Citation : 2022 Latest Caselaw 8680 Cal
Judgement Date : 23 December, 2022
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
W.P.A. No.20408 of 2017
Kalimata Ispat Industries Private Limited
and another
Vs.
West Bengal State Electricity Distribution Company Limited
and another
For the petitioners : Mr. Tanoy Chakraborty,
Mr. Kallol Saha,
Mr. Shounak Mukhopadhyay
For the WBSEDCL : Mr. Sujit Sankar Koley
Hearing concluded on : 15.12.2022
Judgment on : 23.12.2022
Sabyasachi Bhattacharyya, J:-
1. The petitioner no.1 is a manufacturer and supplier for the Indian Railways
and has its factory at 1/98, Bidhan Sarani, Saheb Dihi, Barjora, District-
Bankura. Both the Damodar Valley Corporation (DVC) and the West Bengal
State Electricity Distribution Company Limited (WBSEDCL) are
Distribution Licensees authorised to supply electricity to the consumers
within the said command area. The petitioner no.1 is a consumer of
WBSEDCL.
2. The petitioner no.2 is a Director of the petitioner no.1.
2
3. The petitioner no.1 has been taking electricity supply from the WBSEDCL
and has preferred the instant writ petition contending that all benefits of
the Scheme notified by the respondent no.1 (WBSEDCL) on October 15,
2015 have not been given to the petitioners and seeking extension of such
benefits as well as refund of a sum of Rs.16,81,155/-, being allegedly the
actual financial loss of the petitioners in the form of difference in revenue
collected by the WBSEDCL.
4. The petitioners also claim benefits of Load Factor Rebate (including
additional Load Factor Rebate) as per the Scheme of extension of additional
rebate notified by the WBSEDCL in its Notice dated February 10, 2017 on
the basis of the Order dated February 8, 2017 passed by the West Bengal
Electricity Regulatory Commission (WBERC).
5. It is contended that as per the Scheme Dated October 15, 2015, effect to
the same had to be given from 15 days after the Notification, that is, from
November 1, 2015 but with regard to the petitioners, effect has been given
only from the month of February, 2016, thereby subjecting the petitioners
to a loss of Rs.16,81,155/-, a chart containing the break-up of which is
also given by the petitioners.
6. The petitioners applied for rebate under the Notification dated October 15,
2015 on October 29, 2015.
7. Vide Letter dated February 11, 2016, the WBSEDCL indicated that the
effect of the said Notification in respect of the petitioner would be given
from the month of February, 2016. The WBSEDCL reiterated such stand
on April 21, 2016, refusing the petitioners' claim on the ground that no
retrospective effect had been allowed by the competent authority.
8. It is argued by learned counsel for the petitioners that the petitioner no.1 is
entitled to tariff at competitive rates as per the Notification dated October
15, 2015 since November 1, 2015. In view of such specific representation
having been given by the WBSEDC, which is a public authority, the said
authority is bound under the principles of promissory estoppel and
legitimate expectation to give such benefit to the petitioners from the
appointed date. However, such benefit was refused to the petitioners
without any cogent reason. For such proposition, learned counsel for the
petitioners relies on the Judgment reported at (2020) SCC OnLine 968 [State
of Jharkhand and others Vs. Brahmputra Metallics Ltd., Ranchi and
another].
9. It is next contended that vide Order dated February 8, 2017 passed by the
WBERC on an application submitted by the WBSEDCL for issuance of
order on a Scheme for revenue enhancement through increased sale to the
industries under WBSEDCL through rationalization under Regulation 8.10
of the Regulation No.48 dated April 25, 2011 of the WBERC, it was
categorically decided that the load factor rebate as proposed in the Scheme
would be in addition to the rebate already allowed in the tariff order in
respect of WBSEDCL for 2016-2017 for respective categories of consumers.
It is also stated therein that the WBSEDCL shall publish a notification in
this regard, clearly mentioning the rates of rebates and the consumers to
whom those would be applicable, before introduction of such Scheme both
in the newspaper and on the website of WBSEDCL.
10. Pursuant to such order, the WBSEDCL issued a Notice on February 10,
2017, whereby the Revenue Enhancement Scheme of the WBSEDCL was
made effective from the consumption-month of February, 2017.
11. It is argued that the said Scheme contemplates exemption in Demand
Charge for additional drawal up to 50 per cent from existing 30 per cent
during off-peak period for all 33 and 132 KV industrial consumers, within
which category the petitioner no.1 also comes.
12. It is argued that since the said exemption has been applied to all such
industrial consumers, the WBSEDCL acted patently without authority in
refusing the same to consumers enjoying competitive rates. It is argued
that such action is de hors the Order of the WBERC as well as violative of
Article 14 of the Constitution of India. Discrimination has been
unreasonably made between the competitive rate-holders and other
consumers, thereby creating a class within a class, which is not sanctioned
in law.
13. Learned counsel for the petitioners further contends that as per the first
proviso to Clause 2.1.1 of Chapter-II of the 2011 Regulation, which speaks
of determination of tariff in case of distribution of electricity in the same
area by two or more licensees, the Commission may, for promoting
competition among licensees, fix the maximum ceiling of tariff for retail sale
of electricity. It is further argued that as per Clause 8.10 of the same
Regulation, if any difficulty arises in giving effect to any order based on the
Regulations, then the Commission, by subsequent supplementary order,
may remove the difficulties keeping consistency with the provisions of the
Act and the Regulations.
14. It is submitted that the WBSEDCL acted in contravention of such
provisions in refusing to extend the rebates-in-question to the petitioners.
15. Learned counsel for the WBSEDCL argues that as per the first proviso of
Section 66 of the Electricity Act, 2003 (for short, "the 2003 Act") as well as
the third proviso to Clause 2.2.2 of the 2011 Regulations, the appropriate
Commission may, for promoting competition among Distribution Licensees,
fix only the maximum ceiling of tariff for retail sale of electricity and not
further.
16. Inasmuch as the grant of rebates is concerned, nothing is provided in the
said provisions to justify the present challenge.
17. It is further argued that the competitive tariff holders already enjoyed
preferential rates of tariff, due to which the rebate in respect of load factors,
as per the Notification of 2017, was given to the other consumers. As such,
the basis of such classification is reasonable and there is no violation of
Article 14 of the Constitution of India.
18. It is next argued that although the Notification was published on October
15, 2015, the application was filed by the petitioners only on October 30,
2015. About three months were taken to process the said application, due
to which the effect thereof was given from the month of February, 2016. As
such, it is argued that in the absence of any retrospective provision in the
Notification of 2015, the effect of the same could not be given from any
prior date.
19. Upon hearing learned counsel for the parties, it is quite evident from the
first impugned Notification dated October 15, 2015 that the competitive
rates stipulated therein were to be effective after 15 days from the date of
the said Notification. The application in that regard was made by the
petitioners on October 29, 2015, which was, one day prior to expiry of the
15 days after issuance of the Notification.
20. Irrespective of the time taken by the WBSEDCL for processing the said
application, such time cannot have any bearing upon the entitlement of the
petitioners, since the petitioners cannot suffer for such delay.
21. There is no conceivable reason as to why the WBSEDCL flouted its own
Notification, which is the source of the grant of competitive tariff, by giving
effect to such competitive rates for the petitioners from February 1, 2016,
that is, three months after the date of commencement of such rates.
22. A period of 15 days after the issuance of the Notification dated October 15,
2015 brings us to October 30, 2015 and, as such, the petitioner no.1 could
legitimately claim the rates on and from November 1, 2015 itself.
23. Thus, such action of the WBSEDCL is violative of Article 14 of the
Constitution of India as well as patently contrary to its own Notification and
cannot be sustained in law.
24. Insofar as the first proviso to Section 62 of the 2003 Act is concerned, the
same provides that the appropriate commission may, for promoting
competition among the Distribution Licensees, fix only maximum ceiling of
tariff for retail sale of electricity.
25. Neither the said proviso nor any of the provisions of the 2011 Regulations
leaves any scope of discrimination between consumers. As such, there is
no reason why the petitioner no.1 should be deprived of getting the
competitive rates of tariff from November 1, 2015 itself.
26. With regard to the Order dated February 8, 2017 passed by the WBERC,
the same is squarely in consonance with Clause 8.10 of the WBERC
Regulations of 2011. The said clause provides that if any difficulty arises in
giving effect to any order based on these Regulations, the Commission, by
subsequent supplementary order, may remove the difficulties keeping
consistency with the provisions of the Act and the Regulations.
27. The said provision was invoked as the source of power for issuance of the
Order dated February 8, 2017. The order, in fact, was issued by the
Commission, which is authorised under Section 62 to determine the tariff.
28. It is seen from Clause 6.0 of the Order that sub-clause (b) thereof stipulates
that the load factor rebate as proposed in the Scheme will be in addition to
the rebates already allowed in the tariff order in respect of the WBSEDCL
for 2016-2017 for respective categories of consumers.
29. As such, the line of distinction sought to be drawn between consumers
enjoying competitive rates as per the 2015 Notification and those not
enjoying such rebate is artificial and not sanctioned by the Order itself.
30. Sub-clause (d) of Clause 6.0 says that the WBSEDCL shall publish a
Notification in that regard clearly mentioning the rate of rebates and the
applicable consumers before introduction of the Scheme, both in the
newspaper and the website of WBSEDCL.
31. The concerned Scheme, a copy of which is annexed at page 32 of the Writ
Petition, clearly stipulates that the exemption contemplated therein was
intended for all 33 and 132 KV industrial consumers. As such, the
expansive language of the Scheme, read in conjunction with the Order
dated February 8, 2017, does not leave scope for discriminating between
consumers enjoying competitive tariff rates and other consumers. The
principle envisaged in sub-clause (b) of Clause 6.0 of the Order provides
clearly that the load factor rebate contemplated in the latter scheme would
be in addition to and not alternative to the rebates already allowed in the
tariff order of WBSEDCL for 2016-2017.
32. Hence, the said competitive rates of 2016 could not be a relevant yardstick
for discriminating against the competitive tariff consumers inasmuch as the
extension of the 2017 relief is concerned.
33. In the absence of any such distinction being shown by the WBSEDCL, it
has to be deemed that all consumers of electricity fell within the category of
entitlement for Load Factor Rebate as proposed in the Scheme of 2015,
irrespective of whether they enjoyed competitive tariff rates or not.
34. The competitive tariff rates in respect of command areas where more than
one distributors operate and the load factor rebate given to consumers
operate in two different fields and are distinct in scope of operation.
Therefore applicability of one cannot exclude any consumer, if otherwise
entitled, to be deprived of the other benefit.
35. However, since Clause 6.0 (e) of the 2017 Notification stipulates that the
Scheme would be effective on and from the consumption month in which
the Notification was published, there is no irregularity in the effect to the
same being given from the month of February, 2017, since the date of
publication of the concerned Notification was February 10, 2017.
36. Nothing in the Regulations of 2011 empowers the WBSEDCL to
discriminate between the consumers enjoying principle tariff as per the
2015 Notification and the others. As such, the refusal to extend such
additional rebate as per the 2015 Scheme to the petitioner no.1, on the
ground that consumers enjoying competitive tariff Scheme were not entitled
to get such additional rebate, as communicated vide Letter dated May 15,
2017 (annexed at page 43 of the Writ Petition) is palpably de hors the
principles of Natural Justice as well as the concept of equality as enshrined
in Article 14 of the Constitution of India.
37. Such discrimination contravenes the extant law and the Regulations of the
WBERC as well as the Order dated February 8, 2017 passed by the
appropriate Commission (that is, the WBERC) in consonance with the
statutory provisions.
38. Insofar as the decision in Brahmputra Metallics Ltd., Ranchi (supra) is
concerned, the same lays down that promissory estoppel and legitimate
expectation principles are to be applied even in case of public authorities.
Such ratio is apt for the present adjudication and applies squarely to the
parties herein as far as the rebates-in-question are concerned.
39. After having notified the conferment of a right by way of rebate/competitive
tariff, the same cannot be resiled from by the authorities themselves. Such
deviation violates the principle of promissory estoppel as well as the
doctrine of legitimate expectation and ought to be set aside.
40. Insofar as the quantification of the financial loss suffered by the petitioner
no.1 for not getting the benefit of the 2015 Scheme to the tune of
Rs.16,81,155/- is concerned, a chart showing the corresponding break-up
of extra payments made by the petitioner no.1, in the form of difference in
revenue collected by the respondent no.1, has clearly been given in
Annexure P-12 at page 44 of the Writ Petition.
41. There being nothing on record to controvert the veracity of the said chart
and/or such quantification, the WBSEDCL ought to refund such excess
payment made by the petitioner no.1 in order to compensate for the
unlawful act of the WBSEDCL in not extending the benefit of the 2015
Notification to the petitioner no.1 on and from November 1, 2015 till
January 31, 2016.
42. In view of the above considerations, W.P.A. No.20408 of 2017 is hereby
allowed, thereby directing the WBSEDCL to apply the benefit of the
Competitive Tariff Rate Notification dated October 15, 2015 to the petitioner
no.1 and, accordingly to refund the amount of Rs.16,81,155/- to the
petitioner no.1 by January 31, 2023.
43. The WBSEDCL is further directed to extend the Scheme of additional rebate
(including additional load factor rebate) notified in the Notice of the
WBSEDCL dated February 10, 2017, on the basis of the Order dated
February 8, 2017 passed by the WBERC to the petitioner no.1. The
amount due on such count shall be calculated by the WBSEDCL within
January 15, 2023 and intimated immediately thereafter to the petitioners.
In the event the petitioners have any grievance in respect of such
calculations, it will be open to the petitioners to approach the WBSEDCL-
Authorities with the suggested corrections as pointed out by the petitioners.
44. If and when such approach is made by the petitioners, the WBSEDCL shall
resolve the issue upon giving an opportunity of hearing to the petitioners
and/or their authorised agent within January 31, 2023. The amount found
payable shall be disbursed in favour of the petitioners by March 31, 2023.
45. There will be no order as to costs.
46. Urgent certified copies, if applied for, be issued by the department on
compliance of all requisite formalities.
( Sabyasachi Bhattacharyya, J. )
Later:
After the judgment is passed, learned counsel for the WBSEDCL seeks an
order of stay of operation of the said judgment. However, due to the relaxed time-
line given for compliance of the judgment/order, no further stay is required to be
granted.
Hence, the prayer for stay is refused.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!