. In fact, for about two decades, no
steps were taken to acquire the aforesaid land, by issuing any notice
under section 4(1) of Act II 1948.
3. With the passage of time Act II 1948, which was a temporary Act was
re-enacted and extended from time to time to give a fresh lease of life to
the same. However, after 1997, the Act II 1948 lost its validity. By such
time, however, several requisition proceedings had been initiated,
acquisition in respect whereof, was either yet to commence or the same
was not complete. Thus, to overcome the aforesaid incongruous
situation, the Land Acquisition Act of 1894 was amended by West Bengal
Act No. VII of 1997 and Sub-sections 3A and 3B were inserted. This
enabled the state to overcome the problem of losing pending requisition
proceedings, the same also afforded an opportunity to the state to
acquire the same. In the present case the aforesaid requisition
proceedings under Act II of 1948, were subsequently converted to an
acquisition proceeding under Land Acquisition Act 1 of 1894 (hereinafter
referred to as the Act I 1894) by issuing notices under section 3A and 3B
of Act I 1894.
4. Records would reveal that such acquisition proceedings did not
ultimately culminate in an Award and stood lapsed. Still later, on a writ
application filed by the respondent, which was registered as W.P. No.
7332 (W) of 2004, this Hon'ble Court by an order dated 10th September,
2004, having found that the land in question was utilized by the
requiring body, directed that the Land Acquisition Collector to issue a
notice under section 4 of Act I 1894 and to ascertain compensation
within a period of three months from the date of publication of notice
and after serving notices on all interested persons.
5. Pursuant to the aforesaid direction, Land Acquisition case was
initiated for acquisition of 2.45 acres and 0.25 acres of land respectively
in Mouza Durlavgunj and Bila respectively, P.S. Garhbeta, District
Paschim Midnapore, by issuing notification under section 4(1) of the Act
I of 1894, publication whereof was made on 3rd November 2004.
6. Records would further reveal that in the land acquisition proceedings
subsequent to publication of declaration under section 6 of Act I 1894,
the same was renumbered as LA Case No 3 of 2004-05 and the L.A.
Collector passed an Award on 3rd July, 2007, under section 11 of Act I of
1894. Notice of Award under Section 12(2) of Act I 1894, was duly
served on the respondent.
7. The respondent had received the compensation awarded by the
Collector, under protest and had thereafter by written application
addressed to the Collector sought for reference of the matter, for
determination of compensation by Court, in terms of section 18 of Act I
1894. On contested hearing by a judgment and decree dated 30th August,
2011 passed by the learned Additional District Judge, 5th Court,
Paschim Midnapore in L.A. Misc. Case No. 20 of 2010 the compensation
payable in favour of the respondent was determined.
8. A review application, being J. Misc. Case No. 10 of 2011, was filed by
the respondent seeking review of the aforesaid judgment and decree
dated 30th August, 2011, inter alia, on the ground that the learned Court
ought to have directed the L.A. Collector to pay interest @ 9% per annum
for one year from the date of possession i.e. 5th December, 1979 and
thereafter @ 15% on the excess amount of compensation.
9. By a judgment and order dated 6th February, 2012 the learned Court
allowed the review application on contest and partly modified the
judgment dated 30th August, 2011, thereby directing the L.A. Collector to
pay interest in terms of section 28 of Act I 1894, on the excess amount
of compensation including solatium as awarded by the Court at the rate
of 9% per annum, from the date on which the Collector had taken
possession of the land in question, for the period of one year and at the
rate of 15% per annum, from the date of expiry of the period of one year,
till payment of such excess amount of compensation in Court.
10. Records would reveal that the appellant had challenged both the
judgment and decree dated 30th August 2011 passed by the learned
Additional District Judge, 5th Court, Paschim Midnapore in LA Misc.
Case No. 20 of 2010 as also the order dated 6th February, 2012 passed in
J. Misc. Case No. 10 of 2011 arising out of L.A. Misc. Case No. 20 of
2010 by which the judgment and order dated 30th August, 2011 was
modified. The same was registered as FAT 386 of 2012. Records would
further reveal that a cross appeal was also filed by the respondent which
was registered as COT 21 of 2013.
11. By judgment and order dated 12th September 2014 a Coordinate
Bench of this Court observed that the learned Additional District Judge,
5th Court at Paschim Medinipur, while determining the compensation did
not take into account the classification of the land and the issue needs
further evidence. As such, the matter was remanded, so as to afford an
opportunity to adduce evidence with regard to the classification of land.
The question whether the landowner is entitled to valuation as on the
date of notification under section 4 of Act I 1894 and also compensation
for the period from 5th December, 1979 was kept open, to be decided in
accordance with law, with a further direction upon the learned trial
Court to readmit the matter under its original number and to proceed
and try out the same.
12. Consequent upon the same the matter was heard by the learned
Court below and by judgment and decree dated 15th September, 2016,
passed in L.A. Case No. 20 of 2010, the Learned Additional District
Judge, 5th Court, Paschim Medinipur allowed the L.A. case and the J.
Misc. Case upon ascertaining the classification of land and by
determining the compensation payable to the respondent.
13. Being aggrieved, the appellant has preferred the instant appeal which
was registered as F.A. No. 39 of 2019. At the time of admission of the
appeal, the appellant pursuant to directions passed by a coordinate
bench of this Hon'ble Court dated 16th January, 2019, had deposited a
sum of Rs 40,00,000/- (Rupees Forty lakhs) only with the Registrar
General of this Hon'ble Court.
14. Mr. Dhar, learned advocate appearing in support of the appeal
submits that the learned Court below did not segregate the amount of
compensation payable in respect of different classes of land. The learned
Judge had also not taken note of the largeness of the land while
determining the compensation payable to the respondent; the rates at
which the smaller plots are sold cannot be the criteria for determining
market value of land in respect of larger plots. No reasoning has been
given by the learned Judge to arrive at a figure of Rs. 75,000/- per
decimal. Drawing our attention to the evidence-in-chief and cross-
examination of the PW1, he submits that the plots of land in question
were vacant at the time of acquisition. Such fact has not been
considered at all by the learned Judge.
15. Placing reliance upon the judgment delivered in the case Shaji
Kuriakose & Anr. -Vs.- Indian Oil Corporation Ltd. & Ors. reported in
(2001) 7 SCC 650, he submits that while fixing market value of the
acquired land, comparable sales method of valuation is preferred, than
other methods of valuation of land. The factors which are to be
considered for determining valuation have been set forth in the said
judgment. Drawing our attention to paragraph 3 of the aforesaid report,
it is submitted that the land covered by sales must be smaller similar to
the acquired land and the size of plots of land covered by sales be
comparable to the land acquired. The learned Judge has not taken into
consideration the aforesaid factors. On such ground itself the judgment
impugned should be set aside.
16. He argues that the learned Judge had also erred in awarding excess
amount of compensation in the form of interest from the date when
possession was taken. The learned Judge ought to have awarded
interest from the date of issuance of notification under Section 4 of Act I
1894 and not from the date on which possession had been taken. He
further argues, if the claimant is entitled to market value from the date
of notice under section 4 of Act I 1894, in such case the claimant should
not be entitled to interest from any date, anterior to such date when the
aforesaid notification was published.
17. Placing reliance upon the judgment delivered in the case of Siddappa
Vasappa Kuri & Anr. -Vs.- Special Land Acquisition Officer & Anr.,
reported in (2002)1 SCC 142, he submits that starting point for
computing compensation under Section 23(1-A) of Act I 1894 @ 12% per
annum on the market value, commences on and from the date of
publication of the notification under section 4(1) of Act I 1894 and the
same continues up to the date of Award or taking over possession
whichever is earlier. The Hon'ble Supreme Court has made it clear that
determination of compensation for the aforesaid purpose would at best
be limited to the date of publication of notice under section 4 of Act I
1894 and not prior thereto. As such the learned Judge had erred in
awarding interest from the date of possession, which is prior to the
notification issued under Section 4 of Act I 1894.
18. Reliance has also been placed upon the judgment delivered in the
case of R.L. Jain -VS.- DDA & Ors., reported in (2004)4 SCC 79. In the
said case, the Hon'ble Supreme Court in paragraphs 17 and 18 of such
report had taken a view that the landowner is not entitled to interest
under the Act I 1894 from the date of possession for the purpose of
determination of compensation, if such possession is taken before the
preliminary notification. He argues that the judgment impugned is
contrary to law and should be set aside.
