Citation : 2022 Latest Caselaw 2211 Cal/2
Judgement Date : 18 August, 2022
1
IN THE HIGH COURT AT CALCUTTA
Ordinary Original Civil Jurisdiction
Original Side
IA NO. GA/1/2022
In RVWO/2/2022
EASTERN COALFIELDS LIMITED
Vs.
RREPL-KIPL (JV)
With
IA NO. GA/2/2022
In RVWO/2/2022
EASTERN COALFIELDS LIMITED
Vs.
RREPL-KIPL (JV)
IN
A.P. NO. 371 OF 2020
For the Applicant : Mr. Manik Das, Adv.
Ms. Tanushree Dasgupta, Adv.
For the Respondent : Mr. Sudip Deb, Adv.
Mr. Riju Ghosh, Adv.
Hearing concluded on : August 12, 2022 Judgment on : August 18, 2022 DEBANGSU BASAK, J. :-
1. The applicant has applied for review of the judgement
and order dated April 9, 2021 passed in AP No. 371 of 2020.
The applicant has also applied for stay of the operation of
such order by way of an interim application filed in the
review petition. Both the applications for stay as well as the
review petition have been heard analogously.
2. The respondent herein had applied under Section 11 of
the Arbitration and Conciliation Act, 1996 for appointment
of an arbitrator in respect of disputes arising out of a
contract entered into between the respondent and the
applicant which the respondent claimed to contain an
arbitration agreement. Such application under Section 11 of
the Arbitration and Conciliation Act, 1996 had been
disposed of by an order dated April 9, 2021 review of which
has been sought in the present review petition.
3. Learned advocate appearing for the applicant has
submitted that, the applicant had preferred a special leave
petition before the Hon'ble Supreme Court against the order
dated April 9, 2021 passed in AP No. 371 of 2020. The
special leave petition had been disposed of by the order
dated November 26, 2021. By the order dated November 26,
2021, the Hon'ble Supreme Court had permitted the
applicant to file a review application before the High Court.
Pursuant to such liberty being granted, the applicant had
filed a review petition which was dismissed as withdrawn
with liberty to file a fresh on February 10, 2022.
Subsequent thereto, the applicant had filed the present
review application.
4. Learned advocate appearing for the applicant has
referred to the clause alleged to be containing the
arbitration agreement. He has submitted that, similar
clauses in contracts have been considered by a single judge
of this Hon'ble Court, the division bench of this Hon'ble
Court, and the Hon'ble Supreme Court. In all such
occasions, the Courts had held that, such clause does not
contain any arbitration agreement. He has relied upon the
order dated December 22, 2021 passed in AP No. 817 of
2021 (R N Samanta Versus Coal India Ltd), judgement
and order dated June 27, 2018 passed in FMA 1497 of
2018 (South-Eastern Coalfields Ltd versus Cart Road
Wings JV), and the judgement and order dated July 25,
2022 passed in Civil Appeal No. 4914 of 2022
(Mahanadi Coalfields Ltd versus M/s IVCL AMR Joint
Venture) in support of his contentions.
5. Learned advocate appearing for the respondent has
submitted that, the order dated April 9, 2021 was passed
largely on consent of the parties. He has referred to the body
of the order dated April 9, 2021. He has submitted that,
immediately after the arbitration clause contained in the
agreement having been set out in the order dated April 9,
2021, the Court had recorded that, the existence of
arbitration agreement is not disputed. He has contended
that, such recording in the order tantamount to the parties
to the litigation, agreeing to the existence of an arbitration
agreement governing the disputes between the parties. He
has drawn the attention of the Court to the fact that, the
applicant subsequently raised counterclaim as against the
respondent.
6. Learned advocate appearing for the respondent has
drawn the attention of the Court to the conduct of the
applicant subsequent to the order dated April 9, 2021. He
has contended that, the applicant had waived its alleged
right of review of the order dated April 9, 2021 by conduct of
the applicant subsequent to the order dated April 9, 2021.
The applicant had participated in the arbitration
proceedings unconditionally. The applicant had applied
under Section 16 of the Arbitration and Conciliation Act,
1996. He has referred to the minutes of the meeting of the
arbitral tribunal dated July 31, 2022. He has contended
that, the applicant has not taken any steps thereafter with
regard to the finding of the arbitral tribunal as recorded in
the minutes of the meeting July 31, 2022.
7. Learned advocate appearing for the respondent has
referred to the clause in the contract containing the
arbitration agreement between the parties. He has
submitted that, the second last paragraph contains the
word 'shall' whereas the last paragraph of such clause
contains the word 'may'. He has contended that, in respect
of parties other than government agencies, the redressal of
the disputes was left to the discretion of the party who is
not a government agency. According to him, the options
available to a party other than government agencies, are to
approach a Court of law or to invoke the provisions of the
Arbitration and Conciliation Act, 1996. In the facts of the
present case, the respondent had invoked the provisions of
the Arbitration and Conciliation Act, 1996. The applicant
had participated in the arbitration proceedings. The
respondent had accepted that such clause means that there
was an arbitration agreement between the contracting
parties as will appear from the body of the order dated April
9, 2021.
8. Learned advocate appearing for the respondent has
relied upon 2021 Volume 5 Supreme Court Cases 671
(Pravin Electricals Private Limited versus Galaxy Infra
And Engineering Private Limited) and contended that,
when the issue of the existence of an arbitration agreement
requires a deeper consideration than a prima facie
examination, then, the matter should be left for final
determination by the arbitral tribunal. In the facts of the
present case, he has submitted that, since a deeper
consideration of the clause is required so as to return a
conclusive finding as to the existence of the arbitration
agreement, the same may be referred to the arbitral tribunal
already appointed. He has therefore contended that, the
application for review should be dismissed.
9. The applicant had issued an electronic tender dated
December 18, 2017 for hiring of HEMM for re handling
39.20L cum OB from existing dump near Bhadotola for safe
extraction of coal near west side of Bhadotola of RCML
patch at Rajmahal Area. The respondent had been formed
on December 20, 2017 pursuant to a joint-venture
agreement between diverse private companies.
10. The respondent had participated in the electronic
tender of the applicant and was successful therein. The
applicant had awarded the work contained in the electronic
tender dated December 18, 2017 to the respondent. The
applicant had issued a letter of acceptance dated February
14, 2018 and a work order dated April 18, 2018 in favour of
the respondent. The work order dated April 18, 2018 and
the electronic tender dated December 17, 2017 have the
same settlement of disputes clause. The settlement of
disputes clause appearing in both the electronic tender
dated December 17, 2018 and the work order dated April
18, 2018 to which, the parties have referred to in course of
the hearing, is as follows: -
"13. Settlement of Disputes It is incumbent upon the contractor to avoid litigation and disputes during the course of execution. However, if such disputes take place between the contractor and the department, effort shall be made first to settle the disputes at the company level.
The contractor should make request in writing to the Engineer-in-charge for settlement of such disputes/claims within 30 (thirty) days of arising of the cause of dispute/claim failing which no disputes/claims of the contractor shall be entertained by the company.
Effort shall be made to resolve the dispute in two stages.
In first stage dispute shall be referred to Area CGM, GM. If difference still persists the dispute shall be referred to a committee constituted by the owner. The committee shall have one member of the rank of Director of the company who shall be chairman of the company.
If differences still persist, the settlement of the dispute shall be resolve in the following manner:
Sector Enterprises/Govt. Departments (except Railways, Income Tax, Customs & excise duites)/ State Public Sector Enterprises shall be referred by either party for Arbitration to the PMA (Permanent
Machinery of Arbitration) in the department of Public Enterprises.
In case of parties other than Govt. Agencies, the redressal of the dispute may be sought in the Court of law."
11. Disputes and differences had arisen between the
parties with regard to the working of the contract in relation
to the electronic tender dated December 17, 2017. The
respondent had applied under Section 11 (6) of the
Arbitration and Conciliation Act, 1996 which was disposed
of by the order dated April 9, 2021. The special leave
petition directed against such order was disposed of by the
order dated November 26, 2021 permitting the applicant
herein to apply for review of the order dated April 9, 2021.
The applicant had applied for review of the order dated April
9, 2021. Such review petition had been withdrawn with
liberty to file a fresh by an order dated February 10, 2022.
The applicant had thereafter filed the present review
application along with the application for stay.
12. The order dated November 26, 2021 passed by the
Hon'ble Supreme Court granting liberty to the applicant
herein to file a review application with regard to the order
dated April 9, 2021 has noted that, R N Samanta (supra)
and South-Eastern Coalfields Ltd (supra) were not placed
before the Court on April 9, 2021.
13. R N Samanta (supra) has been rendered in an
application under Section 11 of the Arbitration and
Conciliation Act, 1996. A similar settlement of disputes
clause had been considered. The last clause in that case
which is same as that of the one obtaining in the present
case, has been understood not to amount to an arbitration
agreement between the parties. Consequently, the
application under Section 11 of the Arbitration and
Conciliation Act, 1996 had been dismissed as not
maintainable.
14. South-Eastern Coalfields Ltd (supra) has considered
an appeal against an order passed under Section 9 of the
Arbitration and Conciliation Act, 1996. It has considered a
similar clause of settlement of disputes as obtaining in the
present case. In fact, the last paragraph of the settlement of
disputes clause in that case is the same as the one
obtaining in the present case. It has held that, such a
clause cannot be construed to mean that there was an
arbitration agreement between the parties.
15. In Mahanadi Coalfields Ltd (supra) the Supreme
Court has considered the same last paragraph as obtaining
in the clause relating to settlement of disputes in the
present case. It has observed as follows: -
"10. In the present case, clause 15 of the Contract Agreement is titled "Settlement of Disputes/Arbitration". However, the substantive part of the provision makes it abundantly clear that there is no arbitration agreement between the parties agreeing to refer either present or future disputes to arbitration.
11. Clause 15.1 contains a reference to the steps to be taken for settlement of disputes between the parties. Clause 15.2 stipulates that if differences still persist, the settlement of the disputes with government agencies shall be dealt with in accordance with the guidelines of the Ministry of Finance. In the case of parties other than government agencies, the redressal of disputes has to be sought in a court of law.
13. The above extract makes it abundantly clear that clause 15 of the Contract Agreement is a dispute resolution mechanism at the company level, rather than an arbitration agreement. Consequently, in case of a dispute, the respondent was supposed to write to the Engineer-in-charge for resolving the dispute. Clause 15 does not comport with the essential attributes of an arbitration agreement in terms of section 7 of the 1996 Act as well as the principles laid down under Jagdish Chander (supra). A plain reading of the above clause leaves no manner of doubt about its import. There is no written agreement to refer either present or future disputes to arbitration. Neither does the substantive part of the clause refer to arbitration as the mode of settlement, nor does it provide for a reference of disputes
between the parties to arbitration. It does not disclose any intention of either party to make the Engineer-in- Charge, or any other person for that matter, an arbitrator in respect of disputes that may arise between the parties. Further, the said clause does not make the decision of the Engineer-in-Charge, or any other arbitrator, final or binding on the parties. Therefore, it was wrong on the part of the High Court to construe clause 15 of the Contract Agreement as an arbitration agreement."
16. The last paragraph of the settlement dispute clause as
obtaining in the present case and R N Samanta (supra),
South-Eastern Coalfields Ltd (supra) and Mahanadi
Coalfields Ltd (supra) and which has been considered in
the three authorities is as follows: -
"In case of parties other than Govt. Agencies, the redress of the dispute may be sought in the Court of Law."
17. Such paragraph in the settlement dispute clause of the
contract has been construed not to be an arbitration
agreement between the parties by the Hon'ble Supreme
Court in Mahanadi Coalfields Ltd (supra) and by our
High Court in R N Samanta (supra) and South Eastern
Coalfields Ltd (supra).
18. Learned advocate appearing for the respondent has
submitted that, the conduct of the applicant prior to the
application under Section 11 of the Arbitration and
Conciliation Act, 1996, during the pendency of such
applications, during the hearing on April 9, 2021 and its
conduct subsequent to such order, should be taken into
consideration by the Court in order to arrive at the finding
that, there was an arbitration agreement between the
parties.
19. Section 2 (b) read with Section 7 of the Arbitration and
Conciliation Act, 1996 enjoins the existence of a writing of
the parties agreeing to refer present or future disputes to
arbitration. There has to be an agreement in writing
between the parties to refer the disputes to arbitration
conduct will not substitute the statutory requirement of an
agreement in writing. The Court while considering an
application under Section 11 of the Arbitration and
Conciliation Act, 1996 has to arrive at a finding, even on a
prima facie basis, if the fact situation so warrants, that,
there exists an arbitration agreement between the parties in
writing.
20. In the facts of the present case, the settlement of
disputes clause has seven paragraphs. The first paragraph
requires the contractor to avoid litigation and disputes
during the course of execution of the work. It provides that
should disputes take place, then effort should be made first
to settle the disputes at the company level. The second
paragraph requires the contractor to make a request in
writing to the Engineer in Charge for settlement of disputes.
The third paragraph envisages resolution of the disputes in
two stages. The fourth paragraph recognises the first stage.
It requires the dispute to be referred to the area chief
general manager, general manager at the first stage. If
difference still persists then the dispute is to be referred to a
committee constituted by the owner. The fifth paragraph
speaks of the second stage. The second stage provided in
the fifth paragraph is broken into two parts. In the first
part, disputes relating to commercial contracts with Central
Public Sector Enterprises/Government Departments (except
Railways, Income Tax, Customs and Excise Duties)/State
Public Sector Enterprises are to be referred by either party
for Arbitration to the PMA (Permanent Machinery of
Arbitration) in the Department of Public Enterprises. The
second part specifies that, in case of parties other than
government agencies, the redress of the dispute may be
sought in the Court of law.
21. It has to be held that, the parties herein are guided by
the second part of the relevant settlement of disputes clause
as, the respondent is not a central public sector enterprise
or a state public sector enterprise or a government
department.
22. Learned advocate appearing for the respondent has
juxtaposed the word "shall" used in the fifth paragraph 1 st
portion with the word "may" appearing in the second portion
of such paragraph. He has contended that, the word "may"
used in the clause permits the respondent to approach for
arbitration in addition to approaching the Court of law.
Such contention cannot be accepted in view of the
authoritative pronouncements in R N Samanta (supra),
South-Eastern Coalfields Ltd (supra) and Mahanadi
Coalfields Ltd (supra). In absence of a written agreement
to refer the present and future disputes to the contract to
arbitration, the conduct between the parties cannot be
construed to mean that, the parties had agreed to
arbitration.
23. In the facts of the present case, there is no positive
assertion on the part of the applicant herein that it had
agreed to arbitration. The applicant herein had been silent
with regard to the existence of the arbitration agreement
between the parties in the affidavit in opposition which it
had filed in AP No. 371 of 2020. It had allowed the Court to
record that, the existence of arbitration agreement is not
disputed, on April 9, 2021, when the Court was considering
the application under Section 11 (6) of the Arbitration and
Conciliation Act, 1996. However, the fundamental basis for
referring the parties to arbitration being an arbitration
agreement in writing between them, never existed between
the parties for the applicant herein to waive or acquiesce
any of its rights.
24. There had been disputes between the parties with
regard to the existence of the arbitration agreement itself in
Pravin Electricals Private Limited (supra). The
arbitration agreement was claimed to be in the consultancy
agreement dated July 7, 2014 which one of the parties
thereto had contended that it had never entered into it. In
such context, the Supreme Court has held that, where it is
not possible for a Court exercising jurisdiction under
Section 11 of the Arbitration and Conciliation Act, 1996, to
weed out manifestly and ex-facie non-existent and invalid
arbitration agreements and non arbitrable disputes, then, in
such cases, the issue of the existence of arbitration
agreement can be referred to the arbitrator for
determination as a preliminary issue. Such fact scenario is
not obtaining in the present case inasmuch as, three
authorities had construed the clause in question and held
that, it did not amount to an arbitration agreement.
Therefore, in view of such authoritative pronouncements, it
cannot be said that, there is any issue with regard to the
existence of the arbitration agreement requiring reference to
the arbitrator for determination as a preliminary issue.
25. In view of the discussions above, RVWO No. 2 of 2022
is allowed. The order dated April 9, 2021 is reviewed and
held that, there is no arbitration agreement between the
parties. AP No. 371 of 2020 is therefore dismissed as not
maintainable in view of nonexistence of arbitration
agreement between the parties. No order as to costs.
26. In view of this judgement and order, no further order
need be passed in the pending interim application. The
same may also be treated as disposed of by the Department.
[DEBANGSU BASAK, J.]
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!