Citation : 2021 Latest Caselaw 1654 Cal/2
Judgement Date : 20 December, 2021
In The High Court at Calcutta
Constitutional Writ Jurisdiction
Original Side
The Hon'ble Justice Sabyasachi Bhattacharyya
WPO No. 281 of 2020
Madho Das Mundhra
Vs.
Railtel Corporation of India Limited and another
For the petitioner : Mr. Suddhasatva Banerjee,
Mr. S. Dasgupta
For the respondents : Mr. Vikas Baisya
Hearing concluded on : 22.11.2021 Judgment on : 20.12.2021 The Court:
1. The petitioner has challenged the Notice Inviting Tender (NIT) dated
August 26, 2020, floated by the respondent-authorities for deployment
of maintenance teams for maintenance of Optical Fibre Cable
Network. The date stipulated for seeking clarification regarding NIT
was September 4, 2020 (12 noon to 2.00 pm), the bid submission was
to start on September 10, 2020 and end on September 24, 2020 at
2.00 pm.
2. Learned counsel for the petitioner, allegedly an intending bidder,
contends that although the petitioner sought for certain clarifications
regarding certain terms of the tender notice by a letter dated
September 3, 2020, the reply thereto, given by the respondent-
authorities, did not carry any such clarification worth the name.
Subsequently, the present writ petition was affirmed on September
18, 2020 and filed before the last date of submitting bids.
3. Learned counsel for the petitioner argues that the petitioner is entitled
to challenge the NIT even without having participated in the tender
process, since the petitioner, being a prospective bidder, has
challenged the legality and constitutionality of several terms of the
tender documents itself which, according to the petitioner, are unfair
and illegal.
4. In further reply, the learned counsel distinguishes a judgment
reported at (2020) SCC OnLine (Cal) 2213 [Subir Ghosh Vs. State of
West Bengal and others], which was cited by the respondents. Counsel
contends that, in the said case, the online bid submission date was
April 1, 2019, but the writ petition was filed in January, 2020. In
such context, it was found that a person who has not participated in
the bidding process at all cannot challenge the tender conditions on
any ground whatsoever.
5. However, in the present case, the petitioner has affirmed and filed the
writ petition before closure of the submission of bids.
6. While seeking to distinguish another judgment cited by the
respondents, reported at (2018) 8 SCC 243 [National Highways
Authority of India Vs. Gwalior Jhansi Expressway Limited], learned
counsel for the petitioner contends that the same is inapplicable to
the facts of the present case. In the said judgment, the Apex Court
held that, having failed to participate in the tender process, the
respondent in that matter could not contend similar rights as bidders
who had participated in the process.
7. However, in the said decision, the Supreme Court considered the fact
that the validity of the tender document itself had not been challenged
before any competent forum, as opposed to the present case. It is
argued that the petitioner does not complain of any breach or non-
fulfilment of the terms and conditions of the tender but challenges the
clauses of the tender itself.
8. As far as the other unreported judgment cited by the respondents,
passed in A.P.O.T. No.98 of 2021 [Madho Das Mundhra Vs. Railtel
Corporation of India and another] is concerned, learned counsel for the
petitioner submits that no ratio was laid down therein and the same
was an order passed in connection with an interlocutory application.
9. Learned counsel submits that, on the contrary, if the petitioner had
participated in the tender process and then sought to challenge the
terms of the tender, the petitioner would have been barred from doing
so by the principle of estoppel.
10. In support of such contention, learned counsel for the petitioner cites
M/s. Opaque Infrastructure Private Limited Vs. Union of India and
another, reported at MANU/DE/0964/2015, Poorvanchal Caterers &
Anr. Vs. Indian Railway Catering and Tourism Corporation Limited &
Ors., reported at 2009 SCC OnLine (Delhi) 1012 and the judgment of
the Supreme Court rendered in Tafcon Projects (I) (P) Ltd. Vs. Union of
India and others, reported at (2004) 13 SCC 788. Learned counsel
submits that, as per the proposition laid down in the said judgments,
a bidder having participated in a tender process cannot challenge the
tender terms on the ground of vagueness subsequently.
11. The challenge to the tender terms and conditions was necessarily
required to be made prior to participation. For the proposition that
the petitioner would have been precluded from challenging the clauses
of the tender after participation, learned counsel for the petitioner also
cites New Bihar Biri Leaves Co. And others Vs. State of Bihar and
others, reported at (1981) 1 SCC 537.
12. Learned counsel for the petitioner next argues that in the instant
case, the tender conditions are vague and uncertain and, as such,
deny the petitioner a level playing field with the other operators who
had participated in the tender process, many of whom had previous
experience of working on earlier identical projects of the Railways and
thus privy to many information regarding the ground realities and
conditions of the optical fibres-in-question. This, the petitioner argues,
violates Articles 14 and 19(1)(g) of the Constitution of India.
13. Clause 11 of the NIT, it is argued, reserves right unto the respondents
to add or delete any maintenance section, which made the tender
process extremely uncertain. Several particulars were supposed to be
furnished by the bidders along with other bids, which could only be
ascertained on the basis of such maintenance sections. In the
absence of relevant particulars being furnished, the intended bids
would be treated as incomplete. Learned counsel argues that the
right so reserved by Clause 11 of the NIT affects the commercial
viability of the work itself and would tantamount to reserving unto the
respondents the right to change the rules of the game after the game
has commenced, which is impermissible in law. There could not be
any effective participation in the tender process without knowing the
exact contours off the maintenance clause.
14. The NIT further required a contractor to accept the site on 'as is where
is' basis, as per Clause 1.1.1 of Chapter V of the NIT. The said Clause
also mandates that the awardee would be fully responsible for the
end-to-end performance between two nodes in the entire jurisdiction
of the team's reach. However, no provision was given in the NIT
allowing the intending tenderers to survey the routes and/or test the
quality and condition of the existing fibre. Without such survey, it
was not possible to commercially arrive at an amount by way of
estimate for the purpose of bid. Optical Time-Domain Reflectometer
(OTDR) is a fibre optic instrument used to test detailed information
regarding overall condition of the fibre. It is evident from the NIT
conditions that all the other participating bidders were privy to such
OTDR test reports and the exact condition of the fibre, having been
engaged on previous occasions for work in respect of the same
sections.
15. Withholding such information was deliberate, it is argued, to ensure
favouritism and encourage cartelization, which is contrary to Article
14 of the Constitution of India.
16. Learned counsel for the petitioner further argues that it has been
consistently held by various High Courts in exercise of their powers
under Article 226 of the Constitution of India that, in a tender process
pertaining to State resources and/or contract, the endeavour is to
fetch the best possible price, to be secured through maximum
participation of intending bidders.
17. Such opportunity was denied to the petitioner and others who are on
the same footing by dint of the prior special knowledge of most of the
other bidders, which amounts to violation of Articles 14, 19(1)(g) and
21 of the Constitution of India.
18. On the other hand, learned counsel appearing for the respondent-
authorities submits that the tender document was approved by the
Competent Authority and the entire contents of the terms thereof are
uniform throughout all regions of India - East, West, North and
South. The discretion given to the corporate office is extremely limited
in respect of the discretion to vary the terms.
19. In this case, the respondent-authorities, it is argued, had given
sufficient reply to the petitioner's query.
20. Fifteen different sections are covered by the NIT and the technical and
financial criterion are to be met separately for each of the sections of
the total length of fibre for an appropriate evaluation of the bid.
Keeping in view past experience and considering the imperative
aspect, since the work related to a public interest and involved
expenditure of public money, the tender process, it is submitted,
ought not to be interfered with.
21. Learned counsel for the respondent-authorities next contends that
there were total 100 participants, within whom 80 were existing
contractors and 20 new contractors who participated in 15 different
sections.
22. In view of the extreme urgency of the work covered by the NIT, which
plays a pivotal role in the signalling system of railways, since the
respondent-authorities are technology (ICT) infrastructure providers,
the entire work could not be stopped and, therefore, the work orders
were issued even during pendency of the writ petition.
23. In another writ petition, bearing WPO No.71 of 2021, between the
same parties, the petitioner has also challenged the NIT Clauses
pertaining to five different sections
24. Learned counsel for the respondent next argues that the petitioner
does not have the locus standi to file the application under Article 226
of the Constitution of India, since the petitioner did not participate in
the tender process at all.
25. In such context, the respondents place reliance on the following
judgments:-
(i) 2020 SCC OnLine Cal 2213 (Subir Ghosh Vs. State of West Bengal & Ors.);
(ii) (2018) 8 SCC 243 (National Highway Authority of India Vs. Gwalior Jhansi Expressway Limited); and
(iii) A.P.O.T. No.98 of 2021 (Madho Das Mundhra Vs. Railtel Corporation of India & Anr.
26. The respondent-authorities cites the abovementioned judgments to
clinch the issue as regards the absence of locus standi of the
petitioner to prefer the instant challenge, in view of having not
participated in the tender process intentionally. It is reiterated by
learned counsel that the interest of the public at large cannot be put
at stake at the whims of the petitioner, since the work relates to the
controlling of the signalling system of the Railways.
27. That apart, it is argued that the tender terms are in the realm of
contract and cannot be altered and/or amended, since the same has
been drafted upon considering every aspect regarding the interest and
safety of the public at large and are uniform in respect of all zones of
India.
28. As such, it is contended that the writ petition ought to be dismissed.
29. As regards maintainability of the writ petition and the petitioner's
locus standi to file the writ petition, despite having abstained from
participating in the tender process, the Division Bench judgment of
this Court in Subir Ghosh (supra) lays down the ratio that it is
possible that a prospective bidder finds the terms of the tender
documents to be unfair or illegal and challenges the same; but such
challenge has to be before the time to put in the bids is closed. In the
present case, the petitioner did precisely that and, as such, the said
ratio cannot be held to go against the petitioner. Albeit, it was further
observed by the Division Bench that if a bid is made and thrown out
on an illegal or unfair ground contained in the tender document, even
then a challenge can be fashioned, but a person who has not
participated in the bidding process at all cannot challenge the tender
conditions on any ground whatsoever, such subsequent observation
was qualified by the preceding phrase in paragraph no.5 of the said
judgment which says that a challenge against unfair or illegal terms of
the tender document is maintainable before the closure of the
submission of the bids.
30. As far as National Highways Authority of India (supra) is concerned,
although in the context of the case the challenge against the tender
was refused on the ground on non-participation of the tenderer, the
Supreme Court clearly held in paragraph no.18 of the said judgment
that the tenor of the terms of the documents made it obligatory for the
respondent to so participate to be considered as a responsive bidder
along with others. Such perspective is further reflected in Clause 30.5
of the tender document in the said case, where it was provided that,
notwithstanding anything to the contrary, for the purposes of
eligibility and qualification of the BOT-Annuity Concessionaire, if it
has participated in the bidding process it shall be deemed to fulfil all
the requirements of Clauses 3 and 6 of the RFP, being the existing
concessionaire of the Four-Lane Project. Similar provisions found
place in several other clauses of the tender as well, including Clauses
3.2(f), 26.9 and 27.6 of the said tender document, as quoted in
paragraph no.8 of the cited report.
31. As such, the proposition laid down in the said case was in the limited
factual context which arose therein, which are clearly distinguishable
from the present case insofar as there is no participation clause in the
NIT of the present case.
32. As far as Madho Das Mundhra (supra) is concerned, with utmost
respect, the said judgment does not lay down any proposition of law
but merely records the facts and circumstances of the case, in which
context the judgment was passed. Hence, the said Division Bench
judgment does not help the objection raised by the respondents on the
locus standi of the petitioner.
33. On the other hand, in M/s. Opaque Infrastructure Private Limited
(supra), which is cited by the petitioner, the contrary proposition was
upheld and it was found that the bidder would be barred by the
principle of estoppel from challenging the tender process if it had
participated in the process and thereafter sought to challenge the
same. It was categorically laid down that the law precludes a person
from challenging the tender terms after having participated in the
same. The same proposition of law was followed in Poorvanchal
Caterers (supra) by the Delhi High Court and in Tafcon Projects (I) (P)
Ltd. (supra) by the Supreme Court. As such, the issue of
maintainability is held in favour of the petitioner and against the
respondents, as the present writ petition is held maintainable at the
instance of the petitioner.
34. The cardinal premise of challenge of the petitioner in the writ petition
is that the tender conditions are vague and uncertain and deny the
petitioner a level playing field.
35. In that context, several issues have been raised by the petitioner
which pertain to various facets of the tender document.
36. To address such issues, a perusal of the NIT itself and its annexures
is essential.
37. It is seen from the entire tender document that the work was divided
into several specific units, for each of which separate tenders with
separate criteria were to be filed by the prospective bidders.
38. The different maintenance sections are clearly indicated in a chart
given in Annexure-A of Section 1, Chapter 1 of the tender document,
which is exhaustive in nature.
39. Immediately after the chart, a pre-bid meeting was mentioned as
scheduled to be held on September 4, 2020 at 12.00 hours. Even the
venue of the meeting was clearly indicated.
40. Thus, there was ample scope for the petitioner to approach the tender-
issuing authorities for necessary clarifications and raise their
objections by participating in the said meeting. However, for
unexplained reasons, the petitioner did not avail of such opportunity.
41. The respective scope of work in the various sections is also reflected,
even to a layman, from a complete reading of the tender terms. For
example, another chart is given in Annexure C in Chapter 7 of the NIT
indicating in detail the jurisdiction of the OFC maintenance sections.
The length and bi-monthly cumulative repair time allowed were clearly
indicated against each of the fifteen sections.
42. That apart, the right reserved by the Railtel, to add or delete any
maintenance section, was clearly coupled with the rider that payment
would be made as covered in the preamble. It is specifically stated in
the NIT (Section 1, Chapter 1, Annexure-A) that evaluation shall be
done section-wise. If interpreted literally, in the absence of any
ambiguity, the terms of the tender document were clear enough to
indicate that the reserved right of the Railtel did not pertain to
addition or deletion to any section, on any yardstick whatsoever, but
the addition or deletion of entire maintenance sections to the work of
a particular contractor.
43. Hence, the allegation of the petitioner, that the rules of the game were
kept open to be changed after the game has started, has no basis
whatsoever. Not only were the specific areas of the respective
maintenance sections and other specifications clearly mentioned in
the NIT, Chapter 8, Annexure-D thereof clearly mentioned in detail the
minimum manpower and machine/equipment required to be engaged
under one maintenance team. Each detail of such requirement was
specifically laid down under the said head.
44. That apart, Clause 16 of the General Conditions mentioned in the
tender document clearly provided that, before quoting, the tenderers
were advised to ascertain the nature of work involved and invariably
undertake a site inspection. Thus, the allegation that the prospective
bidders were denied the right to examine the existing optical fibres
before submitting their bid does not hold water.
45. It was further mentioned in Clause 3.2 of Chapter 5 of the NIT that,
before quoting, it was advisable that the prospective tenderers should
make themselves fully conversant with the locations, OFC routes and
types of jobs in details to be carried out therein as per the tender
requirement, so that they can clearly understand the scope of work
and assess the requirement of resources to complete the work in a
scheduled time.
46. The nature of the work to be done was clearly elaborated in several
clauses of the tender document.
47. It was merely for the petitioner to approach the tendering authority for
the purpose of getting a clear picture of the existing condition and the
dimensions of the existing optical fibre cables, as provided galore in
the several terms and conditions of the NIT itself. Hence, the
petitioner's objection, that there was no such scope to pre-assess the
conditions and parameter of the existing cables and routes, is belied
by the provisions of the NIT itself.
48. As regards the further allegations of the petitioner that, as per the
NIT, the list of personnel for maintenance was to be submitted with
the bid, financial and technical criterion to be met separately for each
section and that the number of personnel was to be given, which was
allegedly not possible within the scope of the NIT, it is evident from
the NIT terms that amply opportunity was given to the prospective
bidders to assess the scope and ambit of the work to be done. The
petitioner, of his own choice, failed to avail such option.
49. Hence, although it was stipulated in the NIT that the contractor has to
do the work on 'as is where is' basis, in view of the right of prior
inspection given in the tender document itself, as discussed above,
there was no hindrance to the petitioner taking adequate inspection to
ascertain the existing scenario in terms of the NIT itself and thereafter
to submit their bid.
50. Hence, in the present case, the allegations of vagueness and
favouritism, levelled by the petitioner, are falsified by the terms and
conditions of the tender document itself. To any bona fide bidder,
there could not have been any difficulty in having an inspection and to
ascertain, prior to the bid, the exact nature of the work to be done and
the extent thereof.
51. That apart, since specific date, time and venue were fixed for the pre-
bid meeting, it was always open to the petitioner to participate in the
said meeting for the purpose of further elucidation of doubts, if any.
Instead of doing so, the petitioner preferred to take out the writ
petition prior to the last date of submission of dues, which would
unnecessarily stall the work envisaged by the tender.
52. Since the work contemplated in the tender is of a public nature and
concerns the safety and security of the public at large and public
utility in general, there is no justification in setting aside the entire
tender process merely because of the perceived inconvenience of the
petitioner.
53. There cannot arise any question of favouritism or arbitrariness on the
part of the tendering authority in view of the clear contours of the
contemplated work being provided in the tender document itself.
54. It is well-settled that a tender process is set aside by courts only in
exceptional circumstances and certainly not because the terms of the
tender do not suit an individual prospective bidder. In the present
case, several bidders participated and many got selected on the same
terms and conditions which are complained of by the petitioner.
55. Moreover, the petitioner has not denied the respondents' specific
contention that the terms of the tender document are uniform for all
similar tenders floated by the Railways throughout the country. As
such, picking and choosing certain clauses or altering them merely
because it would convenience the petitioner does not even come
within the zone of consideration for maintaining a writ petition.
56. In view of the above, WPO No. 281 of 2020, being devoid of merits, is
dismissed on contest.
57. There will be no order as to costs.
58. Urgent certified copies of this order shall be supplied to the parties
applying for the same, upon due compliance of all requisite
formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!