19. Per Contra Mr. Biswas, learned advocate appearing for the
respondent, draws our attention to exhibit nos. 7 to 11 and 14 & 15,
pages 10 & 11, Part-II of the paper book and he takes us through record
of rights to identify the classification of land. He then takes us to the
several exhibits, the sale deeds and submits that the aforesaid sale deeds
are comparable to the land acquired and have been rightly taken into
consideration by the learned Judge, for deciding the market value of
land.
20. It is submitted, that admittedly, possession of land had been taken
over in the year 1979. The order dated 10th September, 2004 by virtue
whereof the instant acquisition proceedings were initiated had not been
challenged by the appellant. The same would demonstrate that the land
had been utilized by the appellant long back, though the lands remained
un-acquired. Consequent upon direction passed by the Hon'ble Court
on 10th September, 2004 in W.P. No. 7332 (W) of 2004, a notification
under Section 4 of Act I 1894 had been published. According to Mr.
Biswas, the claimant ought to be awarded additional interest @ 15% per
annum on the amount awarded by the Land Acquisition Collector, from
the date of taking over possession and not from the date of publication of
notification under Section 4 of Act I 1894. The issue as regards right to
receive compensation in the form of damages for the period when
possession was actually taken over, till the period of publication of
notification under Section 4 of Act I 1894 is no longer res-integra. Relying
upon the judgment delivered in the case of Balwan Singh & Ors. -Vs.-
Land Acquisition Collector & Anr., reported in AIR 2016 SC 1565, he
submits that considering paragraph 18 of the judgment in R. L. Jain
(Supra) the Hon'ble Supreme Court in the case of Madishetti Bala
Ramul (dead)1 LRS -Vs.- Land Acquisition Officer, reported in (2007)
9 SCC 650 took a view that the additional interest @ 15% per annum on
amount awarded by the Land Acquisition Collector, to be a reasonable
amount to be paid to the claimant for the period from the date
dispossession till the date of notification under Section 4(1) of the Act I,
1894. The above view had also been accepted in the case of Tahera
Khotoon & Ors. -Vs.- Revenue Divisional Officer/Land Acquisition
Officer & Ors., reported in (2014) 13 SCC 613. Accordingly, he
submits that the claimant should be awarded 15% interest as damages
for the period for which he had remained out of possession till the date of
issue of notification under Section 4 of the said Act I, 1894.
21. He submits that the judgment delivered in the case of Shaji
Kuriakose & Anr. -Vs.- Indian Oil Corporation Ltd. & Ors., reported in
(2001)7 SCC 650 and the judgment delivered in the case of Siddappa
Vasappa Kuri & Anr. -Vs.-Special Land Acquisition Officer & Anr.,
reported in (2002)1 SCC 142, are otherwise distinguishable on facts and
have no bearing to the instant case. Mr. Biswas further submits that
this Hon'ble Court in exercise of its power under Order 41 Rule 33 has
ample authority and jurisdiction to pass such decree or orders as are
required to be passed. In support of the aforesaid proposition, he places
reliance upon the judgment delivered in the case of K. Muthuswami
Gounder -Vs.-Palaniappa Gounder reported in AIR 1998 Supreme
Court 3118.
22. We have heard learned advocates appearing for the respective
parties. We have considered the lower Court record, exhibits, pleadings
of the parties and other available materials on record. We find that
notwithstanding issuance of two several requisition notices under
Section 3(1) of Act II 1948 and despite taking over possession of property
on 5th December, 1979, no steps had been taken by the Land Acquisition
Collector to acquire such property during the tenure of the aforesaid Act
II 1948. It was only at the intervention of the Hon'ble Court in W.P. No.
7332 (W) of 2004, that a fresh proceeding for acquisition of the land
belonging to the respondent, was initiated, which had already been
utilized by the requiring body. It would appear from the aforesaid order
dated 10th September, 2004, that the respondent up to that stage, had
been deprived of its property without any recourse to law. Consequent
upon the order passed on 10th September 2004 in W.P. No. 7332 (W) of
2004 as aforesaid, a notification under Section 4 of the Act I 1894 was
published and L.A. Case 3 of 2007 was initiated. We have been able to
ascertain from the Lower Court record that the LA Collector, Paschim
Midnapore had identified 2.60 acres of land in Mouza Bila and
Durlabhgunge covered under L.A. Case No. 3 of 2004-05 to be a Rice Mill
while .25 acres of land in Mouza Durlabhgunge to be partly Rice Mill and
partly (Orchard). The computation of market value appears to have been
made based on the classification declared therein. We find that the
respondent had accepted the awarded compensation issued by the
Collector on 3rd July 2007, under protest and since thereafter had made
a reference under Section18 of the Act I, 1894. Originally, by a judgment
and decree dated 30th August, 2011 the learned Court below had
determined the excess compensation payable to the respondent to be
Rs.23,95,965/-(Rupees Twenty-Three Lakhs Ninety-Five Thousand Nine
Hundred and Sixty-Five) only. A review application appears to have been
filed, which was allowed by a judgment and decree dated 6th February,
2012, thereby directing that the respondent shall be entitled to interest
payable under Section 28 of Act I 1894. The learned Judge, by the
aforesaid judgment directed that the interest shall be computed at the
rate of 9% from 5th December 1979, when possession had been taken, for
a period of one year and subsequently @ 15% from the expiry of such
period of one year, till payment of excess amount of compensation in
Court.
23. Being aggrieved, the appellant had preferred an appeal, which was,
however, remanded back to the learned Court below to ascertain the
classification of land by keeping the other points open. Since then, the
respondent, as claimant, had led evidence. Ultimately by detailed
judgment and decree dated 15th September, 2016, the learned Court
below had inter alia, concluded by placing reliance upon the exhibit nos.
5 and 6 being the relevant record of rights, that 36 decimals in plot no.
81/555 is a rice mill and plot no. 81 measuring 159 acres is Sali/patit
i.e. partly agricultural land and partly fallow land and the classification
and nature of plot no.213/466 measuring 52 decimals is orchard and
the land measuring 3.24 acres is mill. Since the parties did not challenge
the record of rights, the learned Judge concluded that the classifications
of some portion of the plots are Sali and some are patit (fallow), while
some are rice mill/bastu while certain other portions are orchard/Mill.
The learned Judge had also taken into consideration the evidence led by
Sandip Kumar Bose, Ramsundar Molla, Subrata Chattopadhyay and
Swarup Ranjan Ghosh and the documentary evidence in the form of sale
deeds which were exhibited. The appellant, however, did not lead any
oral evidence. While taking note of both documentary as well as oral
evidence in respect of transfer of land, which were close to the date of
notification published under section 4 of Act I 1894, the learned Judge
concluded, that the claimant had been able to prove market value of the
land ranging between Rs.53000/- to Rs.80000/- per decimal. While
ascertaining the market value of the land as aforesaid, the learned Judge
had also taken note of the fact, that rates at which small plots are sold
cannot be a safe criterion for ascertaining the market value of the land
and for such reason, did not take into consideration the land purchased
by PW5. The learned Judge ultimately while keeping in mind the
classification of land, valuation of the land, transfer in the locality,
possession and documents relating to the land filed by both sides
determined and assessed Rs.75,000/- per decimal to be the market
value of the land acquired. The learned Judge further awarded 12% on
such market value from the date of taking over possession of land to the
date of Award of the Collector as per section 23(1A) of Act I 1894 (West
Bengal Amendment) Act, 1997. The learned Judge further awarded the
additional compensation @ 30% on the market value as per sub-section
2 of section 23 of Act I, 1894 as solatium and further provided that in
default of payment within two months by the LA Collector the
respondent shall be entitled to the interest @ 10% per annum over and
above the balance amount from the date of judgment till payment of full
awarded amount.
24. We find that the learned Judge had not segregated the market value
as per classification of land, however, the same does not vitiate the
determination of excess compensation for the following reasons. We find
that out of the two plots acquired, plot no 81/555, 36 decimals are
recorded as rice mill while the rest are recorded as sali land. In so far as
plot no 213/466 only 52 decimals are recorded as orchard while 3.24
acres are recorded as rice mill. The respondent only has interest, to the
extent of 11.17 decimals out of 2.60 acres of land acquired. The record
of rights reveals that the land forming subject matter of acquisition was
previously held by a rice mill (Bangalaxmi rice mill). It is thus obvious
that the land that was acquired, formed part of a developed land and was
more likely, that there was less chance of variation in value of the land
so acquired. As such it was not necessary for the learned Judge to
provide for individual market value as per classification of land. We find
from the judgment impugned that the learned Judge has not awarded
Rs.80,000 per decimal, although the respondent had been able to prove
market value of land up to Rs.80,000/- per decimal. We are of the view
that the learned Judge obviously factored in the minor variations on
account of the classification of land, while determining market value. It
is well settled that the Court may make some guess work before it could
arrive at a final determination, which is in consonance with statutory law
as well as principal stated in judicial pronouncements. The principal is
only intended to bridge the gap between calculated compensation and
the actual compensation, that the claimant may be entitled to receive as
per the facts of their case, to meet ends of justice.
