Citation : 2021 Latest Caselaw 5616 Cal
Judgement Date : 9 November, 2021
Form J(2) IN THE HIGH COURT AT CALCUTTA
Criminal Appellate Jurisdiction
Appellate Side
Present :
The Hon'ble Justice Bibek Chaudhuri
C.R.R. 2959 of 2004
With
IA NO. CRAN 1 of 2019 (Old No. CRAN 2357 of 2019)
Dipankar Chatterjee
Vs.
S.Kundu Inspector of Factories, W.B.
For the petitioner : Mr.Sandipan Ganguly, Sr. Adv.
Mr.Somopriyo Choudhury, Adv.
Mr.Arunabha Deb, Adv.
Mr. Ayush Jain, Adv.
For the State : Mr. Sandip Chakrabarty, Adv.
Heard on : 08.11.2021
Judgment On : 09.11.2021
Bibek Chaudhuri, J.
Affidavit-of-service be kept with the record.
The instant criminal revision under Section 482 of the Code of
Criminal Procedure praying for quashing of proceedings in Case No.C-
2895 of 2000 pending before the learned Chief Judicial Magistrate,
Alipore, South-24-Parganas under Section 92 of the Factories Act and
all orders passed therein including order dated 18 th May, 2001.
Indisputably the petitioner is a business man. He used to carry
on a business under the name and style of "Dipankar Industries" at
premises No.1, Nimak Mahal Road within South Port Police Station. It
is the case of the complainant that the petitioner set up a factory as
per approved plan dated 17th December, 1993. On 14th September,
2000, the complainant inspected the said factory premises and found
that the petitioner constructed the said factory deviating from the
approved plan. One door on the existing western side of the wall of
the machine room and five windows of the entire south side wall of
the machine room and office room were not yet constructed, in
contravention to the provision of Rule 3(3) of the West Bengal
Factories Rules, 1958, prescribed under the provision of Section 6(1)
and 112 of the Factories Act, 1948. It was alleged that such deviation
in constructing the factory amounts to an offence under Section 92 of
the Factories Act. On the basis of the said complaint, the learned
Chief Judicial Magistrate, Alipore took cognizance of the offence.
It is submitted by Mr. Sandipan Ganguly, learned Senior
Advocate on behalf of the petitioner that the petitioner used to
manufacture audio cassette cover in his factory. At present the said
factory is closed. He also submits under instruction that on the date
of inspection of the factory by the complainant, the construction of
the factory was not completed. It is pertinent from the written
complaint itself that the complainant has alleged that the petitioner
has not yet constructed the door and windows in the factory premises
as per the approved plan. According to Mr. Ganguly the word "yet" in
the petition of complaint denotes that the construction work was yet
to be completed on the date of inspection of the factory by the
complainant. Mr.Ganguly further submits that subsequently the
petitioner constructed one door and five windows in his factory
premises as per the approved plan. So he has prayed for quashing of
the entire proceedings in case No.C-2895 of 2000.
Section 92 of the Factories Act, 1948 is the provision for general
penalty for offences. The provision runs thus:-
"92. General penalty for offences.- Save as is otherwise
expressly provided in this Act and subject to the provisions of Sec.93,
if in, or in respect of, any factory there is any contravention of the
provisions of this Act or of any rules made thereunder or of any order
in writing given thereunder, the occupier and manager of the factory
shall each be guilty of an offence and punishable with imprisonment
for a term which may extend to [two years] or with fine which may
extend to [one lakh rupees] or with both, and if the contravention is
continued after conviction, with a further fine which may extend to
[one thousand rupees] for each day on which the contravention is so
continued:
[Provided that where contravention of any of the provisions of
Chapter IV or any rule made thereunder or under Sec.87 has resulted
in an accident causing death or serious bodily injury, the fine shall not
be less than [twenty-five rupees] in the case of an accident causing
death, and [five thousand rupees] in the case of an accident causing
serious bodily injury."
Rule 3(1) of the West Bengal Factories Rules, 1958 deals with
approval of site and plan. It is provided that no building shall be
constructed, extended or taken into use as a factory or a part of a
factory on any site unless previous permission in writing has been
obtained from the State Government or the Chief Inspector for the
site and for the construction, extension or use of the building on such
site. Rule 3(3)of the said Rules states that no deviation of any kind
from approved plan shall be made without written permission of the
Chief Inspector.
During the pendency of the instant revision for last 17 years,
the opposite party, the Inspector of Factories did not appear in spite
of service of notice. However, the State of West Bengal is
represented by Mr.Sandip Chakrabarty.
A close perusal of Rule 3(3) read with Section 92 of the
Factories Act goes to show that deviation of any kind from approved
plan in constructing factory is not per se an offence inviting penalty
under Section 92 of the Factories Act. If the Inspecting Officer finds
some deviation in construction of a factory from the approved plan,
he is under obligation to give an opportunity to the occupier or the
user of the factory to obtain written permission of the Chief Inspector.
If Chief Inspector on consideration of the extent of deviation does not
grant permission, then only there will be violation of Rule 3(3) of the
West Bengal Factories Rules, 1958. On the first blush no complaint
can be lodged by the Inspector of Factories finding deviation in
construction from the approved plan. He shall first give opportunity
to the factory owner to obtain written approval from the Chief
Inspector to regularize such deviation.
In the instant case, no document has been filed on behalf of the
opposite party or the State of West Bengal under whom the opposite
party is a functionary to show that opportunity was given to the
petitioner to regularize the deviation by filing an application before
the Chief Inspector. During the hearing of the instant proceeding, the
learned Advocate for the State fails to file any approved plan of the
factory in question. There is no report as to whether the construction
work of the factory was complete or not. In the absence of such
documents, I am of the considered view that it was not proper for the
learned Chief Judicial Magistrate, Alipore to take cognizance on the
basis of the written complaint.
As the petitioner was not given opportunity to regularize so-
called deviation from the approved plan, while constructing factory
and that the petitioner has completed the construction following the
approved plan by setting up the door and windows in the factory, I
find that the instant complaint is not maintainable.
As a result, the instant criminal revision is allowed on contest,
however, without costs.
The order of taking cognizance by the learned Chief Judicial
Magistrate, South-24-Parganas at Alipore in C Case No.2835 of 2000
on 15th September, 2000 and all subsequent orders are quashed.
(Bibek Chaudhuri, J)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!