Citation : 2026 Latest Caselaw 2459 Bom
Judgement Date : 10 March, 2026
2026:BHC-OS:6211-DB WP 485 OF 2021,J.DOC
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
WRIT PETITION NO. 485 OF 2021
Shabbir A. Tambawala ]
1901, Tivoli, Central Enclave ]
Hiranandani Gardens, Powai, ] ... Petitioner
Mumbai - 400 076 ]
Versus
1. State of Maharashtra ]
Backbay Reclamation ]
Mumbai 400 020. ]
]
2. Council of Architecture ]
Through its Secretary ]
Having its office at ]
Indian Habitat Center, ]
... Respondents
Core - 6A 1st Floor, Lodhi Road ]
New Delhi - 110003. ]
]
3. Hafiz Contractor, Architect, ]
29 Bank Street, Fort, ]
Mumbai 400 023. ]
]
4. Suhas Joshi, Architect, ]
29 Bank Street, Fort, ]
Mumbai 400 023. ]
Mr. Rohit Kapadia, Senior Advocate (Through VC) with Mr.
S.C. Naidu, Mustafa Kachwala, and Sakshi Sri i/b. K.
Law, Advocate for the Petitioner.
Ms. Anupamaa Pawar, AGP for Respondent - State.
Digitally
signed by
RAJESHRI
Mr. P.V. Dhopatkar, Advocate for Respondent No.2.
RAJESHRI PRAKASH
PRAKASH AHER Mr. Karl Tamboly a/w. Mr. Ernest Tuscano i/b. Mr. Anil
AHER Date:
2026.03.10
19:49:56
+0530
Page 1 of 22
Rajeshri Aher
::: Uploaded on - 10/03/2026 ::: Downloaded on - 10/03/2026 21:03:30 :::
WP 485 OF 2021,J.DOC
D'souza, Advocate for Respondent No.3.
Mr. Chetan Kapadia, Senior Advocate with Ms. Vidisha
Rohira i/b. M/s. Dastur Kalambi & Associates, Advocate
for Respondent No.4.
CORAM: BHARATI DANGRE &
MANJUSHA DESHPANDE, JJ.
DATED: 10th MARCH 2026.
JUDGMENT (PER : MANJUSHA DESHPANDE, J.):
-
1. The Petitioner challenges the order dated 06.12.2019,
passed by the Council of Architecture in Disciplinary Enquiry
No. 332, wherein it is held that Respondent Nos. 3 and 4 are
not guilty of professional misconduct, resultantly dismissing
the complaint of the Petitioner.
2. The Petitioner had purchased 4 flats in a building
named 'Tivoli' at Powai developed by Lakeview Developers, a
company of the Hiranandani Group of Companies. The
agreements for sale of the four flats were executed on
21.02.2004 on the basis of brochures and layout plan of the
building, which included a common club house and
recreation ground for the building. Upon completion of
building and issuance of occupation certificate by the MCGM,
the Developer handed over the possession in September
Rajeshri Aher
WP 485 OF 2021,J.DOC
2004. The Developer had not constructed a common club
house, as assured and indicated in the building layout plan.
On 12.05.2006, the Developer sent an Email to the Secretary
of the Society accompanied by a copy of a plan dated
11.05.2004. This Email sought permission of Society for
connecting a podium ramp to the building with the adjacent
under construction building, and it was further informed
that both the societies i.e. 'Tivoli' and 'Evita', will be sharing
the same entrance, and a common club house which was
altogether removed from the plan.
3. It is alleged that this plan was signed by Respondent
No. 4 on behalf of Respondent No. 3 as an Architect. This plan
was different from the plan which was shown to the
Petitioner while entering into the agreement to sale.
Therefore, being aggrieved by the conduct of Respondent
Nos. 3 and 4, the Petitioner has filed a complaint against
them, under Chapter VII of Council of Architecture Rules,
1973 on 24.04.2009. After hearing the parties, the complaint
of the Petitioner came to be dismissed vide order dated
22.03.2010.
Rajeshri Aher
WP 485 OF 2021,J.DOC
However, the Petitioner thereafter preferred another
complaint against Respondent Nos. 3 and 4 on 22.12.2010. In
response to the second complaint, Respondent Nos. 3 and 4
were called upon to file their reply. Even the second
complaint was dismissed by the Respondent No.2 vide order
dated 16.11.2011. Being aggrieved by the order of dismissal
and complaint, the Petitioner filed Writ Petition No. 130 of
2013 in this Court. This Court vide its order dated
17.06.2015, has quashed and set aside both the orders dated
22.03.2010 and 16.11.2011 passed by Respondent No.2 and
directed to hear the complaints of the Petitioner on its own
merits and pass appropriate orders in accordance with law.
After the remand of the matter to Respondent No.2, the
Petitioner was informed that it was decided to refer the
matter to the Disciplinary Committee for detailed
investigation, and after considering the oral and written
submission of the parties, the disciplinary committee
submitted its report to Respondent No.2 on 16.05.2018. It
was decided by Respondent No.2 to refer the matter to the
Full Council in its 70th meeting held on 22.11.2018. On
27.07.2019, a Full Council of Respondent No.2 heard the
Rajeshri Aher
WP 485 OF 2021,J.DOC
Petitioner and Respondent Nos. 3 and 4 and thereafter an
order came to be passed on 06.12.2019, which is impugned in
this Petition.
4. The learned Senior Advocate, Mr. Rohit Kapadia, for
the Petitioner appeared through Video Conferencing and
submitted that, the impugned order does not reflect
application of mind by the Respondent No.2. It is the specific
case of the Petitioner that, the plan sent by the Developer
and stamped by Respondent Nos. 3 and 4 is forged, fabricated
and materially different from the sanctioned plan.
Respondent Nos. 3 and 4 alongwith the Developer have
misled the Petitioner and the society by changing the plan of
the entire project without the flat purchaser's knowledge or
consent which constitute professional misconduct on the
part of Respondent Nos. 3 and 4 under Section 22(2) of the
Architects Act, 1972 read with Architects (Professional
Conduct) Regulations, 1989.
5. The impugned order does not consider that there are
material differences in these two plans, the original one
contained 10 buildings, while the forged plan contained 12
Rajeshri Aher
WP 485 OF 2021,J.DOC
buildings. The common club house which was part of the
original plan was altered by removing the common club
house and recreational area. The sanctioned plan contained
signatures of MCGM personnel (Authorities) in the right
hand side column, whereas in the forged plan, it was absent.
The plan was sanctioned on 11.05.2004, there could not have
been two materially different plans approved by the MCGM
on the same date and under the same file name/number.
6. He further submits that the stand of Respondent No.3
has shifted multiple times with regard to this matter. The
Respondent Nos. 3 and 4 have not given any explanation
regarding the discrepancies in the two plans. Respondent
No.2 has not passed a reasoned order, and no finding is
recorded, about the discrepancies in sanctioned plan and
forged plan. The complaint has been disposed of by merely
directing Respondent No. 4 to apologize to the Petitioner.
Without recording any reason as to why it was decided to
absolve Respondent No.4, when in fact, the intentional
fabrication and manufacturing of a document, and an
attempt to pass that document as an original document were
writ large on the face of the record.
Rajeshri Aher
WP 485 OF 2021,J.DOC
7. It is further submitted that, the order passed by the
Respondent No. 2 is contrary to the report of the Disciplinary
Committee dated 16.5.2018, wherein the Respondent Nos. 3
and 4 have been found to have acted in violation of
Regulation 2(1) (iv), (x) and (xii) of the Architects
(Professional Conduct) Regulations, 1989, for purportedly
carrying out work in the absence of a written agreement.
Most importantly, the impugned order is not supported by
any reason for arriving at the conclusion that Respondent
No. 4 had inadvertently signed the forged plan.
8. It is submitted that creating and circulating a forged
plan cannot be brushed aside casually by holding it to be just
an error, since it has resulted in misleading the Petitioner.
This conduct of Respondent Nos. 3 and 4 warranted strictest
action against them. Therefore, the order impugned is
required to be set aside and this Court may be pleased to hold
Respondent Nos. 3 and 4 guilty of misconduct under the
provisions of Architects Professional (Conduct Regulation),
1989, and direct Respondent No.2 to remove their names
from the Register and terminate their license to practice.
Rajeshri Aher
WP 485 OF 2021,J.DOC
9. Mr. Karl Tamboly, Advocate for Respondent No.3, has
resisted prayer in the Petition by contending that the
building named 'Tivoli' was completed in the year 2004.
Respondent No. 3 was an Architect and Licenced Surveyor
for the Powai Area Development Scheme Project i.e.
Lakeview Developers of the Hiranandani Group of
Companies, while Respondent No.4 was the Consultant
Architect of Hiranandani Group of Companies. Respondent
No.3 had given a Special Power of Attorney to sign and
execute layout plans and building plans or any other letter or
document, as may be required for submission to the
authorities of MMC Or MMRDA or Government body or
Authority mentioned therein for the purpose of development
of the properties belonging to the Hiranandani Group of
Companies in Greater Mumbai and Navi Mumbai.
Respondent No. 3 has ceased work with Lakeview Developer
on 06.03.2009 and the Power of Attorney stood terminated
since then. Respondent No. 3 had nothing to do with the
incorrect certification of the layout plan dated 24.06.2005,
since he was not aware that, any such plan was being sent via
Email to the Society by the Developer. It is pertinently
Rajeshri Aher
WP 485 OF 2021,J.DOC
pointed out that, only the Petitioner has raised such a
grievance, the society has not raised any grievance against
Respondent No.3 or Respondent No. 4, for the inadvertent
mistake. No prejudice or loss is caused to the Petitioner or
the Society. Therefore, there is no substance in the challenge
raised by the Petitioner and the Writ Petition deserves to be
dismissed.
10. The Respondent No.4 led by Mr. Chetan Kapadia has
resisted the Petition by contending that the Petitioner who
had purchased 4 flats in the 'Tivoli' building forms part of
larger layout comprising of many other buildings in the
residential cum commercial scheme at Powai, developed by
the Lakeview Developers. The Tivoli Building was
constructed in accordance with the approved plan dated
03.03.2001. After the Petitioner purchased 4 flats in the
Tivoli Building on 21.02.2004, occupation certificate was
granted by the MCGM on 11.05.2004. It is submitted that
after the earlier layout plan dated 03.03.2001, the MCGM
approved an amended layout plan on 24.06.2005. It is
further submitted that two Emails were received by the
society from the Lakeview Developers requesting permission
Rajeshri Aher
WP 485 OF 2021,J.DOC
to use the access from 'Tivoli' for an adjacent building,
named, 'Evita', which was then under construction. The
society also received an Email seeking permission for an
access, which would connect 'Evita' with another building
proposed to come up as, 'Tivoli-II (Vidisha)'. Pursuant to the
aforesaid request, the Managing Committee of the Tivoli
Committee passed the Resolution recording that the society
had no objection to sharing common access with the 'Evita'
building alongwith, 'Tivoli-II (Vidisha)'. It is also urged that
the club house shown in the layout plan on 03.03.2001 was
only a proposed layout, the MCGM has approved amended
layout plans on 24.06.2005 and 29.11.2006, respectively.
Therefore, there is no element of cheating or attempt to
mislead the Petitioner.
As regards the signature of the Respondent No.4 which
appeared on the plan of the building, which is alleged to be
forged is concerned, it is submitted that the clerk cum
assistant of Respondent No.4 had inadvertently stamped the
plan as 'true copy stamp of full occupation certificate of Tivoli
building', instead of copy of stamp of 'approved layout plan
dated 24.06.2005'. This was sheer inadvertence and there
Rajeshri Aher
WP 485 OF 2021,J.DOC
was no intention of committing any fraud or collusion. He
has already tendered an apology for the inadvertent mistake
committed by him, hence, the Writ Petition does not deserve
any consideration.
11. Mr. P. V. Dhopatkar appearing for contesting
Respondent No.2, relying on the affidavit filed through the
Registrar-Secretary of Respondent No.2 submitted that, the
Disciplinary Committee of the Respondent Council, after
conducting several hearings of the Petitioner's aforesaid
complaint, submitted its report to the Full Council of the
Respondent No.2. The Full Council, in its 70 th Meeting held on
22.11.2018, after going through the report of Disciplinary
Committee has decided to summon both the parties i.e. the
complainant as well as the Respondent Nos. 3 and 4.
Accordingly, both the parties appeared before the Full
Council on 27.07.2019. They were granted full opportunity of
hearing and after considering the submissions, the Full
Council passed the order on 06.12.2019. The Learned
Counsel raises a preliminary objection for the belated
challenged to the impugned order and submits that the
Petition suffers from delay and laches. It is submitted that
Rajeshri Aher
WP 485 OF 2021,J.DOC
the Council dismissed the complaint only after following the
due procedure prescribed under the Architects Act, 1972 and
Rules made thereunder. It is also submitted that this is a
private contractual dispute between the complainant and the
developer for which an alternate remedy is available for
redressal of his grievance and Writ Petition would not be
maintainable. Full opportunity of hearing was given to all the
parties by Respondent No.2, there are no procedural lapses
while conducting the Disciplinary proceedings.
12. The Disciplinary Committee has rightly observed that
in absence of an agreement, it would be impossible to draw a
conclusion, on the levels of performance of omissions and
commissions of Respondent Nos. 3 and 4, due to which, the
Disciplinary Committee is not in a position to adjudicate on
the merits of the case in absence of any signed agreement or
contract. There are no grounds made out for causing
interference, in the decision taken by the Respondent No. 2
Council. The Respondent No.2 is an competent expert body
consisting of the nominees of Central Government, all State
Government undertakings, Head of Architectural
Institutions, IIA, Institutions of Engineers India, these
Rajeshri Aher
WP 485 OF 2021,J.DOC
Members of the body are the experts in the field, hence their
decision does not warrant any interference, unless there is
some irregularity or breach committed during the enquiry
that is obvious from the face of the record.
13. We have heard the respective counsel and we have also
perused all documents placed on record, relied upon by the
parties. The grievance of the Petitioner in short appears to be
that while entering into an agreement for sale on 21.02.2004,
the Petitioner was shown an approved layout plan, which
included a common club house and recreation ground. After
issuing the completion certificate by the Municipal
Corporation of Greater Mumbai, the possession was handed
over in September 2004. The approved building plan dated
11.05.2004 accompanying the Email was received by the
society in May 2006, which did not show the common club
house, on the contrary, additional buildings were shown in
the plan. This plan according to the Petitioner is a forged
plan. Upon noticing the difference in the two plans, the
Petitioner obtained the copy of the sanctioned approved plan,
by the MCGM dated 11.05.2004, through RTI. Upon
comparing the two plans, there was material difference in
Rajeshri Aher
WP 485 OF 2021,J.DOC
these two plans. The number of buildings were increased
from 10 to 12; club house was removed in the forged plan; the
recreation area and its location were altered; the sanctioned
plan bore signature of the officers, whereas it was absent in
the forged plan; and the forged plan was signed by
Respondent No. 4 on behalf of Respondent No.3.
14. Although the two complaints filed against Respondent
Nos. 3 and 4 were dismissed by Respondent No.2. This Court
in Writ Petition No.130 of 2013, remanded the matter to be
heard afresh. After the remand, initial hearing was
conducted by the Disciplinary Committee, and a report was
submitted in May 2018. Since a prima facie case of
professional misconduct was recorded in the report, it was
referred to the Full Council by Respondent No.2.
15. The Petitioner and the Respondents were heard by the
Full Council in its 70th meeting. After hearing the explanation
given by Respondent No. 4 about the inadvertent stamping of
plan, the Petitioner was again granted an opportunity to
rebut the submissions and finally, after deliberating over the
issue, by the majority of the Full Council, decided that there
Rajeshri Aher
WP 485 OF 2021,J.DOC
was no professional misconduct, by Respondent No.3 and 4;
however, there was a mistake committed by Respondent No.4
in signing and stamping a building plan on 24.06.2005, for
which he needs to tender an apology to the Petitioner as well
as the Council, and also assure that such conduct will not be
repeated in future. By making these observations, the
complaint has been dismissed.
16. In the wake of the above facts and circumstances as
well as the documents on record, we are called upon to decide
the correctness of the decision of Respondent No.2, who is
the Apex Regulating body of the Architects in India. The
Apex Regulating body has already evaluated the case of the
Petitioner and has come to the conclusion that there is no
professional misconduct committed by the Respondent Nos. 3
and 4, however, it was directed that Respondent No.4 should
apologize to the complainant as well as the Council, and
assure that no such conduct would be repeated in future.
This decision has been challenged before this Court by
invoking powers of judicial review. The powers of this Court
for entertaining such petitions challenging the decisions of
Rajeshri Aher
WP 485 OF 2021,J.DOC
statutory or regulatory authorities are very limited. It is
trite law that correctness of the decision of a statutory/quasi-
judicial authority cannot be decided by treating it as an
Appeal and re-appreciating the findings recorded by such
Authority. The jurisdiction of this Court is limited; it can
interfere in the findings only in case of an illegality
committed in the decision-making process, such as decision
is flawed due to lack of jurisdiction; or exercise of jurisdiction
not vested in such Authority. Only in case the order
impugned is irrational, arbitrary or unreasonable to such an
extent that it shocks the conscious of a normal human being
it can be interfered with by this Court.
17. In the present case when we perused the impugned
order, it is passed in the exercise of its powers conferred
under the Architects Act 1972, and the Regulations of 1982
framed in exercise of power conferred under Section 45 Sub-
clause (1) read with clauses (a), (b), (c), (d), (e), (f), and (i)
with sub-section 2 of the Architects Act, 1972, approved by
the Central Government read with Regulations of 1989. The
Council of Architect is constituted under the said Act and the
disciplinary authority is constituted under Rule 35 of the
Rajeshri Aher
WP 485 OF 2021,J.DOC
Council of Architecture Rules, 1973. The Disciplinary
Committee is constituted to inquire into the professional
misconduct of an architect as provided under Rule 35 of the
Rules of 1973. The procedure to inquire into the complaints
against the Architect is provided in Rule 35 Sub-clause 3 to 8
and Rule 36. Upon completion of the inquiry, a report is to be
submitted to the Council, as provided under Rule 37, upon
receipt of such report from the Disciplinary Committee, if the
Council is of the opinion that further report is necessary, it
may call further report from such Authority and thereafter
proceed accordingly.
Upon perusal of the impugned order, we find that there
are no procedural irregularities committed by the Council.
All the parties were afforded an opportunity to put forth
their case and after receiving the report of the disciplinary
committee, it was decided to place the complaint before the
Full Council. Even before the Full Council, all the parties were
heard, after hearing both the parties again the opportunity
was granted to the Petitioner to rebut the submissions made
by Respondents Nos. 3 and 4, and only after detailed
deliberations in the matter, the majority of the Full Council
Rajeshri Aher
WP 485 OF 2021,J.DOC
decided that, there is no misconduct either on part of
Respondent No. 3 or Respondent No.4. This procedure,
adopted by Respondent No.2 in no way can be faulted with
since it has proceeded in accordance with the prescribed
rules. All the parties were heard and the orders passed are in
accordance with the powers conferred on the Council of the
Architects Act 1972, and the Regulations of 1982.
18. It is well within the powers of the Council as provided in
Rule 37 (2) of Rules of 1973 to call for further report, if it is
of the opinion that further report is necessary. Therefore,
when a report dated 16.05.2018 held that the Respondent
Nos. 3 and 4 have violated Regulation No.2 (1) (iv), (x) and
(xii) of the Architects (Professional Regulations, 1989, by
reason of absence of an agreement while giving their
professional services to the Developer, was placed before the
Council. Respondent No.2 thought it fit to place it before the
Full Council for passing an order in terms of Section 30 Sub-
clause 2 of the Architect's Act, 1970. The Full Council by
majority has taken a decision. Thus, there is no irregularity
or illegality in the procedure committed by Respondent No.2,
Rajeshri Aher
WP 485 OF 2021,J.DOC
while exercising its powers and passing the order which is
impugned in this Petition.
19. So far as the contention of the Petitioner that the order
impugned is not a reasoned order and a penalty should have
been imposed as provided in the Regulations is concerned,
the Full Council has arrived at a conclusion that the conduct
of Respondent No.4 of stamping of plan as a true copy of the
full occupation certificate, was an inadvertent mistake which
necessitated apology and assurance of not repeating the
same conduct in the future. While passing this order, a
finding is recorded that there is no fraud, collusion or
malafide intention in the matter. Even no particulars for
collusion have been provided by the Complainant. Therefore,
in view of the admission of the inadvertent mistake by
Respondent No.4, appropriate punishment has been
awarded. Similarly, the stand of the Respondent No.4 that
the signature was affixed by him in his personal capacity and
not in exercise of the power conferred on him by the Special
power of Attorney given to him by Respondent No.3, a finding
is recorded that there was no misuse of power by Respondent
No.4.
Rajeshri Aher
WP 485 OF 2021,J.DOC
20. Thus, even on merits there is no substance in the
contention of the Petitioner that the order impugned is an
unreasoned order. The order impugned is a reasoned order
passed after hearing of parties at length and taking into
consideration the law and facts applicable to the given case.
21. So far as the grievance of the petitioner that a harsher
penalty ought to have been imposed on Respondents Nos. 3
and 4, the quantum of punishment to be imposed is always
the discretion of the Disciplinary Authority, i.e. Respondent
No.2, who is an expert body consisting of technical persons
appointed by the Central Government, State Government and
Institute of Architect. The opinion of Respondent No.2 being
an opinion of an expert body, are in a better position to
assess the misconduct of the Architects and to impose
appropriate penalty in proportion to the alleged misconduct.
Respondent No.2 has accordingly acted and arrived at a
conclusion that it would be sufficient if an apology is tendered
by Respondent No.4 with a request not to repeat the mistake
in future. We do not find penalty of tendering apology to be
shockingly disproportionate for the alleged misconduct,
which would warrant interference in the order impugned.
Rajeshri Aher
WP 485 OF 2021,J.DOC
22. We may profitably refer to the land mark decision of the
Hon'ble Supreme Court in case of Union of India and Ors. Vs.
P. Gunasekaran1, wherein the bounds within which the
Courts can exercise its powers of judicial review have been
stated. In paragraph no. 12, in the case of Union of India and
Ors. Vs. P. Gunasekaran (Supra), the Hon'ble Supreme Court
has observed thus:
" (12) Despite the well-settled position, it is painfully disturbing to note that the High Court has acted as an appellate authority in the disciplinary proceedings, reappreciating even the evidence before the enquiry officer.
The finding on Charge I was accepted by the disciplinary authority and was also endorsed by the Central Administrative Tribunal. In disciplinary proceedings. the High Court is not and cannot act as a second court of first appeal. The High Court, in exercise of its powers under Articles 226/227 of the Constitution of India, shall not venture into reappreciation of the evidence. The High Court can only see whether:
(a) the enquiry is held by a competent authority;
(b) the enquiry is held according to the procedure prescribed in that behalf;
(c) there is violation of the principles of natural justice in conducting g the proceedings;
(d) the authorities have disabled themselves from reaching a fair conclusion by some considerations extraneous to the evidence and merits of the case;
1 (2015) 2 SCC 610
Rajeshri Aher
WP 485 OF 2021,J.DOC
(e) the authorities have allowed themselves to be influenced by irrelevant or extraneous considerations;
(f) the conclusion, on the very face of it, is so wholly arbitrary and capricious that no reasonable person could ever have arrived at such conclusion:
(g) the disciplinary authority had erroneously failed to admit the admissible and material evidence;
(h) the disciplinary authority had erroneously admitted inadmissible evidence which influenced the finding;
(i) the finding of fact is based on no evidence."
Thus, from the aforementioned judgment as well as
catena of other judicial pronouncement, governing the field,
it is evident that power of this Court while exercising powers
of judicial review are restricted only to the breach of certain
conditions in the decision-making process. Nevertheless, it is
a settled position of law that this Court cannot exercise
powers of judicial review by sitting in Appeal over a decision
of a Statutory or Regulatory Authority.
23. Hence, we do not find any arbitrariness or illegality in
the decision rendered by Respondent No.2. As a result, the
challenge to the impugned order fails and Writ Petition is
dismissed. No order as to costs.
(MANJUSHA DESHPANDE, J.) (BHARATI DANGRE, J.) {
Rajeshri Aher
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!