Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mumbai Metro Rail Corporation Limited vs Land T Stec Jv Mumbai
2025 Latest Caselaw 6719 Bom

Citation : 2025 Latest Caselaw 6719 Bom
Judgement Date : 10 October, 2025

Bombay High Court

Mumbai Metro Rail Corporation Limited vs Land T Stec Jv Mumbai on 10 October, 2025

   2025:BHC-OS:19481


                                                                                  OJ-904-IAL-28857-2025.doc



                                     IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                            ORDINARY ORIGINAL CIVIL JURISDICTION
                                 INTERIM APPLICATION (L) NO. 28857 OF 2025
                                                   IN
                            COMMERCIAL ARBITRATION PETITION (L) NO.28855 OF 2025

                        Mumbai Metro Rail Corporation Limited                               ...Applicant/
                                                                                            Petitioner
                                   Versus
                        L&T-STEC JV Mumbai                                                  ...Respondent


                            Mr. Birendra Saraf, Advocate General, Senior Advocate, a/w
                            Simil Purohit, Ameya Gokhale, Kriti Kalyani, Siddhant Marathe,
                            Ansh     Kumar,     i/b  Shardul      Mangaldas,     for   the
                            Applicant/Petitioner.
                            Mr. Vikram Nankani, Senior Advocate, a/w Indrnil Deshmukh,
                            Saloni Kapadia, Karan Ghandhi, i/b Cyril Amarchand Mangaldas,
                            for Respondent.

                                                  CORAM         : SOMASEKHAR SUNDARESAN, J.
                                                  DATE          : OCTOBER 10, 2025

                       Oral Judgment:


                       Context and Factual Background:



1. Interim Application (L) No.28857 of 2025 is an Application

seeking a stay on the execution of an arbitral award dated June 16, 2025

("Impugned Order") pending the hearing and final disposal of Digitally signed by ASHWINI ASHWINI JANARDAN JANARDAN VALLAKATI VALLAKATI Date:

Commercial Arbitration Petition (L) No.28855 of 2025, which is an 2025.10.16 19:15:03 +0530

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

application under Section 34 of the Act.

2. The Petitioner, Mumbai Metro Rail Corporation Limited

("Corporation") is essentially pressing for an unconditional stay without

any requirement to make any deposit of any component of the amounts

awarded, on the premise that the award is ex facie perverse and has

made such obvious blunders that no reasonable arbitral tribunal could

have taken the approach adopted by the Learned Arbitral Tribunal.

3. The contract in question entailed design and construction of

specific stations and tunnels in the Mumbai Metro Rail Project. The

price quoted and agreed upon was a firm and composite lumpsum price.

The bid for the contract had been made by the Respondent, L&T-STEC

JV Mumbai ("Contractor") in May 2015 before the introduction of

Goods and Services Tax ("GST"). The parties had agreed on a Change in

Law provision in Clause 13.7 to be used for effecting adjustments for the

impact of introduction of GST - the rationalization of indirect taxes in

the GST had led to fiscal benefits and exemptions that had been

available in other indirect taxes before GST getting subsumed into the

GST regime. This is the first head of the dispute between the parties.

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

4. Whether a certain standard directed by the Corporation for

adoption by the Contractor constituted "additional work", necessitating

compensation for the Respondent, is the second head of dispute

between the parties. The standard of 'one strut failure' in place of

temporary earth retaining structures as plainly contracted, and whether

that necessitates compensation for the Respondent has been considered.

Impugned Award:

5. The Impugned Award is a majority award (passed by the

Presiding Arbitrator and the Learned Arbitrator nominated by the

Contractor) awarding a sum of Rs.~250.82 crores to the Contractor, of

which, Rs. ~21.26 crores is attributable to cost variation on account of

additional work said to be carried out outside the scope of the project,

while Rs. ~229.56 cores is attributable to the claim towards

reimbursement for the impact of GST introduction for the period

between July 1, 2017 and September 30, 2022.

6. The Learned Arbitrator nominated by the Corporation has

dissented from the majority. The Dissenting Arbitrator has held that on

the additional works, the Contractor would owe a refund of Rs. ~27.09

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

Lakhs to the Corporation. On the GST front, the Dissenting Arbitrator

has not denied the claim on the reimbursement for GST, but has sought

a pro-rata weighted adjustment to the amount or Rs. ~229.56 crores

awarded by the majority by giving weightage to the two disputed

percentage components of the tax impact on the contract price (10.3%

as claimed by the Contractor and 6.78% as claimed by the Corporation).

Depicting the working of such adjustment, the Dissenting Arbitrator has

ruled that the impact of GST should be Rs. ~134.42 crores, about Rs.

~95 crores lower than what was granted by the majority. In the same

breath, the Dissenting Arbitrator also concludes that a reputed

chartered accountant firm must make an assessment to compensate the

Contractor for introduction of GST in terms of the Change in Law

provisions in the contract.

Contentions of the Parties:

7. Dr. Saraf, Learned Advocate General for the State of

Maharashtra would contend that the foundational perversity in the

approach of the Learned Arbitral Tribunal lies in the Learned Arbitral

Tribunal finding it unnecessary to call for components of the contract

price to examine the precise component of tax in the price quoted by the

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

Contractor. He would submit that it was vital to investigate and

ascertain the precise impact of introduction of the GST regime on the

contract price, which was impossible knowing the other ingredients and

components of the price. It is contended that it is entirely arbitrary to

provide any compensation for impact of GST introduction, without such

data breaking down the components of the price bid of the Contractor.

8. Dr. Saraf would also point to various components of the

Impugned Award and submit that there was no itemized analysis of

each sub-segment of specific notifications and exemptions that had been

available earlier, with no means of analysing what precise effect the

introduction of GST would have. He would point to the exemptions

considered by the Learned Arbitral Tribunal to indicate that there was

nothing to show that such exemptions had been relied upon and

factored in while bidding by the Contractor, thereby rendering the

findings in this regard arbitrary.

9. Likewise, Dr. Saraf would contend, exemption that had been

available for work on construction of monorail and metro projects, that

were removed in the GST regime, has been applied even to elements

unconnected to construction such as housekeeping and refurbishment

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

of certain components of contract. The upshot of this submission is that

without an itemized analysis of sub-elements, it would not be possible to

examine whether the removal of the exemption indeed had a material

impact on the contract price.

10. Dr. Saraf would also point to the agreed base date of April 4,

2015 for the assessment of impact of change in service tax on royalty. He

would submit that the Finance Bill introduced in Parliament in

February 2015 had been passed on April 30, 2015. Therefore, when the

contractor made a bid on May 15, 2015, the Contractor was well aware of

the implications of the Finance Bill. Yet, the Learned Arbitral Tribunal

has factored in the element of Presidential Assent for the Finance Bill

having been given only on May 14, 2015 (two days after the bid was

made by the Contractor). The upshot of the submission is that the

Impugned Award is contrary to commercial common sense, since no

bidder would shut his eyes to impact of tax changes in legislation

already passed by Parliament (the Finance Bill being a money bill),

solely on the premise that Presidential Assent was awaited.

11. As regards, compensation of additional work done, the

Learned Advocate General would submit that originally it was envisaged

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

that a process of "anchoring" would be used when tunnelling for the

metro, to ensure that there is no collapse of structures including

heritage structures in the vicinity of the tunnelling. In the course of the

operation of the contract it had been decided to use the standard of a

"one strut failure". The dispute in this regard is about whether setting

up a one strut failure structure in the course of tunnelling constitutes

additional work. For purposes of making such a claim, the Contractor

was required to show how much additional steel had become necessary

and no evidence has been provided in this regard.

12. Most damagingly, the Learned AG would claim that the

Corporation's witness statement had been shut out. This witness was

the Engineer-in-Charge of the project. It is contended that the witness

has been disqualified by the Learned Arbitral Tribunal. The witness was

asked whether he is an expert with experience on the subject, and he

responded in the affirmative. This purportedly led to the Learned

Arbitral Tribunal taking a view that the evidence of this witness could

not be considered since he could not be regarded as an independent

expert witness but as a fact witness who was not on the pay roll of the

Corporation but had a specific role to play in the project. At the same

time, Dr. Saraf would contend, the Learned Arbitral Tribunal selectively

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

chose to rely upon certain elements of the cross-examination of the

same witness but otherwise ignored the evidence in his examination in

chief.

13. Mr. Vikram Nankani, Learned Senior Advocate on behalf the

Contractor who would submit that none of the contentions on behalf of

the Corporation is tenable inasmuch as it is not open to the Corporation

to expect a "vivisection" of the contract price, which was a lumpsum

contract price, with the bidders competing on the margins they sought

to earn. The impact of GST is a narrow point and had been examined in

two rounds - once by the Engineer-in-Charge who chose to appoint a

chartered accountant, and then by the Dispute Adjudication Board

("DAB") set up under the contract.

14. The methodology for assessing the GST impact, Mr. Nankani

would submit, had already been thrashed out, and the dispute was about

the computation of amount, applying the agreed methodology. Mr.

Nankani would contend that it was the Corporation's case that the tax

component of the contract price had been 10.03% while it is the

Contractor's case that the tax component had been 6.65%. The DAB had

arrived at 6.78%. All three had converged on the same methodology

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

with the assessment of impact varying among them.

15. Mr. Nankani would also submit that all the members of the

Learned Arbitral Tribunal were engineers and technically qualified to

deal with contracts of this nature. There were other contracts for other

metro projects that the Contractor had brought to bear, and the Learned

Arbitral Tribunal has well understood the parameters of the issues

involved.

16. Addressing the issue of how the Corporation's witness had

been handled, Mr. Nankani would submit that the witness was not shut

out at all. The Learned Arbitral Tribunal only took a view that the

factual inputs from the witness would be considered but his claim of

having expert knowledge and the probative value of his expert

extrapolations from the facts were handled with scepticism. This is a

perfectly logical and fair approach, he would submit, to treat with a

higher degree of scepticism, the evidence that had been led by a partisan

witness, claiming to be an expert, with the Learned Arbitral Tribunal not

treating his expertise as relevant for the determination. The legal

implications of law language used by engineers, Mr. Nankani would

submit, must not be analysed through the same prism as how language

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

used by judges and lawyers should be analysed.

17. According to Mr. Nankani, the Learned Arbitral Tribunal

comprising technically qualified people would carry greater weight in

relation to the assessment of compensation for additional work.

According to Mr. Nankani, the Impugned Award is based on empirical

analysis for the material on record and merely because the Learned

Arbitral Tribunal used a phrase "preponderance of probability" it would

not follow that its assessment of damages and costs is speculative

without an appropriate adjudication.

Analysis and Findings:

18. At the threshold it is clarified that all observations by me here

are solely in aid of deciding whether a case for an unconditional stay has

been made out and nothing else.

GST Issue:

19. Having heard Learned Senior Advocates for the parties, and

having examined the record with their assistance, some broad facets of

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

the matter are noteworthy. The contract was for building a few stations

in the metro rail project and the related tunnelling. The bidding took

place before the introduction of the GST regime. The parties indeed

have consensus that the impact of rationalization of GST, the framework

of the GST and its implications would lead to an impact on the contract

price and the consequential adjustments. The parties conducted

themselves in line with the GST regime for the residual period of the

contract after its introduction. Some of the benefits that were earlier

available to the Contractor were subsumed in the wider indirect tax

reform that the GST constituted. In terms of economic costs, the

dispute really is what is the manner in which these rationalized benefits

have to be split between the parties.

20. It is seen that the parties indeed engaged in minute detail on

the specific heads of differences on the GST impact. Ekbote Deshmukh

& Co, a chartered accountant firm engaged by the Engineer-in-Charge

who also deposed as the Corporation's witness, came up with an

assessment on August 27, 2022 that the tax component of the contract

price was 10.03%. The Contractor was of the view that the tax

component had been 6.65%.

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

21. The difference of opinion among the parties centred around

the change in taxation treatment under seven heads, accounting for 99%

of the differences between the parties. These were: service tax on

labour; octroi on fuel and locally procured materials; service tax on

royalty; excise on safety materials; special additional duty on capital

goods; MVAT implications for overhead allocations; MVAT on sub-

contracting items and consequential octroi. Whether these heads were

subsumed under the GST regime, and if so, how and in what quantum

they were subsumed, fell for consideration.

