Citation : 2021 Latest Caselaw 3579 Cal
Judgement Date : 6 July, 2021
IN THE HIGH COURT AT CALCUTTA
CIVIL APPELLATE JURISDICTION
The Hon'ble Justice Harish Tandon
And
The Hon'ble Justice Kausik Chanda
F.A.T. 294 OF 2019
With
CAN 1 OF 2019 (Old CAN 5852 OF 2019)
With
CAN 2 OF 2019 (Old CAN 5854 OF 2019)
EXECUTIVE OFFICER, BURDWAN DEVELOPMENT AUTHORITY
-VERSUS-
SK. KORBAN AND ANOTHER.
For the appellant : Mr. Sorujit Nath Mitra, Sr. Adv.,
Mr. Arindam Banerjee, Adv.,
Ms. Sanchari Chakroborty, Adv.,
Mr. Soumik Chakraborty, Adv.,
Mr. Sarosij Dasgupta, Adv.
For the respondent no. 1 : Mr. Gopal Ghosh, Adv.,
Mr. Prabir Rej, Adv.
Hearing concluded on : 09.03.2021 Judgment on : 06.07.2021 Kausik Chanda, J.:-
This is an application for condonation of delay of 2684 days in preferring
the present appeal beyond the statutory period for preferring the appeal.
(2) This appeal has been preferred against an award dated 21 ST January,
2012 passed by the learned Additional District Judge, 1 st Court, Burdwan, in
Land Acquisition Case no. 39 and 127 of 2010. By the impugned award the
learned Judge in the Court below determined the market price of the land in
question @ Rs. 35 lakh per acre. In the said award, other components of
compensation in terms of the Land Acquisition Act, 1948 were also awarded in
favour of respondent no. 1/opposite party no. 1.
(3) It has been contended in the application for condonation of delay that
after the award was passed by the Court below, the then Executive Officer of
the petitioner immediately took steps to obtain a certified copy of the judgment
and decree and instructed their Advocate for taking steps who did not take any
initiative.
(4) Thereafter, there was a change in the post of Executive Officer till
December, 2017 for a number of times. Due to frequent changes in the head of
the organization, the said Executive Officer in the short tenure, could not take
any effective steps for preferring the appeal before this Court arising out of the
said land acquisition proceeding. Especially, due to the splitting of Burdwan
district into two parts.
(5) The petition for condonation of delay further explains that a new Chief
Executive Officer was appointed in the month of December, 2018 who
appointed a new Advocate for filing this appeal. It was found that most of the
papers were not available in the file and it took time till October, 2018 to
arrange for the papers, including the certified copy of the impugned order.
Thereafter, the puja vacation of the High Court intervened, and the appeal was
ultimately filed in the month of June, 2019 resulting in a delay of about 2684
days in preferring the appeal.
(6) To summarize, the petitioner sought to justify the delay by citing the
reasons including frequent change of key officials, unavailability of the record
and delay on the part of Advocates.
(7) It has further been stated that there are a number of appeals already
filed against similar type of judgments whereby the compensation amount was
fixed @ Rs. 35 lakh per acre. A list of such appeals has been annexed to this
application for condonation of delay. The petitioner contended that for the
purpose of maintaining uniformity in the rate of compensation awarded against
the relevant Mouza, this appeal preferred should also be heard along with other
pending appeals.
(8) In support of such contention, the petitioner relies upon a judgment
passed by a Division Bench of this Court in FAT 587 of 2014 (CAN 12049 of
2014) (Executive Officer, Burdwan Development Authority vs. Anwar Ali
and Others) whereby a delay of 1235 days in filing the appeal, arising out of a
Land Acquisition case concerning the same Mouza was allowed.
(9) Though on January 24, 2020 the respondent no.1/opposite party no. 1
intended to file an affidavit-in-opposition to this application, for condonation of
delay, no such opposition has been filed by the respondent no.1/opposite party
no. 1.
(10) The respondent no.1/opposite party, however, verbally submitted at the
time of hearing that the petitioner could not explain the delay in preferring the
appeal beyond the statutory period of limitation. It was further submitted that
such inordinate and huge delay in preferring the appeal could not be condoned
in view of the judgments reported in Basawraj vs. The Spl. Land Acquisition
Officer [(AIR 2014 SC 746)], Pundlik Jalam Patil (D) by Lrs. vs. Exe. Eng.
Jalgaon Medium Projects [(2008) 17 SCC 448)].
(11) We may also notice some recent judgments of the Supreme Court where
the Apex Court observed that no latitude should be shown to the Government
or its instrumentalities in considering the delay for filing an appeal beyond the
statutory period of limitation. (See: Postmaster General vs. Living Media
India Limited, [(2012) 3 SCC 563], State of Madhya Pradesh vs. Bherulal
[(2020) 10 SCC 654]). The judgments relied upon by respondent no.
1/opposite party no. 1 also support such proposition.
(12) We, however, feel it is necessary to take into consideration the judgment
passed in FAT 587 of 2014 (CAN 12049 of 2014) (Executive officer, Burdwan
Development Authority vs. Anwar Ali and Others) where it has been held as
follows:-
" That apart when several appeals have already been filed and those are still under consideration before us, we do not feel that the State gained anything to the prejudice of the respondents by not filing this appeal within the prescribed period of limitation.
Accordingly, we hold that the explanations which were given for the delay in this application are sufficient to condone the delay.
That apart, we find that for maintaining uniformity in the process of assessment of compensation of the lands situated in the same Mouza covered under several notifications issued for the same project, this appeal should also be decided along with the other pending appeals."
(13) Though there has been much more delay in preferring the present appeal
in comparison with the aforesaid case, it is necessary for the sake of comity,
uniformity and consistency in judicial decision to follow the said judgment
passed by a coordinate bench which held that appeals arising out of the said
land acquisition proceeding pending in this Court should be heard together to
avoid the conflicting decision with regard to payment of compensation.
(14) Accordingly, this application is allowed subject to payment of Rs. 2 (two)
lakh as costs to be paid by the appellant. Appellant shall deposit such cost to
the State Legal Services Authority, West Bengal within a period of four weeks
from date. If such a deposit is made, the State Legal Services Authority will
keep the said amount in the account earmarked for the juvenile. In default,
this order will automatically stand recalled, and the application for
condonation of delay be dismissed.
(15) The application being CAN 1 of 2019 (Old CAN 5852 of 2019) is, thus,
disposed of.
(16) Urgent certified website copy of this judgment, if applied for, be given to
the parties upon compliance with all requisite formalities.
I agree.
(Harish Tandon, J.) (Kausik Chanda, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!