Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Smt. Alka Chandewar vs Shamshul Ishrar Khan
2026 Latest Caselaw 3350 Bom

Citation : 2026 Latest Caselaw 3350 Bom
Judgement Date : 2 April, 2026

[Cites 12, Cited by 0]

Bombay High Court

Smt. Alka Chandewar vs Shamshul Ishrar Khan on 2 April, 2026

2026:BHC-AS:15662


                                                                              Judgment-ARBP-19-2015-CP-102-F+.doc




                               IN THE HIGH COURT OF JUDICATURE AT BOMBAY
          Digitally
          signed by
          CHAITANYA
CHAITANYA ASHOK
                                    ORDINARY ORIGINAL CIVIL JURISDICTION
ASHOK     JADHAV
JADHAV    Date:
          2026.04.02
          18:35:26
          +0530


                            COMMERCIAL ARBITRATION PETITION NO. 19 OF 2015

                        Shamshul Ishrar Khan                                                    ...Petitioner
                                   Versus
                        Alka Chandewar                                                          ...Respondent

                                                       WITH
                                         CONTEMPT PETITION NO. 102 OF 2015
                                          (CIVIL APPELLATE JURISDICTION)

                        Alka Chandewar                                                          ...Petitioner
                                   Versus
                        Shamshul Ishrar Khan                                                    ...Respondent


                          Mr. Harinder Toor a/w Mr. Sandeep Parikh, Ms. Sabreen
                          Siddiqui, Ms. Pooja Jaiswal i/b Mr. A. C. Mahimkar, for
                          Petitioner in CARBP No.19/2015 and for the Respondent in CP
                          No.102/2015.

                          Mr. J.P. Sen, Senior Advocate a/w Mr. Sameer Bhalekar,
                          for the Respondent in CARBP No.19/2015 and for the Petitioner
                          in CP No.102/2015.


                                                 CORAM        : SOMASEKHAR SUNDARESAN, J.

                                        RESERVED ON : MARCH 11, 2026

                                   PRONOUNCED ON : APRIL 2, 2026.


                       JUDGEMENT :

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

Context and Factual Background:

1. Commercial Arbitration Petition No. 19 of 2015 is a Petition

filed under Section 34 of the Arbitration and Conciliation Act, 1996

("the Act"), impugning an Arbitral Award dated March 7, 2015, passed

by the Learned Arbitral Tribunal ("Impugned Award"), holding that

the Respondent, Alka Chandewar ("Alka"), is a partner in a

partnership firm named M/s Saras Developers ("Saras Developers"),

with an 80% share in Saras Developers, and directing the Petitioner,

Shamshul Ishrar Khan ("Khan") to pay Alka a sum of Rs. 7,39,72,584,

which is an amount computed as Alka's share on dissolution of Saras

Developers, along with interest at the rate of 10% per annum, from the

date of filing of the reference till the date of the arbitral award and

thereafter until realisation.

2. Khan challenges the Impugned Award on two fundamental

grounds, namely; that Alka's claim was barred by limitation, and that

the quantification of Alka's share in the proceeds of dissolution of Saras

Developers is grossly incorrect to a degree that renders the Impugned

Award perverse.

3. The factual matrix that is relevant for the purpose of

adjudicating this Petition may be summarised thus :-

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

A) Saras Developers was constituted under a

Partnership Deed dated May 15, 1990 ("Partnership

Deed"). The Partnership Deed was amended and restated

from time to time and the last available executed Partnership

Deed forming part of the record is dated October 22, 1997,

which would indicate that Alka and Khan were partners in

Saras Developers with Alka holding an 80% share and Khan

holding a 20% share;

B) Saras Developers was engaged in the business of

construction and land development. Land bearing CTS Nos.

558 and 558/1 to 558/18, admeasuring an aggregate of

approximately 3936 square metres, situated in Malad,

constituted Saras Developers' property. This property was

called "Gambers Estate".

C) Alka and her then husband Mr. Sovind Chandewar

("Sovind"), carried out business in the form of a

Partnership Firm called M/s Saraswati Developers

("Saraswati Developers"). The property of Saraswati

Developers was essentially another parcel of land, and the

building standing thereon, also situated in Malad, in which

the business of Hotel Kuber Palace was carried out;

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

D) Various disputes arose between Alka and Sovind in

relation to Saraswati Developers, which are ancillary to the

disputes between Alka and Khan in relation to Saras

Developers, which forms subject matter of the captioned

proceedings;

E) Initially, on May 15, 1990, a Partnership Deed was

executed in relation to Saras Developers, among one Mr.

Sushil Kumar Chamaria ("Chamaria"), Alka, one Mr.

Ramesh Gopal Chandewar ("Ramesh"), one Mr.

Krushnarao Lahuji Nirwan ("Nirwan") and Khan. This

partnership intended to carry on the business of property

development in the name and form of Saras Developers.

Each partner had a 20% share. Nirwan was Alka's father,

while Ramesh was Alka's nephew, but from Sovind's side of

the family;

F) Saras Developers purchased the land known as

Gambers Estate, referred to above between April 10, 1991 and

October 12, 1993. On January 06, 1994, Alka, Nirwan and

Ramesh executed a power of attorney constituting Alka's

husband Sovind as an attorney to represent them in the day-

to-day conduct of business by Saras Developers;

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

G) The Partnership Deed was modified from time to

time, and in particular on April 30, 1995, when Chamaria was

expelled from Saras Developers. Alka's share rose to 30%, the

share of Ramesh and Nirwan rose to 25% each, while Khan's

share remained at 20%;

H) Between 1994 and 1997, a building by the name

"Sarala Sadan," having seven storeys, was completed by Saras

Developers, and it is contended by Khan that most of the flats

in Sarala Sadan had been sold between 1994 and 2001;

I) On September 02, 1997, Nirwan passed away, and on

October 22, 1997, Ramesh retired as a partner of Saras

Developers. Consequently, another deed was executed among

the parties on October 22, 1997, and by this time the

partnership firm came to comprise only Alka, with a

partnership share of 80%, and Khan, with a partnership

share of 20%. Save and except for the modification of the

profit-sharing ratio, the existing terms of the earlier

Partnership Deed were continued without being disturbed;

J) It is contended by Khan that no further construction

or development on Gambers Estate was carried out by Saras

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

Developers between 1997 and 2002. Meanwhile, sometime in

2000, discord emerged between Alka and Sovind;

K) On June 19, 2002 ("First 2002 Deed"), a new

partnership deed is purported to have been executed in

relation to Saras Developers, with Alka's share being diluted

to 75%; Khan remaining at 20% and one Mr. Siddharth

Vinod Bathia ("Bathia"), acquiring a share of 5%. Shortly

thereafter, on June 27, 2002, a Supplemental Deed of

Partnership ("Second 2002 Deed") was purportedly

executed between the parties by which the shares were

significantly restructured, with Alka's stake coming down to

34%, Khan's stake going up to 33% and Bathia's stake rising

to 33%. This Second 2002 Deed recorded the agreement of

the partners to acquire and utilize Transferable Development

Rights ("TDR") to further develop and construct buildings

on Gambers Estate;

L) On January 19, 2003, the Partnership Deed was

purported to have been further reconstituted ("2003

Deed"), this time around, Alka's stake falling to 25%; Khan's

stake rising to 33.33%; Bathia's stake increasing to 33.33%;

and Sovind acquiring a stake of 8.34%;

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

M) On February 17, 2003, Saras Developers wrote to the

Registrar of Firms through one Mr. Haresh Shah, its

Chartered Accountant, seeking a change in the constitution

of Saras Developers. By this letter, the Registrar of Firms was

requested to note that Bathia had joined Saras Developers as

a new partner with effect from April 25, 2002;

N) Very shortly after the 2003 Deed, a Deed of

Retirement dated February 19, 2003 ("Retirement Deed"),

is purported to have been executed, by which Alka is said to

have retired from Saras Developers, with Khan, Bathia and

Sovind each having a one-third share, i.e. 33.33%, in Saras

Developers. It is claimed that a letter dated April 28, 2003

was issued by the same Mr. Haresh Shah to the Registrar of

Firms requesting it to note that Sovind had joined Saras

Developers as a new partner with effect from January 19,

2003, and that Alka had retired from Saras Developers with

effect from February 19, 2003;

O) The Registrar of Firms wrote to Saras Developers,

indicating a discrepancy in the address and signature of Alka

in the documents submitted on behalf of Saras Developers

through Mr. Haresh Shah. This was communicated by letters

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

dated April 07, 2003 and June 19, 2003 - in reasonable

proximity to the 2003 Deed and the Retirement Deed;

P) About two years later, on May 03, 2005, Alka issued a

legal notice to Sovind, stating that the power of attorney

dated January 06, 1994, which had been executed in favour

of Sovind, stood revoked;

Q) Meanwhile, between 2003 and 2006, construction

took place on Gambers Estate, and a building named Dr.

Gambers Residency, comprising Wings "B" and "C," each

having seven floors, was completed. Most of the flats in this

building are claimed to have been sold by Saras Developers

between 2004 and 2006;

R) On November 30, 2005, Sovind filed a Divorce

Petition in the Family Court against Alka;

S) Between 2005 and 2009, further construction of Dr.

Gambers Residency, namely Wing "A" having ten storeys,

was also completed by Saras Developers. It is claimed by

Khan that most of the flats in this building, i.e. Wing "A," had

been booked for sale in advance by Saras Developers between

2005 and 2006;

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

T) On April 24, 2008, Alka (who contends that she had

no notice of the deeds executed in 2002 and 2003 including

the Retirement Deed) issued a notice through her Advocates,

dissolving Saras Developers as a partnership firm

("Dissolution Notice") and invoking the arbitration clause

contained in the Partnership Deed dated May 15, 1990 and

the modified Partnership Deed dated April 30, 1995. Several

disputes that had arisen between the parties were sought to

be referred to arbitration;

U) By an order dated September 22, 2008, two

Arbitration Petitions filed by Alka seeking interim protection

pending arbitration under Section 9 of the Act, came to be

disposed of. Arbitration Petition No. 275 of 2008 filed by

Alka against Sovind in connection with Saraswati Developers

was dismissed, while Arbitration Petition No. 276 of 2008,

filed against Khan in connection with Saras Developers was

also disposed of;

V) On October 24, 2008, the Family Court dissolved the

marriage between Sovind and Alka by granting a decree of

divorce;

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

W) On June 22, 2009, a Learned Division Bench of this

Court allowed the withdrawal of an appeal filed by Alka

against the dismissal of the Section 9 Petition but mediation

was recommended in the said order;

X) Thereafter, an Application under Section 11 was filed

by Alka for appointment of an Arbitral Tribunal and this led

to constitution of the Learned Arbitral Tribunal, which

eventually passed the Impugned Award.

4. In the arbitration proceedings, Alka had essentially sought a

declaration that the First 2002 Deed, the Second 2002 Deed, the 2003

Deed and the Retirement Deed were forged, fabricated, null and void

and not binding on Alka. It was also prayed that the Learned Arbitral

Tribunal declare that the partnership firm of Saras Developers stood

dissolved with effect from April 24, 2008, pursuant to the Dissolution

Notice. A further relief for payment of Rs.~28.39 crores, representing an

80% share in the profits of Saras Developers, along with interest at the

rate of 10% per annum from the date of filing of the claim until

realisation was also sought by Alka.

5. Pleadings were completed, issues were framed, and evidence

was led by Alka and Khan in the form of affidavits along with

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

compilations of documents. On October 01, 2013, the Learned Sole

Arbitrator appointed by this Court recused himself in the arbitration

proceedings relating to Saraswati Developers, pursuant to a challenge to

his independence and impartiality filed by Sovind. The same arbitrator

had also been appointed as Sole Arbitrator in connection with disputes

and differences relating to Saras Developers. Khan too filed an

application on June 23, 2014 calling upon the Learned Sole Arbitrator to

recuse from the arbitration relating to disputes connected to Saras

Developers.

6. After filing such application, Khan refrained from attending

the arbitration proceedings any further. Khan's application seeking

recusal was dismissed by the Learned Sole Arbitrator approximately six

months later, on December 8, 2014. Considering that Khan simply went

missing and refrained from participating in the arbitration proceedings,

the Learned Sole Arbitrator had to deal with the proceedings and

consider the material before him without any assistance or participation

on the part of Khan to arrive at an assessment of the matter.

7. Alka obtained various documents utilizing her rights under

the provisions of Right to Information Act, 2005 ("RTI Act") and

referred to and relied on the Income Tax Returns filed by Saras

Developers obtained through such process. The Learned Sole Arbitrator,

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

therefore, interpreted such documents, and these indicated that Alka

was a partner of Saras Developers until Assessment Year 2003-04.

8. While the Learned Arbitral Tribunal framed 13 points for

determination and dealt with the same, for purposes of adjudicating this

Section 34 Petition, the Petitioner presses into service his grievances on

three counts. These are the findings that Alka's claim was not barred by

limitation; that Alka continued to be a partner right until the date of the

Dissolution Notice; and that Alka was entitled to a sum of Rs.~7.39

crores, in view of her 80% share in the partnership of Saras Developers.

Hearing in the Matter:

9. It is in this context that I have heard Mr. Harinder Toor,

Learned Advocate on behalf of Khan, Mr. J. P. Sen, Learned Senior

Advocate on behalf of Alka. With their assistance, I have examined the

material on record.

10. The matter was heard last year. Owing to efflux of time, the

matter was released and listed afresh for further hearing on March 11,

2026. With the assistance of Learned Advocates, the submissions and

further clarifications provided by them were taken on board, and the

matter was reserved afresh for Judgement.

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

Khan's Submissions:

11. Mr. Toor, Learned Advocate on behalf of Khan would

essentially attack the finding in the Impugned Award in respect of Alka's

continued partnership until the Dissolution Notice, and the amounts

held to be payable by Khan to Alka in respect of her share in Saras

Developers. Mr. Toor would point out that after examining the

annexures to the statement of claim and the particulars set out therein,

as indeed the documents procured pursuant to an application made

under the RTI Act, including the Income-tax returns, the Learned

Arbitral Tribunal has arrived at a view that the receipts of Saras

Developers from the sale of units developed by Saras Developers stood

admitted by Khan, inasmuch as Khan had stated in his Written

Statement dated August 30, 2010 that the receipts of Saras Developers

from sales is a matter of record.

12. Mr. Toor would point out that based on the aforesaid

conclusions, the Learned Arbitral Tribunal proceeded to compute Alka's

share of benefits from Saras Developers. Towards this end, the cost of

construction for Sarla Sadan and Gambers Residency Wings "B" and "C"

has been taken at 20%, while for Gambers Residency Wing "A," the cost

has been taken at 30%. The Learned Arbitral Tribunal thereafter

adopted a uniform deduction of 30% towards cost of construction in

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

respect of all three buildings. The total sale consideration for the three

buildings, namely Sarla Sadan and Gambers Residency Wings "A," "B"

and "C," has been computed by the Learned Arbitral Tribunal at Rs.

13.20 crores, from which a 30% deduction towards cost has been

effected, bringing the figure to Rs. 9.24 crores, which has been assessed

as the profit earned by Saras Developers. On such profit, Alka's 80%

share has been computed at Rs. 7.39 crores, which is the amount

awarded, along with interest at the rate of 10% per annum from August

30, 2010until the date of the Award and thereafter until realisation at

the same rate.

13. Mr. Toor would submit that the aforesaid findings are

vitiated by patent illegality and perversity. He would submit that the

patent illegality is writ large on the face of the Impugned Award, while

the perversity is borne out by the ignoring vital evidence in arriving at

the aforesaid decision. To substantiate the aforesaid contentions, Mr.

Toor would submit that the Income Tax Returns of Saras Developers

had indeed been available to the Learned Arbitral Tribunal. These had

been procured by Alka through the RTI Act and had been brought on

record before the Learned Arbitral Tribunal.

14. Yet, Mr. Toor would contend, the vital evidence in the form of

the computation and settlement of accounts of the partnership firm as

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

evidenced in the Income-tax returns, were not relied upon by the

Learned Arbitral Tribunal. The failure to rely on the data contained in

such Income-tax returns is assailed by Mr. Toor as being egregiously

perverse, despite being available as evidentiary material brought on

record by Alka herself.

15. The interpretation of Khan's Written Statement dated August

30, 2010 and the Additional Written Statement dated October 26, 2010

is also assailed by Mr. Toor on the premise that, while Khan had

categorically denied Alka's allegations as made in the Statement of

Claim, the Learned Arbitral Tribunal had ignored vital elements in both

the Written Statements filed by Khan. Pointing to the contents of Khan's

statements, Mr. Toor would submit that Khan had clarified that after

the financial year 1993-94, Saras Developers had regularly paid and

reflected the profit and remuneration to all the partners, including Alka,

as per the ratio of their respective shares. He would submit that such

payment of the respective shares would also be borne out by the Income

Tax Returns.

16. Mr. Toor would submit that Khan had explicitly reiterated

that Alka's allegation of being deprived of her share of profits was totally

incorrect and baseless. On the contrary, Khan is said to have clarified

that the books of Saras Developers had been destroyed during the

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

unprecedented volume of rainfall on July 26, 2005 and July 27, 2005,

and that a police complaint had been lodged to this effect on August 03,

2005. This is presented as another facet of vital evidence having been

ignored.

17. Moreover, the other piece of vital evidence allegedly ignored

by the Learned Arbitral Tribunal is Clause 2 of the undisputed Deed of

Retirement dated October 22, 1997, documenting the retirement of

Ramesh, which stated that accounts of Saras Developers had been

mutually made up and settled by the parties until that date. Therefore,

he would submit that the ignoring of this vital piece of evidence too

would vitiate the Impugned Award.

18. Mr. Toor would contend that, when one examines the

dissolution of a partnership firm, one must apply the provisions of

Section 48 read with Section 11 of the Indian Partnership Act, 1932. The

failure and neglect to apply these provisions would indicate, according

to Mr. Toor, that the Impugned Award is in direct conflict with

applicable statutory provisions, which are mandatory and

indispensable, thereby rendering the Impugned Award utterly illegal

and incapable of being sustained.

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

19. Mr. Toor would also point to an additional affidavit of Khan

filed on April 30, 2011, which indeed contained information on the

expenditure of Saras Developers incurred in the rehabilitation of

existing tenants and occupants, purchase of TDR, etc. Therefore, he

would submit that this vital evidentiary material, which would

demonstrate how the data contained in Exhibits TT, UU and VV could

not have been ignored, shows that the Impugned Award is perverse,

because it simply takes the total receipt of consideration from the

proceeds of sale of all three buildings. This, according to him, would

demonstrate that the computation is, on the face of it, contrary to these

very Exhibits and, therefore, the findings returned are not reasoned or

substantiated, thereby attracting the vice of patent illegality and

perversity.

20. Mr. Toor also finds fault with the Learned Arbitral Tribunal

having failed to factor in that Alka's share between December 03, 1992

and April 30, 1995 was only 20% and that her share between April 30,

1995 and October 22, 1997 was only 30%. These facets ought to have

been worked out in detail by the Learned Arbitral Tribunal, if it was

planning to work out the dissolution mechanism to ascertain the

benefits that were claimed by Alka and have been found to be payable to

her by the Learned Arbitral Tribunal.

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

21. Finally, Mr. Toor would also submit that the Learned Arbitral

Tribunal blatantly disregarded the vital evidence that Alka was fully

aware of the conduct of the partnership business and that she had

appropriated the assets of the partnership business. The entries at Sr.

No. 27 and 33 in Exhibit TT, about allotment and transfer of flats 601

and 701 on December 16, 1999 in Sarala Sadan, would clearly show that

Alka was one of the signatories regarding the sale of the said flat. The

full cause title to the statement of claim filed by Alka describes Alka to

be residing at Flat No. 601 and 701 of Sarala Sadan. Therefore, failing to

factor in the value of flats 601 and 701 which had been appropriated by

Alka would also point to the Learned Arbitral Tribunal having blatantly

ignored vital evidence that would be necessary in the computation of

benefits that the Learned Arbitral Tribunal has chosen to make.

22. As regards the claim being barred by limitation, Mr. Toor

would submit that the findings in the Impugned Award are untenable

again on the count of being initiated by patent illegality and for ignoring

vital evidence. According to him, the Learned Arbitral Tribunal has

adjudicated the issue of limitation on the basis of the consent order

dated June 18, 2010 by which reference was made to arbitration rather

than by reference to substantive claims made by Alka as set out in

Exhibits TT, UU, VV and XX appended to the Statement of Claim. The

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

provisions of Section 43 of the Act read with Section 3 of the Limitation

Act, according to Mr. Toor, ought to have been applied by the Learned

Arbitral Tribunal. In this context, he would submit that Khan had

categorically pleaded in the Written Statement that Alka's claim was

hopelessly barred by the law of limitation and this had in fact been

appreciated by the Order dated September 22, 2008 by which this Court

had dismissed the two Arbitration Petitions filed by Alka under Section

9 of the Act. This order, rejecting the Section 9 Petitions, had explicitly

noted that the Petitions were liable to be dismissed on the ground of

delay and laches.

23. Applying the contention of Alka's claims being barred by

limitation to the facts of the case, Mr. Toor would make a further

contention that the arbitration proceedings commenced on April 24,

2008, since arbitration was invoked on that date. Therefore, he would

submit that any claim that could be made as of that date and being

capable of being ruled upon by the Learned Arbitral Tribunal ought to

have been restricted to the three preceding years, namely April 24, 2005

to April 24, 2008. In sharp contrast, the contents of Exhibits TT and UU

would indicate that Alka has claimed a share in the purported sale

proceeds of flats sold and registered during the entire period ranging

from 1994 to 2005.

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

Alka's Submissions:

24. In sharp contrast, Mr. J. P. Sen, Learned Senior Advocate

appearing on behalf of Alka, would submit that the Learned Arbitral

Tribunal has returned considered findings upon evaluating the evidence

available on record. By withdrawing from the arbitration proceedings

and simply refraining from participating therein, Khan had adopted a

"catch me if you can" approach, which would point to the basis of the

Learned Arbitral Tribunal drawing an adverse inference from the

conduct of Khan, which had substantially increased the burden upon the

Learned Arbitrator of interpreting the documentary material placed

before the Tribunal.

25. Mr. Sen would submit that the last admitted position in

relation to the constitution of the partnership was reflected in the

Partnership Deed dated October 22, 1997, which unequivocally recorded

Alka's 80% share in Saras Developers, and that this position has been

rightly held to have continued without being altered lawfully. He would

further submit that Alka and Sovind, between whom matrimonial

disputes arose around 2005, have themselves yielded contemporaneous

documentary material in the form of pleadings and correspondence

exchanged between them. In this regard, Mr. Sen would contend that

reliance was rightly placed on a letter dated May 16, 2005, addressed by

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

Sovind to Alka, wherein it was asserted that Alka had retired from Saras

Developers, which, according to Mr. Sen, would itself demonstrate that

the question of Alka's alleged retirement was a matter of dispute and

could not be treated as an admitted or concluded position.

26. Mr. Sen would submit that Application under the RTI Act

was taken out primarily on July 4, 2005, which led to the Registrar of

Firms providing various documents pertaining to the composition and

ownership of Saras Developers. It is at this stage, Mr. Sen would

contend, that the alleged First 2002 Deed, the Second 2002 Deed, the

2003 Deed and the Retirement Deed came to her knowledge. While

these documents were purportedly filed with the Registrar of Firms,

evidently there was no entry in respect of such deeds found in the

Register of the Registrar of Firms. These deeds, purport to bear

signatures of Alka which were found to have been forged upon fair

appreciation of evidence.

27. Mr. Sen would submit that Alka took various steps in this

regard including the filing of police complaints and seeking

interlocutory relief under Section 9 of the Act. While the Arbitration

Petition came to be withdrawn on April 24, 2008, on the very same

date, Alka issued the Dissolution Notice, thereby dissolving Saras

Developers and also invoking the arbitration clause in the Partnership

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

Deed dated October 22, 1997, which is the last admitted document in

respect of the ownership and charter of Saras Developers. Mr. Sen

would point out that the Learned Arbitral Tribunal came be constituted

by appointment of a retired High Court Judge as a Sole Arbitrator on

June 18, 2010. However, after participating in the proceedings for four

years, Khan suddenly demanded that the Learned Arbitral Tribunal

recuse from the matter. This was fairly and correctly rejected by the

Learned Arbitral Tribunal, Mr. Sen would contend, also pointing out

that immediately after filing the application seeking recusal, Khan

simply stayed away from the arbitration proceedings and refrained from

participating any further.

28. Such act of staying away, Mr. Sen would submit, was

deliberate and wilful to frustrate and make it very difficult for the

arbitration proceedings to be conducted, evidently hoping that such an

approach would lead to some errors or shortcomings, which could then

be used to challenge the final adjudication if the outcome were adverse

to Khan.

29. On the facet of limitation, Mr. Sen would submit that the very

contention is vague and ambiguous. It is contended that the claim is one

of dissolution of Saras Developers and for rendering of accounts of Saras

Developers. Such a claim is squarely governed by Article 5 of the

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

Limitation Act, which provides for a period of limitation of three years

running from the Dissolution Date. Mr. Sen would submit that the

invocation of arbitration was well within time and related to rendering

of accounts and the financial statements including the balance sheet,

which are running accounts of the Saras Developers. Therefore, the

claim of limitation is unsustainable, he would contend, also pointing to

the grounds of challenge to the Impugned Award to contend that the

Learned Arbitral Tribunal has fairly and accurately returned findings of

forgery and fabrication of the intermittent Partnership Deeds after the

last admitted Partnership Deed alluded to by Alka.

30. The purported and fake dissipation of Alka's partnership

interests by diluting first to one third and below and eventually retiring

are untenable, Mr. Sen would contend, since evidently, she had not

executed any of these deeds. Therefore, Mr. Sen would contend that the

Learned Arbitral Tribunal has been reasonable in appreciating evidence

to hold that Alka had not retired, and owing to the wanton attempt at

frustration of the proceedings, the Learned Arbitral Tribunal made best

judgement assessment of Saras Developers' financials, from the material

available on record and applied itself to examination of the data relating

to the sales turnover, discounting it significantly by a factor of

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

construction cost, to arrive at the conclusion as to what her share would

be.

31. Mr. Khan not having participated in the arbitration

proceedings, Mr. Sen would submit the Learned Arbitral Tribunal

justifiably addressed itself to the period between the commencement of

arbitration proceedings i.e. the invocation of arbitration and the date of

appointment of the Learned Arbitral Tribunal. No objection had been

raised in this regard and Khan ceased to participate after four years of

participation, and yet, the ambiguous and incoherent contention on the

ground of limitation has been squarely addressed in the Impugned

Award.

32. The other contention raised on behalf of Khan, namely that

the Learned Arbitral Tribunal could not have granted direction to

release any payment in respect of any amounts preceding the period

prior to three years before the Dissolution Date, Mr. Sen would point

out, was never urged before the Learned Arbitral Tribunal. Mr. Sen

would also point out that no such contention has been raised even in the

Section 34 Petition. Therefore, he would submit that this is an entirely

new objection that has been conjured up on the run on behalf of Khan

and that in any case the objection is devoid of merit.

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

33. According to Mr. Sen, until Saras Developers is actually

dissolved and accounts are finalized, a partner in a partnership firm is

neither a creditor nor a debtor. On the contrary, he would submit the

partner is an owner of the partnership business and therefore, there is

no question of suing for any amounts during the subsistence of the

partnership prior to the Dissolution Date. On dissolution, Mr. Sen

would submit the partner is entitled to the amounts in his capital

account which should be dependent on the taking of accounts.

