Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Dogus - Soma Joint Venture vs The State Of Maharashtra And 2 Ors.
2026 Latest Caselaw 2558 Bom

Citation : 2026 Latest Caselaw 2558 Bom
Judgement Date : 12 March, 2026

[Cites 12, Cited by 0]

Bombay High Court

Dogus - Soma Joint Venture vs The State Of Maharashtra And 2 Ors. on 12 March, 2026

Author: Bharati Dangre
Bench: Bharati Dangre
2026:BHC-OS:6882-DB

                                                  1/27             Dogas SOma.doc


                        IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                              ORDINARY ORIGINAL CIVIL JURISDICTION
                                    WRIT PETITION NO. 4583 OF 2022

               DOGUS - SOMA Joint Venture, a Joint           .. Petitioner
               Venture having its office at Recreation
               Garden, Plot No.1895, Sane Guruji
               Marg, Agripada, Mumbai-400011.

                                         Versus

               1. State of Maharashtra, through the          ..
               Government Pleader, High Court,
               Mumbai.
               2. The Revenue and Forest Department
               of the State of Maharashtra thru the               Respondents
               Collector of Bombay having office at
               Old Custom House, Fort, Mumbai.
               3. The Additional Collector (R/B),
               Old Custom House, Shahid Bhagat
               Singh Marg, Fort, Mumbai 400001.
                                                         ...
              Mr. Sriram Sridharan with Mr.Shanmuga Dev and Ms.Aditi Jain
              for the petitioner.
              Ms.Jyoti Chavan, AGP for the State.

                            CORAM : BHARATI DANGRE &
                                      MANJUSHA DESHPANDE, JJ
                             DATED : 12th MARCH, 2026.
              JUDGMENT (Per Bharati Dangre, J.)

1 The petitioner, a Joint Venture of Dogus Insaat Ve Ticaret A.S. and Soma Enterprise Ltd, participated in the bidding process when the Mumbai Metro Rail Corporation Limited (hereinafter referred to as 'MMRCL') invited bids for

Tilak

2/27 Dogas SOma.doc

design and construction of underground sections including five underground stations at Mumbai Central, Mahalaxmi, Science Museum, Acharya Atre Chowk and Worli and associated tunnels. The petitioner's bid was accepted on 1/7/2016 which was followed by a contract being awarded to the petitioner.

Under the contract, the petitioner was responsible for excavation and construction of underground tunnels and underground Metro Stations, and for undertaking the aforesaid activity, it was expected to conduct a detailed geological investigation of the areas at which these tunnels and metro stations were to be constructed.

The Contract stipulated specific conditions as regards excavation of the material as a part of execution of the project and instructions for deposit of the excess material at muck-disposal site.

2 We will be referring to the relevant clauses in the course of our deliberation, but at this stage, we take note of the contention of the petitioner that it followed the terms and conditions of the contract, relating to the disposal of the excavated and excess material and it is the case of the petitioner that he utilised the services of the sub-contractors who dumped the excavated ordinary earth at the dumping site at Dapode, and the petitioner did not commercially utilise the same nor did it earn any revenue therefrom. It is the case of the petitioner that it duly complied with all necessary formalities and obtained requisite permissions, licences etc from

Tilak

3/27 Dogas SOma.doc

the Traffic Police Department, Municipal Corporation of Greater Mumbai, Brihan Mumbai Electric Supply and Transport Undertaking. The petitioner also secured necessary permission from the Additional Collector for excavation and disposal of the excavated material for the design and construction of underground sections at the underground stations in the course of execution of the work allotted to it.

3 The petitioner, in undertaking the aforesaid exercise, carried an impression that the excavations being carried out in the execution of the project are not liable to the levy of royalty under the provisions of the Mines and Minerals (Development and Regulation Act), 1957 (for short, MMDR Act) or the Mineral Concession Rules, 1960 or even the Maharashtra Minor Mineral Extraction (Development and Regulation) Rules, 2013. However, as the petitioner wanted to avoid any practical difficulties as stoppage of his trucks which would cause delay in execution of the project, without prejudice to its rights and liabilities, the petitioner made payment of royalty on the material excavated by it in the course of construction in the underground sections and metro stations and the petition is filed claiming its refund. 4 The learned counsel Mr. Sriram Sridharan appearing for the petitioner urged before us that the case of the petitioner is strictly governed by the decision of the Apex Court in case of Promoters and Builders Association of Pune Vs. State of Maharashtra and ors,1 but it is his submission that though no 1 2015(12) SCC 736

Tilak

4/27 Dogas SOma.doc

demand of royalty was raised, the petitioner paid royalty @ Rs.400/- on the excavated material, at different sites with reference to the material excavated by it in the course of execution of the work and deposited the same through different challans. The petitioner paid a sum of Rs. 8,20,02,000/- by way of royalty and also paid a sum of Rs.1,45,000/- by way of application fees till September 2019.

The petition is accompanied with the copies of the challans under which the payment was made under protest.

It is urged on behalf of the petitioner that the amount of royalty paid was under protest, so as to avoid any practical hindrance in the execution of the project and after its payment, the petitioner sought appropriate legal advise and expressed to respondent no.3 that the royalty was not leviable on the activities carried out by the petitioner and sought its refund.

The first communication addressed by the petitioner to the Additional Collector is dated 5/8/2017, seeking refund of the amount by submitting that the excavation carried out do not attract royalty. The objection raised was very specific that the MMDR Act is enacted by the Parliament by invoking Entry No.54 of List-1 of Seventh Schedule of the Constitution, and since the said statute govern mines and mineral development, the State legislature is not empowered to legislate on the subject and if the MMDR Act levies royalty on extraction of material, the State cannot levy royalty on the same extraction.



Tilak





                                  5/27                 Dogas SOma.doc


Submitting that Section 9 of the MMDR Act provide for levy of royalty by the holders of a mining lease and Section 9-A thereof provide for payment of dead rent, the field according to the petitioner, is occupied and the State is automatically precluded from legislating on the same.

Apart from this, it was also urged that the activities carried out by the Joint Venture was in relation to the involved excavation for the purpose of constructing tunnels and metro stations and is not covered by the phrase "filling and levelling purposes" and the ordinary earth excavated by the petitioner is not covered by notification dated 3/2/2000 issued by the Central Government, notifying 'ordinary earth' used for levelling purposes in construction of embankments, roads, railways, buildings to be a minor mineral. Thus, contending that the excavated material was not 'minor mineral', it was urged that no royalty can be imposed.

Yet, another point which was canvassed by placing reliance upon the decision of the Apex Court in Promoters and Builders Association of Pune (supra), it was urged that it is only ordinary earth used for the purposes of filling or levelling in construction of embankments, roads, railways and buildings which is a minor mineral and excavation of ordinary earth for uses not contemplated in the aforesaid notification, would not amount to a mining activity so as to attract the wrath of provisions of the Code of 1957 Act.





Tilak





                                    6/27               Dogas SOma.doc


In these circumstances, it was urged that when the Additional Collector had granted permission for carrying out excavation at different sites, and the payment on such excavated material was done by the petitioner (Joint Venture) without prejudice to its rights and contentions, the amount is liable to be refunded as payment of royalty was not a pre- condition for grant of the permissions.

Thereafter, with reference to different payments made towards royalty, refund letters were addressed to the Additional Collector and when the amount is not refunded, the petitioner has chosen to approach this Court by seeking a declaration that the material excavated by the petitioner for the purposes of constructing Mumbai Metro underground station is not minor mineral as per notification No. GSR 95-E dated 3/2/2000 read with Section 3(e) of the Mines and Minerals (Development and Regulation) Act, 1957 and the activity do not amount to mining operation and thus, it is entitled for refund of Rs.8,20,02,000/- paid under protest. 5 Learned counsel for the petitioner has urged before us that the royalty or dead rent can be only levied under the provisions of MMDR Act an enactment of the Parliament and the corresponding entries in the State list for regulation of Mines and Regulation of Mineral Development is entry no.53 and 50 of List-2 which are subject to the provisions of List-1.

In exercise of Section 15 of the MMDR Act, the State has enacted Maharashtra Minor Mineral Extraction

Tilak

7/27 Dogas SOma.doc

(Development and Regulation) Rules 2013, which has levied royalty on extraction of minor minerals. By invoking Rule 46, it is the submission of the learned counsel that the lessee in terms of the said provision is liable to pay royalty on minor minerals removed from leased area at the rate specified by the Government from time to time on the date of grant of lease. It is his contention that pursuant to the decision of the Apex Court in Promoters and Builder's case, Rule 46 is amended by notification of 11/5/1950, which since then read as below :-

"46 Every quarry lease shall be subjected to conditions :-

(i) The lessee shall pay royalty on minor minerals removed from the leased area at the rates specified in Schedule I. Provided that, such rates may be revised only once in every three years.

Provided further that, no royalty shall be required to be paid on earth which is extracted while developing a plot of land and utilised on the very same plot for land levelling or any work in the process of development of such plot."

6 On behalf of the petitioner, on relying upon the aforesaid notification, it is contended that by, it is contended that a person who is involved in excavation activities would either be liable to royalty under section 9 of the MMDR Act, 1957, if minerals are being extracted or shall be liable to royalty under Rule 46 of the Mining Rules, if minor minerals are being extracted, subject to the proviso stipulated therein. 7 Learned counsel for the petitioner would submit that u/s.3(a) of the MMDR Act, minerals include all minerals except mineral oils and Section 3 has defined 'minor minerals' as building stones, gravel, ordinary clay, ordinary sand other

Tilak

8/27 Dogas SOma.doc

than the sand used for prescribed purposes, and any other mineral which the Central Government may notify and declare to be a minor mineral. Relying upon the said provision in the MMDR Act read with Rule 70 of the Central Mining Rules and various notifications issued from time to time, it is the contention of the petitioner that the material being excavated by the petitioner is nothing other than ordinary earth and therefore, do not fall within the category of 'minor mineral'.

The Central Government on 3/2/2000, vide notification No.GSR 95-E, notify 'ordinary earth used for filling or levelling purposes in construction of embankments, roads, railways, buildings' to be minor mineral. It is therefore the contention advanced on behalf of the petitioner that ordinary earth extracted and utilised for prescribed purposes alone shall amount to minor mineral and if it is not utilised for prescribed purpose, then, it will not amount to minor mineral, and therefore, only if ordinary earth is used for filling or levelling, it would be falling within the legislative purview of State Legislature, as if ordinary earth is used for purposes other than the one specified in the notification of 3/2/2000, then it is not a minor mineral and would be outside the ambit of State Legislature. It is therefore, the contention of the petitioner that the earth excavated is not used for filling or levelling purposes in construction of embankments, roads, railways and buildings, but the activity in which the petitioner was involved was of construction of tunnels for metro stations, and since it is not for

Tilak

9/27 Dogas SOma.doc

the purpose of filling or levelling purpose and when the ordinary earth excavated is carried away from the excavated site and dumped at specified locations and not used for re- filling or levelling, then it is not covered by notification of 3/2/2000 and therefore, the State is not empowered to regulate the excavated ordinary earth.

8 Strong reliance is placed upon the decision of Promoters and Builders Association of Pune (supra) where it is held that ordinary earth not used for the purposes specified in notification of 3/2/2000 is not minor mineral, and the imposition of penalty under Section 48(7) of the Maharashtra Land Revenue Code, 1966 for non-payment of royalty upon builders who were digging earth for the purpose of laying foundation of building, was held to be outside the purview of the State.

It is also the contention of the petitioner that the petitioner did not engage itself in any reconnaissance of prospecting activity and strictly speaking, the petitioner is not carrying out any mining operation as defined in Section 3(d) of the MMDR Act, 1957 as any operations undertaken for the purpose of 'winning of any mineral".

Thus, according to the learned counsel, if the purpose of the activity of excavation is other than recovery of the said material, then the activity is not mining operation and since the petitioner has not commercially exploited the excavated material and it is not engaged in the mining activity

Tilak

10/27 Dogas SOma.doc

and no royalty can be imposed upon the excavated material, as the operation of the petitioner was restricted to construction of underground tunnels and metro stations. Since the royalty paid by the petitioner was under a wrong premise that the royalty is payable and immediately after the payment, the petitioner sought its refund, according to the learned counsel, the refund shall be granted to the petitioner.

9 The relief prayed in the petition are strongly opposed by the Additional Government Advocate Ms.Jyoti Chavan and she would place reliance upon the affidavit filed by Dr. Mansi Marlewar, Tahsildar, Collector Office, Mumbai City, where a specific stand is adopted to the following effect :-

"3. At the outset I submit that the above Writ Petition is not maintainable as there is alternate efficacious remedy available to the Petitioner under the provisions of Maharashtra Land Revenue Code and Maharashtra Minor Minerals Extraction (Development and Regulations) Rules 2013.

4 I say that the Petitioner has categorically admitted in paragraph no.6 of the Writ Petition that the Petitioner were solely entitled to use the soil excavated and remove the said soil from the plot hence the judgment of Hon'ble Apex Court reported in 2015 12 SCC 736 is not applicable in the present case. Furthermore the Petitioner has admitted that upon excavation of soil he becomes the owner and hence under the provisions of Maharashtra Land Revenue Code read with Maharashtra Minor Minerals Extraction (Development and Regulations) Rules 2013, the Petitioner is liable to pay royalty.

5 I say that the other ground raised by the Petitioner that the Petitioner has paid royalty under protest is an after thought as the applications made by the petitioner to the Collector seeking permission does not mention that the petitioner has made royalty under protest."

10 Ms.Chavan would place reliance upon the decision of this Court in Ikea India Private Limited Vs. State of

Tilak

11/27 Dogas SOma.doc

Maharashtra through Revenue and Forest Department (Writ Petition No.494 of 2024 decided on 10/04/2024), and it is her contention that if any person without lawful authority extracts, removes, collects, replaces, picks up or disposes of any mineral from working or derelict mines, quarries, wherever situated, the right to which vests in, and has not been assigned by the State Government, shall be liable to pay penalty as contemplated under Section 48(7) of the MLR Code. According to her, when the petitioner, IKEA India, in the course of developing leasehold land to set up a large "IKEA Store" for retail of furniture and home furnishing, faced an auction of penalty for unauthorised excavation, the Division Bench considered the grievance of the petitioner in the background that the Tahsildar, Thane, on account of the unauthorised excavation of earth from the subject land where the development activity was to take place, and it invited payment of royalty, imposed the penalty at maximum level i.e. five times of the market value of excavated earth.

Recording that for payment of royalty towards extraction of "minor minerals" under Section 48(7) of MLRC, it was noted that the earth extracted must be intended to be put to use, as contemplated in the notification issued by the Government of India on 3/2/2000 and the notification clearly stipulated that the earth excavated towards filling and levelling purposes in construction of embankments, roads, railways, buildings, would constitute minor minerals.



Tilak





                                    12/27                       Dogas SOma.doc


With reference to the decision of the Apex Court in case of Promoters and Builders Association of Pune (supra), when the amendment was effected in Rule 46(1) of the Extraction Rules of the State Government, the Bench held that where the earth extracted while developing a plot of land is utilised on the same plot of land for levelling or any work in the process of development, no royalty shall be payable.

Referring to the pronouncements of the same Bench in AIGP Developers (Pune) Private Limited Vs. State of Maharashtra,2 the following conclusion is drawn :-

"19. Such an analysis flies in the face of the law declared inPromoters and Builders and AIGP Developers. The excavation of earth in the course of development would not automatically attract royalty. To the extent that such earth is redeployed in development of the very same plot of land, no royalty whatsoever would be attracted. Therefore, there is no question of there being any scope for alleging the need for a permit to extract earth. Consequently, there is no question of imposing penalty for non- payment of royalty. However, any quantum of excavated earth that is in excess of the redeployed earth that is required to be removed from that plot of land i.e. gets disposed in the market, would attract royalty under the MLRC.

20. A party developing a plot of land would have to estimate and reassess the quantum that may be required for redeployment and the quantum required to be removed. For the quantum redeployed, no royalty, and therefore, no authorisation would be required. For the quantum removed, royalty would be payable and permission for removal would be required. The explanation provided by Petitioner No.1 in response to the Second Show Cause Notice (which is reproduced in the December 2022 Order), sets out the sequence of such estimation and determination of the quantum of earth for which permissions and royalty became necessary. It is apparent that Petitioner No. 1 sought approvals from time to time in conformity with its intended removal of excavated earth. In line with the law declared in Promoters and Builders, and indeed in the evidently-consequential amendment to Rule 46(i) of the Extraction Rules, Petitioner No. 1 did not seek any permission for that quantum of excavated earth that was redeployed on the same plot of land."

2 2024 SCC Online 762

Tilak

13/27 Dogas SOma.doc

11 Apart from this, while quashing the impugned order, we must take note of paragraph no.25 of the observations which read thus :-

"25 In fact, by reason of Rule 46(1) of the Extraction Rules, the State ought to have dealt with the vital element of quantum of redeployment in order to assess what the charge of royalty should be. Abandoning this due process, Respondent No.3 has simply indulged in a mathematical computation of the difference between the Circle Officer's report and the permissions for removal obtained until the date of the report, rejecting approval for removal after that date. The State ought to have considered whether there was even a plausible rationale to any developer holding on to excavated earth in the course of development of land until the project nears completion so that the developer can finally decide what quantum of excavated earth would need to be removed, and therefore, what quantum of removal should be visited with royalty, and permission for removal. None of such factual analysis having been done, the Impugned Order cannot be sustained and deserves to be quashed and set aside."

12 Ms.Chavan would assertively submit before us that what is most important is the conditions of the contract executed with the petitioner, as ordinary earth which was excavated as part of the execution of the project was required to be disposed of in the manner set out and in any case, it is her vehement submission that this contract was executed between the petitioner and the Metro Railway, but since the petitioner sought permission to excavate from the Additional Collector and it has in fact excavated, in accordance with the said permission, it is liable for payment of royalty.

Inviting our attention to one such application which the petitioner itself has annexed to the petition at Exhibit D-1,

Tilak

14/27 Dogas SOma.doc

she would submit that the petitioner informed the Collector, Mumbai City that it was awarded the contract for design and construction of underground sections, including five underground stations and associated Bored tunnels, and since it was planning to excavate the station box, they are intending to get royalty permission for 10000 brass in initial stage. Further, request was also made to the Collector, Mumbai City for issuance of royalty passes for the transportation of the excavated material with specific validity period. It is in the light of the aforesaid correspondence with the Collector, Mumbai it is her contention that the petitioner has rightly paid the royalty and it need not be refunded.

In alternative, it is her submission that no royalty was demanded by the respondents i.e. Additional Collector of State Government, but the petitioner had tendered it on its own and therefore, now he should not be allowed to back-up.

13 With the consent of the respective counsel, we have taken up the petition for final hearing at the stage of admission and hence, we issue Rule which is made returnable forthwith.

With the able assistance of the respective counsel, we have perused the Writ Petition along with its annexures. We have noted that the petition has not impleaded the Metro Rail as a respondent and when we queried with the counsel for the petitioner, he would submit that the petitioner do not desire to seek any relief against the Corporation and in fact, the

Tilak

15/27 Dogas SOma.doc

Corporation expressed no complaint of any nature whatsoever, as regards the work allotted to the petitioner.

14 It is not in dispute that the petitioner, a Joint Venture was awarded the contract of design and construction of underground stations and associated tunnels for UGC - 03 of Mumbai Metro Line - 3.

Since the alignment of the Metro Line-3 Corridor UGC 03 was running through inner urban area with high building density, the contractor (JV) appointed a design consultant to carry out design work of permanent structures and permanent/temporary earth retaining structure for underground section, including five underground stations and the associated tunnels. The Geo-technical investigation was carried out which helped in the assessment of boreholes, soil and rock conditions and potential problems which may be encountered during the excavation. In addition, the field and laboratory works was also carried out by an expert, and after in-depth study of the geology of the City being presented through the geotechnical investigation report, providing details of the configuration/ disposition of soil and lithological valuation and/or weathering grade and the geotechnical characteristics at various points and analysis of the data collated and tested by co-relations and usual geotechnical methodology, the contract was awarded in favour of the petitioner.




Tilak





                                   16/27                      Dogas SOma.doc


15              As we are only concerned with the limited aspect of

the various stipulations and terms, which form part of the contract, and this included the specific clause in relation to 'disposal of excavated material' (muck) spoil from tunnel and station excavation, we would only refer to the said relevant portion of the contract.

16 We have noted the following clauses which according to us, deserve a reproduction as the bone of contention between the parties revolve around the said clauses :-

"23. The surplus excavated material (that cannot be used in the Works), shall be treated as Contractor's property. The Contractor shall be free to take away and make use of this surplus spoil (including rock spoil) in the manner he wishes to. However, the method of handling, transportation, place of storage, any processing/reprocessing at a plant (including its location) and its end use shall comply with all the rules and regulations in force including that pertaining to Occupational Health, Safety & Environment (OHS&E) etc and as approved by the Employer/Engineer. The Contractor shall submit a detailed proposal to the Engineer for seeking the Employer's/Engineer's approval for the same.

24. The muck/spoil that is acceptable and can be used at a later stage in the Works, shall be temporarily stockpiled in a dumpsite as proposed by the Contractor and agreed by the Engineer and the concerned regulating authorities with no extra cost to the Employer.

No extra land shall be provided by the Employer for such stockpiling.

25. The surplus muck/spoil (soil/spoil/material/building debris), which is not acceptable or cannot be accommodated for use in the Works or cannot be made use of by the Contractor for his own purpose, shall be disposed of at the approved dumping area(s) only duly fulfilling all the Contract stipulations including compaction to the desired levels to the satisfaction of the Engineer.

26. The Employer has identified a muck disposal site located at

Tilak

17/27 Dogas SOma.doc

Dhapode (Padghe-Thane) with a disposal volume capacity adequate to dispose of the spoil/muck generated on this Contract package. This site can be utilized by the Contractor for disposing of surplus muck/spoil.

27. The designated muck-disposal site at Dhapode is only an indicative site and the Contractor can use this site only for the purpose of surplus spoil/muck disposal, if he so decides. However, the Contractor shall also be allowed to propose any other alternative site for disposing of the spoil/muck, in which case he shall be required to obtain all the requisite clearances from the concerned authorities and the consent of site's owner and Engineer's Notice of No Objection.

28. For disposing of the spoil/muck at a muck-disposal site, the Contractor shall take, but not be limited to, the following measures to ensure proper muck/spoil disposal and adequate site rehabilitation:

 The muck disposal site shall be ecologically restored to the maximum extent possible duly ensuring that the water quality, air quality and the soils and vegetation of surrounding areas are not contaminated.

 The adequate precautionary measures shall be implemented by the Contractor at disposal site to ensure that there is no possibility of soil erosion and other impacts of loose soils on the local water bodies.,  The Contractor shall ensure that the muck disposal site will be free from active landslides or creeps and will not have a possibility of toe erosion related slope failure.

 The Contractor shall ensure that disposal of muck/spoil at muck dumping site shall not lead to flooding being caused in the surroundings.

 The dumped muck shall be mechanically compacted in layers and properly levelled with suitable safe slopes duly ensuring that proper drainage is provided for to eliminate problems being caused due to lack of or improper drainage. In this respect the Contractor shall submit a detailed method statement to the Engineer for obtaining a Notice of No Objection.

 To protect the dump from getting disturbing by human and domestic animals activities fencing shall be provided at the perimeter of the muck/spoil disposal site. The Contractor shall also establish temporary wind barrier around the dump areas to eliminate air pollution being caused due to wind blowing over the dumping site.




Tilak





                                  18/27                      Dogas SOma.doc


In addition to the measures as stipulated in the Contract elsewhere, the following measures shall also be taken by the Contractor for lorry movement/operations carrying muck/spoil to and from the muck disposal site:

➤ All dumpers and trucks shall be well maintained and equipped with tarpaulin sheets and hooks for covering of the loose spoil properly during its transportation. ➤ The vehicle speeds on unpaved roads shall be restricted to 25 Kmph.

➤ The Contractor shall maintain valid PUC -Pollution under Control certificates and maintain proper maintenance records for their fleet;

➤ Wheel wash system shall be installed and operated at the exit of the muck/spoil disposal, so that the muck on the tyres of the trucks is cleaned properly before they move on the roads to prevent dirtying of the public roads.

➤ To control fugitive dust emissions arising during material handling, the heights from which muck/spoil is dropped shall be reduced to a practical minimum height.

➤ Dumping shall be avoided during the high speed wind, so that suspended particulate matters (SPM) level could be maintained to the acceptable level.

29. The Contractor shall note that the muck disposal site location designated for this Contract package falls in the semi urban area with reasonable road access. However, if good motorable conditions lack either within the disposal site or its approaches during the course of muck-disposal, any attention needed to these roads to make them worthy of Lorries' movement shall be the Contractor's responsibility.

30. The Contractor is responsible for obtaining the requisite approvals from the concerned local authorities for his Lorries' movement plan and their operation.

31. In case the Contractor chooses to recycle the spoil(including the rock spoil) for his own purpose, the temporary storage and processing facilities shall have to be taken care of by the Contractor at his own cost.




Tilak





                                  19/27                     Dogas SOma.doc


32. Any Octroi, Royalty, statutory payments/levies or any other charges etc. payable on the spoil/muck for its disposal or recycling (for Contractor's own purpose) shall have to be borne by the Contractor."

17 The petition is accompanied with the work order issued in favour of the petitioner with the description "Earthwork in Excavation in all types of Soils and up to Weathered Rock including drilling and blasting in Hard Rock (if required) for Mumbai Central Station".

With the specific description of the work which included lifting of excavated muck by bucket and Crane deployed by the Sub-contractor. For this purpose, the petitioner entered into sub-contract agreement with various sub- contractors in continuation of the work order in its favour by the MMRCL i.e. the work of design and construction of underground sections, including five underground stations and associated tunnels being referred to as "Project" and the sub- contract involved adequate and experience man power, machinery, tools and tackles including all materials and consumables etc. for carrying out the work of "earth work in excavation in all type of soils and upto weathered rock including drilling and blasting in hard rock for Mumbai Central Station. Another sub-contractor engaged by the petitioner was assigned the work of transportation of muck, as a product of excavation of Station Box including loading and unloading etc, as per the directions of Engineer in charge. The sub-contract work order, highlighted the scope of work as transportation of

Tilak

20/27 Dogas SOma.doc

muck obtained by earth work excavation of station box, as per drawings and specifications, and the sub-contractor was under

an obligation to provide adequate and experience manpower, machinery and tools and tackles for carrying out the subject work. The said contract included a specific clause for 'disposal of muck' and clause 4.3 of the Contract clearly specified as below :-

"Contractor will use the designated dumping yard only to dispose the generated muck. Designated Dumping Yard for Mumbai Metro Line-3, Package UGC-03 is in Thane. Address is as follows :-

Village: Dapode, Tehsil: Bhiwandi, District: Thane, Maharashtra.

Approximate lead is 50 Kms.

However, the Sub-Contractor shall be free to identity the suitable dumping yard time to time during the tenure of this Agreement and can dispose the muck only after proper submission of below mentioned documents and getting NOC from DSJV Environmental Department:

a) Agreement Copy of Dumping Yard

b) Location Map and Layout of Dumping Yard

c) Route Map of Dumping Yard

d) NOC from local govt. body for dumping the material

e) NOC from MCGM to transport the Muck

The Sub-Contractor agrees to provide suitable rebate if the generated muck is being used in upcoming Coastal Road Projects in Mumbai.

The Sub-Contractor shall maintain the proper record of muck disposal trips. The challans shall be maintained for disposal muck with proper details i.e. registration number of dumper, type of muck, quantity of muck, etc. or and as required by DSJV Site in-charge, stamped and signed by the owner of the respective dumping yard. Any penalty occurred due to delay in

Tilak

21/27 Dogas SOma.doc

submission of the supportive documents shall be bear by the Sub-Contractor and same shall be deducted from the Sub- Contractor's RA Bills."

18 In light of the aforesaid sub-contracts awarded by the petitioner in the execution of the work order issued in its favour by MMRCL, it is to be noted that the petitioner earned no revenue from the said material and no invoices were issued by it in regard to the excavated earth (muck). The petition is also accompanied with the communication addressed by Maple consortium, General Consultant for Mumbai dated 21/3/2017 addressed to the petitioner J.V, with reference to the muck disposal site which was fixed by City Survey Officer, requesting the representative of the petitioner to demarcate the land to be acquired for the said purpose.

This was accompanied with a communication from the Chief Project Manager, MMRC addressed to Maple Consortium, informing that the Collector, Thane had accorded permission to use 22-92 H.A. land for muck disposal purposes to the Corporation for Metro Line 3 purpose. Maple was therefore, requested to conduct the survey of allotted land, fix the boundaries and take up the land allotment process to the contractors respectively at the earliest.

This document has a reference to the letter from the Collector, Thane, addressed to Mumbai Metro Rail Corporation dated 14/3/2017, demarcating the land within its jurisdiction for deposit of earth, soil, murum, stones, while the project of

Tilak

22/27 Dogas SOma.doc

Metro-3 was under implementation. It was also directed that since the land was to be used for deposit of minor minerals, Metro Rail Corporation shall be liable to pay such lease rent which would be decided by the State Government and it shall ensure that the said land and the Rail Corporation shall take necessary precaution that after filling and levelling of the land at Government Gur-Charan, there shall be no encroachment.

19 In light of these communications, we would refer to the communication addressed by the petitioner to the Collector, Mumbai City, seeking permission for excavation and transportation of the materials at different sites, while it was awarded the contract for design and construction of underground sections at five underground stations. The communications placed on record at Exhibit D-1 to D-5 sought permission for excavation and transport of the material from the project area, as the petitioner was to transport the excavated material from Mumbai City to Thane district and since it involved transportation of the excavated material to another district, it was necessary to have the transit passes by specifying the quantity of the excavated material and that is the reason why the permissions are sought, but it is not the case of the respondent no.3 that the excavated material was put to commercial use by the petitioner, as the petitioner engaged the sub-contractor for transportation of the muck/waste material, which was the surplus excavated material which was not used in the works and which was treated as the contractor's property

Tilak

23/27 Dogas SOma.doc

and the contractor was free to take away and make use of the surplus soil by ensuring the compliance of the rules and regulations in force, including those pertaining to occupational health, safety and environment. The contractor was duty bound to submit a detail proposal to the Engineer for seeking his approval.

The contract also contemplated that if the muck/soil that is accepted and can be used at a later stage in the works, shall be temporary stock-piled in a dump site as proposed by the Contractor and agreed by the Engineer, but the one which is not acceptable or cannot be accommodated for use in works or cannot be made used by the Contractor for his own purpose, shall be disposed of at the approved dumping area and in this case, the MMRCL had identified a muck disposal site at Dhapode with a disposal volume capacity adequate to dispose of the spoil/muck generated on the contract package and this site was permitted to be utilised by the Contractor for disposing of surplus muck/soil.

20 In the wake of the peculiar clauses in the contract entered between the petitioner and MMRCL and the pleadings in the petition, it is evident that the excavated material which was not acceptable and was not accommodated for use in work and could not have been used by the Contractor for his own purpose, has been disposed of at a site allotted by the Collector,

Tilak

24/27 Dogas SOma.doc

Thane i.e. Dhapode and this site was indicated by the employer i.e. the MMRCL.

We fail to understand on what basis the respondent no.3 can recover royalty on this excavated material as it is not excavated by the petitioner/contractor for commercial exploitation, but it is in due course of execution of work allotted to it by the Metro Rail Corporation, the muck has been excavated and dumped at a place indicated by the MMRCL. The imposition of royalty under the Maharashtra Minor Mineral (Extraction) Rules 2013, is for removal of minor mineral from the leased area, and definitely, the petitioner is not the lessee and has not excavated the material for commercial use.

Clause No.46 has been amended by adding a proviso that no royalty shall be required to be paid on earth which is extracted while developing a plot of land and utilise on the very same plot for land levelling or any work in the process of development of such plot.

The petitioner, in our considered opinion, do not fall in either of the clauses or Rule 46 of the MLR Code as he has not excavated minor mineral from the leased area and therefore, is not duty bound to pay royalty and secondly, no royalty is liable to be paid by him if some portion of the earth excavated/extracted while developing the plot is utilised on the very same plot for any work in the process of development.

The contract entered by the petitioner with the Mumbai Metro Rail Corporation is very specific in regards to

Tilak

25/27 Dogas SOma.doc

the disposal of the excavated material (muck/spoil) from tunneling and station excavation site and since the petitioner has acted in compliance with the conditions of the said contract, and has disposed of the spoil/muck at the site indicated by the MMRCL, we find no justification in the petitioner being charged with royalty on the said material. 21 It is worth to note that it is not the respondent no.3 who ever raised a demand of payment of royalty, but petitioner on its own, deposited the money through challans by computing the royalty on the excavated material for different quantity of excavated material and paid the royalty proportionate to the quantity in brass that was excavated, which according to us, was an unwarranted exercise and merely because the petitioner sought permission for excavation and transportation, in our considered view, the royalty cannot be imposed upon the excavated material as the petitioner was operating under a contract with the Metro Rail Corporation for five underground stations and the contract is between MMRCL and the petitioner and the Corporation has never made any grievance about the non-performance of the obligations on its part.

Merely because the petitioner has now deposited the royalty, definitely, the State cannot enrich itself, unless and until it is entitled to recover the amount of royalty.

In the case of Promoters and Builders Association of Pune (supra), the Apex Court has clearly ruled that digging

Tilak

26/27 Dogas SOma.doc

ordinary earth for laying foundation of buildings and its re- deployment without any commercial usage or usage as contemplated under notification of 3/2/2000, would not attract Section 48(7) and penalty under the Maharashtra Land Revenue Code, 1966.

In no uncertain terms, with reference to the definition of the term 'minor minerals' as defined in Section 2(e) of the 1957 Act read with notification dated 3/2/2000 issued by the Government of India, the Apex Court has concluded thus:-

"15 Though Section 2(j) of the Mines Act, 1952 which defines 'Mine' and the expression "mining operations" appearing in Section 3(d) of the Act of 1957 may contemplate a somewhat elaborate process of extraction of a mineral, in view of the Notification dated 3.2.2000, insofar as ordinary earth is concerned, a simple process of excavation may also amount to a mining operation in any given situation. However, as soon, the operation of the said Notification has an inbuilt restriction. It is ordinary earth used only for the purposes enumerated therein, namely, filling or levelling purposes in construction of an embankment, road, railways and buildings which alone is a minor mineral. Excavation of ordinary earth for uses not contemplated in the aforesaid Notification, therefore, would not amount to a mining activity so as to attract the wrath of the provisions of either the Code or the Act of 1957."

22 In fact, the reliance on the decision in Ikea India Private Limited (supra) is also unfounded, as it had applied the principle in Promoters and Developers Association of Pune (supra) and we have already reproduced the relevant observation above.

23 In light of the aforesaid, since we do not find any lawful justification on part of the respondent, in not refunding

Tilak

27/27 Dogas SOma.doc

the amount towards royalty deposited by the petitioner through various challans, under misconception that the excavated material, arising out of its contract would entail imposition of royalty, we direct the respondent State to refund the amount of Rs.8,20,02,000/- within a period of 12(twelve weeks) from today, as the State cannot enrich itself by retaining the amount to which it was not entitled. Though a request is made to make the refund with interest, we are not inclined to grant the said request, as we find that without any demand being raised, the petitioner on his own has deposited the amount and it is only who has to take the blame, as the State never demanded the amount of royalty.

However, we make it clear that if the amount of Rs. 8,20,02,000/- is not refunded within a period of 12 weeks, it shall carry an interest @ 12% p.a. Writ Petition is made absolute as above.

(MANJUSHA DESHPANDE,J) (BHARATI DANGRE, J.)

Tilak

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter