Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Rajasthan State Co-Op. Oil Seed Growers ... vs B.G.Shirke Construction Technology ...
2025 Latest Caselaw 7051 Bom

Citation : 2025 Latest Caselaw 7051 Bom
Judgement Date : 3 November, 2025

Bombay High Court

Rajasthan State Co-Op. Oil Seed Growers ... vs B.G.Shirke Construction Technology ... on 3 November, 2025

  2025:BHC-AS:46528


                                                                                    ARA;47.2013.docx



                             IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                          CIVIL APPELLATE JURISDICTION

                                    ARBITRATION APPEAL NO. OF 47 OF 2013
                                                  WITH
                                    ARBITRATION APPEAL NO. OF 48 OF 2013
                                                  WITH
                                    ARBITRATION APPEAL NO. OF 49 OF 2013

                      Rajasthan State Co-op Oil Seed Growers                    ...Appellant
                      Federation Ltd. (Tilam Sangh)
                             Versus
                      B.G. Shirke Construction Technology Pvt.                  ...Respondents
                      Ltd. & Anr



                      Mr. Rajiv Narula a/w Tarang Jagtiani, i/b Thangiani, Narula &
                      Associates, for the Appellant.
                      Mr. Sukand Kulkarni for Respondent No.1.

                      Ms. Archita Gharat a/w Prabhakar M. Jadhav for Respondent
                      No.2 in ARA/47/2013.

                      Mr. Prabhakar M. Jadhav for Respondent No.2 in ARA/48/2013
                      & ARA/49/2013.



                                   CORAM                   : SOMASEKHAR SUNDARESAN, J.
                                    RESERVED ON            : March 11, 2025
                                   PRONOUNCED ON : November 3, 2025




ASHWINI
JANARDAN
VALLAKATI
Digitally signed by
ASHWINI JANARDAN
VALLAKATI
                                                          Page 1 of 32
Date: 2025.11.03
15:02:50 +0530
                                                        November 3, 2025




                         ::: Uploaded on - 03/11/2025                      ::: Downloaded on - 03/11/2025 21:21:37 :::
                                                                   ARA;47.2013.docx



JUDGEMENT :

Context and Factual Background:

1. The captioned appeals are filed under Section 37 of the

Arbitration and Conciliation Act, 1996 ("the Act") challenging orders

passed by the Learned District Court Pune, disposing of challenges to

arbitral awards passed by a three-member arbitral tribunal in three

separate arbitral awards, in all of which the issues are just the same.

2. In a nutshell, the Appellant, Rajasthan State Co-op Oil Seed

Growers Federation Ltd. ("Tilam Sangh") was desirous of setting up

silos for storage and process of mustard seeds in three different

locations - a 100-tonnes per day facility at Merta City (Nagaur District);

a 50-tonnes per day facility at Gangapur City (Sawaimadhopur District);

and a 100-tonnes per day facility at Sri Ganganagar (Ganganagar

District) - in the State of Rajasthan. Towards this end, Tilam Sangh

engaged National Heavy Engineering Co-operative Ltd. (" NHEC") as the

Project Management Consultant ("PMC"), which in turn engaged Shirke

Structurals Pvt. Ltd. ("Shirke") to carry out the works involved in each

of the aforesaid projects. Shirke underwent a name change later.

3. Work was completed, and payment claims were made by

Shirke, which filed civil suits. NHEC filed applications under Section 8

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

of the Act indicating that the disputes are subject matter of an

arbitration agreement. These were allowed and an arbitral tribunal was

constituted in each matter, and arbitral awards came to be passed.

4. The Learned Advocates for the parties have consented to take

up Appeal No. 47 of 2013 as the representative lead matter, indicating

that adjudication of issues in that Appeal would be dispositive of all

Appeals. By consent of the parties, all references to facts, dates and the

record are made to those contained in Appeal No. 47 of 2013, on the

understanding that this judgement would cover all the captioned

proceedings.

5. A brief overview of relevant facts is set out below:-

a) On November 6, 1987, Tilam Sangh executed an

agreement with NHEC as the PMC (" PMC

Contract");

b) PMC executed an agreement dated September 28,

1989 ("Agreement") appointing Shirke as the

contractor to carry out the work. The work was to

be commenced by October 5, 1989 and completed

by January 20, 1990;

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

c) Work was completed and a certificate of completion

was issued on October 31, 1993;

d) On April 4, 1994, Shirke made a claim for a sum of

Rs. ~4.83 lakh;

e) Shirke filed a Special Civil Suit 1734 of 1995 (" Civil

Suit") against Tilam Sangh and NHEC, but it was on

an application filed by NHEC, the Civil Suit was

rejected, referring the parties to arbitration;

f) On May 20, 2002, Tilam Sangh filed a Written

Statement in response to the Statement of Claim

and also filed a Counter-claim;

g) On April 4, 2003, Tilam Sangh claimed to have

made a mistake, withdrew the Counter-Claim, and

claimed that the Learned Arbitral Tribunal had no

jurisdiction since there was no privity of contract

between Tilam Sangh and Shirke under the

Agreement, and the arbitration clause could not

bind Tilam Sangh;

h) On June 2, 2003, an arbitral award was passed

awarding Rs. ~4.83 lakh coupled with interest at

15% per annum from September 4, 1993 and at 12%

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

per annum from May 1, 2002 until realisation

("Arbitral Award"). Both Tilam Sangh and NHEC

were made jointly liable to pay the amount to Shirke

under the Arbitral Award;

i) Special Leave Petition filed in the Supreme Court

was disposed of giving leave to Tilam Sangh to raise

jurisdictional grounds when pursuing a challenge

under Section 34;

j) Each of Tilam Sangh and NHEC filed their

respective challenge under Section 34 of the Act.

NHEC claimed that it was merely an agent of Tilam

Sangh and could not be liable while Tilam Sangh

claimed that the arbitral award was entirely without

jurisdiction. Tilam Sangh claimed that its

participation in the arbitration was under protest;

and

k) On July 18, 2013, the District Court, Pune upheld

the Arbitral Award but also ruled that NHEC was

merely an agent and that Tilam Sangh would be

responsible. Therefore, the Section 34 Petition of

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

NHEC was allowed while the Section 34 Petition of

Tilam Singh was rejected.

Contentions of Parties:

6. I have heard at length Mr. Rajiv Narula, Learned Advocate on

behalf of Tilam Sangh, Mr. Sukand Kulkarni, Learned Advocate on

behalf of Shirke and Ms. Archita Gharat, and Mr. Prabhakar Jadhav,

Learned Advocates on behalf of NHEC.

Tilam Sangh's Contentions:

7. At the heart of Mr. Rajiv Narula's submissions lies the

contention that there was no scope for privity of contract between

Shirke and Tilam Sangh, and therefore, the Arbitral Award is per se

without jurisdiction. Merely because the work was commissioned by

Tilam Sangh, it would not follow that Shirke had privity with Tilam

Sangh, which had appointed NHEC to take care of the work. The

Agreement is an instrument not executed by Tilam Sangh at all but was

executed between NHEC and Shirke. Therefore, to direct Tilam Sangh

to pay Shirke for the claims under the Agreement to which Tilam Sangh

is not even a party, is untenable. That apart, the Section 34 Court

having set aside the Arbitral Award in relation to NHEC's challenge

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

could not have deleted NHEC's liability and maintained the Arbitral

Award as against Tilam Sangh - this would constitute modification of

the Arbitral Award, which is impermissible.

8. Mr. Narula would also point to the Agreement having been

contracted on a principal-to-principal basis, leaving no scope for any

agency relationship being inferred. Participating by Tilam Sangh in the

process of appointing Shirke as a sub-contractor of NHEC would not

lead to privity of contract between Tilam Sangh and Shirke, Mr. Narula

would submit. He would also indicate that the PMC Contract made it

clear that the work could be withdrawn and any element of liability

being owed to NHEC was ruled out.

Shirke's Contentions:

9. Mr. Sukand Kulkarni on behalf of Shirke would contend the

PMC Contract led to NHEC being appointed as the PMC by Tilam

Sangh. The contract price was set out in Clause 3.1 of the PMC Contract

and Tilam Sangh had agreed to pay NHEC in terms of the schedule

contained in it. On the strength of the PMC Contract, NHEC was the

"Delegated Constituted Purchaser" in the Agreement, which defined the

term "Purchaser" as Tilam Sangh. Mr. Kulkarni would point to Clauses

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

3.1 and 13.2 of the Agreement to indicate that when read with the PMC

Contract, it was clear the principal employer was Tilam Sangh and it

ought to have made the payments due. The disputes being covered by

an arbitration agreement in Clause 24.2, the Arbitral Award has rightly

recognised Tilam Sangh's role.

10. Shirke had brought the Civil Suit against both the principal

Tilam Sangh, and the PMC agent, NHEC, who jointly and severally owed

monies to Shirke, Mr. Kulkarni would contend. It was on NHEC's

application under Section 8 of the Act that the disputes under the Civil

Suit got referred to arbitration, which too he would submit can be

regarded as an act of the agent on behalf of the principal. Tilam Sangh

participated in the arbitration and even filed a Counter-Claim, he would

contend, to indicate that it could not then pretend to have participated

under protest when there was no protest before the Learned Arbitral

Tribunal. Mr. Kulkarni would contend that Tilam Sangh participated in

the actions taken under the Agreement all along - right from selection

of Shirke; authorising NHEC by Tilam Sangh's own resolution to

appoint Shirke; participating in meetings relating to the work;

overseeing and certifying the work; and even participating in

constitution of the Learned Arbitral Tribunal. Mr. Kulkarni would point

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

to various clauses in the Agreement and in the PMC Contract to indicate

that they were interwoven agreements.

11. Defending the Impugned Judgement and thereby the Arbitral

Award, Mr. Kulkarni would submit that the Arbitral Award was not

modified but was partially set aside insofar as it related to NHEC, which

is an eminently plausible view of the Learned District Court, which

should not be disturbed. He would invoke multiple judgements on

partial setting aside of an arbitral award so long as it does not affect the

other portions of the Arbitral Award.

NHEC's Contentions:

12. Ms. Archita Gharat and Mr. Prabhakar Jadhav would invoke

the various provisions of the Agreement and read them with the PMC

Contract to indicate how the flow of obligations owed to Shirke are

relatable to obligations of Tilam Sangh. If the Arbitral Award as a

culmination of adjudication has found that amounts are payable to

Shrike, it can only be Tilam Sangh that is liable to pay. They would

defend the Impugned Judgement in its finding that imposing a joint

liability on NHEC is improbable. Shirke always knew that NHEC would

facilitate payments by Tilam Sangh and was not personally liable to pay.

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

No bill raised by Shirke would be paid by NHEC, which would only

approve it and Tilam Sangh would pay, they would contend.

13. Ms. Gharat would contend that Tilam Sangh did not raise any

objection to the Section 8 Application filed by NHEC when it was

considered by the Learned District Court in the Civil Suit. Worse, in the

arbitration, the opposition was on merits and even a Counter-Claim was

filed and as an afterthought, the objection to jurisdiction was filed with

the Counter-Claim being withdrawn. Ms. Gharat would invoke the

judgement by the Constitution Bench of the Supreme Court in Cox and

Kings1 to indicate that Tilam Sangh's implied consent to the Agreement

is writ large and there is no erosion of party autonomy. Participation by

a non-signatory in the negotiation of an agreement, the unravelling of

commercial arrangements, the common intention and purpose, the

implied intention of being bound by the terms of the agreement,

estoppel after receiving the benefit of the agreement, and the common

subject matter between the PMC Contract and the Agreement, are all

points that would inexorably demonstrate that Tilam Sangh is a

veritable party.

Cox and Kings Ltd. Vs/ SAP India (P) Ltd - (2024) 3 SCC 1

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

ANALYSIS AND FINDINGS:

14. Having heard the parties at length, and having navigated and

reviewed the material on record with the benefit of the written

submissions filed by the Learned Advocates before and after judgement

was reserved, the following facets become clear:

a) NHEC was the PMC appointed by Tilam Sangh,

which conceptualised the projects for which bids were to be

invited;

b) NHEC's role was that of a consultant and it was to be

remunerated on the basis of overseeing and implementing

the work through professional engagement of entities such as

Shirke to undertake and complete the work. NHEC was

incentivised for timely completion and proper oversight;

c) The very title clause in the Agreement identifies

NHEC as the PMC of Tilam Sangh. The term "Delegated

Constituted Purchaser" is used to describe NHEC, which is

also identified as "PMC", but more importantly, the term

"the Purchaser" is defined to mean Tilam Sangh;

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

d) The Agreement is replete with references to "the

Purchaser" and the various rights and action points of Tilam

Sangh. Provisions relating to impact of variation in taxes on

the "Contract Price" point to implications of Tilam Sangh

and not for NHEC. The beneficiary of insurance is of Tilam

Sangh and insurance policies were to be sent to Tilam Sangh.

Warranties are provided for and warranty claims were to be

raised by Tilam Sangh on Shirke;

e) Clause 23 of the Agreement is titled "Purchaser's

Rights and Obligations" and contains a detailed framework

of rights enjoyed by Tilam Sangh and duties owed by NHEC

to Tilam Sangh; and

f) Clause 23.1.4 of the Agreement provides that NHEC's

discretionary decisions must be taken in a manner fair to

both Tilam Sangh and Shirke. It explicitly provides that " if

either party disagrees with the action taken by the Project

Management Consultant, it shall be at liberty to refer the

matter to arbitration in accordance with the provisions of the

Contract";

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

Scope of Review:

15. The core question to ask is whether the Impugned Judgement

calls for any interference. It is now settled law that the scope of

jurisdiction under Section 37 of the Act, when sitting in appeal over a

decision under Section 34, is identical to the contours of the Section 34

jurisdiction. The question to ask is whether the Section 34 Court

adhered to the mandate of Section 34 and conducted itself in line with

the jurisdiction or whether it exceeded the jurisdiction or failed to

exercise such jurisdiction. Equally, it must be remembered that there

has to be due deference to an arbitral award and the Section 34 Court,

and indeed the Section 37 Court must not lightly disturb and displace

plausible findings contained in arbitral awards. The following passage

from Konkan Railway2 would be apt to quote in this regard:

14. Analysis: At the outset, we may state that the jurisdiction of the Court under Section 37 of the Act, as clarified by this Court in MMTC Ltd. v. Vedanta Ltd., is akin to the jurisdiction of the court under Section 34 of the Act. Scope of interference by a court in an appeal under Section 37 of the Act, in examining an order, setting aside or refusing to set aside an award, is restricted and subject to the same grounds as the challenge under Section 34 of the Act.

Konkan Railway Corporation Ltd. Vs. Chenab Bridge Project Undertaking - (2023) 11 SCR 215

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

15. Therefore, the scope of jurisdiction under Section 34 and Section 37 of the Act is not akin to normal appellate jurisdiction. It is well-settled that courts ought not to interfere with the arbitral award in a casual and cavalier manner. The mere possibility of an alternative view on facts or interpretation of the contract does not entitle courts to reverse the findings of the Arbitral Tribunal. In Dyna Technologies Private Limited v. Crompton Greaves Limited (2019) 20 SCC 1, this Court held:

"24. There is no dispute that Section 34 of the Arbitration Act limits a challenge to an award only on the grounds provided therein or as interpreted by various courts. We need to be cognizant of the fact that arbitral awards should not be interfered with in a casual and cavalier manner, unless the court comes to a conclusion that the perversity of the award goes to the root of the matter without there being a possibility of alternative interpretation which may sustain the arbitral award. Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under Section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute adjudicated by an alternative forum as provided under the law. If the courts were to interfere with the arbitral award in the usual course on factual aspects, then the commercial wisdom behind opting for alternate dispute resolution would stand frustrated.

25. Moreover, umpteen number of judgments of this Court have categorically held that the courts should not interfere with an award merely because an alternative view on facts and interpretation of contract exists. The courts need to be cautious

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays perversity unpardonable under Section 34 of the Arbitration Act."

[Emphasis Supplied]

16. The challenge in this Appeal filed by Tilam Sangh has to be

examined in this light. NHEC has not challenged the Impugned

Judgement to support Tilam Sangh on merits, in its capacity as PMC, by

claiming that Shirke's claim was untenable. Shirke has not challenged

the Impugned Judgement for letting off NHEC, which was jointly made

liable, and that too when Tilam Sangh has been claiming some

protections and immunities under State laws of Rajasthan. Therefore,

the scope of review is restricted to the challenge mounted by Tilam

Sangh, which would claim that the Arbitral Award is untenable on the

basic ground of absence of jurisdiction of the Learned Arbitral Tribunal

over Tilam Sangh. The objection to modification of the Arbitral Award

by Tilam Sangh has to be seen in this light - as an added argument on

the implausible conduct by the Learned District Court. Such challenge

has to be examined in the light of the scope outlined in Konkan Railway

and extracted above.

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

Veritable Party Analysis:

17. First, on a careful perusal of the PMC Contract and the

Agreement, and based on a conjoint reading of the two together, Tilam

Sangh's contention of being a disconnected third party by reason of

being a non-signatory is an implausible contention. The Agreement is

not only dependent on NHEC's role as a PMC as contracted by Tilam

Sangh under the PMC Contract but also makes it explicitly clear that if

Tilam Sangh or Shirke have any disagreement with NHEC, the

disagreement would be amenable to arbitration under the Agreement.

Clause 23.1.4 (quoted from above), thereby expands and extrapolates

the reach of the jurisdiction of the arbitration agreement contained in

the Agreement to Tilam Sangh too. One need not look any further to

ascertain privity of Tilam Sangh to the arbitration agreement as a non-

signatory who is indeed a veritable party.

18. Second, the law declared in Cox and Kings expansively

articulates how one must ascertain if a non-signatory to an agreement

containing an arbitration clause is a veritable party to the arbitration

agreement. While Cox and Kings was rendered in the context of

examining if the 'group of companies doctrine' could be invoked to treat

parties who are not signatories to an arbitration agreement as veritable

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

parties to the agreement, it elaborated on the factors and principles to

be borne in mind when making such assessment. The following extracts

are noteworthy:

37. Over time, this Court has identified certain additional factors for the invocation of the Group of Companies doctrine. In Reckitt Benckiser (India) (P) Ltd. v. Reynders Label Printing (India) (P) Ltd. [Reckitt Benckiser (India) (P) Ltd. v. Reynders Label Printing (India) (P) Ltd., (2019) 7 SCC 62 : (2019) 3 SCC (Civ) 453] , a two-

Judge Bench of this Court was dealing with an application under Section 11(6) of the Arbitration Act seeking the appointment of an arbitrator. This Court prima facie observed that the parties belonged to the same group of companies. Subsequently, the issue before this Court was whether there was a clear intention of the parties to bind both the signatory and non-signatory parties based on their participation in the negotiation of the underlying contract. The Court held that the non-signatory party, even though a constituent part of the corporate group, did not have "any causal connection with the process of negotiations preceding the agreement or the execution thereof, whatsoever". Thus, the participation of the non-signatory party in the negotiation and performance of the underlying contract was held to be the key determinant of the intention of the parties to be bound by an arbitration agreement.

50. In Swiss law, the consent of the parties to be bound by an arbitration agreement may be express or implied by conduct. In a 2008 decision, the Swiss Federal Court held that certain behaviour or conduct may substitute compliance with a formal requirement of an arbitration agreement. [ Decision 4A_376/2008 of 5-12-2008.] To determine the implied consent, it was held that the Courts or tribunals may take into consideration the fact whether the non-signatory party was involved in the negotiation and performance of the contract, and

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

thereby expressed its willingness to be bound by the arbitration agreement. [X v. Y Engg. S.p.A. & Y S.p.A. 4A_450/2013, ASA Bull., 160 (2015).] Thus, the subjective element of willingness to be bound by an arbitration agreement ought to be expressed through an objective element in the form of negotiation or performance of the contract.

[Emphasis Supplied]

19. Applying this principle to the facts of the case, not only did

Tilam Sangh conceive and commission the project covered by the

Agreement, it appointed NHEC as the PMC to oversee it on its behalf

and yet retained control even in the provisions of the Agreement that it

permitted NHEC to execute, and even more importantly, oversaw the

insertion of Clause 23.1.4 to provide for arbitration over disputes in

terms of the arbitration clause in the Agreement. It is arguable that the

scope of arbitration under Clause 23.1.4 is relatable to situations where

the PMC has exercised discretion and not to other situations. However,

it is equally arguable that the existence of a provision of this nature

would point to Tilam Sangh necessarily being a veritable party to the

Agreement.

20. Third, the common objective and purpose of the parties is

also writ large. The subject matter of the PMC Contract and the

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

Agreement is the works commissioned by Tilam Sangh. NHEC was

engaged as a consultant i.e. a service provider. NHEC was not meant to

taken on the risk and reward of the project. It was paid a commission as

a percentage of the project cost with an incentive structure to enable

speedy and timely commissioning of the work. It is quite clear that

Tilam Sangh has not signed the Agreement is not expressly a party to

the arbitration agreement, although the very Agreement refers to Tilam

Sangh.

21. Therefore, the question to examine is whether Tilam Sangh is

an implied party to the arbitration agreement i.e. a "veritable party".

Towards this end, the following discussion from Cox and Kings would

be noteworthy:

(ii) Parties to arbitration agreement

70. The general method to figure out the parties to an arbitration agreement is to look for the entities who are named in the recitals and have signed the agreement. The signature of a party on the agreement is the most profound expression of the consent of a person or entity to submit to the jurisdiction of an Arbitral Tribunal. However, the corollary that persons or entities who have not signed the agreement are not bound by it may not always be correct. A written contract does not necessarily require that parties put their signatures to the document embodying the terms of the agreement. [ Pollock and Mulla, The Indian Contract and Specific Reliefs Act (14th Edn., 2016)

235.] Therefore, the term "non-signatories", instead of the traditional

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

"third parties", seems the most suitable to describe situations where consent to arbitration is expressed through means other than signature. A non-signatory is a person or entity that is implicated in a dispute which is the subject-matter of an arbitration, although it has not formally entered into an arbitration agreement. [ Stavros Brekoulakis, "Rethinking Consent in International Commercial Arbitration : A General Theory for Non-signatories" (2017) 8 Journal of International Dispute Settlement 610.] The important determination is whether such a non-signatory intended to effect legal relations with the signatory parties and be bound by the arbitration agreement.

There may arise situations where persons or entities who have not formally signed the arbitration agreement or the underlying contract containing the arbitration agreement may intend to be bound by the terms of the agreement. In other words, the issue of who is a "party" to an arbitration agreement is primarily an issue of consent.

72. Chitty on Contracts explains the difference between express and implied contracts as follows:

"Contracts may either be express or implied. The difference is not one of legal effect but simply of the way in which the consent of the parties is manifested. Contracts are express when their terms are stated in words by the parties. They are often said to be implied when their terms are not so stated, as, for example, when a passenger is permitted to board a bus :

from the conduct of the parties the law implies a promise by the passenger to pay the fare, and a promise by the operator of the bus to carry him safely to his destination.[...] Express and implied contracts are both contracts in the true sense of the term, for they both arise from the agreement of the parties, though in one case the agreement is manifested in words and in the other case by conduct. Since, as we have seen, agreement is not a mental state but an act, an inference from conduct, and since many of the terms of an express contract are often

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

implied, it follows that the distinction between express and implied contracts has little importance." [Chitty on Contracts, Hugh Beale (Ed.), (32nd Edn., Sweet and Maxwell, 2015) para 1-104.]

73. The above exposition gives rise to the inference that in case of an implied contract, the question revolves around the determination of the consent of the parties to be bound by the terms of the contract. Such determination is manifested through the acts or conduct. The theory of implied contract by conduct has also been accepted by this Court. In Haji Mohd. Ishaq v. Mohd. Iqbal & Mohd. Ali & Co. [Haji Mohd. Ishaq v. Mohd. Iqbal & Mohd. Ali & Co., (1978) 2 SCC 493] , the plaintiff supplied tobacco to the defendant. Although there was no express agreement between the parties, the defendant accepted the goods, but allegedly failed to clear the outstanding dues despite repeated demands raised by the plaintiff. A Bench of three Judges of this Court observed that the conduct of the defendants in accepting the goods and not repudiating any of the demand letters raised by the plaintiff "clearly showed that a direct contract which in law is called an implied contract by conduct was brought about between them". Under the Indian contract law, it is posited that actions or conduct can be an indicator of consent of a party to be bound by a contract. This also applies to an arbitration agreement considering the fact that it is a creature of contract. However, an arbitration agreement also has to meet the requirements laid down under the Arbitration Act to be valid and enforceable.

83. Reading Section 7 of the Arbitration Act in view of the above discussion gives rise to the following conclusions : first, arbitration agreements arise out of a legal relationship between or among persons or entities which may be contractual or otherwise; second, in situations where the legal relationship is contractual in nature, the nature of relationship can be determined on the basis of general contract law principles; third, it is not necessary for the persons or

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

entities to be signatories to the arbitration agreement to be bound by it; fourth, in case of non-signatory parties, the important determination for the Courts is whether the persons or entities intended or consented to be bound by the arbitration agreement or the underlying contract containing the arbitration agreement through their acts or conduct; fifth, the requirement of a written arbitration agreement has to be adhered to strictly, but the form in which such agreement is recorded is irrelevant; sixth, the requirement of a written arbitration agreement does not exclude the possibility of binding non- signatory parties if there is a defined legal relationship between the signatory and non-signatory parties; and seventh, once the validity of an arbitration agreement is established, the Court or tribunal can determine the issue of which parties are bound by such agreement.

84. It is presumed that the formal signatories to an arbitration agreement are parties who will be bound by it. However, in exceptional cases persons or entities who have not signed or formally assented to a written arbitration agreement or the underlying contract containing the arbitration agreement may be held to be bound by such agreement. As mentioned in the preceding paragraphs, the doctrine of privity limits the imposition of rights and liabilities on third parties to a contract. Generally, only the parties to an arbitration agreement can be subject to the full effects of the agreement in terms of the reliefs and remedies because they consented to be bound by the arbitration agreement. Therefore, the decisive question before the Courts or tribunals is whether a non-signatory consented to be bound by the arbitration agreement. To determine whether a non-signatory is bound by an arbitration agreement, the Courts and tribunals apply typical principles of contract law and corporate law. The legal doctrines provide a framework for evaluating the specific contractual language and the factual settings to determine the intentions of the parties to be bound by the arbitration agreement. [ Gary Born, International Arbitration Law and Practice, (3rd Edn., 2021) at p. 1531.]

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

(ii) Adopting a pragmatic approach to consent

96. An arbitration agreement encapsulates the commercial understanding of business entities as regards to the mode and manner of settlement of disputes that may arise between them in respect of their legal relationship. In most situations, the language of the contract is only suggestive of the intention of the signatories to such contract and not the non-signatories. However, there may arise situations where a person or entity may not sign an arbitration agreement, yet give the appearance of being a veritable party to such arbitration agreement due to their legal relationship with the signatory parties and involvement in the performance of the underlying contract. Especially in cases involving complex transactions involving multiple parties and contracts, a non-signatory may be substantially involved in the negotiation or performance of the contractual obligations without formally consenting to be bound by the ensuing burdens, including arbitration.

97. Modern commercial reality suggests that there often arise situations where a company which has signed the contract containing the arbitration clause is not always the one to negotiate or perform the underlying contractual obligations. In such situations, emphasis on formal consent will lead to the exclusion of such non-signatories from the ambit of the arbitration agreement, leading to multiplicity of proceedings and fragmentation of disputes. In A. Ayyasamy v. A. Paramasivam [A. Ayyasamy v. A. Paramasivam, (2016) 10 SCC 386 :

(2017) 1 SCC (Civ) 79] , this Court observed that it is the duty of the Courts "to impart to that commercial understanding a sense of business efficacy". The Courts must interpret contracts in a manner that would give them a sense of efficacy rather than invalidating the commercial interests of the parties. The meaning of the contract must be gathered by adopting a common sense approach, which should "not be allowed to be thwarted by a narrow, pedantic and legalistic interpretation". [Union of India v. D.N. Revri & Co., (1976) 4 SCC

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

147] Therefore, there is a need to adopt a modern approach to consent, which takes into consideration the circumstances, apparent conduct, and commercial facets of business transactions.

100. Arbitration law is an autonomous legal field. While the main purpose of corporate law and contract law is imputation of substantive legal liability, the main purpose behind the law of arbitration is to determine whether an Arbitral Tribunal has jurisdiction over the dispute arising between parties to an arbitration agreement. On the one hand, the Courts and tribunals cannot lightly brush aside the decision of the parties to not make a person or entity a party to the arbitration agreement. The fact that the non-signatory did not put pen to paper may be an indicator of its intention to not assume any rights or responsibilities under the arbitration agreement. On the other hand, courts and tribunals cannot adopt a rigid approach to exclude all persons or entities who, through their conduct and relationship with the signatory parties, intended to be bound by the underlying contract containing the arbitration agreement. The area of arbitration law not only concerns domestic law, but it also encompasses the international law, particularly when it pertains to the enforcement of international arbitral awards. Therefore, this Court ought to adopt a balanced approach without comprising (quaere compromising) on the basic principles of arbitration law, contract law, and company law to ensure that the resultant legal framework is consistent with internationally accepted practices and principles.

101. A formalistic construction of an arbitration agreement would suggest that the decision of a party to not sign an arbitration agreement should be construed to mean that the mutual intention of the parties was to exclude that party from the ambit of the arbitration agreement. Indeed, corporate entities have the commercial and contractual freedom to structure their businesses in a manner to limit their liability. However, there have been situations where a corporate entity deliberately made an effort to be not bound by the underlying

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

contract containing the arbitration agreement, but was actively involved in the negotiation and performance of the contract. The level of the non-signatory party's involvement was to the extent of making the other party believe that it was a veritable party to the contract, and the arbitration agreement contained under it. Therefore, the Group of Companies doctrine is applied to ascertain the intentions of the parties by analysing the factual circumstances surrounding the contractual arrangements. [ Gary Born, International Arbitration Law and Practice, (3rd Edn., 2021) at p. 1568.] [Emphasis Supplied]

22. A prolix reproduction became necessary since the aforesaid

extracts speak for themselves in their relevance to the matter at hand.

The role of Tilam Sangh looming large over the Agreement and the

commonality of subject matter of the PMC Contract and the Agreement,

and the inter-connected nature of the two contracts and the bundle of

rights and obligations contained therein cannot be ignored. In the

application of the aforesaid principles, the following further extracts

from Cox and Kings would complete the framework in which the matter

at hand must be examined:-

120. In case of multiple parties, the necessity of a common subject-

matter and composite transaction is an important factual indicator. An arbitration agreement arises out of a defined legal relationship between the parties with respect to a particular subject-matter. Commonality of the subject-matter indicates that the conduct of the non-signatory party must be related to the subject-matter of the arbitration agreement. For instance, if the subject-matter of the contract underlying the arbitration agreement pertains to distribution

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

of healthcare goods, the conduct of the non-signatory party should also be connected or in pursuance of the contractual duties and obligations, that is, pertaining to the distribution of healthcare goods. The determination of this factor is important to demonstrate that the non-signatory party consented to arbitrate with respect to the particular subject-matter.

121. In case of a composite transaction involving multiple agreements, it would be incumbent for the Courts and tribunals to assess whether the agreements are consequential or in the nature of a follow-up to the principal agreement. This Court in Canara Bank [MTNL v. Canara Bank, (2020) 12 SCC 767] observed that a composite transaction refers to a situation where the transaction is interlinked in nature or where the performance of the principal agreement may not be feasible without the aid, execution, and performance of the supplementary or ancillary agreements.

122. The general position of law is that parties will be referred to arbitration under the principal agreement if there is a situation where there are disputes and differences "in connection with" the main agreement and also disputes "connected with" the subject-matter of the principal agreement. [Olympus Superstructures (P) Ltd. v. Meena Vijay Khetan, (1999) 5 SCC 651] In Chloro Controls [Chloro Controls India (P) Ltd. v. Severn Trent Water Purification Inc., (2013) 1 SCC 641 : (2013) 1 SCC (Civ) 689] , this Court clarified that the principle of "composite performance" would have to be gathered from the conjoint reading of the principal and supplementary agreements on the one hand, and the explicit intention of the parties and attendant circumstances on the other. The common participation in the commercial project by the signatory and non-signatory parties for the purposes of achieving a common purpose could be an indicator of the fact that all the parties intended the non-signatory party to be bound by the arbitration agreement. Thus, the application of the Group of

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

Companies doctrine in case of composite transactions ensures accountability of all parties who have materially participated in the negotiation and performance of the transaction and by doing so have evinced a mutual intent to be bound by the agreement to arbitrate.

123. The participation of the non-signatory in the performance of the underlying contract is the most important factor to be considered by the Courts and tribunals. The conduct of the non-signatory parties is an indicator of the intention of the non-signatory to be bound by the arbitration agreement. The intention of the parties to be bound by an arbitration agreement can be gauged from the circumstances that surround the participation of the non-signatory party in the negotiation, performance, and termination of the underlying contract containing such agreement......

[Emphasis Supplied]

23. The law declared by the Supreme Court is clear. A conjoint

reading is necessary in the situation at hand. The PMC Contract and the

Agreement have a common subject matter. The PMC is but a consultant

of Tilam Sangh. The PMC was authorised by Tilam Sangh to appoint

Shirke. The Agreement was authorised by Tilam Sangh. The Agreement

being on a principal-to-principal basis can only mean that Shirke is not

an agent of NHEC. The PMC Contract is purely to enable NHEC to

carry out the specific tasks assigned to NHEC by Tilam Sangh. The risk

and reward from the project work flowed to Tilam Singh. The only

reward for NHEC is the fees and the incentive for timely completion.

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

24. Therefore, to my mind, the objection on the ground of Tilam

Sangh having no implied privity to the Agreement and thereby the

Learned Arbitral Tribunal having no jurisdiction over Tilam Singh are

implausible propositions.

Making NHEC Pay is Implausible:

25. Moreover, it is totally implausible that a PMC is made to pay

on the primary payment obligations owed by the principal employer. To

that extent, making NHEC jointly and severally liable to Shirke is indeed

implausible. Therefore, the intervention by the Learned District Court

in severing and excising that portion of the Arbitral Award that makes

NHEC jointly liable to discharge duties owed to Shirke cannot be

faulted. It is only where a finding is implausible such that no reasonable

person could take that view that an intervention can be made. The

Learned District Court's limited intervention cannot be faulted.

26. When this matter was argued, the case law cited on partial

setting aside of awards were all rendered prior to the Constitution

Bench judgement of the Supreme Court in Gayatri Balasamy3, which has

clearly declared the law on partial setting aside of arbitral awards.

Without meaning to add more length to this judgement by extracting

Gayatri Balasamy vs. M/s ISG Novasoft Technologies Limited - 2025 INSC 605

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

from it, it would be only apt to say that by now it is trite law that if any

portion of an arbitral award deserves to be set aside, the Section 34

Court could do so if it is completely severable and its contents are not

inseparably intertwined to the other components of the arbitral award

found to be valid and legal. Part II of the majority judgement ( Per.

Sanjiv Khanna, CJI -paragraphs 33 to 36) and in the concurring

contents of the separate judgement ( Per. K.V. Vishwanathan J -

paragraphs 142 to 152), clearly lay down the law. I have examined the

Arbitral Award from this perspective, and I note that excising the

portion that makes NHEC liable for what is payable by Tilam Sangh to

sustain the Arbitral Award in its material substance and removing the

vulnerability posed by NHEC's challenge under Section 34, does not

undermine the Arbitral Award. There is nothing inextricably

interwoven and interconnected about NHEC being jointly liable with

Tilam Sangh that makes its excision undermine anything in the rest of

the Arbitral Award. In fact, it is because this element is out of sync with

the rest of the Arbitral Award, that the excision of this offending portion

is found to be a meritorious means of sustaining the Arbitral Award.

27. There are other facets contended - about Tilam Sangh not

having filed an application under Section 16 of the Act, and in fact

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

having participated in the arbitration. On the other hand, the Supreme

Court has indeed given liberty to raise contentions on jurisdiction in the

Section 34 Petition and thereby in this Section 37 Appeal. To my mind,

it is unnecessary to deal with this strand of submissions and counter-

submissions since, for the reasons set out above, I do not think this

Appeal has merit and, in any case, even assuming the liberty granted

permits making these submissions, I have examined the substance and

dealt with the same.

Summary of Conclusions:

28. To summarize:

a) Tilam Sangh is a veritable party to the Agreement.

Therefore, the Arbitral Award is not without jurisdiction over

Tilam Sangh;

b) The obligation to pay, which is a determination on

merits, cannot be visited upon NHEC, which was merely a

PMC;

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

c) The Agreement has to be interpreted in accordance

with its terms as well as customs and usages. It cannot be

contended that it is customary for a project management

consultant to undertake the liability owed by the principal

employer owed to sub-contractors. To this extent, the

Arbitral Award had returned an implausible finding of joint

liability of NHEC;

d) The excision of the joint liability fastened on NHEC is

permissible and is well covered by the law declared in

Gayatri Balsamy. Such partial setting aside is not an

impermissible modification and in fact, removes the

vulnerability to the Arbitral Award;

e) Therefore, there is nothing in the Impugned

Judgement that warrants interference by this Court in

exercise of jurisdiction under Section 37 of the Act.

29. In the result, the captioned Appeal would fail. The Appeal is

dismissed. Interim Applications, if any, shall stand disposed of

accordingly. Amounts, if any, lying in the Registry of this Court shall be

November 3, 2025 Ashwini Vallakati

ARA;47.2013.docx

released within a week of the expiry of four weeks from the upload of

this judgement on this Court's website.

30. All actions required to be taken pursuant to this order shall

be taken upon receipt of a downloaded copy as available on this Court's

website.

[SOMASEKHAR SUNDARESAN, J.]

November 3, 2025 Ashwini Vallakati

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter