Citation : 2022 Latest Caselaw 3413 Cal
Judgement Date : 15 June, 2022
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
W.P.A. No.16016 of 2019
Sri Prasanta Sen and another
Vs.
Ombudsman, West Bengal and others
For the petitioners : Mr. Aniruddha Sarkar,
Mr. Goutam Dey,
Ms. Sweta Bhatta
For the WBSEDCL : Mr. Srijan Nayak,
Mrs. Rituparna Maitra
Hearing concluded on : 09.06.2022
Judgment on : 15.06.2022
Sabyasachi Bhattacharyya, J:-
1. The petitioners, as partners of the firm, namely, M/s. Technocrats &
Associates, have been running business at the premises-in-question.
2. For the said purpose, the petitioners had been enjoying industrial
electricity connection from the West Bengal State Electricity
Distribution Company (WBSEDCL) (respondent no.3). The electricity
supply to the petitioners was disconnected on January 22, 2014 on
the allegation of outstanding dues of electricity charges. The
petitioners applied for taking service connection at the premises and
issued a letter to that effect to the concerned Station Manager of the
WBSEDCL on March 27, 2014, expressing the intention of clearing the
amount allegedly outstanding.
3. On several occasions the petitioners allegedly appeared in the office of
the Station Manager, but without any fruitful result. Ultimately upon
being so advised at the office of the Station Manager, the petitioners
filed a complaint with theconcerned Regional Grievance Redressal
Officer (RGRO) on February 3, 2017. Ultimately, vide Memo No.
RM/24-PNR/PG dated March 29, 2017, the RGRO decided the
complaint by directing the complainant/petitioners to pay the total
outstanding dues. However, although it was recorded by the RGRO in
his order that the petitioners had asked for compensation as per law,
such request was not dealt with specifically and/or granted by the
RGRO.
4. Being thus aggrieved, the petitioners approached the Ombudsman,
West Bengal who, vide final order dated November 20, 2018 passed in
the petitioners Representation No. W-99 AKT/2017, decided the issue
in favour of the petitioner.Upon consideration of a report filed by the
distribution licensee and coming to the finding that the allegation
against the petitioners that the premises were often closed could not
be sustained, the Ombudsman arrived at the conclusion that the
Regulatory requirements for disconnection of the service line of the
complainants had not been properly fulfilled by the distribution
licensee. The Ombudsman further directed that the WBSEDCL (the
license) shall cancel electricity bills in respect of the service
connection of the complainant from January 16, 2014 to January 30,
2014 and regenerate the same on the basis of consumption recorded
in the installed meter along with other charges as per the regulatory
provisions, without claiming any LPSC (Late Payment Surcharge) after
adjustment of payment made by the complainant, if any.
5. The electricity bills from the date of restoration of the service
connection on January 12, 2018 were directed to be cancelled and
regenerated. However, the Ombudsman, despite having found that
the petitioners were otherwise entitled to compensation, refused to
pass any order of compensation for wrongful disconnection and
delayed restoration of service connection on the ground of violation of
Regulation 15.1 of the West Bengal Electricity Regulatory Commission
(Standards and Performance of Licensee Relating to Consumer
Services) Regulations, 2010, as amended. It was observed that the
petitioners had approached with the claim of compensation beyond 90
days from the date from which compensation arises.
6. Learned counsel for the petitioners argues that the date from which
compensation arises can only be the date of restoration of the
electricity supply and payment and/or payment of the compensation.
7. Since the cause of action for compensation accrues day-to-day, it is
argued that the claim for compensation did not crystallize before the
same was paid. It is submitted that,vide Clause 21 of Regulation
No.57 dated August 26, 2013 framed by the West Bengal Electricity
Regulatory Commission (WBERC), Clause 15.1 was inserted in the
principal Regulation of 2010.
8. Clause 15.1 provides that the limitation for claiming compensation is
90 days from the date from which compensation arises. However, in
Regulation No.46 dated May 31, 2010, the original Clause 15.0, which
remained substantially the same even after the amendment of 2013,
clearly stipulated the rates at which the compensation is to be paid.
9. Thus, it is contended that since the first complaint was alleged on
March 27, 2014, which was rejected after the period of three years on
March 29, 2017 by the RGRO, the date of rejection of the claim for
compensation has to be treated as the date on which the cause of
action for compensation arises.
10. Learned counsel appearing for the distribution licensee submits that
the complaint filed by the writ petitioners is not annexed to the writ
petition and, as such, no basis for calculation of compensation has
been disclosed by the petitioners.
11. It is further submitted that the date on which the claim for
compensation arose was the date of disconnection and not the date of
rejection by the RGRO.
12. Based on the rival contentions of parties, the following deductions can
be arrived at:
13. The amended Clause 15.1, inserted by the 2013 Regulation, provides
that no compensation as determined under Regulation 15.0 of the
principal Regulation of 2010 is payable if compensation is not
claimed by the affected person at the appropriate forum within 90
days from the date from which compensation arises. In the present
case, compensation was claimed before the RGRO on the date of filing
of the complaint, that is, on February 3, 2017. Although the
disconnection took place on January 22, 2014, the petitioners
communicated in writing to the Station Manager of the Madhyamgram
Sector Office of the WBSEDCL within 90 days therefrom, that is, on
March 27, 2014 (Annexure P1 at page 15 of the writ petition). In the
said communication, the petitioners clearly offered to pay up the
outstanding dues for the purpose of getting restoration of connection.
14. A complete reading of the order of the Ombudsman, however, reveals
that the Ombudsman, upon considering all relevant documents and
materials-on-record, came to the conclusion that the requirements for
disconnection of the service line of the complainant had not been
properly fulfilled by the distribution licensee. It was clearly observed
by the Ombudsman that the distribution licensee could not explain
the reason for the bills generated from their system for the relevant
period. Hence, the bills from 2018 onwards, raised during the
pendency of the case, were held to be unjustified and were directed to
be cancelled.
15. The Ombudsman further observed that the disconnection took place
without any valid notice as per Section 56(1) of the Indian Electricity
Act, 2003 and, as such, the disconnection was labelled as 'wrongful
disconnection' of the service line. Although the Ombudsman arrived
at the conclusion that the petitioners were otherwise entitled to be
compensated, such compensation was refused due to alleged violation
of Regulation 15.1 of the 2010 Regulation. Hence, in the present case,
the disconnection was held to bepatently wrongful by the
Ombudsman. In such view of the matter, the suffering of the
petitioners for disconnection started from the date of disconnection,
that is, January 22, 2014.
16. However, the restoration of the electricity connection took place in
January 12, 2018, subsequent to the RGRO's order dated March 29,
2017.
17. To determine the quantum of compensation, the relevant clause to be
looked into is Clause 15.0 of the Regulation No.57 dated August 26,
2013. Sub-clause (c) thereof provides for compensation for delay in
reconnection whereas sub-clause (d) deals with compensation for
wrongful disconnection. In the present case, in view of the clear
finding of the Ombudsman that the disconnection of the petitioners'
connection was wrongful, which has not been assailed by the
distribution licensee, sub-clause (d) of Clause 15.0 is squarely
applicable.
18. Clause 15.1, introduced by the 2013 Resolution No.57, stipulates the
time-limit for seeking compensation. It provides that, notwithstanding
anything contained contrary elsewhere in any other Regulation of the
Commission, no compensation as determined under Regulation 15.0
is payable if compensation is not claimed by the affected person at the
appropriate forum within 90 days "from the date from which
compensation arises".
19. The expression "from the date from which compensation arises" is also
found in sub-clause (c) of Clause 15.0. In paragraph (ii) thereof, the
number of days for which compensation will be applicable has been
stipulated to be the number of days or slab, as applicable, between
the date of the order of the compensation and the date from which
compensation arises.
20. For LT industrial categories of consumers, the chart given under
Clause (d)(ii) provides that the rate of compensation would be,
Rs.3,000/- per instance plus the amount paid by the consumer to the
licensee in getting reconnection plus Rs.500/- per day or part thereof
during which period the supply remained wrongfully disconnected.
21. Since the present petitioners have been enjoying an industrial
connection of LT category, the calculation of compensation shall be at
the rate as indicated above.
22. In the present case, the disconnection took place on January 22, 2014
and the connection was restored on January 29, 2018. Hence, the
date "from which compensation arises" for the purpose of Clause 15.1,
in order to calculate limitation, could only be the date on which the
reconnection was given, since the period during which the supply
remained wrongfully disconnected has to be calculated from the date
of disconnection to the date of restoration thereof. The claim of
compensation crystallizesonly when connection is restored.
23. Thus, there is an apparent anomaly between the senses conveyed by
the same expression, "from which compensation arises", as used in
Clause 15.0 (e) ii), read in conjunction with Clause 15.0 (d)i), on the
one hand and Clause 15.1 on the other. The first conveys the sense
that the claim for compensation matures upon connection being
restored, since all three categories of the chart under sub-clause (d) i)
speak of compensation to include the reconnection charge and the
period during which the supply remained wrongfully disconnected,
which can be calculated only after reconnection is given.
24. However, applying the Rule of Harmonious Construction, there ought
to be a parity in the sense conveyed by the phrase "from which
compensation arises", as used in Clause 15.0 (e) ii) and Clause 15.1.
Otherwise, the 90 days' limitation for the claim has to be calculated
from the date of reconnection, taking reconnection to be the starting
point of limitation, which signifies that the order of compensation can,
theoretically, precede the claim itself, on which it is passed.
25. As for example, in the present case, the disconnection took place
onJanuary 22, 2014 and reconnection onJanuary 12, 2018; whereas
the complaint (apparently including the claim of compensation) was
lodged onFebruary 3, 2017 and the RGRO passed order on the
complaint on March 29, 2017. So, applying the logic proposed above,
the limitation would start when the compensation claim matures, that
is, on reconnection (January 12, 2018) whereas the RGRO order is
passed before that, on March 29, 2017. Such an interpretation, thus,
would lead to absurdity, which cannot be attributed to legislative
intent.
26. To avoid such absurdity, the expression "from which compensation
arises" has to be taken as the date when the cause of action first
arises, that is, the wrongful disconnection takes place, and not the
date of reconnection, when the claim matures.
27. Proceeding on such premise, the Ombudsman was justified in
observing that the claim of compensation was made much after the
expiry of 90 days from the date of disconnection and, as such, was
time-barred. The first communication of the petitioners dated March
27, 2014, made within 90 days from disconnection, was merely an
offer to pay up the outstanding dues for the purpose of getting
restoration of connection and contained no claim of compensation.
Rather, arguably, such claim was waived by the petitioners, as
implicit in the offer to pay up and clear the outstanding dues.
28. Thus, the finding of the Ombudsman that the petitioners' application
was time-barred was fully justified. Hence, there is no scope of
interference with the decision of the Ombudsman under Article 226 of
the Constitution of India.
29. Accordingly, W.P.A. No.16016 of 2019 is dismissed, thereby affirming
the impugned order of the Ombudsman.
30. There will be no order as to costs.
31. Urgent certified copies of this order shall be supplied to the parties
applying for the same, upon due compliance of all requisite
formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!