Citation : 2022 Latest Caselaw 1192 Cal
Judgement Date : 15 March, 2022
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
WPA No. 19019 of 2021
M/s. Bengal Energy Limited & Anr.
Vs.
The West Bengal Electricity Regulatory
Commission & Ors.
With
WPA No. 21013 of 2021
Tata Power Company Limited (Haldia) & Anr.
Vs.
West Bengal Electricity Regulatory Commission
For the petitioners
in WPA 19019 of 2021 : Mr. Saktinath Mukherjee,
Mr. Rahul Karmakar,
Mr. Aasish Chowdhury,
Ms. Aindrila Basu
For the petitioners
in WPA 21013 of 2021 : Mr. Sanjoy Sen,
Mr. Anand Srivastava,
Mr. R. Elwin,
Ms. Neha Dabral,
Mr. Shivam Sinha,
Mr. Avik Ghatak,
Mr. Kumarjeet Ray
For the WBERC : Mr. Pratik Dhar,
Ms. Sharmistha Ghosh,
Mr. Victor Chatterjee
2
For the WBSEDCL : Mr. Jishnu Chowdhury
Mr. Chayan Gupta
Mr. Sandeep Dasgupta
Mr. Saaqib Siddqui,
Mr. Ariroop Mitra
For the CESC Limited : Mr. Shounak Mitra,
Mr. Zulfiqar Ali,
Ms. Prerona Banerjee
For the State : Mr. Anirban Roy,
Ms. Amrita Panja Moulick
For the respondent no.7 : Mr. Bratin Kumar Dey,
Hearing concluded on : 18.02.2022
Judgment on : 15.03.2022
Sabyasachi Bhattacharyya, J:-
1. The present writ petitions have been taken out primarily against the
2020 amendments brought by the West Bengal Electricity
Regulatory Commission (WBERC) to the WBERC (Co-generation of
Electricity from Renewable Sources of Energy) Regulations, 2013,
that is, Regulation No.50 dated March 22, 2013.
2. A consequential challenge has also been preferred against the
September 2, 2020 Order which was passed by the WBERC suo
moto in Case No. SM - 24/20-21, on the basis of which the
amendment was allegedly brought.
3. Certain ancillary reliefs have also been claimed by the writ
petitioners in their respective petitions.
4. It is argued on behalf of the petitioners, who are co-generating
companies of electricity, is that a body corporate can express itself
only through a resolution. By placing reliance on the case of The
Vice-Chancellor, Utkal University and others Vs. S.K. Ghosh and
others, reported at AIR 1954 SC 217, it is contended that the order
of the State Commission, on the basis of which the 2020
Amendment was brought in, is not a reasoned order. The learned
Senior Advocate appearing for the writ petitioners seeks to draw
support from Regulation 2.14 of the WBERC (Conduct of Business)
Regulations, 2013, which provide for reasons to be given by the
Commission in support of its orders.
5. It is next argued by the writ petitioners that the Lloyd's case dated
December 2, 2013, rendered by the Appellate Tribunal for
Electricity (APTEL), was passed in an appeal against an interim
order. By placing reliance on Empire Industries Limited and others
Vs. Union of India and others, reported at AIR 1986 SC 662 and
State of Assam Vs. Barak Upatyaka D.U. Karmachari Sanstha,
reported at (2009) 5 SCC 694, it is contended that decisions taken
in interim orders are not precedents.
6. The writ petitioners further argue that Section 86(1)(e) of the
Electricity Act, 2003 (hereinafter referred to as 'the 2003 Act')
requires the Commission to promote co-generation and generation
of electricity from renewable sources of energy by suitable
measures. It is contended that the National Tariff Policy, 2016,
promulgated on January 28, 2016, by its proviso to Clause 6.4(1),
rendered the Lloyd's case's decision inoperative.
7. It is submitted that Section 181 of the 2003 Act requires the
Regulations framed by the State Commissions to be consistent with
the parent Act and Rules. Section 86(4) of the 2003 Act also
requires that, in the discharge of its functions, the State
Commission shall also be guided by the tariff policy.
8. It is argued that on July 15, 2021, the Government of West Bengal
issued a direction under Section 108 of the 2003 Act upon the State
Commission in public interest, which was neither refuted nor
heeded by the WBERC. The writ petitioners cite Real Food Products
and others Vs. A.P. Electricity Board and others, reported at (1995) 3
SCC 295, for the proposition that such directions of the State
Government are binding on the State Commission. Section 78A of
the 1948 Act (on which the said decision was rendered), it is
submitted, is similar in scope with Section 108 of the 2003 Act
(which is applicable to the instant case).
9. It is contended that the proviso to Clause 6.4(1) of the tariff policy
clearly stipulates that co-generation cannot be excluded from the
benefit of Renewable Purchase Obligations (RPO). However, by the
impugned amendment, the State Commission altered several
clauses, which placed 'co-generation' on equal footing with
'renewable sources', and excluded co-generation from the purview of
RPO.
10. That apart, the expression "industrial waste" was excluded in the
2020 amendment from the purview of the definition of "renewable
sources".
11. The writ petitioners have co-generating units of electricity which are
primarily powered by industrial waste. As such, the petitioners'
interests are directly hit by the impugned amendment.
12. It is further contended that the APTEL (Appellate Tribunal for
Electricity), in JSW Steel Limited Vs. Tamil Nadu Electricity
Regulatory Commission, reported at 2021 SCC OnLine APTEL 38,
discussed the observations made by it in Century Rayon Vs. MERC
(Appeal No.252 of 2018) dated January 28, 2020 and further
explained the scope of the Lloyd's case (supra). It is submitted that
the APTEL, in JSW (supra), took into consideration Section 86(1)(e)
of the 2003 Act and observed that the co-generating plants are
required to be treated at par with renewable energy generating
plants. Irrespective of the nature of fuel used in the co-generation
process to generate power, co-generation has to be encouraged and
promoted in terms of Section 86(1)(e) of the Act, it was held. Thus,
co-generation plants, it was concluded, cannot be fastened with the
liability of purchasing power of renewable sources to meet its RPO
obligations irrespective of the fuel used.
13. It is contended that Lloyd's case (supra) was rendered in the context
of the Maharashtra Regulations, which did not include co-
generation in the definition of renewable energy source. On such
basis, the APTEL, in Lloyd's case (supra), held that co-generation
could not be included within the ambit of renewable sources.
However, the 2013 Regulations of the WBERC clearly mandated, as
opposed to the Maharashtra Regulations, that co-generation and
renewable sources are to be treated at par. Hence, the WBERC
acted patently without jurisdiction in placing reliance solely on the
Lloyd's case, which was not relevant in the context, to bring about a
sea change in its own regulations.
14. It is next contended that there is nothing intrinsic in the concept of
renewable energy which precludes the inclusion of industrial waste,
as directed by the State of West Bengal under Section 108 of the
Act. It is argued that the directions under Section 108 are binding
on the WBERC.
15. Learned counsel, in the above context, places reliance on the
definition of "co-generation" and "generate" as given in sub-sections
(12) and (29) of Section 2 of the 2003 Act. It is argued that in
Section 61(g), pertaining to tariff regulations and Section 86(1)(e),
dealing with functions of the State Commission, promotion of co-
generation and generation of electricity from renewable sources of
energy have been equated.
16. It is submitted that the doctrines of promissory estoppel and
legitimate expectation were violated by the WBERC in approving the
agreements of the writ petitioners for co-generation even
subsequent to the Lloyd's case and, in the same breath, permitting
RPO to be applicable to such co-generation, contrary to the
provisions of the agreements.
17. Articles 14 and 19 of the Constitution of India, it is argued, were
violated by the WBERC by dint of the 2020 Amendments, by
excluding co-generation from the scope of RPO.
18. By virtue of the 2020 Amendments, a distinction was brought about
between co-generation from renewable sources and non-renewable
sources. The specific stipulations in the Preamble as well as
Section 86(1)(e) and the other provisions of the 2003 Act, which
treat co-generation and renewable source at par insofar as
promotion is concerned, were thus flouted.
19. It is argued that, being contrary to the National Tariff Policy, 2016
as well as the 2003 Act and the judgments prevailing in the field,
the impugned amendments of 2020 ought to be set aside.
20. Learned counsel for the writ petitioners argue on the contemporary
evolution of the concepts of co-generation and generation of
electricity vis-à-vis renewable sources. Although co-generation is
defined as a process which simultaneously produces two or more
forms of useful energy (including electricity), generate means to
produce electricity from a generating station for the purpose of
giving supply to any premises or enabling a supply to be so given.
Hence, the process of co-generation has not been distinguished
inter se on the ground of its sources, renewable or otherwise, from
the inception in the statute as well as West Bengal Regulations.
However, by the 2020 amendments, such sub-classification has
been incorporated by the WBERC, which is contrary to the law and
not based on either the definition clause or anywhere else in the
statute.
21. By placing the relevant provisions from the 2013 and 2020
Regulations, the writ petitioners contend that wherever "co-
generation" and "renewable sources" were mentioned
simultaneously, qualified by the conjunction "and" or "and/or", the
2020 amendment has deleted the expression "co-generation",
thereby excluding co-generation from the purview of RPO.
22. It is submitted that a previous writ petition, challenging the 2020
amendments, was not pressed by the petitioners solely in view of
the State Government directions under Section 108, which had
come in the meantime. However, the WBERC blatantly flouted the
said directions of the State Government, de hors the law.
23. The CESC Limited, being a respondent in the writ petitions,
supports the contention of the writ petitioners.
24. The learned Senior Advocate appearing for the WBERC contends
that the 2020 amendment has been brought about in consonance
with similar provisions in several other State Regulations, including
Assam, Arunachal Pradesh, Chhattisgarh, Delhi, Gujarat, Haryana,
Jharkhand, Kerala, Meghalaya, Nagaland, Odisha, Tripura,
Uttarakhand and Uttar Pradesh. It is contended that in all the said
Regulations, "renewable energy sources" means the usual sources
such as small hydro, wind, solar as well as bio-mass, bio-fuel co-
generation and urban or municipal waste and other sources as
recognised or approved by the Ministry of New and Renewable
Energy (MNRE).
25. It is contended that the Lloyd's case (supra) could not be confined
to the interim stage of the said mater, since a proposition of law was
settled in the said judgment of the APTEL. The present
amendment, it is argued, rightly segregates between co-generation,
which is merely a process of generation and renewable sources,
which pertains to the resources used in production of electricity.
26. The distinction between co-generation from renewable and non-
renewable sources is sought to be justified by the learned Senior
Advocate appearing for the WBERC on the ground that the
renewable source co-generation plants fall within the broader
category, "renewable sources" and are, thus, entitled to RPOs.
However, co-generation from non-renewable sources does not merit
such special incentive as applicable to renewable sources.
27. It is further contended by the WBERC that, in consonance with the
contemplation in the 2003 Act and the Tariff Regulations,
exemptions were given to co-generation. Promotion of fossil fuel
based co-generation, for example, can be found in the amended
Regulation at Clause 4.2, which stipulates that the purchase of
power from such co-generation plants would be subject to the
ceiling price specified in the Regulations. Although such co-
generation plants have been kept outside the purview of RPO, the
price cap for co-generation plants introduced by the amendment
offsets the gross differences in cost of production of generation and
co-generation from renewable and non-renewable sources. Whereas
co-generation is always cheaper than thermal generation, the
determination of prices has been left under the Regulations to the
mutual negotiations between the co-generators and the distribution
licensees, only subject to a ceiling price. Such price cap does not
operate as a deterrent to co-generation but is, rather, an adjunct of
promotion in view of the cheaper prices of the co-generating units.
28. It is argued that industrial waste does not come within the scope of
renewable sources.
29. The directions of the State under Section 108 of the 2003 Act, in the
present case, it is argued, are not binding on the State Commission
but only have persuasive effect.
30. It is argued by the WBERC that, without impleading the MNRE
(Ministry of New and Renewable Energy) as a party to the instant
writ petitions, the writ petitions suffer from non-joinder of
necessary party, since the MNRE is the only authority under the
law which can approve other renewable sources than the existent
ones. Despite such point having been taken categorically, at the
outset, it is argued, the writ petitioners chose not to implead the
MNRE as a party. In the event the MNRE, at any future point of
time, includes industrial waste within the scope of renewable
sources, the Commission has no issues in incorporating such
change as a part of the Regulations.
31. By placing reliance on Polyplex Corporation Limited Vs. Uttarakhand
Regulatory Commission and others, reported at (2011) SCC OnLine
APTEL 15, the Commission contends that directions of the State
Government under Section 108 of the 2003 Act are not binding to
the extent those are contrary to the statute and/or the Regulations.
32. The arguments regarding the order preceding the amendment of
2020 being devoid of reasons is not tenable in law, it is argued. The
State Commission has both adjudicatory and regulatory functions.
In the latter role, the Commission acts as a delegated legislator;
thus, such amendments to the Regulations as in the present case
are not required to be backed by any specific order, let alone
reasoned order, which could be relevant only in respect of decisions
taken in the Commission's adjudicatory capacity. In order to
elaborate the above arguments, the learned Senior Advocate for the
WBERC cites the following judgments, which are on similar
propositions:
i) (2013) SCC OnLine APTEL 147, reported at Lloyds Metal & Energy Pvt. Ltd. Vs. Maharashtra Electricity Regulatory Commission & Ors.
ii) (2011) SCC OnLine APTEL 15, reported at Polyplex Corporation Limited Vs. Uttarakhand Electricity Regulatory Commission & Ors.
iii) (2010) 4 SCC 603, reported at PTC India Limited Vs. Central Electricity Regulatory Commission.
iv) (2015) 12 SCC 611, reported at Hindustan Zinc
Limited Vs. Rajasthan Electricity Regulatory
Commission.
v) (2020) SCC OnLine APTEL 5, reported at Century
Rayon (A Division of Century Textiles and
Industries Limited) Vs. Maharashtra Electricity
Regulatory Commission through its Secretary & Anr.
vi) (2019) SCC OnLine APTEL 19, reported at JSW
Steel Limited Vs. Tamil Nadu Electricity
Regulatory Commission.
33. Upon hearing learned counsel for the parties and considering the
materials on record, the following questions fall for consideration in
the instant case:
i) Whether the direction of the State Government dated July
15, 2021 is binding on the State Electricity Regulatory
Commission;
ii) Whether the principles of promissory estoppel and/or
legitimate expectation are applicable in the present case;
iii) Whether the impugned 2020 amendments of the WBERC are
ultra vires in the context of the statute or the Constitution
of India.
34. The Central and State Regulatory Electricity Commissions
contemplated under the 2003 Act have a large degree of autonomy
and insulation from State interference. Section 108 of the 2003 Act
governs the interplay of the two. Sub-section (1) of the section
provides that, in the discharge of its functions, the State
Commission shall be guided by such directions in matters of policy
involving public interest as the State Government may give to it in
writing. Interestingly, sub-section (2) of Section 108 lends primacy
to the State Government's decision on questions "whether any such
direction relates to a matter of policy involving public interest".
35. The power conferred on the State under sub-section (2) is more
fundamental than meets the eye at the first blush; it leaves the
decision on the State Government, as to whether its own directions
relate to "matters of policy involving public interest".
36. Neither the Commission nor the Court can impose their own
notions of public policy, since the State Government has been
vested by the legislature, in its own wisdom, with the power to
decide which are matters of public policy and which are not, under
Section 108 (2) of the 2003 Act.
37. The limited domain of judicial interference is only to test the
Constitutionality and legality of such decisions. Section 108 of the
2003 Act stipulates the law. No fundamental right can be said to
have been violated by the direction of the State. "Renewable
Purchase Obligation" or "RPO", in brief, is in the nature of an
incentive which is a valid mode of economic and technological
course-correction by the Executive. Hence, any breach of Article 14
or Article 19 of the Constitution of India cannot be ideologically
imported in the context.
38. The basis of classification sought to be demarcated either by the
State, in its directions under Section 108, or the State Electricity
Regulatory Commission, in its impugned 2020 amendment of
regulations, cannot be said to be patently unreasonable.
39. The direction of the State Government in the present case is found
in the communication dated July 15, 2021. In such written
communication, the Government refers repeatedly to the directions
made therein to pertain to "public policy". Conspicuously, in
paragraph no. 4 of the communication, the State Government
clearly states that, "after carefully considering the various salient
aspects including the Industrial Development in the State, the
continued existence of the Industries which have set up the
cogeneration plant, the interest of the economy, the employment
situation and resolving the adverse impact that may be caused to
the industries as well as the DISCOMs in the fulfilment of the RPO
obligations", it "considers in the public interest that there is a
necessity to issue the directive under Section 108 of the Electricity
Act, 2003 as a policy decision of the State Government".
40. Hence, in the instant case, the directions incorporated in the
directive dated July 15, 2021 are binding on the West Bengal
Electricity Regulatory Commission since, in the notion of the State
Government those pertain to policy decisions within the
contemplation of Section 108 of the 2003 Act.
41. Hence, the first issue is answered in the positive.
42. As regards the second question, it is well settled that the principles
of promissory estoppel and/or legitimate expectation cannot be
broadened to the extent that those override the law.
43. Section 108 of the 2003 Act, as it stands, makes it amply clear that,
inasmuch as the final word as to whether a directive pertains to a
policy decision in the public interest is concerned, the same is
retained in the State Government.
44. On the other hand, Section 181 of the 2003 Act, which empowers
the State Commission to make regulations "consistent with" the
Act, by so providing, circumscribes such power by Section 108,
which mandates the Commission to be "guided by" such directions
in writing which, in the notion of the State Government, are policy
decisions in public interest. Where there is a conflict between public
policy of the Government and the technical acumen of the
Commission, the State Government has the final say in the matter
in terms of sub-section (2) of Section 108. The language of Section
108 of the 2003 Act leaves no room for discretion on the part of the
Commission when a public policy decision of the State is involved.
Such an approach is justiciable, since the public mandate behind
the Executive rationalizes its notion of 'public interest' as opposed
to the technical opinion of the Commission. Undoubtedly, the Court
is vested with the power of judicial review, but such domain is not
unbridled and has to adhere to the test of Constitutional/legal
legitimacy of such decision; otherwise there might arise an anarchy
of democracy.
45. Rule of Law is a much more cardinal principle than the legal
fictions of promissory estoppel and legitimate expectation. Hence, in
the instant case, such doctrines are not applicable.
46. The second question is, accordingly, answered in the negative.
47. In view of the above discussions, the third issue acquires supreme
importance in order to ascertain as to whether the power under
Article 226 of the Constitution ought to be exercised in the case.
48. As discussed above, Section 181, read in conjunction with Section
108, of the 2003 Act lend a legitimate legal basis to the State
directions, more so, since the previously existing 2013 Regulations
of the WBERC itself, which is in parity with the State directions,
had held the field for seven years, before the impugned
amendments were introduced in the year 2020.
49. Although the Commission was well within its competence and
authority otherwise to revisit the issue of RPO and to reframe the
particular modes of incentives to be given to cogeneration and
renewable energy sources, such authority is, in turn subjugated to
the State Government's directions, if such directions relate to
"policy decisions in public interest" from the perspective of the
Government.
50. The Wednesbury touchstone of reasonableness has to be ruled out
at the outset, since neither of the views, adopted either by the State
Government or the State Commission respectively, defy the common
man's logic. The issue, however, requires and deserves a tad more
detailed examination.
51. From the perspective of the WBERC, the existing Regulations of
2013 required a paradigm change in view of evolving circumstances.
The writ petitioners' argument, that the amendments had to be
backed by reasoned orders, does not find support in reason or law.
The State Commission, within the contemplation of the 2003 Act,
plays the dual role of an adjudicator and a regulator. In its first
capacity, the State Commission has to issue sufficiently reasoned
orders to pass the test of legality and reasonableness.
52. However, in its second Avatar, the Commission is to regulate and
frame rules which would supplant and further the cause of the
existing body of law. Delegated legislation is subtly implicit in such
regulatory functions, since the Regulations framed by the State
Commission have the force of law. However, Section 181 of the 2003
Act puts in a note of caution that the Regulations are subjugated by
the existing law. The Regulations can 'supplant' the law and acquire
a binding nature akin to delegated legislation, but can, under no
circumstance, 'supplement' or contradict the law. The 'policies'
adopted by the regulator in discharge of its functions cannot be
equated with 'public policy' enunciated by the State, although there
is an interplay, as well as intersecting spheres, between the two.
53. The Commission's viewpoint is not patently unjustified. The proviso
to Clause 6.4 (1) of the National Tariff Policy, 2016 clearly stipulates
that cogeneration from sources other than renewable sources shall
not be excluded from the applicability of RPOs. Such a provision
can be interpreted in both ways - from the demand and the supply
perspectives. It can be argued that, as per the said proviso,
cogenerating units are also subject to Renewable Purchase
obligations and have to comply therewith as distribution licensees.
However, it can equally be contended that the cogenerators, as
generating companies, are also entitled to get the benefit of the
incentivisation of RPOs keeping in parity with generators from
renewable sources of energy.
54. Again, co-generation, although defined as a "process" in the 2003
Act, can also acquire the characteristics of a "source". Taking a
pragmatic approach, a co-generation gives rise to two phases - the
first, where the cogenerators themselves utilize other resources,
either fossil fuel or renewable sources, for undertaking the process
of co-generation itself. However, at the second level, the co-
generators, by definition, "co-generate" electricity as energy. In the
latter phase, thus, the co-generation itself becomes a "source" of
electricity, to be transmitted to distribution licensees for being
distributed to the consumers. Therefore, "co-generation", in the
same breath, can signify a process using energy and a source of
energy (including electrical energy). Taken in the second sense,
such source would have characteristics of a "renewable" alternative
energy source from the perspective of a distribution licensee. From
such perspective, "industrial waste", along with municipal and
urban waste, is a renewable source of the co-generated electricity,
since such source can replenish itself with reasonable frequency.
There is no demarcation line, strictly speaking, to delineate a
renewable from a non-renewable source. The terms "renewable" and
"non-renewable" denote differences of degree and frequency of
refilling and are not pigeon-hole straitjacket entities qualitatively.
55. Hence, it would be equally valid to argue that the proviso to Clause
6.4 (1) of the 2016 Tariff Regulations indicates that the co-
generators, as generators, are entitled to get the benefit of the
incentive given in the form of RPOs which bind the distribution
licensees to the obligation to purchase their electricity from the co-
generators on an equal footing as that of renewable sources of
generation, as it would be to reason that, as per the said proviso,
the co-generators are subject to the RPO regime as distribution
licensees.
56. The sub-classification of co-generation into co-generation from
renewable and non-renewable sources does not find place in the
governing statute, that is, the 2003 Act. Even after the Lloyd's Case
(supra) judgment, the WBERC approved several co-generation
agreements of the writ petitioners, which included "industrial waste'
within the ambit of renewable sources and applied the concept of
RPO to co-generation plants as well. Thus, such sub-classification,
even if otherwise rational (since both co-generation and generation
from renewable sources may have common features), is alien to the
statute and the Tariff Regulations and is, thus, amenable to
challenge.
57. In any event, in view of the State Government directives in the
present case relating to policy decisions in public interest, at least
in the State's notion (the final arbiter of which proposition is the
Government, not the Commission, under Section 108 (2) of the
2003 Act), those are binding on the WBERC and ought to have been
implemented by the latter.
58. In the circumstances, the impugned amendment of 2020, which
substantially alters the 2013 Resolution on cardinal aspects, cannot
withstand judicial scrutiny, being contrary to the State Government
directives under Section 108 of the 2003 Act, which prevail over the
WBERC decision in terms of Section 108 of the 2003 Act. The said
amendment is, thus, bad in law and, accordingly, set aside.
59. Since various provisions of the 2020 amendment are ultra vires,
being contrary to the State Government's directions under Section
108 of the 2003 Act as well as the Electricity Act, 2003 and the
National Tariff Policy, 2016, and as such provisions are
interconnected with the other provisions of the 2020 amendment,
which, in some cases, operate as mutual checks and balances,
there is no scope of culling out the ultra vires provisions in
isolation, which would effectively demolish the entire scheme of the
Regulations. Thus, there is no other option but to strike down the
entire 2020 amendment as a whole.
60. However, it is beyond the jurisdiction of the writ court to grant the
other reliefs of declaration in respect of agreements, sought by the
writ petitioners. Hence the merits of such reliefs are not entered
into, since such a consideration would be without jurisdiction.
61. Accordingly, WPA 19019 of 2021 and WPA 21013 of 2021 are
partially allowed, thereby quashing and setting aside the impugned
Resolution, being the West Bengal Electricity Regulatory
Commission (Cogeneration and Generation of Electricity from
Renewable Sources of Energy) Regulation [Notification No.
71/WBERC] dated December 21, 2020 and reviving Notification No.
50/WBERC dated March 22, 2013 as it stood immediately prior to
the 2020 amendment.
62. All acts or action, if any, done or taken on the basis of the
impugned 2020 Resolution, stand reversed.
63. Nothing in this order shall, however, preclude the WBERC from
drawing up a fresh Resolution in consonance with the State
Government's directives.
64. The agreements of the writ petitioners, not being a valid subject
matter of the writ petitions and having never been directly
abrogated, continue to stand on their own footing subject, however,
to the consequence of the above quashing; however, no specific
declaration can be granted by the writ court on such aspect of the
matter.
65. There will be no order as to costs.
66. Urgent certified server copies of this order, if applied for, be
supplied to such applicants upon satisfaction of all requisite
formalities.
( Sabyasachi Bhattacharyya, J. )
Later
Since substantial questions of law are involved in the matter, on the
prayer of the learned Senior Advocate appearing for the WBERC, the
operation of the above judgment and order is stayed till April 30, 2022.
However, for the ends of justice, the operation of the impugned
Regulations of 2020 shall also remain stayed for the same period, that is, till
April 30, 2022.
This order be deemed to be a part of the above judgment.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!