25. More often, than not, it is not possible to fix the compensation with
exactitude or with arithmetic accuracy. It is in such circumstances an
estimate is made based on mixture of calculations. We find that
sufficient evidence has been led in the instant case on behalf of the
respondent to prove market value of the land. On the other hand, the
appellant has not led any oral evidence. We also find from evidence
adduced by the parties, that in the year 1979 construction of milk
chilling plant was started at the site were Bangalakhmi Rice Mill, was
situated, as such we do not find any irregularity on the part of the
learned Judge in not determining market value of land for the individual
classification of land.
26. Propositions of law as laid down in the judgments cited by the
appellant are well settled. The judgment reported in the case of Shaji
Kuriakose & Anr. (Supra) and Siddappa Vasappa Kuri & Anr. (Supra)
are otherwise distinguishable from the facts of this case. A little variation
in facts may alter the very basis of a judgment. The judgment delivered
in the case of R. L Jain (Supra), however, takes into consideration the
peculiar circumstance of a case, where a landowner is dispossessed prior
to issuance of notification under section 4(1) of the Act I 1894. The
Hon'ble Supreme Court has categorically provided, that in cases where
the possession is taken over prior to issuance of notification under
section 4(1) of Act I, 1894, it would be just and equitable for the Collector
to determine rent or damages for use of the property for the period the
government retains possession of the same, to which the landowner is
otherwise entitled to. It is also well settled that Order 41 Rule 33
enables the appellate Court to pass any decree or order which ought to
have been made in the circumstances even if such decree would be in
favour of the parties who have not filed any appeal [See the judgment
delivered in the case of K. Muthuswami Gounder (Supra)].
27. We find that the judgment delivered in the case of R.L. Jain (Supra)
had been considered by the Hon'ble Supreme Court in the case of
Balwan Singh & Ors. (Supra) and it had been held that payment of
interest for the period from the date of dispossession to the date of
notification under section 4(1) of Act I 1894, is no longer res-integra.
Similar such view has been taken in the case of Madishetti Bala Ramul
(Dead)1 LRS (Supra) and in all such cases additional interest @ 15% per
annum on the amount awarded by the Collector, had been directed to be
paid for the period between date of dispossession and the date of
notification under section 4(1) of Act I 1894. There has thus been a
consistent view taken by the benches after R.L. Jain (Supra) that the
claimant can be compensated @ 15% from the date of dispossession till
the date of notification under section 4(1) of Act I 1894 on the basis of
the market value so ascertained.
28. Applying such proposition of law to the facts of the case, we are of
the opinion that it would be appropriate to direct the Collector to make
payment of compensation by awarding an additional interest @ 15% per
annum instead of 12% as directed, on the market value of land on and
from the date possession of the land was taken over till the date of
issuance of notification under section 4 of Act I 1894. The impugned
judgment and decree are accordingly modified. The other directions
contained in the said judgment and decree shall remain unaltered.
29. The appellant is directed to make payment of the balance amount
along with interest to the respondent in terms of the judgment and
decree of the learned Court below, as modified hereinabove.
30. We further direct that the Registrar General shall cause the sum
lying with him/her to the credit of the aforesaid appeal be immediately
released in favour of the respondent along with accrued interest thereon
after deducting commission payable, if any. The respondent shall be
entitled to recover the aforesaid commission amount from the appellant.
31. With the aforesaid direction and observations, the appeal is
disposed of.
32. The department is directed to draw up the decree, accordingly.
33. Urgent Photostat copy of this judgment, if applied for, be made over
to this parties, as expeditiously as possible, upon compliance of
formalities in that regard.
(Raja Basu Chowdhury, J.) (Tapabrata Chakraborty, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!