Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Aleya Bibi And Ors vs Mirjanagar Bajar Jame Masjid Bibi ...
2022 Latest Caselaw 8198 Cal

Citation : 2022 Latest Caselaw 8198 Cal
Judgement Date : 12 December, 2022

Calcutta High Court (Appellete Side)
Aleya Bibi And Ors vs Mirjanagar Bajar Jame Masjid Bibi ... on 12 December, 2022
12.12.2022
 Sl.No. 11
 Ct.No.03
 Amalranjan
                IN THE HIGH COURT AT CALCUTTA
                 CIVIL APPELLATE JURISDICTION
                        APPELLATE SIDE

                           FMAT/422/2022
                               With
                            CAN/1/2022

                         Aleya Bibi and Ors.
                                 Vs.
              Mirjanagar Bajar Jame Masjid Bibi & Ors.

                  Mr. Mohinoor Rahaman
                  Ms. Maria Rahaman
                  Ms. Iqra Rahaman
                                   ...for the appellants/plaintiffs

                  Mr. Mahamudul Hassan
                  Mr. Zeeshan Rahman
                                       ...for the defendant no.1/
                                                   respondent.1

Ms. Indrani Pal Mr. Abhijit Pal ...for the respondent nos. 2-10

Re: CAN/1/2022

We admit the appeal.

As the point involved is not very complicated

and for the ends of justice, we proposed to hear

it out dispensing with all formalities.

The suit in the learned court below is for

declaration of title and partition between the

parties. The title to some very large portions of

the suit property is hotly disputed.

In one of such portions, there is a mosque.

The appellants/plaintiffs as well as the

respondents claim title to it. Each of the two

groups relies on a deed of transfer. The mosque

as it stands now is a G-level structure, as

submitted by learned counsel for the respondent

no. 1. The first floor has been constructed, but

is not complete; plastering, painting etc. work is

going on.

In the midst of this, the respondents/

defendants have started constructing the second

floor.

The appellants/plaintiffs seek an order of

injunction from this court restraining them from

making this construction.

The learned court below in its impugned

judgment and order dated 22nd September, 2022

has, inter alia, said:

"Therefore, considering the principle of

balance of convenience and inconvenience,

methinks, this a fit case to refuse to grant

any relief to the plaintiffs in the form of

injunction. However, the construction, if

any, made by the defendant no. 1, will be

subject to the result of the suit and no

equity can be claimed.

Hence, it is

ORDERED

That the petition U/o 39 r 1 and 2 r/w

Section 151 of CPC is rejected on contest.

To 04/1/23 for framing of issues."

In a partition and administration suit,

where the plaintiffs have been able to, prima

facie, show some title to the property, usually the

court does not permit any construction work to

be proceeded with unless the title to the property

is determined by it and the property distributed

to the owners on partition (see Prasanta Maji &

Ors. Vs. Sukhbinder Singh & Ors, reported in

AIR 2022 Cal 307 and Sopan Maruti Thopte &

Anr. Vs. Pune Municipal Corporation & Anr.,

reported in AIR 1996 Bom 304).

In this case, the learned judge of the learned

court below has tried to carve out an exception

to the above principles on facts by referring to an

agreement dated 24th February, 2018 in which

the appellants/plaintiffs nos. 5 and 6 have

consented to the erection of the mosque by the

defendant no. 1.

The learned judge also held that possession

of the said part of the property is with the said

defendant no. 1.

Learned counsel for the appellants very

strongly denies the agreement dated 24th

February, 2018, alleging that it is a fabricated

document and no consent was granted by his

clients.

We are told that the suit is ready for trial

after completion of the discovery procedure.

All these questions regarding title to the

property, validity of the agreement dated 24th

February, 2018 and so on will be decided in the

suit.

We direct that a final decree of partition be

pronounced by the learned court below, latest by

31st July, 2023.

Having regard to the above general

principles of law regarding the reluctance of the

courts to permit construction in the partition

suit and also taking into account the fact that

the respondents have almost completed the first

floor, we direct that the respondent no. 1 shall

be permitted to complete the construction of the

first floor by doing repairing, renovation,

plastering and painting work etc.

As regards the second floor, the respondents

may proceed with only the preliminary work and

not any major construction work till 31st July,

2023.

If for some reason, the learned court below

is unable to pronounce the final decree by 31st

July, 2023, the respondents shall be at liberty to

apply to the learned court below for permission

to proceed with the construction of the second

floor. The learned court below on consideration

of the, prima facie, case balance of conveyance

and inconvenience etc. shall determine the

application in accordance with law, as

expeditiously as possible.

The impugned judgment and order dated

22nd September, 2022 is modified to the above

order.

The appeal and the connected application

are, accordingly, disposed of.

( Biswaroop Chowdhury,J. ) ( I. P. Mukerji,J. )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter