Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Eastern Coalfields Limited vs Rrepl-Kipl (Jv)
2022 Latest Caselaw 2211 Cal/2

Citation : 2022 Latest Caselaw 2211 Cal/2
Judgement Date : 18 August, 2022

Calcutta High Court
Eastern Coalfields Limited vs Rrepl-Kipl (Jv) on 18 August, 2022
                                  1

               IN THE HIGH COURT AT CALCUTTA
                Ordinary Original Civil Jurisdiction
                          Original Side

                         IA NO. GA/1/2022
                          In RVWO/2/2022
                    EASTERN COALFIELDS LIMITED
                                Vs.
                          RREPL-KIPL (JV)

                                 With

                         IA NO. GA/2/2022
                          In RVWO/2/2022
                    EASTERN COALFIELDS LIMITED
                                Vs.
                          RREPL-KIPL (JV)

                                  IN

                         A.P. NO. 371 OF 2020

For the Applicant           : Mr. Manik Das, Adv.
                              Ms. Tanushree Dasgupta, Adv.

For the Respondent          : Mr. Sudip Deb, Adv.

Mr. Riju Ghosh, Adv.

Hearing concluded on        : August 12, 2022
Judgment on                 : August 18, 2022


DEBANGSU BASAK, J. :-

1. The applicant has applied for review of the judgement

and order dated April 9, 2021 passed in AP No. 371 of 2020.

The applicant has also applied for stay of the operation of

such order by way of an interim application filed in the

review petition. Both the applications for stay as well as the

review petition have been heard analogously.

2. The respondent herein had applied under Section 11 of

the Arbitration and Conciliation Act, 1996 for appointment

of an arbitrator in respect of disputes arising out of a

contract entered into between the respondent and the

applicant which the respondent claimed to contain an

arbitration agreement. Such application under Section 11 of

the Arbitration and Conciliation Act, 1996 had been

disposed of by an order dated April 9, 2021 review of which

has been sought in the present review petition.

3. Learned advocate appearing for the applicant has

submitted that, the applicant had preferred a special leave

petition before the Hon'ble Supreme Court against the order

dated April 9, 2021 passed in AP No. 371 of 2020. The

special leave petition had been disposed of by the order

dated November 26, 2021. By the order dated November 26,

2021, the Hon'ble Supreme Court had permitted the

applicant to file a review application before the High Court.

Pursuant to such liberty being granted, the applicant had

filed a review petition which was dismissed as withdrawn

with liberty to file a fresh on February 10, 2022.

Subsequent thereto, the applicant had filed the present

review application.

4. Learned advocate appearing for the applicant has

referred to the clause alleged to be containing the

arbitration agreement. He has submitted that, similar

clauses in contracts have been considered by a single judge

of this Hon'ble Court, the division bench of this Hon'ble

Court, and the Hon'ble Supreme Court. In all such

occasions, the Courts had held that, such clause does not

contain any arbitration agreement. He has relied upon the

order dated December 22, 2021 passed in AP No. 817 of

2021 (R N Samanta Versus Coal India Ltd), judgement

and order dated June 27, 2018 passed in FMA 1497 of

2018 (South-Eastern Coalfields Ltd versus Cart Road

Wings JV), and the judgement and order dated July 25,

2022 passed in Civil Appeal No. 4914 of 2022

(Mahanadi Coalfields Ltd versus M/s IVCL AMR Joint

Venture) in support of his contentions.

5. Learned advocate appearing for the respondent has

submitted that, the order dated April 9, 2021 was passed

largely on consent of the parties. He has referred to the body

of the order dated April 9, 2021. He has submitted that,

immediately after the arbitration clause contained in the

agreement having been set out in the order dated April 9,

2021, the Court had recorded that, the existence of

arbitration agreement is not disputed. He has contended

that, such recording in the order tantamount to the parties

to the litigation, agreeing to the existence of an arbitration

agreement governing the disputes between the parties. He

has drawn the attention of the Court to the fact that, the

applicant subsequently raised counterclaim as against the

respondent.

6. Learned advocate appearing for the respondent has

drawn the attention of the Court to the conduct of the

applicant subsequent to the order dated April 9, 2021. He

has contended that, the applicant had waived its alleged

right of review of the order dated April 9, 2021 by conduct of

the applicant subsequent to the order dated April 9, 2021.

The applicant had participated in the arbitration

proceedings unconditionally. The applicant had applied

under Section 16 of the Arbitration and Conciliation Act,

1996. He has referred to the minutes of the meeting of the

arbitral tribunal dated July 31, 2022. He has contended

that, the applicant has not taken any steps thereafter with

regard to the finding of the arbitral tribunal as recorded in

the minutes of the meeting July 31, 2022.

7. Learned advocate appearing for the respondent has

referred to the clause in the contract containing the

arbitration agreement between the parties. He has

submitted that, the second last paragraph contains the

word 'shall' whereas the last paragraph of such clause

contains the word 'may'. He has contended that, in respect

of parties other than government agencies, the redressal of

the disputes was left to the discretion of the party who is

not a government agency. According to him, the options

available to a party other than government agencies, are to

approach a Court of law or to invoke the provisions of the

Arbitration and Conciliation Act, 1996. In the facts of the

present case, the respondent had invoked the provisions of

the Arbitration and Conciliation Act, 1996. The applicant

had participated in the arbitration proceedings. The

respondent had accepted that such clause means that there

was an arbitration agreement between the contracting

parties as will appear from the body of the order dated April

9, 2021.

8. Learned advocate appearing for the respondent has

relied upon 2021 Volume 5 Supreme Court Cases 671

(Pravin Electricals Private Limited versus Galaxy Infra

And Engineering Private Limited) and contended that,

when the issue of the existence of an arbitration agreement

requires a deeper consideration than a prima facie

examination, then, the matter should be left for final

determination by the arbitral tribunal. In the facts of the

present case, he has submitted that, since a deeper

consideration of the clause is required so as to return a

conclusive finding as to the existence of the arbitration

agreement, the same may be referred to the arbitral tribunal

already appointed. He has therefore contended that, the

application for review should be dismissed.

9. The applicant had issued an electronic tender dated

December 18, 2017 for hiring of HEMM for re handling

39.20L cum OB from existing dump near Bhadotola for safe

extraction of coal near west side of Bhadotola of RCML

patch at Rajmahal Area. The respondent had been formed

on December 20, 2017 pursuant to a joint-venture

agreement between diverse private companies.

10. The respondent had participated in the electronic

tender of the applicant and was successful therein. The

applicant had awarded the work contained in the electronic

tender dated December 18, 2017 to the respondent. The

applicant had issued a letter of acceptance dated February

14, 2018 and a work order dated April 18, 2018 in favour of

the respondent. The work order dated April 18, 2018 and

the electronic tender dated December 17, 2017 have the

same settlement of disputes clause. The settlement of

disputes clause appearing in both the electronic tender

dated December 17, 2018 and the work order dated April

18, 2018 to which, the parties have referred to in course of

the hearing, is as follows: -

"13. Settlement of Disputes It is incumbent upon the contractor to avoid litigation and disputes during the course of execution. However, if such disputes take place between the contractor and the department, effort shall be made first to settle the disputes at the company level.

The contractor should make request in writing to the Engineer-in-charge for settlement of such disputes/claims within 30 (thirty) days of arising of the cause of dispute/claim failing which no disputes/claims of the contractor shall be entertained by the company.

Effort shall be made to resolve the dispute in two stages.

In first stage dispute shall be referred to Area CGM, GM. If difference still persists the dispute shall be referred to a committee constituted by the owner. The committee shall have one member of the rank of Director of the company who shall be chairman of the company.

If differences still persist, the settlement of the dispute shall be resolve in the following manner:

Sector Enterprises/Govt. Departments (except Railways, Income Tax, Customs & excise duites)/ State Public Sector Enterprises shall be referred by either party for Arbitration to the PMA (Permanent

Machinery of Arbitration) in the department of Public Enterprises.

In case of parties other than Govt. Agencies, the redressal of the dispute may be sought in the Court of law."

11. Disputes and differences had arisen between the

parties with regard to the working of the contract in relation

to the electronic tender dated December 17, 2017. The

respondent had applied under Section 11 (6) of the

Arbitration and Conciliation Act, 1996 which was disposed

of by the order dated April 9, 2021. The special leave

petition directed against such order was disposed of by the

order dated November 26, 2021 permitting the applicant

herein to apply for review of the order dated April 9, 2021.

The applicant had applied for review of the order dated April

9, 2021. Such review petition had been withdrawn with

liberty to file a fresh by an order dated February 10, 2022.

The applicant had thereafter filed the present review

application along with the application for stay.

12. The order dated November 26, 2021 passed by the

Hon'ble Supreme Court granting liberty to the applicant

herein to file a review application with regard to the order

dated April 9, 2021 has noted that, R N Samanta (supra)

and South-Eastern Coalfields Ltd (supra) were not placed

before the Court on April 9, 2021.

13. R N Samanta (supra) has been rendered in an

application under Section 11 of the Arbitration and

Conciliation Act, 1996. A similar settlement of disputes

clause had been considered. The last clause in that case

which is same as that of the one obtaining in the present

case, has been understood not to amount to an arbitration

agreement between the parties. Consequently, the

application under Section 11 of the Arbitration and

Conciliation Act, 1996 had been dismissed as not

maintainable.

14. South-Eastern Coalfields Ltd (supra) has considered

an appeal against an order passed under Section 9 of the

Arbitration and Conciliation Act, 1996. It has considered a

similar clause of settlement of disputes as obtaining in the

present case. In fact, the last paragraph of the settlement of

disputes clause in that case is the same as the one

obtaining in the present case. It has held that, such a

clause cannot be construed to mean that there was an

arbitration agreement between the parties.

15. In Mahanadi Coalfields Ltd (supra) the Supreme

Court has considered the same last paragraph as obtaining

in the clause relating to settlement of disputes in the

present case. It has observed as follows: -

"10. In the present case, clause 15 of the Contract Agreement is titled "Settlement of Disputes/Arbitration". However, the substantive part of the provision makes it abundantly clear that there is no arbitration agreement between the parties agreeing to refer either present or future disputes to arbitration.

11. Clause 15.1 contains a reference to the steps to be taken for settlement of disputes between the parties. Clause 15.2 stipulates that if differences still persist, the settlement of the disputes with government agencies shall be dealt with in accordance with the guidelines of the Ministry of Finance. In the case of parties other than government agencies, the redressal of disputes has to be sought in a court of law.

13. The above extract makes it abundantly clear that clause 15 of the Contract Agreement is a dispute resolution mechanism at the company level, rather than an arbitration agreement. Consequently, in case of a dispute, the respondent was supposed to write to the Engineer-in-charge for resolving the dispute. Clause 15 does not comport with the essential attributes of an arbitration agreement in terms of section 7 of the 1996 Act as well as the principles laid down under Jagdish Chander (supra). A plain reading of the above clause leaves no manner of doubt about its import. There is no written agreement to refer either present or future disputes to arbitration. Neither does the substantive part of the clause refer to arbitration as the mode of settlement, nor does it provide for a reference of disputes

between the parties to arbitration. It does not disclose any intention of either party to make the Engineer-in- Charge, or any other person for that matter, an arbitrator in respect of disputes that may arise between the parties. Further, the said clause does not make the decision of the Engineer-in-Charge, or any other arbitrator, final or binding on the parties. Therefore, it was wrong on the part of the High Court to construe clause 15 of the Contract Agreement as an arbitration agreement."

16. The last paragraph of the settlement dispute clause as

obtaining in the present case and R N Samanta (supra),

South-Eastern Coalfields Ltd (supra) and Mahanadi

Coalfields Ltd (supra) and which has been considered in

the three authorities is as follows: -

"In case of parties other than Govt. Agencies, the redress of the dispute may be sought in the Court of Law."

17. Such paragraph in the settlement dispute clause of the

contract has been construed not to be an arbitration

agreement between the parties by the Hon'ble Supreme

Court in Mahanadi Coalfields Ltd (supra) and by our

High Court in R N Samanta (supra) and South Eastern

Coalfields Ltd (supra).

18. Learned advocate appearing for the respondent has

submitted that, the conduct of the applicant prior to the

application under Section 11 of the Arbitration and

Conciliation Act, 1996, during the pendency of such

applications, during the hearing on April 9, 2021 and its

conduct subsequent to such order, should be taken into

consideration by the Court in order to arrive at the finding

that, there was an arbitration agreement between the

parties.

19. Section 2 (b) read with Section 7 of the Arbitration and

Conciliation Act, 1996 enjoins the existence of a writing of

the parties agreeing to refer present or future disputes to

arbitration. There has to be an agreement in writing

between the parties to refer the disputes to arbitration

conduct will not substitute the statutory requirement of an

agreement in writing. The Court while considering an

application under Section 11 of the Arbitration and

Conciliation Act, 1996 has to arrive at a finding, even on a

prima facie basis, if the fact situation so warrants, that,

there exists an arbitration agreement between the parties in

writing.

20. In the facts of the present case, the settlement of

disputes clause has seven paragraphs. The first paragraph

requires the contractor to avoid litigation and disputes

during the course of execution of the work. It provides that

should disputes take place, then effort should be made first

to settle the disputes at the company level. The second

paragraph requires the contractor to make a request in

writing to the Engineer in Charge for settlement of disputes.

The third paragraph envisages resolution of the disputes in

two stages. The fourth paragraph recognises the first stage.

It requires the dispute to be referred to the area chief

general manager, general manager at the first stage. If

difference still persists then the dispute is to be referred to a

committee constituted by the owner. The fifth paragraph

speaks of the second stage. The second stage provided in

the fifth paragraph is broken into two parts. In the first

part, disputes relating to commercial contracts with Central

Public Sector Enterprises/Government Departments (except

Railways, Income Tax, Customs and Excise Duties)/State

Public Sector Enterprises are to be referred by either party

for Arbitration to the PMA (Permanent Machinery of

Arbitration) in the Department of Public Enterprises. The

second part specifies that, in case of parties other than

government agencies, the redress of the dispute may be

sought in the Court of law.

21. It has to be held that, the parties herein are guided by

the second part of the relevant settlement of disputes clause

as, the respondent is not a central public sector enterprise

or a state public sector enterprise or a government

department.

22. Learned advocate appearing for the respondent has

juxtaposed the word "shall" used in the fifth paragraph 1 st

portion with the word "may" appearing in the second portion

of such paragraph. He has contended that, the word "may"

used in the clause permits the respondent to approach for

arbitration in addition to approaching the Court of law.

Such contention cannot be accepted in view of the

authoritative pronouncements in R N Samanta (supra),

South-Eastern Coalfields Ltd (supra) and Mahanadi

Coalfields Ltd (supra). In absence of a written agreement

to refer the present and future disputes to the contract to

arbitration, the conduct between the parties cannot be

construed to mean that, the parties had agreed to

arbitration.

23. In the facts of the present case, there is no positive

assertion on the part of the applicant herein that it had

agreed to arbitration. The applicant herein had been silent

with regard to the existence of the arbitration agreement

between the parties in the affidavit in opposition which it

had filed in AP No. 371 of 2020. It had allowed the Court to

record that, the existence of arbitration agreement is not

disputed, on April 9, 2021, when the Court was considering

the application under Section 11 (6) of the Arbitration and

Conciliation Act, 1996. However, the fundamental basis for

referring the parties to arbitration being an arbitration

agreement in writing between them, never existed between

the parties for the applicant herein to waive or acquiesce

any of its rights.

24. There had been disputes between the parties with

regard to the existence of the arbitration agreement itself in

Pravin Electricals Private Limited (supra). The

arbitration agreement was claimed to be in the consultancy

agreement dated July 7, 2014 which one of the parties

thereto had contended that it had never entered into it. In

such context, the Supreme Court has held that, where it is

not possible for a Court exercising jurisdiction under

Section 11 of the Arbitration and Conciliation Act, 1996, to

weed out manifestly and ex-facie non-existent and invalid

arbitration agreements and non arbitrable disputes, then, in

such cases, the issue of the existence of arbitration

agreement can be referred to the arbitrator for

determination as a preliminary issue. Such fact scenario is

not obtaining in the present case inasmuch as, three

authorities had construed the clause in question and held

that, it did not amount to an arbitration agreement.

Therefore, in view of such authoritative pronouncements, it

cannot be said that, there is any issue with regard to the

existence of the arbitration agreement requiring reference to

the arbitrator for determination as a preliminary issue.

25. In view of the discussions above, RVWO No. 2 of 2022

is allowed. The order dated April 9, 2021 is reviewed and

held that, there is no arbitration agreement between the

parties. AP No. 371 of 2020 is therefore dismissed as not

maintainable in view of nonexistence of arbitration

agreement between the parties. No order as to costs.

26. In view of this judgement and order, no further order

need be passed in the pending interim application. The

same may also be treated as disposed of by the Department.

[DEBANGSU BASAK, J.]

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter