Citation : 2021 Latest Caselaw 2922 Cal
Judgement Date : 22 April, 2021
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
RVW 2 of 2021
IA No: CAN 1 of 2021
In
WPA 10069 of 2020
Sundarananda Barman and another
Vs.
The State of West Bengal and others
For the review
applicants-petitioners : Mr. Swarup Banerjee,
Mr. Manoj Kumar Bhattacharyya
For the
respondent no.1 : Mr. Samrat Sen,
Mr. Amitava Mitra
Hearing concluded on : 16.04.2021
Judgment on : 22.04.2021
Sabyasachi Bhattacharyya, J:-
1. Since the arguments of the applicants in the review petition and
respondent no.1 were recorded at length in the order dated April 16,
2021, those are not being narrated again in order to avoid
unnecessary repetition. However, such arguments are considered and
referred to in the following order.
2. The review applicants primarily rely on certain documents which,
although in the custody of the applicants when the order under review
was passed, were not with learned counsel for the applicants at that
point of time, due to which those could not be placed before Court on
the said date.
3. The first such document is a print-out of Clause 70.0, which is the
Force Majeure clause contained in the tender agreement entered into
between the applicants and the tender issuing authority. Such clause
is reproduced below:
"70.0 FORCE MAJEURE
If, at any time during the currency of the Contract, the performance in whole
or in part by either party of any obligation under this Contract shall be
prevented or delayed by reason of any war, hostilities, invasion, acts of public
or foreign enemies, rebellion, revolution, insurrection, civil commotion,
sabotage, large scale arson, floods, earthquake, large scale epidemics,
nuclear accidents, any other catastrophic unforeseeable circumstances,
quarantine restrictions, any statutory rules, regulations, orders or requisitions
issued by a Government department or competent authority or acts of God
(hereinafter referred to as "event") then, provided notice of the happening of
such an event is given by either party to the other within 21 days of the
occurrence thereof.
a. Neither party shall by reason of such event be entitled to terminate the
Contract or have claim for damages against the other in respect of such non-
performance or delay in performance."
4. The applicants also rely on a communication dated May 25, 2020
issued from the end of the applicants to the Vice-Chairman, Hooghly
River Bridge Commissioners, seeking further extension of the time for
completion of the work till March 31, 2021.
5. The other document relied on by the applicants is another
communication dated June 15, 2020, reiterating the previous request
for extension of time.
6. It is contended that the said documents, if considered by this Court
while passing the order under review, could have changed the
outcome of the writ petition.
7. By placing reliance on the relevant portions of the order under review,
dated December 9, 2020, learned counsel argues that the primary
basis of dismissal of the writ petition (WPA 10069 of 2020) was that
the applicants had not requested for extension of time before expiry of
the contract on its last-extended date, that is, May 31, 2020.
However, the communications-in-question clearly indicate that such
extension was actually sought by the applicants on May 25, 2020,
that is, prior to the expiry of the extended period of contract on March
31. 2020. As such, it is contended that the premise of the order
under review is rendered irrelevant in view of the said
communications.
8. The primary basis of the contentions of respondent no.1 is that the
materials now produced, even if shown to the court at the juncture
when the order under review was passed, would not have altered the
fate of the writ petition.
9. It has been argued by respondent no.1 that Clause 70.0 (a) restrains
both the parties to the agreement from terminating the contract or
claim for damages against the other in respect of such non-
performance or delay in performance.
10. In the present case, as observed in the order under review itself, the
termination was automatic, that is, by efflux of time. Hence, there
was no positive act of termination from the end of the tender issuing
authority.
11. The scope of a review application is limited. In the present case, no
error apparent on the face of the record is argued by the applicants,
nor was there any reason akin to the grounds provided in Order XLVII
of the Code of Civil Procedure. The only ground invoked by the
applicants is "discovery of new material". In the present case, the
applicants were fully aware and already in custody of the documents
now sought to be produced; but those were not annexed to the writ
petition by the petition. As such, it is doubtful as to whether, strictly
speaking, the documents come within the purview of "new material" or
could be said to have been discovered after the order under review
was passed.
12. However, even a liberal interpretation of such provision in favour of
the petitioner, insofar as it restricts either party to the contract from
terminating the contract or claiming damages by reason of large scale
epidemics or quarantine restrictions, which are mentioned among
other events in the said clause, in the present case there was no
termination from the end of the authorities, on such grounds or
otherwise. The termination was automatic by efflux of time within the
purview of the Indian Contract Act, 1872. Thus, the futile prayers for
extension, even if produced at the time of passing of the order under
review, could not have changed the fate of the writ petition.
13. As seen from the order under review dated December 9, 2020, the
premise of the order was that the contract came to an end by efflux of
time on May 31, 2020. It was categorically held that the impugned
letter dated July 8, 2020 was merely an intimation of the petitioners
based on the prior closure of jural relationship between the parties to
remove the construction materials and machineries of the petitioners
from the contractual site. However, the contract stood terminated on
May 31, 2020.
14. Although, incidentally, it was discussed in the order that the
applicants had a remedy in praying for extension within the extended
date of expiry and that no such prayer was made by the applicants,
the said observation was not the sole basis of the order. Since it was
the discretion of the tender issuing authority whether or not to further
extend the time for completion of the project and the tender issuing
authorities chose not to so extend, the documents sought to be
produced with the review application would not have altered the
outcome of the writ petition since, in any event, the contract expired
by efflux of time on May 31, 2020.
15. As discussed above, Clause 70.0 (a) of the agreement does not confer
any additional benefit on the applicants, since there was no positive
act of termination by the tenderer on the grounds contemplated
therein or otherwise. The termination being automatic, the materials
now placed before court along with the review application would have
been irrelevant for the purpose of deciding the writ petition and could
not have altered the conclusion reached in the order under review.
16. In such view of the matter, RVW 2 of 2021 along with CAN 1 of 2021,
filed in connection therewith, are dismissed.
17. There will be no order as to costs.
18. Urgent certified copies of this order shall be supplied to the parties
applying for the same, upon due compliance of all requisite
formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!