Bharat Shantila Shah And Anr vs The Royal Palms (Indai) Pvt Ltd And 3 Ors on 15 April, 2026

Author: Abhay Ahuja
Bench: Abhay Ahuja
                                                                                   10-S-1186-2007.doc


                                  IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                      ORDINARY ORIGINAL CIVIL JURISDICTION

                                                  SUIT NO. 1186 OF 2007

                    BHARAT SHANTILAL SHAH AND ANOTHER                       )...PLAINTIFFS
                             V/s.
                    THE ROYAL PALMS (INDIA) PVT. LTD. AND ORS. )...DEFENDANTS

                    Mr.Vibhav Krishna a/w. Mr.Tahir Prande i/by Juris Consillis, Advocate
                    for the Plaintiffs.
                    Mr.Shard Bansal a/w. Ms.F.Mehta i/by M/s.Markand Gandhi & Co.,
                    Advocate for the Defendants no.1, 2 and 4.

                                                   CORAM      :    ABHAY AHUJA, J.
                                                   DATE       :    15th April 2026
                    P.C. :


1. This matter was kept back in the morning session as the learned

Counsel appearing in the matter were ironing out the differences in the

draft issues furnished by the Plaintiffs.

2. When the matter is called out in the afternoon session, the

learned Counsel submit that the draft issues have been worked out.

3. Accordingly, the following issues are framed by consent :

ISSUES

(i) Whether the Plaintiffs prove that a valid, binding and concluded Agreement for Sale dated 27th September 1993 was executed ARTI VILAS KHATATE

10-S-1186-2007.doc

between the Plaintiffs and Defendant no.1 and they are entitled to a decree for specific performance of the Agreement ?

(ii) Whether the Defendants prove that the said Agreement is void for uncertainty, vagueness and/or is not a concluded contract in respect of the exact area, location and boundaries of the Suit property ?

(iii) Whether the Defendants prove that the Agreement for Sale dated 27th September 1993 was unlawful, void and incapable of specific performance ?

(iv) Whether the Plaintiffs prove that they are in lawful, settled and continuous possession of the Suit property in part performance of the Agreement ?

(v) Whether the Plaintiffs prove that the Defendants have unlawfully interfered with or threatened to dispossess the Plaintiffs from the Suit property ?

(vi) Whether the Defendants prove that the Plaintiffs were never put in possession of the Suit property ?

(vii) Whether the Plaintiffs prove that they are entitled to protection of their possession of the Suit property ?

(viii) Whether the Plaintiffs prove that the Defendants committed breach of the terms of the Agreement ?

(ix) Whether the Defendants prove that the Agreement stood validly terminated by letter dated 29th January 2003 ?

(x) Whether the Defendants prove that the Plaintiffs have committed breach of the terms of the Agreement and have not performed

10-S-1186-2007.doc

and been willing and ready to perform their obligation under the Agreement ?

(xi) Whether the Defendants prove that the Suit is barred by limitation ?

(xii) In the alternative, whether the Plaintiffs are entitled to compensation in lieu of specific performance and refund of the amount paid with interest and such repayment be secured by security charge on the Suit property to be realized by sale of Suit property ?

(xiii) What decree ?

(xiv) What order ?

(xv) What order as to costs ?

4. Let the Plaintiffs within a period of six weeks file an Affidavit of

examination-in-chief of the Plaintiffs' witness along with Affidavit of

evidence and Compilation of documents duly indexed and paginated

and serve the same upon the Defendants along with list of Plaintiffs'

witnesses.

5. Discovery and inspection to be completed within a period of two

weeks thereafter.

6. Defendants to file Statement of admission and denial within a

period of two weeks thereafter with a copy to the other side.

10-S-1186-2007.doc

7. List for marking of Plaintiffs' documents on 1st July 2026.

8. Let the Plaintiffs' witness remain present in Court on the next

date.

(ABHAY AHUJA, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter