Citation : 2026 Latest Caselaw 1810 Bom
Judgement Date : 17 February, 2026
2026:BHC-AS:8108
8-wp195-2022.doc
AGK
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO.195 OF 2022
Vardhaman Homes, through partner
Sandesh Laxmichandra Vardhan ... petitioner
ATUL V/s.
GANESH State of Maharashtra & Ors. ... respondents
KULKARNI
Digitally signed by
ATUL GANESH
KULKARNI
Date: 2026.02.17
14:50:10 +0530
Mr. Jayesh Joshi for the petitioner.
Ms. Savina R. Crasto, AGP for respondent Nos.1 & 2-
State.
Mr. R.S. Datar for respondent No.3.
CORAM : AMIT BORKAR, J.
DATED : FEBRUARY 17, 2026
P.C.:
1. The petition challenges the order and certificate of unilateral deemed conveyance issued by the Competent Authority under Section 11 of the Maharashtra Ownership Flats Act, 1963, whereby land admeasuring 4954.60 sq. mtrs. together with the structure standing thereon has been conveyed in favour of respondent no. 3 society. The case of respondent no. 3 is that it is a duly registered co operative housing society and the petitioner developer failed to perform statutory obligations cast under the Act. The society therefore invoked Section 11. The Competent Authority, after granting hearing, recorded that the developer disputed area calculation but did not produce any supporting material. The society, on the other hand, produced the Architect's Certificate
8-wp195-2022.doc
certifying proportionate conveyance area. On the basis of 7/12 extracts, agreements for sale, sanctioned plans and architect certification, the authority held the society entitled to unilateral conveyance of proportionate land admeasuring 4954.60 sq. mtrs. out of total land admeasuring 87144.82 sq. mtrs.
2. Learned counsel for the petitioner contends that the conveyance deed stood registered in Writ Petition No. 8120 of 2023 without issuing notice under Section 11(5) of the Act. Reliance is placed upon an interim order of this Court directing that no further steps be taken pursuant to the impugned order. It is further urged that respondent no. 3 forms part of a larger layout under development and under the Flat Purcher Agreement the conveyance was contemplated only in favour of the federation after completion of the entire project. According to the petitioner, the developer retains rights in the entire FSI of the layout and therefore the Competent Authority lacked jurisdiction to grant deemed conveyance to an individual society.
3. Learned counsel appearing for respondent no. 3 supports the impugned order. It is submitted that the Architect's Certificate clearly establishes the proportionate land necessary to sustain the constructed building. The authority examined the sale agreements, sanctioned plans and other relevant documents before granting conveyance. It is further contended that any claim of right, title or interest raised by the developer must be adjudicated in a civil suit and cannot defeat statutory conveyance under the Act.
8-wp195-2022.doc
4. The submissions have been considered and the record has been examined.
5. The material shows that statutory obligations under the Act were not fulfilled by the developer. The society therefore invoked Section 11 seeking conveyance. The Architect's Certificate placed on record specifies constructed area and the corresponding land necessary to sustain the building together with undivided share in common areas. No counter certificate was produced by the developer before the authority. Even before this Court, no material is shown to demonstrate any defect in the certification of area.
6. Government Resolution dated 22 June 2018 prescribes procedure for grant of deemed conveyance in layouts containing multiple buildings and separate societies even where construction of some buildings remains incomplete. The resolution directs that conveyance of the constructed building shall include proportionate undivided occupancy rights corresponding to ground coverage or plinth area together with open spaces, amenities and access roads. It further provides that where TDR is utilized, conveyance must correspond to plinth and appurtenant area. The resolution therefore permits grant of proportionate conveyance even prior to completion of entire layout. The present order follows that principle.
7. The petitioner relies heavily upon the resolution to dispute the area conveyed. However, such challenge required production of technical material or counter certification establishing a different proportionate entitlement. No such material has been
8-wp195-2022.doc
placed on record.
8. The impugned order indicates adherence to the Government Resolution and consideration of all relevant documents before issuance of unilateral conveyance certificate. It is settled law beginning from Mazda Construction Company v. Sultanabad Darshan CHS Ltd. 2012 SCC OnLine Bom 1266 and clarified in Shree Chintamani Builders v. State of Maharashtra (2016) SCC OnLine Bom 9343 that grant of deemed conveyance does not determine title finally and parties may seek declaration in civil proceedings. In view of this settled position, supervisory jurisdiction under Article 227 does not warrant interference. The petitioner may pursue appropriate civil proceedings for declaration of its alleged rights.
9. If such suit is instituted, the Civil Court shall decide the same independently on evidence and without being influenced by observations of the Competent Authority.
10. The writ petition is dismissed. Rule stands discharged.
(AMIT BORKAR, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!