Therefore, in the absence of the accounts of the partnership being

presented to the Learned Arbitral Tribunal, the Learned Arbitral

Tribunal has had to simply factor in all the aggregate turnover, provide

for expenses however old they may be and has come up with a best

estimate and assessment of Alka's entitlement. Mr. Sen would submit

that Khan's absence has resulted in Alka being under-compensated.

34. Alka's assertion that no amounts had been received by her

ever from the business of Saras Developers has not even been

contradicted or even attempted to be disproved by Khan in the course of

the arbitral proceedings. Therefore, Mr. Sen would submit that the

Learned Arbitral Tribunal was duly entitled to take into account all the

sales effected by Saras Developers and linking Alka's entitlement to the

three years before the Dissolution Date is not at all reasonable.

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

35. Addressing the contentions about the manner of

quantification of the claims, Mr. Sen would submit that the business of

Saras Developers comprised construction of units in three buildings and

the proceeds of sale from such units. These buildings namely Sarla

Sadan, Gambers Residency 'B' and 'C' wings, (one building) and

Gambers Residency 'A' wing bracket (another building) were duly

constructed and units in them were actually sold to realise actual

proceeds. Despite being directed to furnish for inspection and produce

the audited financial statements including the profit and loss account

and the balance sheets of Saras Developers, Khan singularly failed to do

so and in fact refrained from doing so. If Khan simply did not provide

the relevant material that would lead to adjudication of these

proceedings, Khan has forfeited the right to find fault with a best

judgement assessment being made by the Learned Arbitral Tribunal.

36. Mr. Sen would submit that the only material that the Learned

Arbitral Tribunal was constrained to deal with were the registered sale

deeds to the premises in the three buildings. At the time of filing of the

Statement of Claim the sale of units in Sarla Sadan and Gambers

Residency 'B' and 'C' Wings had been completed. Exhibits TT and UU

annexed to the Statement of Claim, specifically, summarise and record

the price disclosed in the registered agreements for sale entered into in

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

respect of each of the premises in these buildings. Thereby, it is evident

that 34 flats in Sarla Sadan led to an aggregate value of Rs.~1.84 crores

and 33 flats in Gambers Residency 'B' and 'C' Wings put together

aggregated to Rs.~5.22 crores.

37. The sale of premises in Gambers Residency 'A' wing was still

in progress at the time of filing of the proceedings. Therefore, Mr. Sen

would submit, Alka was able to pursue only a fraction of the real

revenues of Saras Developers and owing to the non-cooperative and

subversive attitude adopted by Khan in the arbitral proceedings,

arguably, Alka has been under compensated by a wide margin, and

therefore the Section 34 Court ought not to pay much heed to the

submissions being made on behalf of Khan on the manner of

computation, which essentially seeks to question the appreciation of

evidence by the Learned Arbitral Tribunal.

38. In the course of the arbitration and pursuant to an order

dated October 7, 2010, passed by the Learned Arbitral Tribunal, Khan

had submitted a list disclosing consideration received in respect of

Gambers Residency 'A' wing. This disclosure admittedly indicated sale

consideration of Rs.~6.13 crores. It is precisely this amount presented

by none other than Khan that has been factored in by the Learned

Arbitral Tribunal to hold that a total consideration of Rs.~13.20 crores

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

had been received from the sale of premises in that building. The

number of flats sold in Sarla Sadan (34) and in Gambers Residency

and C Wing (33) would indicate that the total flats sold were 67 in

number at the time of filing the Statement of Claim. Gambers Residency

A Wing had 29 flats. To contend that the sale of all these flats would

yield a mere Rs.~13 crores in revenues is an extraordinary

understatement, Mr. Sen would submit.

39. Mr. Sen would submit that even from such evidently

understated sales turnover, the Learned Arbitral Tribunal went on to

further reduce 30% towards cost of construction to arrive at a really

under-evaluated profit of Rs.~9.24 crores for the entire project in

question and on that, the Learned Arbitral Tribunal computed an 80%

share at Rs.~7.39 crores in Alka's favour. Mr. Sen would allude to

potential receipts of cash that may have been involved in disposal of

Saras Developer's assets, since it is entirely unlikely that 96 apartments

could have been sold for a meagre sum of Rs.~13.20 crores.

40. As regards interest, Mr. Sen would submit that a partner's

entitlement to payouts should ideally entail interest from the

Dissolution Date because that is the date on which the entitlements are

drawn up, with accounts being firmed up. Yet, the Learned Arbitral

Tribunal has been conservative even on this count and has proceeded to

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

grant interest only from the date of reference to arbitration, which was

in 2010, even while the Dissolution Date was way back on April 24,

2008.

41. In these circumstances, it is contented by Mr. Sen that Khan,

who has deliberately withheld the full true and fair picture of the state of

affairs of Saras Developers; absented himself from the arbitration

proceedings; and has done his best to frustrate the effective conduct of

the arbitration proceedings, could never enjoy the credibility necessary

to invoke principles of fairness and equity to challenge the Impugned

Award, although ostensibly, the challenge to the Arbitral Award is

attempted to be fitted within the two fundamental facets of patent

illegality and ignoring of vital evidence.

Analysis and findings:

42. Having heard the parties and having examined the record, I

find that the matter is fairly straightforward. To begin with, the Learned

Arbitral Tribunal has well articulated how he has appreciated the

evidence before him and arrived at the finding that Alka had not retired

from Saras Developers. The very signatures on the disputed deeds had

been questioned by the Registrar of Firms and despite clarifications

having been sought, none were provided by Saras Developers. This led

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

to the changes reported in the disputed deed i.e. the First 2002 Deed,

the Second 2002 Deed, the 2003 Deed and the Retirement Deed, not

being accepted by the Registrar of Firms. As a result, these changes did

not get into the Register. When this event took place, a notary was

approached and he obliged with a certification of the signature having

been made in his presence. This led to Alka proceeding against the

notary, which culminated in disciplinary action against the notary.

43. The Learned Arbitral Tribunal also examined other

contemporaneous evidence. The Income-tax Department confirmed

that there was no evidence of partnership deeds to support Alka's

cessation as partner as claimed by Saras Developers in its tax returns.

The Learned Arbitral Tribunal also examined the findings of the

Sessions Court in anticipatory bail applications of two individuals

connected with the allegation of fraud in preparing the disputed deeds,

which indicates that Alka's purported signatures on the deeds did not

tally with her signature on the power of attorney signed by Alka. This

finding was upheld by this Court.

44. Having seen the analysis of the evidence and how it has been

weighed and appreciated, no reasonable person could contend that the

findings of the Learned Arbitral Tribunal in relation to the disputed

deeds, are unreasonable, arbitrary or passed without proper

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

appreciation of vital evidence. The Learned Arbitral Tribunal has done

a detailed analysis of the evidence before it, weighed it, and adjudicated

it fairly. It is not for this Court to second-guess the appreciation of

evidence and substitute findings as if it were an appellate Court.

45. Once it was found that Alka was indeed an 80% partner in

the firm and the purported dilution and subsequent retirement in a

series of steps between 2002 and 2003 was not credible at all, the

Learned Arbitral Tribunal's assessment had to move to discerning the

monetary claim. This was actively and positively frustrated by Khan

simply going missing from the arbitration. Evidently, the role of Sovind

and the marital discord between Alka and Sovind looms large over the

proceedings. However, what the Section 34 Court has to consider is

whether the Learned Arbitral Tribunal has done right in its approach to

the adjudication, and whether the grounds on which Khan would

challenge the Impugned Award, lend themselves for acceptance.

Reliance on Sales Turnover and not Tax Returns:

46. A core contention by Mr. Toor is that the Learned Arbitral

Tribunal ignored vital evidence in the form of contents of Income-tax

Returns, which according to him, undermines the adjudication that is

based on assessment of admitted sales turnover of Saras Developers.

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

This may seem attractive but has to be stated to be rejected. Audited

financial statements and the underlying books of accounts of a

partnership firm are meant to present a true and fair view of the state of

affairs of the partnership firm. The tax returns are meant to draw from

such financial information, purely from the perspective of conformity

with tax laws, and determination of taxable income, and effecting of

permissible deductions from them.

47. As such, every business enterprise would have both sets of

financial information - the commercial and mercantile reality of the

business as discernible from the audited financial statements, and the

tax compliance and computation of tax payable being discernible from

the tax returns. The extensive reference to tax returns not having been

analysed in the Impugned Award, and that too by a party that was not

the party that produced the returns, is unacceptable. It would not lie in

the mouth of Khan, who undermined justice delivery in the matter by

refraining from producing the audited financial statements and books of

accounts (even the tax returns became available only from Alka's efforts

under the RTI Act) to try to pick holes in the approach would lead to a

party that has not come to Court with clean hands, who can be non-

suited if he were the one prosecuting the claim, being permitted to

undermine the findings in the adjudication that was sought to be

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

crippled by the very party that came with unclean hands. The abject

refusal to provide the audited financial statements would enable

drawing of an adverse inference and the Learned Arbitral Tribunal has

meticulously analysed the information available to assess the position.

48. Mr. Sen is right that Khan's attempts at undermining the

conduct of the arbitration has led to what could be regarded as an

under-assessment of Alka's entitlements as an 80% partner in Saras

Developers. The very evidence of 97 flats being sold for a mere Rs.

13.20 crores; read with the steadfast refusal to provide the real audited

financial statements; seen along with Khan happily confirming that the

information about the sales being a matter of record; taken together

with the information on the sales figures having been extracted from the

publicly available registered conveyances, all point to the adjudication of

the monetary relief being a reasonable, logical and plausible one. It is

not for this Court to sit in judgement as if it were an appellate court.

On the contrary, all that the Section 34 Court must do is to see if the

grounds on which an arbitral award is challenged fits within the

parameters of challenge under Section 34 of the Act. If it does not so fit,

the arbitral award should be left undisturbed.

49. Seen from this prism, there is no basis to find fault with the

findings on monetary compensation. The Learned Arbitral Tribunal

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

had to examine what was its assessment of the true and fair state of

affairs of Saras Developers, in which very logically and reasonably, Alka

was found to have been a partner with 80% share. It is no argument to

state that the computation of taxable income should inform this

exercise, and that too from the mouth of the party that withheld the

financial information and did not even choose to deal with the

information flowing from the tax returns. Besides, the assessment of

Alka's 80% share has been made on the basis of the sales turnover

confirmed by Khan to be a matter of record and on that, the Learned

Arbitral Tribunal has applied a significant margin of costs and reduced

it further to arrive at financial entitlement of an 80% partner. I see no

reason to interfere with this empirical and logical approach to effecting

a best judgement on the part of the Learned Arbitral Tribunal despite

the party assailing the Impugned Award having been the party that did

its best to frustrate the proceedings.

Varying Partnership Stakes:

50. The next issue is of the Learned Arbitral Tribunal allegedly

not having seen the varying partnership stakes between the 1990s and

the 2000s. Alka had not had an 80% share throughout the period of

sales and therefore, the Impugned Award is assailed by Mr. Toor on

Khan's behalf. This too does not lend itself to acceptance. When

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

dissolution of a partnership firm is sought, the financial position of the

firm as of the date of dissolution is to be seen. The stakes as of that that

have to be examined. Accumulated profits and accumulated losses

accrue and get stated in the financial statements, which were kept

hidden by Khan.

51. It can be nobody's case that the Learned Arbitral Tribunal

believed that the only way to compute a partner's share and the

application of the provisions of the law governing determination of

partner shares can be given a go-by. If the Learned Arbitral Tribunal

had before it the requisite financial information that Khan was meant to

provide and yet deviated, it would be a completely different matter. The

Learned Arbitral Tribunal was doing its best as an arbitrator to conduct

a best judgement assessment of what the financial statements ought to

have contained, bracing against the subversive conduct of Khan and his

other purported partners including Sovind.

52. It is in that context that the Learned Arbitral Tribunal has

meticulously explained why it was taking the approach it did to arrive at

the monetary award. Therefore, the party that refrained from

explaining the varying stakes over a period of time, cannot be heard to

pick holes on the approach. It can also be nobody's case that Khan's

refusal to part with information rendered it a fair game for the Learned

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

Arbitral Tribunal to come up with whatever method it chose to

arbitrarily compute the monetary award. The Learned Arbitral Tribunal

has not done that, and instead it has based its computation on

confirmed sales turnover of the entire project. The adjustments for

varying stakes over time is inherent in the method of a reasonable guess

work that the Learned Arbitral Tribunal was entitled to make. The

margin of 30% was applied and hypothetical costs were reduced, and

then the share was arrived at.

53. The Learned Arbitral Tribunal was inclined to make such

guess work and it has done so reasonably. I am unable to accept Khan's

contention that this is not accurate computation resulting in any

perversity. It is trite law that even any perversity complained of against

an arbitral award ought to be of such order and magnitude that cuts to

the root of the matter. The shoe is on the other foot in this case when it

comes to perversity in approach. It was Khan and his purported

partners who have been fairly held to have not been partners, who have

subverted justice delivery in the instant case and withheld information

necessary to adjudicate.

54. What is a pointer to Khan protesting too much is the

contention that all the records of Saras Developers were somehow

washed away in floods of Mumbai city. When floods wash away records,

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

there should be no reason to file a police complaint but Khan contends

that such a complaint too had been filed. The contentions are simply

not worthy of acceptance - evidently, every possible and conceivable

step to frustrate the ascertainment of truth was adopted against Alka,

leaving the Learned Arbitral Tribunal with no option but to adopt a

reasonable best judgement assessment of what the financials of Saras

Developers would be.

55. For the same reason, the contention that Khan's additional

affidavit had information on costs incurred, purchase of TDR and the

like, and that these had not been considered, are self-serving

submissions. It is not for a party to throw at an Arbitral Tribunal

disparate information, and then refrain from participation in the

proceedings, only to then contend that whatever had been thrown at it

before abandonment of the proceedings ought to have been dealt with

by the Arbitral Tribunal. In fact, the Learned Arbitral Tribunal was

entitled to adopt the position that Khan was not pressing his

contentions in the additional affidavit. Yet, the Learned Arbitral

Tribunal has adopted a reasonable approach to estimation without

arbitrariness, instead of wringing its hands helplessly by Khan

undermining adjudication by the Learned Arbitral Tribunal.

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

Limitation Contention:

56. The contention on limitation too has been dealt with by the

Learned Arbitral Tribunal reasonably and well. First, it noticed that

between 2008 and 2010 the parties had engaged in mediation on the

nudge of this Court. Participation in mediation under the Court's

directions cannot be counted as leading to time-barring of the claim.

57. That apart, as regards the arguments made before this Court

on the facet of limitation, I am unable to accept Khan's contention that

when a dispute over dissolution of a partnership firm arises, only the

activity of the past three years would fall within the zone of

consideration. This would be absurd - every year, every partner would

be considered to have lost the right to make any claims to accruals that

have earned for the period prior to the preceding three years.

Effectively this would be reset of entitlements every year losing anything

attributable to the period prior to the past three years.

58. On the contrary, it should be remembered that the profit and

loss account depicts the picture of the financial year in question (it

always relates to a period) and that culminates in depiction of the

balance sheet as of a particular date (it always depicts the position of a

business on a given date). Accumulated profits and losses, reserves and

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

surpluses, balances in the capital account - all are generated and

accrued over the life of the partnership. When the firm is dissolved, the

balance sheet is broken down and the distribution of such accruals is

effected. If this basic first principle is borne in mind the abstruse and

complicated contentions about limitation would work themselves out.

59. Equally, when a partner retires, the firm moves forward with

remaining partners with the financial position being iterated for the

continuing partners. The contention that accounts were settled up in

1997 when Ramesh retired is also only to be stated to be rejected.

Accounts due to Ramesh would be settled but the accumulated earnings

would continue to enure to the benefit of the continuing partners with

the balances in the capital account.

60. Implicit in the Impugned Award is the fact that the Learned

Arbitral Tribunal was not at all wrong in handling the approach to the

dissolution of Saras Developers either in terms of assessment of value or

in terms of limitation. I am not impressed with the contentions in this

regard, and reject the same for the aforesaid reasons.

Other Facets:

61. The Learned Arbitral Tribunal has returned a finding that,

right until the Dissolution Date, Alka had an 80% share in the business

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

and profits of Saras Developers, and that despite her entitlement, she

had neither received nor been paid anything towards such entitlement.

The claim by Khan that Alka had contributed nothing towards Saras

Developers was found not to form part of the case pleaded by Khan. The

Learned Arbitral Tribunal had placed reliance on Exhibits TT, UU and

VV to the Statement of Claim, the contents of which were held to have

been conceded by Khan.

62. It was also noted that Khan had not dealt with this facet of

the claim and had simply refrained from producing any evidence

whatsoever, including Statements of Accounts and Balance Sheets of

Saras Developers. The Learned Arbitral Tribunal held Alka to be an 80%

partner of Saras Developers and on appreciation of evidence found that

the First 2002 Deed, the Second 2002 Deed, the 2003 Deed and the

Retirement Deed were not proven and could not be believed. This

overall approach indicates a clear and cogent structure to the thinking

and reasoning by the Learned Arbitral Tribunal. The Impugned Award

is not worthy of interference.

63. It is not necessary to expend too much analysis on the

arguments of whether a partner is a debtor or a creditor. Suffice it to

say, a partner is a part owner and on dissolution becomes a creditor or

debtor. The Dissolution Notice is what led to termination of

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

partnership. Until then, the business was running as a going concern

and the partners had their entitlements to the accumulated financial

position of the partnership firm as crystallised pursuant to the

dissolution.

64. The contention that Alka had slept over her rights and

contributed nothing also cannot be accepted. Alka trusted her partners

and was entitled to rely on the legal requirement of every partner having

to act in good faith towards other partners and the partnership firm.

Alka having been given two flats of the partnership too would be a

matter of keeping accounts, which were withheld by Khan from the

Learned Arbitral Tribunal. The computation of turnover and deemed

costs and resultant profits are all based on actuals as depicted from the

registered sale deeds. Therefore, on this count too, no interference is

called for. For the same reason, the contention that tax returns of each

partner and of the partnership indicating every year what the income of

the partner from the partnership firm was, is meaningless, coming as it

does from a litigant who has in his possession the financial statements

but withheld it from the adjudicatory process to subvert the outcome.

65. The Section 34 Petition is finally disposed of in these

terms, except on the facet of costs, which is deferred for consideration

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

along with the Contempt Petition on the next date. Interim Applications

if any shall also stand disposed of.

66. Since costs have to follow the event, Alka shall submit an

affidavit on the costs incurred till date in the matter, along with

supporting documentation for further consideration of this aspect of the

matter. Such affidavit shall be filed within a period of two weeks from

today. Khan may file an affidavit dealing with such affidavit within a

period of two weeks thereafter.

Contempt Petition No. 102 for 2015:

67. This leads me to the Contempt Petition No. 102 for 2015

alleging contempt for wilful disobedience of directions of the Learned

Arbitral Tribunal under Section 17 of the Act. I have upheld the

Impugned Award above. However, it is quite clear that the

administration of justice has been undermined by Khan. Mr. Toor

would point to Khan's ailments to plead against sending him to jail.

68. What has transpired here is that despite explicit protective

orders of the Learned Arbitral Tribunal, and in the teeth of the power of

attorney being revoked by Alka, alienation of flats and properties of

Saras Developers was persisted with by Khan and Sovind.

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

69. This Petition has had a chequered history with the Learned

Single Judge of this Court initially holding that the powers of contempt

could not be available under Section 27 of the Act in connection with

arbitration proceedings and that Section 27 is primarily for

administrative assistance of the Court for taking evidence. This view

came to be set aside by the Supreme Court, which held that the powers

under Section 27 would indeed cover wilful disobedience of directions of

Arbitral Tribunals, in particular, after the amendment of Section 17 of

the Act. Therefore, the Petition was sent back to this Court for

consideration of the same on merits and on facts.

70. In the course of Arbitration Proceedings, Alka filed an

Application under Section 17 of the Act seeking various protective reliefs

in the form of restrictions of alienation of assets and property and

disclosures of Bank Accounts, Statement of Accounts of Saras

Developers for ten years and accounts of income and profits made by

Saras Developers from the sale of flats in the buildings.

71. Khan too filed four Interim Applications seeking to restrain

Alka against filing any complaints to anyone claiming that she was a

partner of Saras Developers; an application seeking dismissal of the

Statement of Claim as being barred by limitation; an application seeking

a declaration that the primary prayer in the Statement of Claim was not

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

within the jurisdiction of the Learned Arbitral Tribunal; and the order

declaring that Khan is entitled to register flats in the name of flat

purchasers.

72. On October 07, 2010, the Learned Arbitral Tribunal issued

directions essentially directing Khan to furnish particulars in respect of

disposal of flats within a week in the format stipulated and directing

that any further disposal of flats would only be after seeking leave of the

Learned Arbitral Tribunal and furnishing particulars to Alka's Advocate

well in advance of making application seeking such need.

