Citation : 2022 Latest Caselaw 4865 Cal
Judgement Date : 29 July, 2022
IN THE HIGH COURT AT CALCUTTA
CRIMINAL REVISIONAL JURISDICTION
APPELLATE SIDE
Present:
The Hon'ble Justice Ajoy Kumar Mukherjee
C.R.R. 2221 of 2019
With
CRAN 1 of 2020
Gautam Das
-vs-
The State of West Bengal & Ors.
For the Petitioner : Mr. Sandip Ghosh
Mr. Subroto Das
Mr. Debayan Ghosh
Mr. Aziz Amin
For the K.M.C. : Mr. Gautam Dinda
Mr. Anindya Sundar Chatterjee
For the State : Mr. S.K. Mukherjee, Ld. PP
Mr. Arijit Ganguly
Mr. Sanjib Kumar Dan
Heard on : 26.7.2022
Judgment on : 29.07.2022
Ajoy Kumar Mukherjee, J.
1. The present revisional application has been preferred for quashing the
charge-sheet being no. 305 of 2016 dated 31.12.2016 filed in connection with
Beliaghata police station case no. 10 dated 5.1.2016 under Section 401A of the
Kolkata Municipal Corporation Act 1980.
2. It has been contended by the petitioner that on or about 2.12.2015 the
opposite party no. 2 lodged a complaint before the Officer-in-charge of the
Beliaghata police station in connection with 43, Barwaritalla Road, Kolkata-
700010 alleging certain unauthorised construction against the petitioner being
the person responsible, in alleged violation of the sanctioned municipal
building plan of the said premises being building plan no. 2014030029 dated
14.7.2014. Followed by the said complaint, concerned authority of the Kolkata
municipal Corporation (hereinafter referred to as KMC) filed a case report in
respect of such violation and/or deviation in connection with the construction
of a partly four-storied and partly five storied building.
3. Prior to the said complaint, at the instance of the opposite party no. 2, a
complaint was initiated under Section 400 (1) read with Section 416 followed a
show cause notice under Section 416 (5) of the KMC Act in respect of the
premises in question for alleged unauthorised construction being the deviation
from the original sanctioned plan dated 14.7.2014 and show cause notice
dated 17.3.2017 was served upon the petitioner in this regard. On the basis of
a hearing which took place on 5.6.2017 the concerned authority of KMC was
inter alia pleased to allow the petitioner to retain the construction along with
change of user subject to submission of an affidavit declaring on oath that no
construction whatsoever in the subject premises without prior sanction from
the authority will be undertaken.
4. Following the direction contended in the said order dated 6.6.2017, the
petitioner duly affirmed an affidavit dated 24.8.2017 and paid demanded
amount towards retention fees and/or regulation of unauthorised construction
and for change of user being a sum of Rs. 19,13,747/- in favour of the KMC
only after which the D-sketch plan was approved by the KMC.
5. In pursuance of aforesaid case report submitted by concerned authority,
Beliaghata P.S. started aforesaid Beliaghata P.S. Case No. 10 dated 05.01.2016
and on 27.7.2018, a charge-sheet has been filed against the petitioner under
Section 401A of the said act before the learned Metropolitan Magistrate
although the charge-sheet appeared to have been prepared on 31.12.2016.
6. Mr. S. Ghosh, learned advocate for the petitioner submits that rule no.
26(2)(a) of the Kolkata Municipal Corporation Building Rules 2009 prescribes
for sanction of the permitted deviation during execution of work and in
accordance with the aforesaid rules the petitioner duly submitted a revised D-
sketch plan before the concerned municipal authorities and upon due
consideration of the said D-sketch plan on or about 24.10.2016, the same was
sanctioned by the municipal authorities and it was made much prior to the
date of submission of the charge-sheet before the learned Metropolitan
Magistrate.
7. Mr. Ghosh, learned advocate for the petitioner further submits that in
any event after the due sanction of D-sketch plan, no construction whatsoever
was undertaken in the premises in question. In fact, the charge-sheet filed by
the police authorities at the behest of the opposite party no. 2 has become
redundant and the said police case cannot be permitted to be proceeded with
in view of the aforesaid facts and circumstances of the case. He further
submits that there has been no continuance work of whatsoever nature in the
premises in question beyond the scope and ambit of the revised D-sketch plan
referred to above. Accordingly the said police case arising out of Beliaghata P.S.
Case No. 10 dated 05.01.2016 and the proceeding on the basis of purported
charge-sheet being no. 305/16 dated 31.12.2016 under Section 401(A) of the
said act cannot be continued or placed for trial.
8. In this connection, Mr. Ghosh, learned advocate for the petitioner has
drawn my attention to the charge-sheet wherefrom it appears that the charge-
sheet was made ready on 31.12.2016 under Section 401A of the KMC Act but
it was submitted before the court after expiry of more than one and half year
i.e. on 27.7.2018. He has further drawn my attention to the order passed in
demolition case no. 03-D/III/2017-18 dated 5.6.2017 by the concerned
authority OSD (Building) of KMC of which ordering portion runs as follows:
"Considering all the available information and document placed with the file, statement of P.R. and keep due regards to the spirit of law, the structure constructed deviating from sanction plan as shown in D. Sketch is allowed to retain along with change of use (Short fall of car parking 4 nos.) subject to submission of affidavit declaring on oath that no construction what-so-ever in the impugned premises without prior sanction from the authority will be done. All the requisition of W.B.F and E.S. are to be complied as risk & cost of applicant/P.R. P.R. have to deposit the demand fees after due concurrence of authority within 30 days from the date of issue of order, failing which action for demolition will be taken on approval of authority, cost of demolition may be recovered from P.R. on approval of authority."
9. He has further drawn my attention to annexure P-4 which is a money
receipt granted by the KMC in favour of the petitioner amounting to
Rs.19,13,747/-
10. In this connection Mr. Ghosh has also drawn my attention to proviso to
Section 619A(1) of the KMC Act of which stipulates that no offence of the
contravention of any condition subject to which sanction was accorded for the
erection of any building or the execution of any work shall be cognizable if
such contravention relates to any deviation from any plan of such erection or
execution sanctioned by the municipal commissioner which is compoundable
on payment of an amount under the rules and regulation relating to building
under the said act and Section 621(1) of the Act provides that the municipal
commissioner or any person authorized by him in this behalf may either before
or after the institution of any proceedings compound any offence punishable
by or under the said Act.
11. Learned advocate for the KMC concedes that in view of the aforesaid
order passed by KMC in aforesaid Demolition Case No. 03-D/111/2017-18
and in view of the compliance of the said order by the petitioner, the
proceeding under Section 401 under the KMC act is not tenable at this stage.
12. Having considered the facts and circumstances of the case and that after
the charge-sheet got ready on 31.12.2016, the aforesaid hearing took place on
5.6.2017 before the officer on special duty in demolition case no. 03-
D/III/2017-18 and on the basis of hearing in the said proceeding, the KMC
authority allowed the deviation from sanctioned plan keeping the spirit of the
law along with change of its user subject to submission of affidavit declaring
on oath and also subject to deposit the demand fees and also considering the
fact that in compliance of the said order, the petitioner deposited the said
amount of Rs. 19,13,747/- before the KMC authority on 24.8.2017 and also in
view of the fact that the offence is compoundable in nature, I find that filing of
the charge-sheet in the above backdrop before the court on 27.7.2018 i.e. after
compliance of the aforesaid direction made by the KMC, has become
redundant and it would be a mere abuse of the process of the court, if the
present proceeding is allowed to be continued, as there is no chance of
conviction of the petitioner in view of aforesaid facts and circumstance of the
case.
13. In view of the above CRR 2221 of 2019 is allowed.
14. The application being CRAN 1 of 2020 is also disposed of.
15. Let all further proceedings in connection with Beliaghata police station
case no. 10 dated 5.1.2016 under Section 401A of the Kolkata Municipal
Corporation Act 1980 is hereby quashed.
16. Urgent photostat certified copy of this order, if applied for, be given to
the parties upon compliance of all requisite formalities.
(AJOY KUMAR MUKHERJEE, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!