Citation : 2022 Latest Caselaw 2502 Cal
Judgement Date : 4 May, 2022
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
W.P.A. No.3360 of 2022
Dimension Steel and Alloys Limited and another
Vs.
Damodar Valley Corporation and others
For the petitioners : Mr. Joy Saha,
Ms. Sanchari Chakraborty,
Mr. Soumik Chakraborty,
Mr. Ayan Sarkar,
Mr. Ishaan Saha
For the respondent no.5 : Mr. Anuj Singh,
Mr. Aman Agarwal
Hearing concluded on : 01.04.2022
Judgment on : 04.05.2022
Sabyasachi Bhattacharyya, J:-
1. The writ petitioner has primarily prayed for immediate restoration of
the petitioner's electricity supply by the Respondent no. 1, the
Damodar Valley Corporation (DVC).
2. The brief facts, shorn of unnecessary details, are:
3. The DVC, upon prior notice, disconnected the electricity supply to the
factory premises of the petitioner no. 1-company on June 7, 2019.
4. On October 18, 2019, the petitioner no. 1 was admitted to a Corporate
Insolvency Resolution Process (CIRP). On April 8, 2021, the
Committee of Creditors approved the Resolution Plan. The NCLT
approved the same on October 8, 2021.
5. Thereafter the Resolution Professional wrote to the DVC tendering
payment of Rs. 7,45,608/- as per the approved Resolution Plan and
requested reconnection of electricity, which request was reiterated by
a later communication by the petitioner no. 1.
6. However, the DVC, by its letter dated November 25, 2021, demanded
payment of Rs. 31,77,33,915/- as outstanding dues of electricity
charges from the petitioner no. 1.
7. The learned Senior Advocate appearing for the petitioners places
reliance on Ghanshyam Mishra & Sons (P) Ltd. V. Edelweiss Asset
Reconstruction Company Ltd. [(2021) 9 SCC 657] and Committee of
Creditors of Essar Steel India v. Satish Kumar Gupta [(2020) 8 SCC
531] and submits that all the pre-existing debts of a creditor stand
extinguished upon the approval of a Resolution Plan. In this context,
the petitioners also rely on the following judgments:
(i) Ruchi Soya Industries v. Union of India (Civil Appeal Nos. 447-
448 of 2013)
(ii) DVC v. Kharkia Steel Pvt. Ltd. [Company Appeal (AT) Insolvency
No. 119 of 2022]
(iii) DVC v. Karthik Alloys Ltd. [Company Appeal (AT) Insolvency No.
13 of 2021
(iv) Shiv Shakti Inter Globe Exports Pvt. Ltd. V. ktc Foods Pvt. Ltd.
[Company Appeal (AT) Insolvency No. 650 of 2020
(v) Sri Vasavi Industries Limited and Another v. WBSEDCL [WPA No.
1936 of 2022]
8. The learned Senior Advocate for the petitioners secondly contends that
Clause 4.6.4 of the West Bengal Regulatory Commission (Electricity
Supply Code) Regulation 2013, on the basis of which the DVC makes
its claim, is contrary to the objectives and provisions of the Insolvency
and Bankruptcy Code (IBC), 2016 and is, thus, hit by Section 238 of
the IBC, which gives the IBC primacy over other laws, including the
Electricity Act, 2003. In support of such submission, the petitioners
cite Paschimanchal Vidyut Vitran Nigam Ltd. V. Raman Ispat Pvt. Ltd.
&Ors. [2019 SCC OnLine NCLAT 883].
9. For effective revival of the debtor company, the Resolution Plan is
binding with immediate effect from its approval by the NCLT on
October 8, 2021, it is argued. Moreover, Section 43 of the Electricity
Act, 2003 mandates the DVC to restore supply of power, since the
claims of the DVC stand extinguished in law.
10. Moreover, it is contended by the petitioners, the DVC has accepted the
amount of Rs. 7,45,608/- tendered by the petitioners and is now
estopped from claiming its pre-CIRP dues as a pre-condition for
restoring electricity supply.
11. The learned Senior Advocate appearing for the petitioners contends
that although an appeal against the order approving the Resolution
Plan is pending at the behest of the DVC before the NCLAT, no stay of
operation of the said order of approval has been passed in the appeal.
On or about January 31, 2022, the NCLAT recorded that the present
petitioners were not proposing to file any contempt application against
the DVC. However, it is submitted that the said recording cannot
debar the writ court from passing any order.
12. Since no contravention of any condition of license has been alleged in
the present case, Section 129 of the 2003 Act is not applicable, it is
argued. Moreover, neither the Grievance Redressal Officer under
Section 42 (5) nor the Ombudsman under Section 42 (6) of the 2003
Act are competent to determine the legal question as to whether or not
the dues of the DVC in respect of a pre-CIRP period survives after the
approval of the Resolution Plan.
13. To stress upon the wide discretionary powers of the High Court under
Article 226 of the Constitution of India, learned senior counsel places
reliance on Maharashtra Chess Association v. Union of India [(2020) 13
SCC 285].
14. On the other hand, the learned Senior Advocate appearing for the
DVC relies on the pendency of the appeal before the NCLAT, against
the order of the NCLT approving the Resolution Plan, as a deterrent in
the petitioners virtually seeking implementation of the said impugned
order of approval.
15. The power supply agreement between the petitioner no. 1 and the
DVC, it is contended, stood terminated independently of the ground of
insolvency, by operation of Clause 4.6.1. of the West Bengal Electricity
Regulatory Commission (Electricity Supply Code) Regulations, 2007,
read with Clause 23 of the said agreement.
16. Even as per Essar Steel (supra), relied on by the petitioners, it is
argued that the Supreme Court treated electricity dues as distinct and
separate from dues of other operational creditors, for which the former
has primacy over the Resolution Plan.
17. The learned Senior Advocate for the DVC next relies on Gujarat Urja
Vikas Nigam's Case, reported at (2021) 7 SCC 209. The Supreme
Court held there that the power purchase agreement was terminated
solely on the ground of insolvency, since the event of default
contemplated under Article 9.2.1(e) was the commencement of
insolvency proceedings against the corporate debtor. In the absence of
the insolvency of the corporate debtor, there would be no ground to
terminate the agreement, since the termination was not on a ground
independent of the insolvency.
18. Applying the same ratio, it is argued, the present claim of the
petitioners for restoration of electricity supply should also be turned
down.
19. As far as the decisions cited by the petitioners are concerned, the
learned Senior Advocate for the DVC submits that there is no
inconsistency between those and Gujarat Urja Vikas Nigam (supra).
20. In DVC v. Karthik Alloys (supra), the DVC had disconnected supply
during the moratorium period, as opposed to the present case, where
such disconnection was earlier.
21. In Sri Vasavi Industries (supra), it is contended, Gujarat Urja (supra)
was not considered.
22. Lastly, learned senior counsel appearing for the DVC submits that the
undertaking given by the petitioners that they will not initiate
contempt proceedings during pendency of the appeal before the
NCLAT, by necessary implication, includes filing the writ petition for
implementation of the directions given by the NCLT.
23. In reply, the learned Senior Advocate for the petitioners seeks to
distinguish Gujarat Urja (supra) on the ground that the ratio decidendi
in the said case and the issues involved in the present matter are
different. There, the question decided was whether the inherent power
of the Tribunal embodied in Section 60(5) of the IBC can be used to
oust all powers vested in regular Courts and Tribunals. However, in
the present case the issue is not whether the termination of electricity
was relatable to the CIRP, but whether the claim of dues of the DVC
still survives or has been extinguished and, if so extinguished,
whether DVC has a mandatory obligation to supply electricity in terms
of Section 43 of the 2003 Act.
24. Upon hearing the contesting parties, this court decides as follows:
25. Gujarat Urja (supra) was on a different footing, inasmuch as the
context was the termination of a power purchase agreement in
exercise of the powers of the Tribunal under Section 60(5) of the IBC,
whereas, in the present case, the germane issues are, whether the
pre-CIRP claims of the DVC survives the acceptance of the approval of
the Resolution Plan and what is the effect of the pendency of the
appeal against the order of approval before the NCLAT and the
'undertaking', if any, made before it on behalf of the petitioners.
26. In the present case, there does not arise any question of the power
purchase agreement itself being terminated. Section 238 of the IBC
clearly provides that the provisions of the said Act shall have effect,
notwithstanding anything inconsistent therewith contained in any
other law for the time being in force or any instrument having effect
by virtue of any such law.
27. A harmony can be struck between the ratio of Gujarat Urja (supra) and
the proposition reiterated in Essar Steel (supra) onwards to Sri Vasavi
(supra), in the context of the facts of the present case.
28. As per Gujarat Urja (supra), the NCLT cannot oust the powers of any
other statute by virtue of its inherent powers under Section 60(5) of
the IBC. Instead of having any quarrel with the said proposition, let us
proceed by accepting the same.
29. In the present case, admittedly, the disconnection of the electricity
supply of the petitioner no. 1 took place prior to the commencement of
the CIRP.
30. The "dues" claimed under Section 56 of the 2003 Act pertain to the
juncture of such disconnection. Section 56 of the 2003 Act confers
dual rights on the licensee - first, to recover the dues and secondly, to
withhold reconnection of electricity till repayment of such dues. Thus,
both the said rights are dependent on the single touchstone - "dues",
which relate to electricity and other charges due from the consumer at
the time of disconnection. Admittedly, in the present case,
disconnection took place prior to commencement of the CIRP; hence,
the dues are pre-CIRP debts.
31. Section 56 further provides that the electricity supply may be
discontinued "until such charge or other sum, together with any
expenses incurred by him in cutting off and reconnecting the supply,
are paid" but no longer. The expression "such charge" refers to the
first part of the section which relates the charge to the time of
disconnection. Insofar as the electricity charges and disconnection
charges are concerned, those obviously refer to the juncture of
disconnection. However, only the reconnection charges, by definition,
are incurred at the time of restoration of connection.
32. Hence, in the present case, as per the scheme of the IBC, as
interpreted in the light of the judgments cited by the petitioners,
including Essar Steel (supra), Ghanshyam Mishra (supra), Sri Vasavi
(supra), etc., all pre-CIRP debts (in other words, "dues") are
extinguished once and for all by approval of the Resolution Plan, so
that hydra heads of new debts do not confront the successor of the
consumer-company even after the approval of the Resolution Plan by
the NCLT.
33. This is not a case of ouster of the powers of the licensee conferred by
the 2003 Act. Even if such powers under Section 56 of the 2003 Act
remain intact, those become illusory in view of the dues themselves
having been extinguished on the approval of the Resolution Plan, by
independent operation of the IBC. Thus, even if the DVC retains its
powers to recover debts and/or withhold electricity supply till the
dues are cleared, there remain no dues to be cleared, since all pre-
CIRP debts of the petitioner no.1-company, that is, the successful
resolution applicant stand extinguished.
34. Thus, the DVC acted without jurisdiction and de hors the law in
further withholding the electricity supply of the petitioner no.1.
35. Insofar as the pendency of the appeal before the NCLAT against the
order of the NCLT approving the Resolution Plan is concerned, it is
well-settled that mere pendency of an appeal does not operate of its
own as a stay. In the absence of any specific stay order being passed
in the appeal, there is no impediment to the petitioners asserting their
right of immediate resumption of business in terms of the approved
Resolution Plan.
36. The so-called undertaking before the NCLAT was a mere submission
that no contempt proceeding shall be initiated against the DVC. It is
well-known that the contempt jurisdiction is penal in nature and is
distinct and different from execution or implementation of an order.
Even without initiating any contempt proceeding, the petitioners are
fully at liberty to seek implementation of the validly approved
Resolution Plan until, if at all, the same is set aside by the NCLAT.
37. That apart, the balance of convenience and inconvenience is squarely
in favour of directing the DVC to restore electricity connection
immediately to ensure that the valid Resolution Plan is given effect to
and, more importantly the previously going concern does not suffer a
serious set-back again, despite the approval of the corporate
resolution plan, due to sitting idle for dearth of power supply. On the
other hand, if the DVC restores electricity supply, the same will not be
an irreversible act, so much to the detriment of the DVC that it would
suffer substantial hardship.
38. Another determinant is the acceptance of the DVC of the amount of
Rs. 7,45,608/- on November 8, 2021, that is, after and in terms of the
order of approval of the Resolution Plan by the NCLT on October 8,
2021. Such acceptance of the amount can definitely be construed as
waiver of the right of the DVC, if there was any, to discontinue
electricity supply.
39. Thus, in the light of the above observations, W.P.A. No.3360 of 2022 is
allowed, thereby directing the Damodar Valley Corporation
(Respondent no. 1) to restore the electricity supply of the writ
petitioner no. 1-company at the earliest, positively within four weeks
from date, subject to payment of the reconnection charges by the
petitioner no. 1. However, such restoration of connection shall be
subject to the final result of the appeal pending at the behest of the
DVC before the NCLAT which will, in turn, affect the approval of the
Resolution Plan itself, which has extinguished the prior debts of the
petitioner no. 1-company as of now, unless set aside.
40. There will be no order as to costs.
41. Urgent certified copies of this order shall be supplied to the parties
applying for the same, upon due compliance of all requisite
formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!