22. The DAB heard the parties at length on the differences

between the two assessments, and concluded in its report dated

December 14, 2023, with detailed reasons, that the component of taxes

in the contract price was 6.78%. This was not acceptable to the

Corporation, which led to the arbitration. Indeed, the Learned Arbitral

Tribunal had the power to re-open and examine the evidence considered

by the DAB and equally, the DAB's report had been agreed by the parties

to constitute evidence for the Learned Arbitral Tribunal. The following

extracts from the arbitration agreement are noteworthy:

The arbitrator(s) shall have full power to open up, review and revise any certificate, determination, instruction, opinion or valuation of the

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

Engineer, and any decision of the DAB, relevant to the dispute. Nothing shall disqualify the Engineer from being called as a witness and giving evidence before the arbitrator(s) on any matter whatsoever relevant to the dispute.

Neither Party shall be limited in the proceedings before the arbitrator(s) to the evidence or arguments previously put before the DAB to obtain its decision, or to the reasons for dissatisfaction given in its notice of dissatisfaction. Any decision of the DAB shall be admissible in evidence in the arbitration.

[Emphasis Supplied]

23. Therefore, the scope of review by the Learned Arbitral

Tribunal was wide and expansive and the DAB's report too formed an

integral part of the evidence. Yet, it cannot be forgotten that the parties

may have finely and sharply debatable differences on nuances of how to

interpret tax circulars and see if any component really had an impact on

the contract price. Fiscal statute by its nature could lead to multiple

interpretations. However, one cannot lose sight of the fact that these

fine multiple competing interpretations are meant for consideration in

the final hearing. The nature of the issues raised on behalf of the

Corporation, in my opinion, fall in this category. They do not scream

themselves aloud calling for an ex facie finding of abject perversity

warranting an unconditional stay. To interfere by way of an

unconditional stay, it would be necessary to establish such perversity

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

that the findings cannot at all be countenanced. The Impugned Award

is more or less in line with the DAB's report, and provides its own

reasons for such conclusions.

24. One cannot lose sight of the fact that the Impugned Award is

in the nature of a money decree. Therefore, the scope of review has to be

one of examining whether the Impugned Award is of a nature that no

reasonable person could have ever come to the conclusions that it drew,

and whether it was so perverse that in the final hearing, there is a high

degree of prospect that the Impugned Award would be set aside.

25. Indeed, the framing of the challenge to the Impugned Award

has been fashioned with this standard in mind, but having examined the

Chartered Accountant's report, the DAB's report and the Impugned

Award, it cannot be said that the assessment of GST impact would be

perverse and that too of a degree warranting an unconditional stay.

One Strut Failure - Additional Works:

26. Likewise, with the issue of whether the one strut failure

standard was to be treated as additional work; or whether the quality of

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

steel used for it was deliberately of a higher quality just to benefit from

its resale value after its temporary use (this was contended by the

Corporation in the arbitration), would at best present issues of

appreciation of evidence. Even in the final hearing of this Petition, the

Learned Arbitral Tribunal would have to be treated as the master of the

evidence and the best judge of the quality and quantity of evidence.

That the Dissenting Arbitrator made a case for refund of monies may be

his informed view, but the view of the majority constitutes the arbitral

award. At a prima facie stage, the view is not so perverse as to warrant

an unconditional stay.

Charge of Witness being Shut Out:

27. I have also examined if there was an abject process failure

such as the alleged shutting out of the evidence of the Corporation's

witness. What is apparent is that the Engineer-in-Charge was presented

as the Corporation's witness. The Learned Arbitral Tribunal found that

significant components of the evidence led by him delved deep into

opinions and matters of expertise. It is apparent that the witness was

not shut out by the Learned Arbitral Tribunal. The witness was

examined and cross-examined. In the Impugned Award, when

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

examining the evidence, the Learned Arbitral Tribunal has stated that it

was discounting his claims to expertise in his opinions since he could

not be treated as an independent expert.

28. The Engineer-in-Charge is the first check and balance in the

relationship between the parties to a construction contract. His decision

was up for review before the DAB. That decision and the Engineer-in-

Charge's decision collided before the Learned Arbitral Tribunal. The

very same person being presented as the Corporation's witness, it is not

inappropriate for the Learned Arbitral Tribunal to have stated that it

would discount the claims to expertise in his opinions, since he was not

an independent expert.

29. The Learned Arbitral Tribunal held that significant portions

of the evidence led by the Engineer-in-Charge contained opinions rather

than facts. The Learned Arbitral Tribunal has stated that it would not

shut him out at all and has indeed taken into account the facts deposed

by him but has asserted that it would not lean on the interpretations and

extrapolations drawn by him.

30. In fact, it is seen that this discussion became necessary in the

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

Impugned Award, because it was the Contractor that moved an

application to strike off the evidence of the Engineer-in-Charge as a

witness. The Learned Arbitral Tribunal rejected this application. The

Learned Arbitral Tribunal analysed the evidence to return a finding that

the witness had gone way beyond deposing to facts and had argued

extrapolations in his deposition, which the Learned Arbitral Tribunal

indicated it discount in its probative value. The language in which such

an observation is framed by the Learned Arbitral Tribunal comprising

all engineers and non-lawyers need not be as finessed in legal terms as

law language used by judges and lawyers, but the plain meaning of what

the Learned Arbitral Tribunal has sought to convey is that they are not

shutting out the witness at all and they were only being circumspect

when considering his probative assertions.

31. Now, even this can be up for adjudication in the course of the

final hearing, but at this stage, considering that the Learned Arbitral

Tribunal had actually rejected the Contractor's application to disallow

the witness and had explained in its words how it would consider the

evidence of this witness, a case is not made out for holding that there

has been a breakdown of natural justice pointing to perversity of a

magnitude that necessitates an unconditional stay on the Impugned

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

Award.

Conclusions and Directions:

32. The multiple arguments about how to truly interpret

individual notifications and circulars can be considered in the final

hearing. At this stage, the interpretations adopted by the Learned

Arbitral Tribunal are not alien, even to the Corporation - they are in

line with much of what the DAB ruled. The Corporation may disagree

with the DAB and indeed with the Learned Arbitral Tribunal, but that

would not mean that the Impugned Award would automatically become

perverse.

33. That apart, even the Dissenting Award that was strongly

relied upon by the Corporation has not taken such an extreme stand as

taken by the Corporation in these proceedings. In fact, the Dissenting

Award provides for an award under the GST head at Rs. ~134 crores in

place of the Impugned Award granting Rs. ~229 crores. It is another

matter that the Dissenting Award, in the same breath, recommends

appointing yet another chartered accountant, little realising that such an

approach would be an abdication of the arbitral role - the parties had

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

already been through the process of having a chartered accountant

examine facts, as also through the process of the DAB. It was now for

the Learned Arbitral Tribunal to rule, which the majority of the

arbitrators have done.

34. When parties proceed to arbitration and that too after a

detailed pre-arbitral process being contracted, there has to be a higher

credibility and credence given to the arbitral award. The contentions

sought to be raised on both counts (tax impact and additional work) fall

in the realm of purporting to raise finely nuanced points that are best

made in the final hearing. They do not constitute grounds to infer

perversity based on any reasonable review on the face of the record, to

warrant an unconditional stay. Taking a holistic view of the matter and

the relative strengths of the prima facie case canvassed by each side, I

am not satisfied that a case for an unconditional stay is made out.

35. In a nutshell, assuming all that is being said on behalf of the

Corporation is taken to be arguable, they present matters to be

considered at the final hearing. The contentions do not lend themselves

to serious interference into a reasoned outcome in the arbitral

proceedings.

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

36. Nothing contained in this order is a final adjudication of

merits canvassed by the parties, but clearly, no case is made out such

that the Impugned Award is tainted by such perversity that it brooks no

deposit for stay on its execution. It is not facially untenable and is not

undermined by patent illegalities - the closest the Corporation came to

approaching this standard was with the contention about the witness

being shut out, but that is not a convincing manner of reading the

approach of the Learned Arbitral Tribunal to the witness.

37. In these circumstances, it is directed that subject to the

amount awarded, along with interest as awarded till date, being

deposited with the Registry of this Court within a period of eight weeks

from today, execution proceedings shall remain stayed.

38. Should such deposit be made, the Contractor shall be entitled

to withdraw the amount deposited along with accruals thereon by

providing a full unconditional bank guarantee for the amount sought to

be withdrawn, in accordance with the applicable rules of this Court.

October 10, 2025 Ashwini Vallakati

OJ-904-IAL-28857-2025.doc

39. All actions required to be taken pursuant to this order shall

be taken upon receipt of a downloaded copy as available on this Court's

website.

[SOMASEKHAR SUNDARESAN, J.]

October 10, 2025 Ashwini Vallakati

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter