Citation : 2022 Latest Caselaw 462 Cal
Judgement Date : 10 February, 2022
12
jdt.
10.02.2022
jb.
W.P.A. 3443 of 2019
(Damodar Prasad Agarwal vs. State of West Bengal & Ors.)
Mr. Partha Chakraborty
Ms. Sharmistha China
... For the Petitioner
Mr. Satyajit Talukder
Mr. Abhishek Sarkar
... For the KMDA
The factual aspect of the matter as made out in the writ
petition and submitted on behalf of the parties has been recorded in
the order dated 28th January, 2022 as hereunder:
"The contention of the petitioner is that he was granted
licence in respect of the property in question by the Kolkata
Metropolitan Development Authority by virtue of deed dated
11th December, 1996 and was handed over possession of the
said property by virtue of possession certificate on 23rd May,
1997. The petitioner was unable to raise/complete construction
of his residential house on the said land in terms of Clause
2(iii) of the deed within a period of five years though he
deposited the entire licence fee before the Authority which was
lastly accepted by the Authority in 2010. On 16th February,
2018 a show-cause notice was issued upon the petitioner
requiring him to show cause as to why the licence deed would
2
not be cancelled on the ground of violation of Clause 2(iii) of
the deed by the petitioner. The petitioner sent a reply to the
said notice on 28th February, 2018 praying for extension of the
period for raising construction. The Authority, by a notice
dated 9th August, 2018 demanded penal charges to the tune of
Rs.99,48,452/- from the petitioner for extension of time to
complete construction till 10th December, 2019. The petitioner
expressed his inability to pay the said amount by a letter dated
5th September, 2018 following which the Authority cancelled
the deed and withdraw possession of the land by a letter dated
31st December, 2018.
Learned counsel for the petitioner submits that he was
unable to complete the construction on the land in question due
to financial stringency as well as on medical grounds and
admittedly did not approach the Authority for extension of the
said period before expiry of the stipulated time frame.
According to the petitioner, as the Authority accepted lease
rent till 2010, such acceptance amounts to waiver of the right
of the Authority to cancel the deed of licence on the ground of
violation of Clause 2(iii) of the deed by the petitioner, as
according to the said clause, the period for completion of
construction expired in 2001-2002. There being no provision
of imposing penal charges upon the petitioner, the Authority
could not have charged such penalty and as such, the Authority
should be directed to extend the time frame for completion of
construction on the land in question by the petitioner.
It is submitted on behalf of the Kolkata Metropolitan
Development Authority that pursuant to the show-cause notice
3
issued by the Authority the petitioner was called for a hearing
by the Authority and subsequent orders were passed upon
hearing the petitioner on 1st November, 2018. The petitioner
did not pray for extension of time before the Authority within
the stipulated time frame. The policy decision of the Authority
permits the Authority to impose penal charges on the petitioner
by way of which the petitioner was given another opportunity
to retain the land and raise construction therein upon payment
of the same."
Learned counsel for the petitioner draws the attention of the
Court to the third paragraph in page 24 (Annexure P/1 to the writ
petition) which demonstrates that in case of default by the licensee
in payment of three consecutive installments of premium and default
to clear the same within six months from the due date, the Authority
shall have the right to determine the agreement and re-enter
possession of the demised premises. Learned counsel points out that
in terms of clause 4(i) of the deed, the Authority was only entitled to
re-enter the premises on breach of any of the terms of the contract
and no specific authority was given to the lessor for determination of
the lease.
Learned counsel further submits that there being no
provision for demanding penal charges for extension of time to raise
construction in the plot, no such charge could have been claimed by
the Authority. The Authority has, in fact, cancelled the deed upon
the petitioner's inability to pay the penal charges as demanded by
them.
4
Learned counsel for the petitioner has placed reliance on a
judgment of a co-ordinate Bench of this Court in W.P. No. 1631 of
2010 wherein it is recorded that in absence of any provision for
charges in the lease deed itself, such charges cannot be imposed
upon the lessee by the Authority. The relevant portion of the
judgment is set out:-
"Under the lease, the appellants were entitled to the
lease rents during the pendency of the lease. Neither the lease
deed nor the provisions of the Calcutta Improvement Act, 1911,
contemplates the levying of transfer-cum-mutation fees. The
decision of the appellants to impose such charges in lieu of
granting permission to assign or transfer the lease-hold interest
in the demised premises appears to be extraneous both to the
terms and conditions of the lease and the provisions of the
aforesaid Act."
In refuting the contention on behalf of the petitioner, learned
counsel for the KMDA submits that the deed was cancelled in terms
of clause 4(i) due to breach of clause 2(iii) by the petitioner. The
Authority, in its meeting dated 1st August, 2017, adopted a policy
decision to safeguard the rights of the lessees defaulting in raising
construction in the leasehold property within the stipulated period of
time. The policy decision says that in case of delayed construction
or non-construction in the leasehold property, cancellation notice
should be issued to the allottee immediately and if the allottee agrees
to pay penal charges for delayed construction at current market
5
value through written prayer against such cancellation notices, a
fresh/modified lease deed shall be executed on payment of the delay
charges by the lessee. Learned counsel submits that the said policy
decision was adopted in addition to the terms of the deed in order to
extend relief/protection to lessees who are in breach of any of the
terms of the contract.
Learned counsel further submits that the premium deposited
by the lessee has been sought to be refunded to the lessee and
cheque in this regard has already been issued.
Learned counsel has relied upon the judgments of the
Hon'ble Supreme Court in Barelly Development Authority and
Another vs. Ajai Pal Singh and Others reported in (1989) 2
Supreme Court Cases 116 and in M/s Radhakrishna Agarwal &
Others vs. State of Bihar & Ors. reported in AIR 1977 Supreme
Court 1496 in support of his contention.
It is not in dispute that the petitioner has failed to raise
construction in the plot in question within five years from the date of
execution of the deed in breach of Clause 2(iii) of the deed. A show-
cause notice was issued upon the petitioner on 16th February, 2018
in this regard and in reply to the said notice, the petitioner prayed for
extension of time for the said construction on the ground that he was
unable to raise construction within the stipulated period of time due
to acute financial crisis and also ignorance of the fact that the deed
may be cancelled due to non-construction within the stipulated time
6
period. Following the said reply dated 28th February, 2018 KMDA
issued a demand notice for penal charges on 9th August, 2018. Upon
the petitioner failing to comply with the notice, the allotment was
cancelled by a notice dated 31st December, 2018.
It is a fact that the provision of payment of penal charges as
recorded in the policy decision of the Authority is not included in
the deed itself and admittedly such policy decision was not
intimated to the petitioner or the other allottees prior to execution of
the deed or even subsequently. Therefore such policy decision
cannot be given much weight and the deed could not have been
cancelled for non-payment of penal charges as demanded by the
Authority {W.P. No. 1631(W) of 2010} in terms of the policy
decision. Of course, the respondents submit that the lease was
cancelled in terms of clause 4(i) of the deed and not for non-
payment of penalty. The provision for payment of penalty as a pre-
requisite to extension of the period of construction is only an
additional leverage offered to the lessee to rectify his omission .
Be that as it may, even without such demand of penal
charges being taken into consideration, it appears that the deed was
cancelled due to breach of the terms thereof by the petitioner. A
technical lapse in clause 4(i) of the deed has been pointed out by the
petitioner. Such provision enables the Authority to re-enter into the
land upon breach of any of the terms of the deed, but does not
specifically indicate that the lease may be determined by the
Authority. It is needless to say that re-entering of the Authority into
the property presupposes determination of the deed of lease and as
such, it can be inferred that the provision entitles the Authority to
determine the deed of lease in terms of clause 4(i) of the deed and
thereafter re-enter the premises in question.
It has been observed by the Hon'ble Supreme Court in the
case of M/s Radhakrishna Agarwal & Others(supra) as under:
"But, after the State or its agents have entered into the
field of ordinary contract, the relations are no longer governed
by the constitutional provisions but by the legally valid
contract which determines rights and obligations of the parties
inter se. No question arises of violation of Article 14 or of any
other constitutional provision when the State or its agents,
purporting to act within this field, perform any act. In this
sphere, they can only claim rights conferred upon them by
contract and are bound by the terms of the contract only unless
some statute steps in and confers some special statutory power
or obligation on the State in the contractual field which is apart
from contract."
In the judgment in Barelly Development Authority and
Another(supra) Hon'ble Apex Court has held that once the parties
after voluntarily accepting the conditions of the contract enters into
such contract they can only claim the right conferred upon them by
the said contract and are bound by the terms of the contract.
In the case in hand, both the parties are governed by the deed
of lease entered into by and between them on 11th December, 1996.
Admittedly the petitioner failed to raise construction in the demised
land within five years from the date of issuance of the deed in
breach of clause 2(iii) of the deed and no extension was prayed for
before the Authority either within the stipulated period of time or at
all. It was only when the show-cause notice was issued to the
petitioner that he woke up from slumber and chose to raise his claim
for extension before the Authority in the reply submitted by him to
the show-cause notice. The deed has been cancelled by the
Authority in terms of clause 4(i) irrespective of the claim of penal
charges by the Authority. Even if the claim for penal charges is
ignored, the Authority still had the right to cancel the deed in terms
of clause 4(i) thereof and as such, the Authority has acted well
within its rights and jurisdiction. As pointed out by learned counsel
for the respondents, acceptance of license fee by the Authority till
2010 does not preclude the Authority from cancelling the deed in
view of clause 4(iii) of the deed which indicates that "any relaxation
or indulgence granted by the Authority to the LICENSEE or by the
said LICENSEE to the Authority shall not in any way prejudice the
rights of the parties under this Deed of License." It is also submitted
that the Authority has taken steps for refund of the premium
deposited by the petitioner.
In view of the above, this Court is of the view that there is no
illegality or irregularity in the act of the respondent Authority which
calls for intervention by this Court in the present writ petition and as
such, the writ petition is devoid of any merit and is liable to be
dismissed.
Accordingly, W.P.A. 3443 of 2019 is dismissed.
There shall be no order as to costs.
Since no affidavit has been invited, allegations contained in
the writ petition shall be deemed not to have been admitted.
Urgent certified website copy of the order, if applied for, be
given to the parties on compliance of requisite formalities.
(Suvra Ghosh, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!