Citation : 2022 Latest Caselaw 1628 Cal/2
Judgement Date : 18 May, 2022
IN THE HIGH COURT AT CALCUTTA
CIVIL APPELLATE JURISDICTION
(Original Side)
A.P.O No. 11 of 2022
With
W.P.O No. 1231 OF 2021
IA No.: GA 1 of 2022
(Through Video Conference)
Reserved on : 08.04.2022
Pronounced on: 18.05.2022
NBCC (India) Ltd..
...Appellant
-Vs-
The State of West Bengal & Ors. ...Respondents
Present:-
Mr. Arnab Chakraborty, Ms. Pragya Bhowmick, Advocates .... for the Appellant
Mr. Samrat Sen, Sr. Advocate, Mr. Soumitra Mukherjee, Advocate ..... for the State of WB
Mr. Jishnu Chowdhury, Mr. Samim Ahmed, Md. Danish Taslim, Mr. Shahrukh Raja, Mr. Souradeep Banerjee, Ms. Somashree Dey, Advocates
Coram: THE HON'BLE JUSTICE PRAKASH SHRIVASTAVA, CHIEF JUSTICE THE HON'BLE JUSTICE RAJARSHI BHARADWAJ, JUDGE
- -2 -
APO 11 OF 2022
Rajarshi Bharadwaj, J:
1. The instant writ petition has been filed in the Original side of this
Hon'ble Court. The appellant/writ petitioner being aggrieved by and
dissatisfied with the order dated 16.12.2021 as modified by another order
dated 24.12.2021 passed by the Hon'ble Justice Rajasekhar Mantha in
WPO No.1231 of 2021 has preferred the instant appeal.
2. The facts in a nutshell are that the appellant/writ petitioner, herein
NBCC (India) Limited, a Government of India enterprise during a time
period of 30.07.2015 to 19.08.2016 had issued four work orders of
different values, inter alia, awarding respondent no.4, herein Saket Infra
Developers Private Limited for undertaking the same. Again, on
15.09.2017, the appellant awarded the work contract of MSTC Building
at New Town to respondent no.4.
3. On 19.11.2016, the respondent no.4 registered itself as a small
enterprise under the Micro, Small and Medium Enterprises Development
(MSMED) Act, 2006. Amongst the five work orders undertaken by
respondent no.4, two have been terminated for breach of contract by the
respondent no.4 and the work has been taken up by new agencies at the
risk and cost of the respondent no.4. However, two project works are still
continuing and one has been completed. Furthermore, some disputes and
discords have arisen between the appellant and the respondent no.4 in
connection with the aforesaid five contracts out of which the MSTC
Limited's project work has already culminated into a commercial suit
before the Commercial Court at Rajarhat. The respondent no.4 in
connection with all the aforementioned five projects, had lodged a claim
before the respondent no.2, herein the Chairman of the West Bengal
- -3 -
APO 11 OF 2022
State Micro and Small Enterprise Facilitation council under the
MSMED Act to which the appellant objected on the ground of
maintainability and also made representation for recalling of the order of
reference on jurisdictional grounds. However, upon the receipt of the
claim the authorities took cognizance and on failure of the conciliation
sought to initiate statutory arbitration.
4. On 22.09.2021, the respondent no.2 issued a notice fixing the first
date of arbitration under the said MSMED Act, referring disputes and
differences to Arbitration under five several contracts with the respondent
no.4 under Section 18(2) and 18(3) of the MSMED Act, 2006 which states
:
"18. Reference to Micro and Small Enterprises Facilitation Council.--
(1) Notwithstanding anything contained in any other law for the time
being in force, any party to a dispute may, with regard to any
amount due under section 17, make a reference to the Micro and
Small Enterprises Facilitation Council. (2) On receipt of a reference
under sub-section (1), the Council shall either itself conduct
conciliation in the matter or seek the assistance of any institution or
centre providing alternate dispute resolution services by making a
reference to such an institution or centre, for conducting conciliation
and the provisions of sections 65 to 81 of the Arbitration and
Conciliation Act, 1996 (26 of 1996) shall apply to such a dispute as if
the conciliation was initiated under Part III of that Act. (3) Where the
conciliation initiated under sub-section (2) is not successful and
stands terminated without any settlement between the parties, the
Council shall either itself take up the dispute for arbitration or refer it
to any institution or centre providing alternate dispute resolution
services for such arbitration and the provisions of the Arbitration and
Conciliation Act, 1996 (26 of 1996) shall then apply to the dispute as
- -4 -
APO 11 OF 2022
if the arbitration was in pursuance of an arbitration agreement
referred to in sub-section (1) of section 7 of that Act."
5. However, the appellant again objected on some elementary issue
stating that the respondents cannot proceed under the MSMED Act and
further, on the date of the awarding of the four work contracts, the
respondent no.4 was not registered under the said act and thus, as per
the decision of the Hon'ble Supreme Court, the MSME Authorities cannot
proceed under the said Act. By a letter dated, 30.09.2021, it was further
requested by the appellant to the respondents to not proceed, till the date
the impugned order has not been recalled. Owing to which the
respondent no.4 filed a rejoinder against the letter dated 30.09.2021.
6. The appellant/writ petitioner preferred an application under
Section 226 of the Constitution of India with the following prayers:
(a) A Writ of or in the nature of Mandamus do issue
directing the respondent No.2 and 3 and each one of them,
their men, agents, assigns or sub-ordinates to recall the
order dated 19.01.2021 (being Annexure "P-5") and
22.09.2021 (being Annexure "P-9") and to set aside
and/or rescind the order by which they assumed the role
of arbitrator in the present case for want of requisite
jurisdiction;
(b) A Writ of or in the nature of Certiorari do issue
commanding the respondent No.2 and 3 and each one of
them, their men, agents, assigns, sub-ordinates to certify
and transmit all documents pertaining to the orders dated
19.01.2021 (being Annexure "P-5") and 22.09.2021 (being
Annexure "P-9") by which the respondent authorities have
- -5 -
APO 11 OF 2022
tried to enter into an Arbitral reference under the said
MSMED Act, 2006, before this Hon'ble Court so that
conscionable justice may be administered by quashing the
said orders and/or decisions stated in the order dated
19.01.2021 and 22.09.2021;
(c) A Writ of or in the nature of Mandamus do issue
directing the respondents specifically respondent No.2 to
decide on the preliminary objections regarding the
maintainability and the jurisdictional issues as raised by
the petitioner, before entering into any arbitral reference in
the matter;
(d) A Writ of or in the nature of Prohibition do issue
prohibiting the respondents especially the respondent No.2
and 3 and each one of them, their men, agents and
sub-ordinates etc. from continuing with the reference of
arbitration which has been sought to be commenced by
the letter 19.01.2021 upon termination of the purported
conciliation proceeding and further prohibit them from
taking any coercive steps or passing any penal order or
impose any order against the petitioner;
(e) A Writ of or in the nature of Mandamus do issue
directing the respondent No.2 and 3 and each one of them
to consider the jurisdictional issue and objection raised by
the defendant before proceeding any further with the
reference upon giving the petitioner an opportunity of
personal hearing without taking the same as a proceeding
before the Arbitral Tribunal;
- -6 -
APO 11 OF 2022
7. After hearing all the parties, the Learned Single Judge passed his
order on 16.12.2021. Thus, being aggrieved by the Order and Judgment
of the Learned Single Judge as modified by the order dated 24.12.2021,
the instant petition has been filed. The appellant raised a preliminary
objection regarding the jurisdiction of the Facilitation council and the
maintainability of the entire proceeding under the MSMED Act. From the
very inception, the appellant has categorically taken its preliminary
objection that no proceeding is maintainable before the Facilitation
Council constituted under the MSMED Act so far as the work contract
between the parties is concerned. It was contended that the MSMED Act,
2006 has no manner of application apropos the 'Work Contract' since
neither section 11 nor the Public Procurement Policy, 2012 envisages a
composite and distinct category of contracts such as work contract.
8. It was held in Kone Elevator India Private Limited v. State of Tamil
Nadu reported in 2014(7) SCC 1 that " the work contract is an individual
contract but, by legal fiction, is divided into two parts, one for sale of
goods and the other for supply of labour and services."
9. As held in Principal Chief Engineer vs M/S Manibhai and Bros
(Sleeper) reported in MANU/SCOR/24287/2017, The Supreme Court
upheld the Gujarat High Court's judgment on the interpretation of
Section 18 of the Act. The High Court held that since the Act is a special
legislation and has an overriding effect, the parties governed by it are
bound to follow the mechanism provided under Section 18 of the Act. It
was further reiterated in Mackintosh Burn Limited v. Micro and Small
Enterprises Facilitation Council reported in 2020 (209) AIC323.
- -7 -
APO 11 OF 2022
10. The Learned Single Judge rightly observed that "without prejudice
to any of the rights and contentions of the writ petitioner, the petitioner
shall participate in arbitration and that the Tribunal shall decide on its
jurisdiction on inter alia the questions raised by the writ petitioner before
entering into other questions."
11. We are not interferring with the order of the Learned Single Judge
and the appeal is dismissed. All other applications connected thereto are
also dismissed.
(PRAKASH SHRIVASTAVA) CHIEF JUSTICE
(RAJARSHI BHARADWAJ) JUDGE
Kolkata 18.05.2022 PA(BS)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!