Citation : 2025 Latest Caselaw 6552 Bom
Judgement Date : 7 October, 2025
2025:BHC-OS:17920
ARBP-200-2014-J - FINAL.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION PETITION NO. 200 OF 2014
Vasanji Assaria Mamania ...Petitioner
Digitally
signed by
Versus
SHRADDHA
SHRADDHA KAMLESH
KAMLESH TALEKAR
TALEKAR Date:
Yadunarayan Mulky Shetty ...Respondent
2025.10.07
14:49:18
+0530
Mr. Dinyar D Madon, Senior Advocate a/w Mr Ramachandran
Narayanan and Mr Ashwin Bhadang i/b Narayanan and
Narayanan, for Petitioner.
Mr. Farhan Dubash a/w. Rahul Jain i/b VBA Legal, for
Respondent.
CORAM : SOMASEKHAR SUNDARESAN, J.
RESERVED ON: JULY 14, 2025
PRONOUNCED ON: OCTOBER 7, 2025
JUDGEMENT:
Context and Factual Background:
1. This is a Petition filed under Section 34 of the Arbitration and
Conciliation Act, 1996 ("the Act") challenging an arbitral award dated
May 31, 2013 ("Impugned Award") passed by a Learned Arbitral
Tribunal comprising a Sole Arbitrator in connection with disputes and
differences between the Petitioner, Vasanji Assaria Mamania
("Mamania") and the Respondent, Yadunarayan Mulky Shetty
("Shetty").
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
2. The parties entered into a memorandum of understanding
("Agreement") by which Mamania agreed to purchase from Shetty a
certain land parcel located in Chembur, described in fuller detail in the
Impugned Award, admeasuring 2,493.9 square metres (" Subject
Property"), for a consideration of Rs. 11.25 crores, of which Rs. 50 lakhs
were payable at execution; Rs. 1 crore was payable as and when Shetty
removed the tenants from the premises and the balance Rs. 9.75 crores
against completion of the conveyance. On the face of the Agreement, a
date of execution is not discernible and there had been some differences
about the precise date although there was no dispute about execution of
the Agreement towards the end of April and start of May 2006. For all
purposes of this judgment the date of the Agreement is taken as May 2,
2006, as indicated in the Impugned Award and in the pleadings in the
Petition. As will be seen from this judgement, nothing would turn on
this facet.
3. The parties agreed that if a survey of the Subject Property
were to indicate a lower area, the consideration would be adjusted
downwards proportionately. Within three months, Shetty was required
to settle with all the tenants to get them to vacate the Subject Property;
make out a marketable title to the Subject Property free from any
encumbrance; have a survey conducted to demarcate the Subject
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
Property at Mamania's cost; and build a boundary wall around the
Subject Property as per the survey coordinates, at Mamania's cost. The
conveyance too was expected to be completed within three months,
subject to Shetty complying with the aforesaid obligations.
4. The Agreement records in two places that time was of the
essence of the contract and on the face of it indicated a timeline of three
months for completion. The parties agreed that in the event of non-
completion due to Shetty's default, Mamania would have the option of
demanding specific performance; or demanding a refund of the "earnest
money" with interest at 12% per annum. Likewise, if Mamania's
payment obligation were to not be honoured, Shetty would have the
option to demand specific performance; or demand interest at 12% per
annum for the period of delay in payment; or cancel the Agreement and
forfeit the "earnest money" with anything excess paid being refunded
with interest at 12% per annum after 30 days of electing to cancel the
Agreement. The Agreement does not define the term "earnest money"
although it is used twice and in one place, indicates a blank that has
remained unfilled. The amount of Rs. 50 lakh agreed to be paid at
signing of the Agreement has been treated as the earnest money.
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
5. Even before executing the Agreement, Mamania had paid a
sum of Rs. 1.5 crores to Shetty. After execution, he made two further
payments aggregating to Rs. 1.5 crores towards the end of July 2006,
taking the total amount paid to Rs. 3 crores.
6. Mamania then filed Suit No.1255 of 2007 in this Court
seeking specific performance of the Agreement. A deposit of Rs. 8.25
crores was made by Mamania with the Registry of this Court on June 27,
2007. By consent of the parties, the matter was referred to arbitration,
which culminated in the Impugned Award.
7. Mamania would contend that the Agreement was valid and
subsisting and that Shetty had not cleared the Subject Property of all
tenants; had not made out a clear and marketable title to the Subject
Property; not built a boundary wall, and therefore the Agreement could
not have been performed. Mamania would contend that although there
was a specific time indication in the Agreement, time was not the
essence of the contract, and since the Agreement subsisted, he was
entitled to specific performance of the Agreement in its terms i.e. at the
very price contracted therein.
8. Shetty would contend that time was of the essence and
Mamania had not performed his obligations under the Agreement
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
before August 2, 2006 while Shetty had complied with his part of the
bargain. On the other hand, Shetty contended that Mamania was not
ready with the money; had second thoughts; and in fact, sought time to
complete the transaction. Shetty would contend that it was only after a
considerable wait that he terminated the Agreement on October 3,
2006. Shetty had sought to bring on record certain further documents
purporting to demonstrate that the tenants had actually been cleared
out. However, Mamania objected to bringing such evidence on record,
on the ground that those documents had not been adequately stamped.
Impugned Award:
9. The Learned Arbitral Tribunal found that time was indeed of
essence of the contract in the Agreement, as was explicitly contracted by
the parties. The Learned Arbitral Tribunal found that Mamania had not
shown readiness and willingness to perform the Agreement proximate
to its execution despite time being of the essence, and had demonstrated
no urgency to complete the transaction, at least until October 3, 2006,
when Shetty purported to cancel and terminate the Agreement.
10. The Learned Arbitral Tribunal held that the general
presumption that time was not of the essence in transactions involving
immovable property, stood displaced in the facts of the case. Not only
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
did the Agreement itself explicitly record that time was of the essence,
but also, by all indications, the parties had intended to perform their
obligations within three months of the Agreement. Therefore, the
Learned Arbitral Tribunal held that the Agreement was not subsisting
and that when it had been subsisting, Mamania had not been ready and
willing to perform.
11. The Learned Arbitral Tribunal held that it would not be
appropriate to let Mamania cloud Shetty's title to the Subject Property
by making a partial payment and then dithering and refraining from
performing to complete the transaction, with Mamania not even
demanding performance until the Agreement was terminated. Citing
the Supreme Court judgment in Arulappan1, the Learned Arbitral
Tribunal found that it was inappropriate to grant specific relief in the
facts of this case.
12. The Learned Arbitral Tribunal found a rapid and remarkable
rise in the value of the property - according to Mamania himself, Rs. 20
crores in 2007, and according to a witness statement, Rs. 16 crores.
Citing copiously from the judgement of the Supreme Court in
Saradamani Kandappan2, the Learned Arbitral Tribunal held against
A.C. Arulappan vs. Ahalya Naik - (2001) 6 SCC 600
Saradamani Kandappan vs. S. Rajalakshmi & Ors. - (2011) 12 SCC 18
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
declaring that the Agreement was amenable to specific performance at
the behest of Mamania at an antiquated price. The Learned Arbitral
Tribunal found, on facts, that the grant of specific performance would
lead to a windfall gain for Mamania and a serious detriment to Shetty,
on account of the steep escalation in market price of the Subject
Property, holding that keeping money in the bank is not a sign of being
ready and willing to perform a contract. The Learned Arbitral Tribunal
held that there has to be something more concrete to demonstrate
actual readiness and willingness to put that money to use and complete
the transaction as obligated under contract.
Analysis and Findings:
13. I have heard Mr. Dinyar Madon, Learned Senior Advocate on
behalf of Mamania and Mr. Farhan Dubash, Learned Advocate on behalf
of Shetty. With their assistance I have examined the material on record.
14. At the threshold, it may be seen that the Learned Arbitral
Tribunal has essentially exercised its discretion not to grant specific
relief. Whether this conclusion is implausible and perverse is the test to
be applied. Merely because another view is possible, it would not be
open to substitute the view of the Learned Arbitral Tribunal with the
view of this Court to arrive at a different outcome. It is now trite law
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
that if the Learned Arbitral Tribunal has otherwise returned reasonable
and plausible findings, it is not open to the Section 34 Court to interfere
and set aside the arbitral award.
15. The Learned Arbitral Tribunal adopted the following extract
from the Supreme Court judgement in Arulappan3:
7. The jurisdiction to decree specific relief is discretionary and the court can consider various circumstances to decide whether such relief is to be granted. Merely because it is lawful to grant specific relief, the court need not grant the order for specific relief ; but this discretion shall not be exercised in an arbitrary or unreasonable manner. Certain circumstances have been mentioned in Section 20(2) of the Specific Relief Act, 1963 as to under what circumstances the court shall exercise such discretion. If under the terms of the contract the plaintiff gets an unfair advantage over the defendant, the court may not exercise its discretion in favour of the plaintiff. So also, specific relief may not be granted if the defendant would be put to undue hardship which he did not foresee at the time of agreement. If it is inequitable to grant specific relief, then also the court would desist from granting a decree to the plaintiff.
[Emphasis Supplied]
16. From the Supreme Court in Saradamani Kandappan4, the
Learned Arbitral Tribunal quoted the following extracts:
A.C. Arulappan vs. Ahalya Naik - (2001) 6 SCC 600
Saradamani Kandappan vs. S. Rajalakshmi & Ors. - (2011) 12 SCC 18
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
37. The reality arising from this economic change cannot continue to be ignored in deciding cases relating to specific performance. The steep increase in prices is a circumstance which makes it inequitable to grant the relief of specific performance where the purchaser does not take steps to complete the sale within the agreed period, and the vendor has not been responsible for any delay or non-performance. A purchaser can no longer take shelter under the principle that time is not of essence in performance of contracts relating to immovable property, to cover his delays, laches, breaches and "non-readiness".
The precedents from an era, when high inflation was unknown, holding that time is not of the essence of the contract in regard to immovable properties, may no longer apply, not because the principle laid down therein is unsound or erroneous, but the circumstances that existed when the said principle was evolved, no longer exist. In these days of galloping increases in prices of immovable properties, to hold that a vendor who took an earnest money of say about 10% of the sale price and agreed for three months or four months as the period for performance, did not intend that time should be the essence, will be a cruel joke on him, and will result in injustice. Adding to the misery is the delay in disposal of cases relating to specific performance, as suits and appeals therefrom routinely take two to three decades to attain finality. As a result, an owner agreeing to sell a property for rupees one lakh and received rupees ten thousand as advance may be required to execute a sale deed a quarter century later by receiving the remaining rupees ninety thousand, when the property value has risen to a crore of rupees.
43. Till the issue is considered in an appropriate case, we can only reiterate what has been suggested in K.S. Vidyanadam:
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
(i) The courts, while exercising discretion in suits for specific performance, should bear in mind that when the parties prescribe a time/period, for taking certain steps or for completion of the transaction, that must have some significance and therefore time/period prescribed cannot be ignored
(ii) The courts will apply greater scrutiny and strictness when considering whether the purchaser was "ready and willing" to perform his part of the contract.
(iii) Every suit for specific performance need not be decreed merely because it is filed within the period of limitation by ignoring the time-
limits stipulated in the agreement. The courts will also "frown" upon suits which are not filed immediately after the breach/refusal. The fact that limitation is three years does not mean that a purchaser can wait for 1 or 2 years to file a suit and obtain specific performance. The three-year period is intended to assist the purchasers in special cases, as for example, where the major part of the consideration has been paid to the vendor and possession has been delivered in part- performance, where equity shifts in favour of the purchaser.
[Emphasis Supplied]
17. The application of these precedents by the Learned Arbitral
Tribunal to the facts of the matter at hand is reasonable and a plausible
means of disposition of the matter at hand. The Learned Arbitral
Tribunal found that Mamania moved court in 2007 when performance
was expected three months after May 2006. There was no firm
movement until October 2006 when Shetty terminated the Agreement.
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
On the contrary, for a person who was keen to complete the transaction
and paid over Rs. 1.5 crores even before signing the Agreement, the
slowing down of the pace of interest in closing cannot be ignored. A
careful scrutiny of the record would show that it was Mamania's case
that Shetty had demanded more money upfront to be able to settle the
tenants, since they were said to be demanding exorbitant amounts, and
this is why further payments of Rs. 1.5 crores were made in July 2006.
That having been paid and Shetty claiming to have settled with the
tenants, the Learned Arbitral Tribunal has drawn an inference about
Mamania objecting to bringing on the record, evidence of settlement
with tenants.
18. In fact, Mamania had claimed that there had been a partial
encroachment on the Subject Property, with a part of the encroachment
being on the road and partly on the Subject Property. Mamania had
claimed that such encroachment would be an eye sore and had
undermined the purpose for which the Agreement had been priced at
Rs. 11.25 crores. In September 2006, Mamania claims to have received
a notice from two persons, Jagatpal Shetty and Sadanand Shetty, with a
copy of an agreement of February 19, 1993 for purchase of the property.
Shetty not having disclosed this past is said to have shocked Mamania
but Shetty is said to have simply requested Mamania to ignore such past
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
claims and indicated that those would be solved. This too would
indicate that Mamania seemed to not having been keen to complete the
transaction and in fact raised doubts about the efficacy of the
Agreement.
19. The aforesaid pleadings in the Suit are reflective of a litigant
who would resist having to perform a contract and not typical of a
litigant who is seeking specific performance. This is why Mamania
wanted a declaration from the Learned Arbitral Tribunal that the
Agreement was still valid and subsisting and was capable of specific
performance. The plaint in the Suit was affirmed in April 2007, a good
six months after the termination of the Agreement by Shetty in October
2006. It is apparent that what has weighed with the Learned Arbitral
Tribunal is that Mamania did not rush to court seeking specific
performance proximate to his grievance that a subsisting agreement was
being breached. From Mamania's own pleadings it appears that he was
picking faults that would aid postponing Mamania's performance.
20. Meanwhile, the value of the Subject Property, by Mamania's
own showing had risen to Rs. 20 crores (from Rs. 11.25 crores) and
Mamania wanted performance at the contracted lower price or even
lower on his purported discovery of shabby structures at the front,
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
which he would claim eroded the value of the land where he planned to
build commercial premises with an attractive frontage.
21. A party that had made some payments even before the
Agreement and another set of payments immediately after the execution
of the Agreement could not be expected to have delayed paying the final
component with the same dispatch and promptitude unless it had
harboured second thoughts about the wisdom of the transaction. The
pleadings and the material on record reasonably point to such second
thoughts, or perhaps a second bite at the cherry by proposing
renegotiation of the bargain.
22. The Learned Arbitral Tribunal appears to have picked up on
that and discerned that Mamania had not been truly ready and willing
to perform within the envisaged time. That apart, he filed the Suit
nearly one year after the execution of the Agreement and a good seven
months after the termination of the Agreement. This is what justifies the
invocation of Saradamani Kandappan and Arulappan by the Learned
Arbitral Tribunal for application to the facts of this case.
23. When seen from this prism, the outcome rendered by the
Learned Arbitral Tribunal cannot be faulted. It is now trite law that the
Section 34 Court cannot re-consider evidence and re-assess the material
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
on record and sit in judgement over the Learned Arbitral Tribunal. The
Section 34 Court may only determine if the arbitral award under
challenge is plausible, reasonable and not in conflict with the grounds
for being set aside in the Section 34 jurisdiction. In my opinion, having
analysed the Impugned Award and examined the material that was
presented to the Learned Arbitral Tribunal, there is nothing to show
that the findings of the Learned Arbitral Tribunal are implausible,
perverse, contrary to the contract, violative of natural justice or in
conflict with the fundamental policy of India to merit any interference
under Section 34 of the Act.
24. The Impugned Award is consistent with the bargain between
the parties, namely, that the parties had explicitly agreed in so many
words, that time was of the essence. While it may be possible to
displace the ordinary presumption that in matters of immovable
property, time was not of the essence, no fault can be found in the
instant case, with the Learned Arbitral Tribunal having found that the
express agreement as to time being of the essence not being displaced.
25. The Learned Arbitral Tribunal has also returned plausible
findings on the grant of specific relief being a matter of discretion, and
that exercise of discretion in favour of specific performance would be
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
inequitable. Mamania had insinuated value erosion by discovery of ugly
encroachments outside the frontage of the Subject Property and at the
same time, also indicated the market value of Rs. 20 crores to canvas the
scale of damages suffered. The Learned Arbitral Tribunal, citing the
case law reproduced above, found that this approach was not acceptable
and that it was not meritorious to exercise discretion in favour of
granting specific performance. A natural corollary was that the
intention to perform on the part of Mamania having been found, going
by the material on record, the Learned Arbitral Tribunal also held that
no case was made out for award of damages.
26. The scope of review by the Section 34 Court is well covered in
multiple judgements of the Supreme Court including Dyna
Technologies5, Associate Builders, Ssyangyong, Konkan Railway6 and
OPG Power7. Even implied reasons are discernible and may be inferred
to support the just and fair outcome arrived at in arbitral awards. To
avoid prolixity, I do not think it necessary to burden this judgment with
quotations from these judgments. It is well settled that the arbitral
tribunal is the master of the evidence and the best judge of the quality
and quantity of evidence. Suffice it to say (to extract from just one of the
Dyna Technologies Private Limited v. Crompton Greaves Limited - (2019) 20 SCC 1
Konkan Railways v. Chenab Bridge Project Undertaking - 2023 INSC 742
OPG Power vs. Enoxio - (2025) 2 SCC 417
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
foregoing judgements) in Dyna Technologies8, the Supreme Court held
thus:
"24. There is no dispute that Section 34 of the Arbitration Act limits a challenge to an award only on the grounds provided therein or as interpreted by various courts. We need to be cognizant of the fact that arbitral awards should not be interfered with in a casual and cavalier manner, unless the court comes to a conclusion that the perversity of the award goes to the root of the matter without there being a possibility of alternative interpretation which may sustain the arbitral award. Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under Section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute adjudicated by an alternative forum as provided under the law. If the courts were to interfere with the arbitral award in the usual course on factual aspects, then the commercial wisdom behind opting for alternate dispute resolution would stand frustrated.
25. Moreover, umpteen number of judgments of this Court have categorically held that the courts should not interfere with an award merely because an alternative view on facts and interpretation of contract exists. The courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays perversity unpardonable under Section 34 of the Arbitration Act."
[Emphasis Supplied]
Dyna Technologies Private Limited v. Crompton Greaves Limited - (2019) 20 SCC
October 7, 2025 Shraddha
ARBP-200-2014-J - FINAL.doc
27. Applying the aforesaid standard, I find it difficult to hold that
the Impugned Award is liable to set aside. It can never be held to be
perverse in a manner that goes to the root of the matter, where no other
view would be possible.
28. Mamania's contentions about how the Agreement and the
material on record ought to be interpreted, would would necessitate
substituting the incumbent plausible view with a competing view (even
assuming that the competing view canvassed is plausible). This, in my
opinion, is not permissible. When the reasoning in the Impugned
Award is reasonable, not arbitrary and not implausible, it would not be
appropriate for me to interfere as if this were an appellate court.
29. In the result, this Section 34 Petition must fail and is hereby
dismissed, along with interim applications, if any. Monies deposited by
Mamania in Court shall stand released to him and paid over by the
Registry along with all accruals thereon, within a period of three weeks
from the upload of this judgement on the website of this Court.
30. All actions required to be taken pursuant to this order shall
be taken upon receipt of a downloaded copy as available on this Court's
website.
[SOMASEKHAR SUNDARESAN, J.]
October 7, 2025 Shraddha
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!