Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Debashis Mitra vs Union Of India And Others
2022 Latest Caselaw 4211 Cal

Citation : 2022 Latest Caselaw 4211 Cal
Judgement Date : 14 July, 2022

Calcutta High Court (Appellete Side)
Debashis Mitra vs Union Of India And Others on 14 July, 2022
                     In the High Court at Calcutta
                    Constitutional Writ Jurisdiction
                             Appellate Side

The Hon'ble Justice Sabyasachi Bhattacharyya

                          W.P.A. No. 14148 of 2022

                               Debashis Mitra
                                     Vs.
                          Union of India and others


     For the petitioner             :     Mr. Ranjan Kali

     Hearing concluded on           :     11.07.2022

     Judgment on                    :     14.07.2022



     Sabyasachi Bhattacharyya, J:-


1.   Upon succeeding in a tender floated by the Bharat Sanchar Nigam

     Limited (BSNL) for the purpose of outsourcing maintenance and

     provisioning of landline and broadband for external plant of copper

     network in CTD under Business Area-West, the petitioner was

     awarded a contract.

2.   Sub-clause 3.6(b) of the said contract provides that the contract will

     be terminated and PBG forfeited upon non-performance and failure to

     meet all the SLAs, that is, MTTR, Provisioning, fault clearance and

     repeat fault parameters for consecutive three months. It was further

     stipulated in the said clause that notice shall be served for non-

     performance in the first month, second month and third month before

     final termination.
                                       2


3.   It is contended that although the petitioner gave written replies to

     each of the three notices issued by the respondent-Authorities, none

of those was considered by the respondents.

4. It is submitted that the respondent-Authorities asked the petitioner to

continue the work, while in the same breath issuing show-cause

notices on allegations of faults on the part of the petitioner.

5. Learned counsel for the petitioner places reliance on the several

replies sent by the petitioner, which have been annexed to the writ

petition.

6. It is contended that the purpose of issuing a show-cause notice is to

give an opportunity to the concerned bidder to present his version on

the allegations levelled in the show-cause notices. However, the said

purpose was defeated by the respondents not giving any opportunity

of hearing to the petitioner and/or not considering such replies.

7. Learned counsel submits that even prior to the termination the

petitioner had sent several communications to the respondent-

Authorities explaining the delay of the petitioner on grounds like the

Amphan Cyclone, 'Bandh'/strike, etc. The said communications were

entirely overlooked by the respondents in terminating the contract

with the petitioner.

8. Learned counsel submits further that while undertaking the job as

per the contract, the BSNL, through the petitioner, had been

discharging public functions. Hence, the contract or the impugned

action could not be said to be a private contract between the parties

simpliciter.

9. Prior to imposing the major penalty of termination, learned counsel

submits, the respondents-Authorities ought to have given an

opportunity to the petitioner to explain the delay, if occasioned, in

executing the work.

10. In an order dated June 29, 2022 passed in a previous writ petition

between the same parties, bearing WPA No.19654 of 2021, the

petitioner specifically contended that no show-cause notice was

issued to the petitioner, as such, there arose no question of the

petitioner giving any reply. Although the said order went against the

petitioner in respect of another contract, it is argued that the facts of

the said case are distinct from the present since in the instant case,

the petitioner gave replies to each and every show-cause notice issued

by the respondents but those were never considered by the

respondents at all.

11. Learned counsel for the petitioner places reliance on another order of

a different co-ordinate Bench dated September 2, 2021 passed in

WPA No.12367 of 2021, wherein a similar clause of a contract was

under consideration, in support of his propositions.

12. Since none appears for the respondents when the matter is called on

for hearing, although the respondents were represented through

counsel previously, the matter is heard ex parte.

13. Upon a perusal of the relevant clauses of the contract between the

parties, it is seen that Clause 3.6 (b) of the contract was satisfied in

the present case inasmuch as the respondents served three notices in

three consecutive months for alleged non-performance of the contract

by the petitioner.

14. In the present case, three separate notices were given respectively in

March, April and May, 2022, in consonance with Clause 3.6 (b).

15. Although Clause 3.6 (c) of the contract provides that the EOI/tender

accepting authority may grant any relief in an action for termination

considering the circumstances/nature of the appeal made by the

bidder if one or more parameters are met, the said sub-clause

categorically reserves such right to grant relief with the authority. We

cannot read into the said clause an additional right of hearing to the

bidder, which would tantamount to changing the terms of the

contract itself.

16. Although the petitioner had given replies to the notice, nothing

prevented the respondent-Authorities from terminating the notice,

even in the teeth of those replies, without giving any opportunity of

hearing to the petitioner. Clause 3.6 (b) does not contemplate a

further opportunity of hearing to the petitioner. In fact, the language

of the said sub-clause does not permit of an interpretation that the

three notices envisaged therein would be "show cause" notices. The

notices, with a month's interval between each other, were clearly

meant to be mere precursors of the termination after three months

and not intended to provide a detailed hearing to the noticee.

17. A plausible ground for termination has been made out from the

communications of the petitioner himself, which have been annexed

to the writ petition. From the communications of the petitioner, both

before and after service of the three notices under Clause 3.6(b), it is

seen that delay in commission of the allotted work was committed by

the petitioner on repeated occasions, on one pretext or the other.

18. It was entirely the discretion of the respondent-Authorities, keeping in

view the exigencies of the public work involved, to terminate or not to

terminate the contract.

19. However, the petitioner has failed to make out any case of mala fides¸

arbitrariness and/or exercise beyond jurisdiction on the part of the

respondent-authorities sufficient to prompt the writ court to set aside

the termination of the contract between the parties.

20. In such view of the matter, WPA No.14148 of 2022 fails and is

dismissed on contest.

21. There will be no order as to costs.

22. Urgent certified copies of this order shall be supplied to the parties

applying for the same, upon due compliance of all requisite

formalities.

( Sabyasachi Bhattacharyya, J. )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter