Citation : 2021 Latest Caselaw 1727 Cal/2
Judgement Date : 24 December, 2021
IN THE HIGH COURT AT CALCUTTA
ORIGINAL CIVIL JURISDICTION
(Original Side)
A.P. No. 394 of 2021
(Through Video Conference)
Reserved on: 16.12.2021
Pronounced on: 24.12.2021
BTL EPC Limited
...Petitioner
-Vs-
Steel Authority of India Limited
...Respondent
Present:-
Mr. Rantanko Banerji, Senior Advocate Mr. Soorjya Ganguli, Ms. Radhika Misra, Advocates ... for the petitioner
Mr. Sauvik Nandy, Advocate ... for the respondent
Coram: THE HON'BLE JUSTICE PRAKASH SHRIVASTAVA, CHIEF JUSTICE
Prakash Shrivastava, CJ:
1. This application under Section 11 of the Arbitration and
Conciliation Act, 1996 (for short, 'the Act') has been filed by the
petitioner BTL EPC Limited with the plea that the contract agreement
dated 28th December, 2010 was entered into between the respondent
Steel Authority of India Limited and a consortium comprising of the
M/s. Bengal Tools Limited (Consortium Leader and Contractor) and
one M/s. The Eastern Research and Development Institute of Coal
Chemistry (Consortium Member and Contractor) for the work of Final
Gas Cooling cum Naphthalene Scrubbing Unit and Benzol Absorption
and Benzol Distillation Plant at Durgapur Steel Plant. Eastern
Research and Development Institute of Coal Chemistry was a
company incorporated under the Laws of Russian Federation (Russian
entity) and the consortium agreement was entered into between the
petitioner and the Russian entity on 25th of March, 2009. According to
the petitioner the work was successfully completed on or about 19th of
March, 2015 but while releasing the payment certain amount was
wrongly deducted from the bills. As per the averments, the petitioner
being the leader of the consortium was to get all the payments from
the respondent and thereafter the same was to be released to the
Russian entity for its scope of work. The attempts were made to
resolve the dispute amicably. Thereafter, petitioner had sent the letter
dated 9th of November, 2019 invoking the arbitration clause and
nominating a retired Judge as its member for arbitration and
requesting the respondent to nominate its arbitrator and thereafter the
petitioner has filed the present petition.
2. Learned Counsel for the respondent has raised objection and
has opposed the prayer for appointment of arbitrator on the ground
that this petition under Section 11 of the Act is not maintainable
because in terms of the arbitration clause, petitioner is required to
approach the ICC and that similar petition was filed before the Delhi
High Court which was dismissed as withdrawn with liberty to
approach the appropriate forum i.e. ICC, therefore, this fresh
application under Section 11 of the Act is not maintainable and that
the petition suffers from the defect of non-joinder of parties and even
otherwise the conciliation proceedings are in progress, therefore, the
issue of appointment of arbitrator does not arise.
3. Learned Counsel for the petitioner has supported the plea of
plea for appointment and has submitted that in terms of the arbitration
clause, petition under Section 11 is maintainable and the objection
relating to non-joinder of parties is not sustainable and that the
Russian partner has already sent the communication dated 31st August,
2021 annexure 'J' indicating that he does not want to be the party in
the Court.
4. I heard learned Counsel for the parties and perused the
record.
5. The Arbitration Agreement dated 28th December, 2010 is
not in dispute which contains the following arbitration clause:
"9.1 Conciliation and Arbitration Any disputes, differences, whatsoever, arising between the parties out of or relating to the construction, meaning, scope, operation or effect of this Contract shall be settled between the Employer and the Contractor amicably. If however, the Employer and the Contractor are not able to resolve their disputes/differences amicably as aforesaid the said disputes/differences shall be settled by Conciliation, failing which, through Arbitration.
Conciliation shall be resorted to prior to invoking Arbitration. The Arbitration Clause is to be invoked by the parties to the Contract only on failure of conciliation proceedings to amicably settle the disputes.
The arbitration shall be governed in accordance with The Arbitration and Conciliation Act, 1996 (hereinafter referred to as the "Act") of India. The language of Arbitration shall be English.
Subject to the stipulations made hereinabove, Arbitration shall be governed by the Rules of Arbitration of International Chamber of Commerce (ICC), Paris. The venue of the arbitral proceedings shall be New Delhi.
During the pendency of the Conciliation or Arbitration proceedings both the parties (i.e. the Contractor and the Employer) shall continue to perform their contractual obligations.
The arbitral tribunal shall give reasons for its award. The tribunal shall apportion the cost of arbitration between the parties, the award rendered in any arbitration hereunder shall be final and binding upon the parties, the parties agree that neither party shall have any right to commence or maintain any suit or legal proceeding concerning any dispute under this agreement until the dispute has been determined in accordance with the arbitration proceeding provided for herein and then only to enforce or facilitate the execution of an award rendered in such arbitration.
Unless otherwise mentioned, the Arbitration shall be held at Durgapur, West Bengal, India. The court of Durgapur, West Bengal, India shall have exclusive jurisdiction over all matters of dispute."
6. The arbitration clause provides that the arbitration will be
governed by the Rules of Arbitration of International Chamber of
Commerce (ICC), Paris. Article 4 Rule 1 of ICC Rules requires a
party wishing to have recourse to arbitration under the Rules to submit
its request for arbitration to the Secretariat. Hon'ble Supreme Court in
the matter of Standard Corrosion Controls Private Limited vs.
Sarku Engineering Services SDN BHD, reported in (2009) 1 SCC
303 in a case where the arbitration clause contained the provision
about arbitration as per Rules of ICC has held that:
"9. Since the parties could not agree, the applicant applied to this Court under Section 11(5) of the Act for appointment of an arbitrator. A counter-affidavit has been filed by the respondent and I have perused the same. The respondent has relied on Article X of the agreement dated
21-2-2006 between the parties and has urged that the arbitration has to be held at Mumbai but by applying the Arbitration Rules of the ICC.
10. As per the Rules of Arbitration of ICC, the party who wishes to have recourse to arbitration under the said Rules is required to request for arbitration to the ICC Secretariat. The respondent submitted that the applicant has not followed that procedure for appointment of an arbitrator because it has not submitted any request to the ICC Secretariat. Instead, the applicant has rushed to this Court without following the procedure mentioned in Article X of the arbitration agreement.
11. Annexed to the counter-affidavit are the Rules of the ICC and I have perused the same. Admittedly, the applicant has not made any request for arbitration to the ICC Secretariat. Hence, in my opinion, this application is not maintainable at all.
12. There is no dispute that the applicant had, with open eyes, signed the contract dated 21-2-2006, which contains Article X, quoted above.
13. Learned counsel for the applicant submitted that the Arbitration Rules of the ICC cannot prevail over the parliamentary law, which is the Arbitration and Conciliation Act, 1996. In my opinion, it is true that a statute overrides the contract, but it has to be noticed that Section 11(2) of the Act states that subject to sub-section (6), the parties are free to agree on a procedure for appointing the arbitrator or arbitrators. Admittedly, the conditions mentioned in sub- section (6) of Section 11 are not attracted in this case. Hence, the procedure to appoint an arbitrator agreed upon by the parties will be applicable.
14. As already stated above, the parties had agreed that any dispute between them shall be settled as far as possible by mutual consultation and consent, failing which by arbitration to be held at Mumbai applying the Arbitration Rules of the ICC. In my opinion, the applicant has to apply
to the Secretariat of the ICC, as mentioned in the Arbitration Rules of the ICC, and it cannot approach this Court for appointment of an arbitrator. No doubt, the arbitration will have to be held at Mumbai, but the entire procedure of appointment of the arbitrator has to be in accordance with the Arbitration Rules of the ICC, which requires that first a request has to be made to the Secretariat of the ICC. Admittedly, the applicant has not approached the ICC Secretariat. Hence, in my opinion, the application filed by the applicant herein, is not maintainable at all. This Court in a series of decisions has held that such an application/petition without approaching the authority nominated and agreed upon by the parties is not maintainable vide Iron & Steel Co. Ltd. v. Tiwari Road Lines, Rite Approach Group Ltd. v. Rosoboronexport, etc."
7. In the matter of Standard Corrosion Controls Private
Limited (supra), the Hon'ble Supreme Court has taken the view that
the applicant is required to approach the Secretariat of the ICC and
cannot approach the Court for appointment of arbitrator. In the matter
of Antrix Corporation Limited vs. Devas Multimedia Private
Limited reported in (2014) 11 SCC 560 has taken the view that where
the parties had agreed that procedure for arbitration will be governed
by the ICC Rules, the same would necessarily include the appointment
of an arbitral tribunal in terms of the arbitration agreement and the
said Rules.
8. An argument has been advanced by the Counsel for the
petitioner that the arbitration clause also provides that arbitration shall
be governed by in accordance with the Arbitration and Conciliation
Act, 1996 but the same will not come in the way of adopting the
procedure for arbitration and conducting the arbitration in accordance
with the ICC Rules.
9. In the present case, nothing has been pointed out to show
that any request was made to the ICC Secretariat therefore, in terms of
judgments noted above, application under Section 11 of the Act
cannot be maintained.
10. It is worth mentioning that the petitioner had approached
the Delhi High court by filing ARB.P. 5/2021 wherein an objection
was taken by the respondent in its counter-affidavit regarding
availability of remedy in terms of ICC Rules and Delhi High Court
had dismissed the petition as withdrawn by passing the following
order:
"1. Mr. Pradeep Gupta, learned Counsel for the petitioner, seeks leave to withdraw the petition with liberty to file a representation before the appropriate forum. Without expressing any opinion on the jurisdictional aspect, leave and liberty is granted, as prayed for.
2. The petition is dismissed as withdrawn."
11. The learned Counsel for the respondent is justified in
making submission that by the above order liberty was granted for
filing representation before the appropriate forum having regard to the
objection about applicability of ICC Rules and there was no liberty to
file a fresh application under Section 11 before this Court.
12. Counsel for the petitioner has placed reliance upon the
judgment of the Supreme Court in the matter of Walter Bau AG,
Legal Successor, of the Original Contractor, Dyckerhoff and
Widmann A.G vs. Municipal Corporation of Greater Mumbai
and Another, reported in (2015) 3 SCC 800 but that was a case of
appointment of arbitration without compliance with the agreed
procedure, hence the same will not be applicable in the facts of the
present case.
13. That apart, it is also noticed that in the arbitration
agreement M/s. The Eastern Research and Development Institute of
Coal Chemistry, Russian partner is also a signatory as consortium
member and contractor but it has not been impleaded as applicant,
respondent or proforma respondent, therefore, the reliance of Counsel
for the petitioner on his communication dated 31st August, 2021
annexure 'J' is of no consequence. Counsel for the petitioner has
relied upon the judgment of the Hon'ble Supreme Court in the matter
of Larsen and Toubro Limited Scomi Engineering BHD vs.
Mumbai Metropolitan Region Development Authority, reported in
(2019) 2 SCC 271 but in that case the application under Section 11 of
the Arbitration Act was dismissed by the Hon'ble Supreme Court
reaching to the conclusion that the lead member of the consortium was
in India and the central management and control of consortium was to
be exercised in India and not in any foreign nation, therefore, it was
found that there was no international commercial arbitration in terms
of Section 2(1)(f) of the Act, hence the said judgment is of no help to
the petitioner. The petitioner has not impleaded the Russian
consortium member who is also signatory to the agreement. Thus the
application also suffers from the defect of non-joinder of necessary
party.
14. The reply filed by the respondent also reveals that in terms
of the agreement the conciliation procedures are in progress and the
amicable discussions were held as recently on 03.09.2021 and pending
the said discussions this application has been filed. The petitioner has
not exhausted the procedure prescribed in the arbitration clause.
15. In the above circumstances, no case is made out for
allowing the prayer for appointment of an arbitrator under Section 11
of the Act. Hence, A.P. No. 394 of 2021 is dismissed.
(PRAKASH SHRIVASTAVA) CHIEF JUSTICE
Kolkata 24.12.2021 ___________ PA(SS/RB)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!