73. However, immediately thereafter, on October 14, 2010, five

flats were actually transferred with the transfers being executed in

blatant violation of the order dated October 07, 2010. Neither was leave

of the Tribunal taken nor was Alka intimated about the same. This led to

Alka seeking a relief in the form of appointment of a Receiver to take

control of the assets and also seeking a direction that Khan's statement

of defence should be struck out.

74. All the applications filed by Khan and Alka were heard jointly

on March 26, 2012. Khan did not press the Application seeking a

restraint on Alka from filing any complaints claiming to be a partner.

The Interim Application containing contentions about jurisdiction was

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

disposed of since the issues had already been framed in this regard. An

Interim Application seeking permission to register the flats on which

third party rights had already been created, was dismissed by the

Learned Arbitral Tribunal.

75. Specifically, for the financial year 2003-04, the Tribunal was

pleased to direct Khan to offer inspection of the books of accounts,

audited statements of income and expenditure, balance sheet and

income tax returns. Khan was also directed to disclose to Alka in writing

the details of the assets of Saras Developers and particulars of bank

accounts maintained by it. Full particulars of the flats that had been sold

and unsold was asked to be provided, all within a period of four weeks

from that date. The prohibition on alienation of assets was reiterated

and the need to ensure that prior notice is given to Alka and prior

approval of the Tribunal is taken for future disposals was also reiterated.

A bank guarantee was directed to be furnished in the sum of Rs.~1.25

crores to be kept alive pending conduct of the arbitration proceedings.

76. The order passed on March 26, 2012 was challenged under

Section 37 of the Act. No interim reliefs were granted on the challenge,

which in turn led to Khan filing a Special Leave Petition in the Supreme

Court, which issued notice and stayed further arbitration proceedings.

However, the Special Leave Petition was dismissed on September 02,

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

2013 making it obligatory on Khan's part to comply with the interim

order dated October 07, 2010 and further directions issued on March

26, 2012. However, none of this was complied with and the gross

defiance of the measures continued.

77. Further non-compliance is also seen with Khan executing in

June 2014, Deeds of Confirmation, confirming the sale of the four flats,

the disposal of which had been explicitly refused by the Learned Arbitral

Tribunal on March 26, 2012. Having examined such conduct, it is clear

that the alleged contemnor has demonstrated utter disregard and

contempt for the justice delivery process in the arbitration proceedings.

There was wilful disobedience and breach of not just the directions

passed in the 2010 Interim Order but also 2012 Interim Order, a

challenge to which came to a nullity with no ability to justify non-

compliance with them. Inspection of records was not granted. No asset

disclosure was made. No bank guarantee was provided. Costs directed

to be paid was not paid, and a further Deed of Confirmation was

executed confirming the sale of the very same flats that had been sold in

utter violation of both the aforesaid Interim Orders.

78. It is in these circumstances that the Contempt Petition sought

punishment of a terms of imprisonment of six months and imposition of

fine of Rs.2,000/- in terms of the Contempt of Courts Act.

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

79. Mr. Toor, on behalf of Mr. Khan would submit that there was

no intention on the part of Khan to commit any wilful disregard of the

directions issued by the Learned Arbitral Tribunal. Khan had

purportedly bona fide believed that the recusal by the Learned

Arbitrator from the proceedings between Alka and Sovind, would also

lead to his recusal from the arbitration in relation to Saras Developers.

Therefore, Khan is said to have tabled the request for recusal. This does

not inspire any confidence, since in any case, Khan simply played truant

with the Learned Arbitral Tribunal after such an application, leaving it

to the vagaries of litigation to evolve an outcome of its own, with a

potential for errors in the adjudication giving grounds to challenge the

outcome.

80. Mr. Toor also submits that in any case, the Learned Arbitral

Tribunal indeed had access to the relevant papers owing to the replies to

the queries under the RTI Act and that the Registrar of Firms and the

Income Tax Department had provided all material that would enable

adjudication of the proceedings and that indeed, the Arbitral Award

relies upon such records to return its findings. Therefore, he would

submit that lenient view may be taken inasmuch as there has been no

frustration of the adjudication process since in any case the material did

become available to the Learned Arbitral Tribunal.

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

81. Mr. Toor would submit an unconditional apology on behalf of

Khan in the matter and submit that a lenient view may be taken, also

bearing in mind the age and the ailments that Khan is going through.

82. Mr. Sen on the other hand would submit that the conduct by

Khan has indeed been contumacious. Khan simply stayed away from

participating in the arbitration proceedings. He did not provide any

data. Specific directions under Section 17 of the Act directing him to

produce information were wilfully ignored. In particular, the order

dated October 7, 2010 was deliberately ignored and therefore in his

view, that Khan was contemptuous of justice delivery processes is

proven beyond reasonable doubt. Mr. Sen would leave it to the Court to

consider such action as considered appropriate by this Court.

83. Having examined the record, it appears that Khan was the

20% partner when Alka was the 80% partner. The disputed deeds (the

First 2002 Deed, the Second 2002 Deed, the 2003 Deed and the

Retirement Deed) would show a systematic fake dilution of Alka in

which Khan was not alone - Sovind has evidently played an out-sized

role in undermining Alka's entitlements and is not before this Court.

Since Alka only recognised the undisputed position as obtaining prior to

her dilution under the disputed deeds, the others were not parties to

these proceedings. Khan being the only other partner has alone been

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

arraigned in the contempt proceedings, when the mastermind may be

elsewhere. The position Khan is in, is abject. However, Khan was not

alone, and he appears to have been one of the many players involved in

subverting the arbitral process. The disputes between Alka and Sovind

have not been heard by this Court. Therefore, this Court is constrained

to examine only Khan's role in these proceedings at this stage.

84. Considering the wanton and deliberate manner of conduct, it

would not be appropriate to let this off lightly. This is a fit case for

framing of charges for consideration of criminal consequences for such

conduct. Yet, taking into account Khan's purported ailments and the

sheer persuasiveness on the part of Mr. Toor, I consider it appropriate

to give Khan an opportunity to truly purge the contempt alleged.

85. In my opinion, the only way for Khan to purge the contempt

alleged is to deposit the entire awarded amount along with interest

computed until the date of pronouncement of this judgement with the

Registry of this Court within a period of six weeks from the

pronouncement of this judgement. This would be the only means of

truly indicating remorse on his part and to assure the Court that the

apology is not lip service. If such deposit is made, the Court would

consider whether the next stage for criminal contempt must be resorted

March 23, 2026 Chaitanya

Judgment-ARBP-19-2015-CP-102-F+.doc

to in terms of framing of charges. If no such deposit is made, the

matter shall be listed for framing of charges.

86. The Contempt Petition shall be listed for further

consideration and reporting compliance after six weeks.

87. As stated above, the assessment of costs for this round of

litigation including in the Section 34 Petition is deferred for further

consideration when the Contempt Petition would come up for

consideration on the next date.

88. All actions required to be taken pursuant to this order shall

be taken upon receipt of a downloaded copy as available on this Court's

website.

[ SOMASEKHAR SUNDARESAN, J.]

March 23, 2026 Chaitanya

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter